CN202755321U - Walking beam bottom working platform for strengthening cable-stayed bridge concrete box beam - Google Patents

Walking beam bottom working platform for strengthening cable-stayed bridge concrete box beam Download PDF

Info

Publication number
CN202755321U
CN202755321U CN201220444032.7U CN201220444032U CN202755321U CN 202755321 U CN202755321 U CN 202755321U CN 201220444032 U CN201220444032 U CN 201220444032U CN 202755321 U CN202755321 U CN 202755321U
Authority
CN
China
Prior art keywords
working platform
bridge
walking
walking beam
stayed bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201220444032.7U
Other languages
Chinese (zh)
Inventor
贺茂生
王业义
刘科
郝海峰
韩学伟
李旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC HIGHWAY MAINTENANCE ENGINEERING TECHNOLOGY Co Ltd
Original Assignee
CCCC HIGHWAY MAINTENANCE ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC HIGHWAY MAINTENANCE ENGINEERING TECHNOLOGY Co Ltd filed Critical CCCC HIGHWAY MAINTENANCE ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201220444032.7U priority Critical patent/CN202755321U/en
Application granted granted Critical
Publication of CN202755321U publication Critical patent/CN202755321U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a walking beam bottom working platform for strengthening a cable-stayed bridge concrete box beam. The working platform comprises a working platform body which comprises a plurality of hanger frames which are arranged on two sides of the working platform body in parallel and a bottom basket support, the hanger frames comprise vertical supports and bearing beams, and bottom ends of the hanger frames are connected with two ends of the bottom basket support; and walking systems are arranged on the inner sides on the upper portions of the hanger frames. The walking beam bottom working platform has the advantages that by aid of a novel structure design, in prior bridge strengthening construction, a prior bridge can be used, sufficient operation space is provided for beam bottom strengthening operation by arranging the walking beam bottom working platform, the platform can move horizontally along the walking direction of the bridge and can cross bridge floor stay cables and hanger rods to reach a next operation plane successfully, a scaffold is not needed to be erected or a bridge inspection van is not needed to be used in water or valleys, and the working platform is safe and efficient and economical and practical.

