CN202745385U - Pouring chute for concrete - Google Patents

Pouring chute for concrete Download PDF

Info

Publication number
CN202745385U
CN202745385U CN 201220388697 CN201220388697U CN202745385U CN 202745385 U CN202745385 U CN 202745385U CN 201220388697 CN201220388697 CN 201220388697 CN 201220388697 U CN201220388697 U CN 201220388697U CN 202745385 U CN202745385 U CN 202745385U
Authority
CN
China
Prior art keywords
chute
bar
support
chute body
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220388697
Other languages
Chinese (zh)
Inventor
王庆勇
孟晓宏
吴坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Group Co ltd
Original Assignee
China 19th Metallurgical Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 19th Metallurgical Group Co ltd filed Critical China 19th Metallurgical Group Co ltd
Priority to CN 201220388697 priority Critical patent/CN202745385U/en
Application granted granted Critical
Publication of CN202745385U publication Critical patent/CN202745385U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a concrete pour chute belongs to civil engineering construction equipment technical field. The concrete pouring chute can effectively reduce manpower and reduce labor intensity of operators. The pouring chute comprises a chute body and a supporting structure, the cross section of the chute body is of a U-shaped structure, and the rear end of the chute body of the U-shaped structure is higher than the front end of the chute body through the supporting structure.

