CN203247506U - Bridge high-pier construction creeping formwork internal formwork lifting frame - Google Patents

Bridge high-pier construction creeping formwork internal formwork lifting frame Download PDF

Info

Publication number
CN203247506U
CN203247506U CN2013202270542U CN201320227054U CN203247506U CN 203247506 U CN203247506 U CN 203247506U CN 2013202270542 U CN2013202270542 U CN 2013202270542U CN 201320227054 U CN201320227054 U CN 201320227054U CN 203247506 U CN203247506 U CN 203247506U
Authority
CN
China
Prior art keywords
construction
pier
bar
formwork
bridge high
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2013202270542U
Other languages
Chinese (zh)
Inventor
王振兴
雷军
李帅
李亚琦
李钢
胡军伟
张志强
孙艳辉
康金坤
杨川
武昆朋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority to CN2013202270542U priority Critical patent/CN203247506U/en
Application granted granted Critical
Publication of CN203247506U publication Critical patent/CN203247506U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to the field of bridge construction, in particular to a bridge high-pier construction creeping formwork internal formwork lifting frame which solves the problems that in the bridge high-pier construction process, an existing creeping formwork inner frame erecting method has safety risks and is low in construction efficiency. The creeping formwork internal formwork lifting frame comprises at least two rows of longitudinal main rods arranged in a pier body, cross rods connected with the upper portion of each row of longitudinal main rods in a three-face all-around welding mode, the two ends of adjacent cross rods are connected through a connecting rod, and a load bearing rod with the two ends respectively arranged on a pier body stiff skeleton is movably inserted under the crossed portion of one main rod and one cross rod. A concrete pouring platform and at least one layer of reinforcing steel bar formwork construction platform are arranged along the main rods from top to bottom, and a creeping ladder is arranged between adjacent platforms. The structure is simple, the design is reasonable, manufacturing cost is low, the bridge high-pier construction creeping formwork internal formwork lifting frame can be used for construction of any hollow thin-wall piers with stiff skeletons, the construction period is shortened, construction cost is saved, and safety of construction staff is guaranteed.