Description

A kind of cable stayed bridge concrete case beam is reinforced and is made platform with walking beam basic skill or training
Technical field
The utility model relates to a kind of cable stayed bridge concrete case beam reinforcing and makes platform with walking beam basic skill or training.
Background technology
Along with different types of rridges more and more appear in the middle of the productive life, the demand that bridge maintenance is reinforced also increases day by day, and the conditionally complete of the maintenance strengthening construction condition of existing bridge when newly-built is different.Reinforcing operation all constructs below the beam face, especially for the water Bridge or cross over the high-altitude bridge of cheuch, adopt conventional full framing or bridge detection vehicle operation, efficient is low, and cost is high, especially reinforces in the job execution at the bottom of the suspension cable beam, platform movement need stride across suspension cable, suspension rod, tear rope open, change rope, the links such as affixing steel plate, affixing carbon fabric, crack, defect mending, not only complex steps, and security performance and the actual effect of using are all had a greatly reduced quality.Therefore provide a kind of novel bridge maintenance strengthening construction platform, thereby overcome the above problems, imperative.
The utility model content
The purpose of this utility model is to provide a kind of cable stayed bridge concrete case beam to reinforce and makes platform with walking beam basic skill or training, on the basis of the basic function that satisfies existing bridge maintenance reinforcement platform, and security performance and the result of use of further Perfect the work platform.
The purpose of this utility model is to be achieved through the following technical solutions:
A kind of cable stayed bridge concrete case beam is reinforced and is made platform with walking beam basic skill or training, comprise the working platform body, described working platform body comprises the some suspension brackets that be arranged in parallel in both sides and end basket support, and described suspension bracket comprises vertical support frame and spandrel girder, and described suspension bracket bottom is connected with basket support two ends, the end; Described suspension bracket upper inner is provided with running gear.
Further, be equipped with raker beam between described vertical support frame and the spandrel girder and between described suspension bracket and the end basket support.
The beneficial effects of the utility model are: by the structure design of innovation, so that in existing Bridge repair and reinforcement construction, can utilize existing bridge, by being arranged in walking working platform at the bottom of the beam, provide enough working spaces for reinforcing operation at the bottom of the beam, platform can move horizontally along the bridge direction of traffic, can stride across bridge floor suspension cable and suspension rod, arrive smoothly the next scope of operation, and not need to set up in water or in the mountain valley scaffold or use bridge inspection vehicle, safe and efficient, economic and practical.
Description of drawings
The below is described in further detail the utility model with reference to the accompanying drawings.
Fig. 1 is that the described a kind of cable stayed bridge concrete case beam of the utility model embodiment is reinforced the structural representation of making platform with walking beam basic skill or training.
Among the figure:
1, suspension bracket; 2, running gear; 3, end basket support; 4, raker beam.
The specific embodiment
As shown in Figure 1, the described a kind of cable stayed bridge concrete case beam of the utility model embodiment is reinforced and is made platform with walking beam basic skill or training, comprise the working platform body, described working platform body comprises the some suspension brackets that be arranged in parallel 1 in both sides and end basket support 3, described suspension bracket 1 comprises vertical support frame and spandrel girder, and described suspension bracket 1 bottom is connected with basket support 3 two ends, the end; Described suspension bracket 1 upper inner is provided with running gear 2.Between described vertical support frame and the spandrel girder, and be provided with raker beam 4 between described suspension bracket 1 and the end basket support 3.
During concrete the use, form agent structure by suspension bracket 1, end basket support 3 and running gear 2, but running gear 2 can be arranged to the combination of walking dolly and track or the combination of other flexible motion; The every side in working platform upstream and downstream forms the suspension centre system by five suspension brackets, when the hanging basket reach needs to cross over suspension rod or suspension cable, removes suspension bracket spandrel girder, raker beam, after the load-bearing girder span is got over suspension rod, this spandrel girder, raker beam is installed again.Successively by suspension rod or suspension cable, whole hanging basket can arrive next operating area by suspension cable to other suspension bracket spandrel girder smoothly by that analogy.After the hanging basket walking put in place, bridge floor upstream and downstream suspension bracket spandrel girder carried out improving the hanging basket safety to drawing with wire rope.Basket leaves enough spaces apart from case beam base plate at the bottom of the hanging basket, for the operation of different types of rridges maintenance and reinforcement.
Working platform installation and the course of work during use are as follows:
1) at the bottom of bridge, hanging basket is assembled in placely, with crane hanging basket is winched to bridge floor, installation in position;
When 2) walking, run into suspension cable, open foremost suspension bracket spandrel girder and diagonal brace, utilize trailer system (hoist engine or Chain block) pulling hanging basket at the uniform velocity to move ahead in orbit.
3) after spandrel girder passes through suspension cable, install this spandrel girder and diagonal brace, open next root spandrel girder and diagonal brace, the rest may be inferred, until whole hanging basket passes through suspension cable.
4) after hanging basket walking puts in place, with smart prick screw-thread steel with hanging basket at the bottom of basket and case beam base plate hang and connect the safety of raising hanging basket.
5) after the hanging basket walking put in place, bridge floor upstream and downstream suspension bracket spandrel girder carried out improving the hanging basket safety to drawing with wire rope.
The utility model is not limited to above-mentioned preferred forms; anyone can draw other various forms of products under enlightenment of the present utility model; no matter but do any variation in its shape or structure; every have identical with a application or akin technical scheme, all drops within the protection domain of the present utility model.