Description

A kind of concrete build chute
Technical field
The utility model relates to a kind of chute of building of concrete, belongs to the civil engineering equipment technical field.
Background technology
In the middle of present construction, if the place confined space of wanting to build is limited, concrete tank car and pouring location have a segment distance, when concrete can not directly reach pouring location from tank car, it is general that what adopt all is that skip car pushes away concrete or carries concrete with keg and build, so need a large amount of manpowers, and need the time also long, from but cost increase and prolong the duration.
The utility model content
Technical problem to be solved in the utility model is: provide a kind of and can effectively reduce manpower, reduce labor intensity of operating staff concrete build chute.
For solving the problems of the technologies described above the technical scheme that adopts be: a kind of concrete build chute, comprise chute body and braced structures, the cross section of described chute body is U-shaped structure, the chute body of U-shaped structure makes its rear end be higher than front end by braced structures.
Further be to comprise that also universal wheel, universal wheel are installed in the lower end of braced structures.
Further be, the chute body comprises skeleton and chute plate, skeleton is made of frame rod and the U-shaped brace rod that is installed on the frame rod, and chute plate is by being installed in the chute body that consists of U-shaped structure in the U-shaped brace rod, and the upper end of braced structures is connected with the chute body by frame rod.
Further be, braced structures is by interconnective support front bar and support rear bar and consist of, and supports the lower end that front bar and each root support rear bar at each root and is separately installed with described universal wheel, supports front bar and is connected rear bar and is connected with the chute body by the upper end.
The optimal way of such scheme is to support front bar and support rear bar interconnecting by horizontal support bar.
Further be, supporting rear bar is made of fixed bar and the expansion link that is socketed on the fixed bar, correspondingly on fixed bar and expansion link be provided with Telescopic Fixed hole, in fixing hole, be plugged with regulating pin, support the logical lower end of keeping fixed bar of rear bar and be connected with universal wheel, the upper end by expansion link is connected with frame rod.
Further be, supporting the expansion link of front bar and support rear bar is made by steel pipe respectively, be provided with shank with supporting front bar and the place of adapting, expansion link position on the chute body, the chute body inserts the support front bar by shank respectively is connected the upper end and is connected with braced structures with the expansion link steel pipe.
The beneficial effects of the utility model are: by the chute body that a cross section is set is U-shaped structure, then by described support construction supports to the concrete delivery outlet of tank car and need to build between the place of concrete, and make the rear end of chute body be higher than front end.Like this, when the concrete in the tank car being poured into to build the place of concrete the time, only need make the interior concrete of tank car flow to the lower of front end with Action of Gravity Field from the eminence of rear end along the U-shaped structure of chute body, and enter the place that need to build concrete and get final product, unlike existing construction, need to adopt trolley transhipment or keg to extract transhipment like that by manpower, time-consuming, effort, and labour intensity is large, thereby has reduced manpower, has reduced operating personnel's intensity.Reduce the purpose that the duration is known in the cost contracting from reaching.
Description of drawings
Fig. 1 is the structural representation of building chute of a kind of concrete of the utility model.
Be labeled as among the figure: chute body 1, braced structures 2, universal wheel 3, skeleton 4, chute plate 5, frame rod 6, U-shaped brace rod 7, support front bar 8, support rear bar 9, horizontal support bar 10, fixed bar 11, expansion link 12, fixing hole 13, regulating pin 14, shank 15.
The specific embodiment
That a kind of that the utility model provides can effectively reduce manpower as shown in Figure 1, reduce labor intensity of operating staff concrete build chute.The described chute of building comprises chute body 1 and braced structures 2, and the cross section of described chute body 1 is U-shaped structure, and the chute body 1 of U-shaped structure makes its rear end be higher than front end by braced structures 2.By the above-mentioned chute body 1 that a cross section is set is U-shaped structure, then support to the concrete delivery outlet of tank car by described braced structures 2 and need to build between the place of concrete, and make the rear end of chute body 1 be higher than front end.Like this, when the concrete in the tank car being poured into to build the place of concrete the time, only need make the interior concrete of tank car flow to the lower of front end with Action of Gravity Field from the eminence of rear end along the U-shaped structure of chute body 1, and enter the place that need to build concrete and get final product, unlike existing construction, need to adopt trolley transhipment or keg to extract transhipment like that by manpower, time-consuming, effort, and labour intensity is large, thereby has reduced manpower, has reduced operating personnel's intensity.Reduce the purpose that the duration is known in the cost contracting from reaching.In the above-mentioned embodiment, for convenient described the build movement of chute and the position adjustment in the casting process, in the lower end of braced structures 2 universal wheel 3 is installed also.
In order to simplify the structure of building chute, reduce manufacturing, use and maintenance cost, described chute body 1 comprises skeleton 4 and chute plate 5, skeleton 4 is made of frame rod 6 and the U-shaped brace rod 7 that is installed on the frame rod 6, chute plate 5 is by being installed in the chute body 1 of the U-shaped structure of U-shaped brace rod 7 interior formations, and the upper end of braced structures 2 is connected with chute body 1 by frame rod 6; Braced structures 2 is by interconnective support front bar 8 and support rear bar 9 and consist of, and supports the lower end that front bar 8 and each root support rear bar 9 at each root and is separately installed with described universal wheel 3, supports front bar 8 and is connected rear bar 9 and is connected with chute body 1 by the upper end; And support front bar (8) and support rear bar 9 and interconnect by horizontal support bar 10.
Further, for in use, the convenient inclined degree of regulating chute body 1, be beneficial to accelerate the concrete in the tank car is poured into the place that need to build concrete by building chute, improve and build efficient, support rear bar 9 of the present utility model is made of fixed bar 11 and the expansion link 12 that is socketed on the fixed bar 11, correspondingly on fixed bar 11 and expansion link 12 be provided with Telescopic Fixed hole 13, in fixing hole 13, be plugged with regulating pin 14, support the rear bar 9 logical lower ends of keeping fixed bar 11 and be connected with universal wheel 3, the upper end by expansion link 12 is connected with skeleton 6 bars.Like this, in the time of regulating the inclined degree of chute body 1, only need the high virtue of adjustable telescopic rod 12 to get final product, easy to adjust quick.
In the above-mentioned embodiment, for convenient described chute the depositing and transporting when not using of building, and in use, can assemble fast, the expansion link 12 of described support front bar 8 and support rear bar 9 is made by steel pipe respectively, be provided with shank 15 with supporting front bar 8 and the place of adapting, expansion link 12 position on chute body 1, chute body 1 inserts support front bars 8 by shank 15 respectively is connected the upper end of steel pipe and is connected with braced structures 2 with expansion link.