Description

Bridge High-pier construction creeping formwork internal mold suspension bracket
Technical field
The utility model relates to field of bridge construction, is specially a kind of Bridge High-pier construction creeping formwork internal mold suspension bracket.
Background technology
Usually bridge hollow thin-wall pier adopts climbing formwork for construction technique, pier shaft have up to 143m, every sections is built height 4.5m.Tradition creeping formwork internal frame erection method is to utilize a upper sections TOC embedded hole (D=40mm) to penetrate Φ 32 reinforcing bars as support bar, in reinforcing bar top colligation bamboo springboard, forms operation platform.There is following shortcoming in this erection method:
1, set up reinforcing bar bamboo springboard operation platform and have higher security risk, the constructor need to fasten the safety belt to stand in and lay the bamboo springboard on the reinforcing bar, and falling accident occurs easily;
2, the every segmental construction height of pier shaft 4.5m, and the internal mold chord position in the construction sections the bottom, the constructor stands on the interior mould bases, can't satisfy the colligation of sections upper reinforcement and template construction.Φ 32 reinforcing bars vertically need to be inserted in the completed reinforcing bar in bottom during assembling reinforcement, the constructor carries out the upper reinforcement colligation above being sitting in Φ 32 reinforcing bars, has higher security risk, can't satisfy the top and the bottom reinforcing bar simultaneously and construct simultaneously, and efficiency of construction is low; When masterplate was worn pull bar, the constructor must stand on the template back arris of bottom, penetrated upper mould to pull bar, had higher security risk.
Summary of the invention
There are the problems such as security risk, efficiency of construction are low in the utility model creeping formwork internal frame erection method when solving existing Bridge High-pier construction, and a kind of Bridge High-pier construction creeping formwork internal mold suspension bracket is provided.
The utility model is to adopt following technical scheme to realize: Bridge High-pier construction creeping formwork internal mold suspension bracket, comprise that being arranged at least two in the pier shaft arranges vertical main force bar, arranges the cross bar that three weld all arounds are carried out on vertical main force bar top with each, the adjacent crossbars two ends connect by connecting rod respectively, and the infall underside of main force's bar and cross bar is inserted with two ends and is set up in respectively bearing bar on the pier shaft stiff skeleton; Be provided with concrete pouring construction platform and one deck reinforcing bar template construction platform at least from top to bottom along main force's bar, be provided with cat ladder between the adjacent platforms.
Be provided with guardrail around the described reinforcing bar template construction platform, guarantee constructor's safety.
Described cross bar is provided with suspension ring, the cross bar two ends are connected with the pier shaft stiff skeleton with snap ring by steel wire loop, whole internal mold suspension bracket can be sling by suspension ring and tower crane, and the setting of steel wire loop and snap ring can further strengthen the stability of whole suspension bracket on the cross bar, guarantees constructor's safety.
Adopt structure design of the present utility model, this internal mold suspension bracket utilizes hollow thin-wall pier own characteristic, hang on the pier shaft stiff skeleton, after a upper sections concrete construction is finished, utilize the tower crane internal mold suspension bracket of slinging, the constructor extracts bearing bar out, when tower crane winches to next sections top with the internal mold suspension bracket, bearing bar is inserted the cross bar below, compared with prior art, the utlity model has following advantage:
1, economic benefit
(1) promote interior mould bases and can be finished in 20 minutes by two workmans, set up interior mould bases method with tradition and compare, every sections can be saved 1.5 hours;
(2) constructor may stand on each platform of internal mold suspension bracket and carries out reinforcing bar binding and template construction, has saved the time, has saved cost, and assembling reinforcement needs every sections can save 5 hours; Mi water river grand bridge hollow thin-wall pier amounts to 765.5m, every sections 4.5m, and 170 sections were saved time 1105 hours altogether.
2, social benefit
Adopt new internal mold suspension bracket, constructor's assembling reinforcement, installation form, concreting are in the suspension bracket of sealing, all are provided with guard rail on every side, and any operation can stand on the platform and finish, greatly improve constructor's inherently safe, avoided the generation of falling accident;
In a word, the utility model is simple in structure, reasonable in design, cost of manufacture is low, can be used for any hollow thin-wall pier construction that stiff skeleton is arranged, and has shortened the duration, has saved construction cost, has guaranteed again constructor's safety.
Description of drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is use state elevation of the present utility model;
Fig. 3 is use state side view of the present utility model;
Among the figure: the vertical main force of 1-bar; The 2-cross bar; The 3-connecting rod; 4-pier shaft stiff skeleton; The 5-bearing bar; 6-concrete pouring construction platform; 7-reinforcing bar template construction platform; The 8-cat ladder; The 9-guardrail; The 10-suspension ring; The 11-steel wire loop; The 12-snap ring; The 13-creeping formwork; 14-has finished sections.
The specific embodiment
Bridge High-pier construction creeping formwork internal mold suspension bracket, as shown in Figure 1, 2, 3, comprise that being arranged at least two in the pier shaft arranges vertical main force bar 1, arranges the cross bar 2 that three weld all arounds are carried out on vertical main force bar top with each, the adjacent crossbars two ends connect by connecting rod 3 respectively, and the infall underside of main force's bar and cross bar is inserted with two ends and is set up in respectively bearing bar 5 on the pier shaft stiff skeleton 4; Be provided with concrete pouring construction platform 6 and one deck reinforcing bar template construction platform 7 at least from top to bottom along main force's bar, be provided with cat ladder 8 between the adjacent platforms, be provided with guardrail 9 around the reinforcing bar template construction platform 7, cross bar 2 is provided with suspension ring 10, is connected with snap ring and is connected with pier shaft stiff skeleton 4 by steel wire loop 11 in the cross bar two ends.
During concrete the making, can adopt following methods and structure:
3 groups of bearing bars, every group is welded mouth to mouth by two ∠ 100*100*10mm angle steel, and cross section forms " mouth " font, is interrupted welding 10cm*10cm, needs to weld Φ 32 reinforcing bars in the angle steel, and spacing is 30cm, the compressive strength of raising angle steel;
6 groups on main force's bar, every group is made of a ∠ 100*100*10mm angle steel;
2 groups of cross bars, every group is made of a ∠ 100*100*10mm angle steel, carries out three weld all arounds, weld bead height 1cm with main force bar;
2 groups of connecting rods, every group is made of a ∠ 100*100*10mm angle steel, carries out three weld all arounds, weld bead height 1cm with cross bar;
4 groups on steel mesh reinforcement platform, top layer be as concrete casting platform, below three layers as reinforcing bar binding, template construction platform, check during Pouring concrete at the same time whether template has loosening to pull bar.Every group is welded by Φ 32 reinforcing bars and Φ 20 reinforcing bars, and the above completely spreads the bamboo springboard, and bamboo springboard and reinforcing bar binding are firm;
3 groups of cat ladders, every group of cat ladder handrail is formed by connecting by steel pipe (d=48mm), laterally uses the cruciform fastening for falsework joint steel pipe;
3 groups of guardrails, every group is welded by Φ 20 reinforcing bars and Φ 12 reinforcing bars, and the below arranges the high foot guard plate of 30cm;
4 groups on suspension ring, every group is made by φ 20 plain bars, and suspension ring need to weld with cross bar, and double welding need satisfy 10cm;
4 groups of steel wire loops, length 1m, (4) are used with snap ring.