Claims (3)

1. a cable stayed bridge concrete case beam is reinforced and is made platform with walking beam basic skill or training, comprise the working platform body, it is characterized in that: described working platform body comprises the some suspension brackets that be arranged in parallel in both sides (1) and end basket support (3), described suspension bracket (1) comprises vertical support frame and spandrel girder, and described suspension bracket (1) bottom is connected with end basket support (3) two ends; Described suspension bracket (1) upper inner is provided with running gear (2).
2. a kind of cable stayed bridge concrete case beam according to claim 1 is reinforced and is made platform with walking beam basic skill or training, it is characterized in that: be provided with raker beam (4) between described vertical support frame and the spandrel girder.
3. a kind of cable stayed bridge concrete case beam according to claim 1 is reinforced and is made platform with walking beam basic skill or training, it is characterized in that: be provided with raker beam (4) between described suspension bracket (1) and the end basket support (3).
CN201220444032.7U 2012-08-31 2012-08-31 Walking beam bottom working platform for strengthening cable-stayed bridge concrete box beam Expired - Lifetime CN202755321U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201220444032.7U CN202755321U (en) 2012-08-31 2012-08-31 Walking beam bottom working platform for strengthening cable-stayed bridge concrete box beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201220444032.7U CN202755321U (en) 2012-08-31 2012-08-31 Walking beam bottom working platform for strengthening cable-stayed bridge concrete box beam

Publications (1)

Publication Number Publication Date
CN202755321U true CN202755321U (en) 2013-02-27

Family

ID=47734510

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201220444032.7U Expired - Lifetime CN202755321U (en) 2012-08-31 2012-08-31 Walking beam bottom working platform for strengthening cable-stayed bridge concrete box beam

Country Status (1)

Country Link
CN (1) CN202755321U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103938555A (en) * 2014-04-28 2014-07-23 昆明理工大学 Method for designing prestress adjustable support for detecting and strengthening

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103938555A (en) * 2014-04-28 2014-07-23 昆明理工大学 Method for designing prestress adjustable support for detecting and strengthening
CN103938555B (en) * 2014-04-28 2016-03-30 昆明理工大学 A kind of method for designing detecting reinforcing prestressing force adjustable support

Similar Documents

Publication Publication Date Title
CN101514586B (en) Hanger rail type electric hanging boat and construction method thereof
CN202881852U (en) Suspension bridge cable installation system
CN202273179U (en) High-altitude steel cable suspended working platform for construction and maintenance on outer side of bridge box girder
CN205223872U (en) Drag and hang novel string of basket structure of convolution
CN202751338U (en) Rail type suspension basket
CN102134833B (en) Construction method for hoisting and disassembling bailey truss
CN105780646A (en) Bridge overhauling equipment capable of automatically walking
CN101481903B (en) Method for constructing hilly region rope-suspension bridge main beam by span cable supported crane assembling
CN101935984A (en) Traveling device of frame beam crane of steel truss girder of cable-stayed bridge and use method thereof
CN202202800U (en) Ropeladder used for lateral tensioning of T-shaped girder
CN102758404A (en) Front fulcrum hanging basket travelling device of spatial V-shaped cable-stayed bridge
CN204418013U (en) Bridge flange plate is constructed self-propelled cantilever hanging basket
CN202755321U (en) Walking beam bottom working platform for strengthening cable-stayed bridge concrete box beam
CN103654610A (en) Rail type hanging basket
CN104452594A (en) Multi-support cable guide method cable replacement device
CN102926330B (en) Installation method of hanging basket suitable for bridge construction
CN210529487U (en) Bridge and box-shaped bridge inspection device with flange plates
CN106320190A (en) Platform of bridge maintenance, consolidation and suspension construction
CN203947413U (en) A kind of bridge top chord check car
CN203307735U (en) Pulley combined type aerial work platform for bridge detection
CN102009929A (en) Movably-assembled anti-collision bridge wall construction hanging basket
CN205276727U (en) Metal roofing inner panel construction and installation platform
CN204185146U (en) Construction of Steel Structure overhang crane between skyscraper two tall buildings
CN211368350U (en) Protector for composite beam cable-stayed bridge
CN202790959U (en) Steel pipe truss structure based on aloft lateral support

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20130227

CX01 Expiry of patent term