Claims (3)

1. Bridge High-pier construction creeping formwork internal mold suspension bracket, it is characterized in that comprising that being arranged at least two in the pier shaft arranges vertical main force bars (1), arranges the cross bar (2) that three weld all arounds are carried out on vertical main force bar top with each, the adjacent crossbars two ends connect by connecting rod (3) respectively, and the infall underside of main force's bar and cross bar is inserted with two ends and is set up in respectively bearing bar (5) on the pier shaft stiff skeleton (4); Be provided with concrete pouring construction platform (6) and one deck reinforcing bar template construction platform (7) at least from top to bottom along main force's bar, be provided with cat ladder (8) between the adjacent platforms.
2. Bridge High-pier construction creeping formwork internal mold suspension bracket according to claim 1 is characterized in that reinforcing bar template construction platform (7) is provided with guardrail (9) all around.
3. Bridge High-pier construction creeping formwork internal mold suspension bracket according to claim 1 and 2 is characterized in that cross bar (2) is provided with suspension ring (10), and the cross bar two ends are connected 12 by steel wire loop (11) with snap ring) be connected with pier shaft stiff skeleton (4).
CN2013202270542U 2013-04-28 2013-04-28 Bridge high-pier construction creeping formwork internal formwork lifting frame Expired - Fee Related CN203247506U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013202270542U CN203247506U (en) 2013-04-28 2013-04-28 Bridge high-pier construction creeping formwork internal formwork lifting frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013202270542U CN203247506U (en) 2013-04-28 2013-04-28 Bridge high-pier construction creeping formwork internal formwork lifting frame

Publications (1)

Publication Number Publication Date
CN203247506U true CN203247506U (en) 2013-10-23

Family

ID=49373953

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013202270542U Expired - Fee Related CN203247506U (en) 2013-04-28 2013-04-28 Bridge high-pier construction creeping formwork internal formwork lifting frame

Country Status (1)

Country Link
CN (1) CN203247506U (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103938856A (en) * 2014-04-09 2014-07-23 中国化学工程第十三建设有限公司 Tower structure slip-form construction operation platform free of bracing pieces and construction method
CN104195954A (en) * 2014-08-29 2014-12-10 上海建工七建集团有限公司 Overhead stand column construction platform without support and erecting method thereof
CN104878700A (en) * 2015-06-23 2015-09-02 广东省水利水电第三工程局有限公司 Truss and formwork
CN105586833A (en) * 2015-12-18 2016-05-18 上海嘉实(集团)有限公司 Construction method for integrally forming large cast-in-place thin-wall high pier through stiff skeleton reinforcement cage
CN106012811A (en) * 2016-06-14 2016-10-12 江苏燕宁建设工程有限公司 Construction method for integrally binding and hoisting reinforcing bars for pier body of vase type bridge pier
CN106760567A (en) * 2017-01-13 2017-05-31 山东中煤能源机械有限责任公司 A kind of shear wall aluminum alloy mould plate fixes hanging apparatus
CN107059633A (en) * 2015-12-14 2017-08-18 中铁上海工程局集团有限公司 A kind of construction method of minimum spacing separate type Thin-Wall Piers
CN108842637A (en) * 2018-08-30 2018-11-20 中铁六局集团广州工程有限公司 Frame built in solid pier pier shaft and solid pier pier construction method
CN114214954A (en) * 2021-12-23 2022-03-22 广东科能工程管理有限公司 Construction method of municipal elevated bridge cast-in-situ pier
CN114561880A (en) * 2022-03-02 2022-05-31 中铁大桥局武汉桥梁特种技术有限公司 Method for modifying loading dock

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103938856B (en) * 2014-04-09 2015-09-02 中国化学工程第十三建设有限公司 A kind of tower-like structure are without support bar slding form operation operating platform and construction method
CN103938856A (en) * 2014-04-09 2014-07-23 中国化学工程第十三建设有限公司 Tower structure slip-form construction operation platform free of bracing pieces and construction method
CN104195954B (en) * 2014-08-29 2016-08-24 上海建工七建集团有限公司 Overhead column erection without scaffolding platform and erection method thereof
CN104195954A (en) * 2014-08-29 2014-12-10 上海建工七建集团有限公司 Overhead stand column construction platform without support and erecting method thereof
CN104878700A (en) * 2015-06-23 2015-09-02 广东省水利水电第三工程局有限公司 Truss and formwork
CN107059633A (en) * 2015-12-14 2017-08-18 中铁上海工程局集团有限公司 A kind of construction method of minimum spacing separate type Thin-Wall Piers
CN105586833B (en) * 2015-12-18 2017-03-29 上海嘉实(集团)有限公司 Stiff skeleton steel reinforcement cage global formation large-scale cast-in-place tall pier and thin wall construction method
CN105586833A (en) * 2015-12-18 2016-05-18 上海嘉实(集团)有限公司 Construction method for integrally forming large cast-in-place thin-wall high pier through stiff skeleton reinforcement cage
CN106012811A (en) * 2016-06-14 2016-10-12 江苏燕宁建设工程有限公司 Construction method for integrally binding and hoisting reinforcing bars for pier body of vase type bridge pier
CN106760567A (en) * 2017-01-13 2017-05-31 山东中煤能源机械有限责任公司 A kind of shear wall aluminum alloy mould plate fixes hanging apparatus
CN108842637A (en) * 2018-08-30 2018-11-20 中铁六局集团广州工程有限公司 Frame built in solid pier pier shaft and solid pier pier construction method
CN114214954A (en) * 2021-12-23 2022-03-22 广东科能工程管理有限公司 Construction method of municipal elevated bridge cast-in-situ pier
CN114214954B (en) * 2021-12-23 2023-08-25 广东科能工程管理有限公司 Construction method of municipal viaduct cast-in-situ pier
CN114561880A (en) * 2022-03-02 2022-05-31 中铁大桥局武汉桥梁特种技术有限公司 Method for modifying loading dock

Similar Documents

Publication Publication Date Title
CN203247506U (en) Bridge high-pier construction creeping formwork internal formwork lifting frame
CN105926448B (en) A kind of construction method of the Cable stayed Bridge Main Tower in the double rope faces of the only tower of curve
CN105113389B (en) Assembled type bridge pier column member with steel-concrete composite structure
CN102535845A (en) Construction method of bearing frame of corridor structure
CN102493341A (en) Construction method for hollow thin-walled high pier non-bracket formwork turnover of railway
CN105239510A (en) Dismounting beam support used for high pier small-radius curve cast-in-situ box beam and construction method
CN205025086U (en) Strength nature skeleton concrete beam construction suspend template in midair
CN103669224A (en) Method and steel pipe support for construction of arch tower of inclined arch tower double-cable-plane prestressed concrete cable-stayed bridge
CN104404887B (en) A kind of long-span steel pipe arch bridge is without support hoisting
CN103184722B (en) Large-span double-layer Bailey truss structure and construction method thereof
CN105862858B (en) Anchor head structure and its construction method being placed in anchored bolt retaining wall concrete slab
CN107905114A (en) A kind of construction method of large span Successive interference cancellation
CN103290784A (en) Arched beam combination bridge lifting construction method
CN106088131A (en) Armored concrete cross tower crane and construction method thereof
CN103410101B (en) Tower crane conversion method for construction of parabola-shaped ultrahigh pier
CN101666205B (en) Foundation pit escape ladder
CN102277836B (en) Construction method of tilting concrete tower base
CN206267031U (en) A kind of solid pier climbing support of bridge construction
CN207793884U (en) The steel frame construction of Sarasota upper king-post strut
CN212452263U (en) Pier stud reinforcing bar construction tower cage and construction structure
CN102691267A (en) High pier construction method for external whole operation platform
CN211666206U (en) Overhanging and landing dual-purpose scaffold
CN106284097B (en) The installation method that pier K is supportted on a kind of tubular arch bridge arch
CN210140771U (en) Construction work platform hoisting frame of high mound of bridge
CN201972095U (en) Chain block lifting platform for thin-walled hollow piers of bridges

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131023

Termination date: 20210428

CF01 Termination of patent right due to non-payment of annual fee