Claims (7)

  1. A concrete build chute, it is characterized in that: comprise chute body (1) and braced structures (2), the cross section of described chute body (1) is U-shaped structure, the chute body (1) of U-shaped structure makes its rear end be higher than front end by braced structures (2).
  2. A kind of concrete according to claim 1 build chute, it is characterized in that: also comprise universal wheel (3), universal wheel (3) is installed in the lower end of braced structures (2).
  3. 3. a kind of concrete according to claim 2 builds chute, it is characterized in that: chute body (1) comprises skeleton (4) and chute plate (5), skeleton (4) is made of frame rod (6) and the U-shaped brace rod (7) that is installed on the frame rod (6), chute plate (5) is by being installed in the chute body (1) that consists of U-shaped structure in the U-shaped brace rod (7), and the upper end of braced structures (2) is connected with chute body (1) by frame rod (6).
  4. 4. a kind of concrete according to claim 2 builds chute, it is characterized in that: braced structures (2) is by interconnective support front bar (8) and support rear bar (9) formation, support the lower end that front bar (8) and each root support rear bar (9) at each root and be separately installed with described universal wheel (3), support front bar (8) be connected rear bar (9) and be connected with chute body (1) by the upper end.
  5. A kind of concrete according to claim 4 build chute, it is characterized in that: support front bar (8) and support rear bar (9) interconnecting by horizontal support bar (10).
  6. 6. a kind of concrete according to claim 4 builds chute, it is characterized in that: support rear bar (9) by fixed bar (11) and be socketed in expansion link (12) formation on the fixed bar (11), in the upper corresponding Telescopic Fixed hole (13) that is provided with of fixed bar (11) and expansion link (12), in fixing hole (13), be plugged with regulating pin (14), support the lower end of rear bar (9) by fixed bar (11) and be connected with universal wheel (3), the upper end by expansion link (12) is connected with skeleton (6) bar.
  7. 7. a kind of concrete according to claim 6 builds chute, it is characterized in that: the expansion link (12) that supports front bar (8) and support rear bar (9) is made by steel pipe respectively, be provided with shank (15) with supporting front bar (8) and expansion link (12) place of adapting, position in that chute body (1) is upper, chute body (1) is connected 12 by shank (15) insertion support front bar (8) with expansion link respectively) upper end of steel pipe is connected with braced structures (2).
CN 201220388697 2012-08-07 2012-08-07 Pouring chute for concrete Expired - Lifetime CN202745385U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220388697 CN202745385U (en) 2012-08-07 2012-08-07 Pouring chute for concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220388697 CN202745385U (en) 2012-08-07 2012-08-07 Pouring chute for concrete

Publications (1)

Publication Number Publication Date
CN202745385U true CN202745385U (en) 2013-02-20

Family

ID=47704804

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220388697 Expired - Lifetime CN202745385U (en) 2012-08-07 2012-08-07 Pouring chute for concrete

Country Status (1)

Country Link
CN (1) CN202745385U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103266613A (en) * 2013-04-17 2013-08-28 中天建设集团有限公司 Large-scale chute device for casting mass concrete in deep foundation pit
CN103541306A (en) * 2013-09-30 2014-01-29 江苏省交通工程集团有限公司 Detachable adjustable and movable sliding chute
CN108894507A (en) * 2018-08-13 2018-11-27 武汉冶建筑安装工程有限责任公司 Adjustable concrete pours chute device
CN109797747A (en) * 2019-01-29 2019-05-24 国网山东省电力公司建设公司 A kind of chute poured for Transmission Line Iron-tower Base

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103266613A (en) * 2013-04-17 2013-08-28 中天建设集团有限公司 Large-scale chute device for casting mass concrete in deep foundation pit
CN103541306A (en) * 2013-09-30 2014-01-29 江苏省交通工程集团有限公司 Detachable adjustable and movable sliding chute
CN108894507A (en) * 2018-08-13 2018-11-27 武汉冶建筑安装工程有限责任公司 Adjustable concrete pours chute device
CN109797747A (en) * 2019-01-29 2019-05-24 国网山东省电力公司建设公司 A kind of chute poured for Transmission Line Iron-tower Base

Similar Documents

Publication Publication Date Title
CN101929249B (en) Double line stream-line type round end entity pier cap steel bar overall binding construction method
CN203961992U (en) Portable full framing chassis
CN202745385U (en) Pouring chute for concrete
CN202544854U (en) Lining trolley for subway station
CN203475790U (en) Hydraulic lifting-type building scaffold
CN201786031U (en) Slip-formed concrete distributing bin device
CN205421940U (en) Concrete spreader
CN204717144U (en) A kind of concrete pump pipe setting tool cribbing
CN204644976U (en) A kind of easily mounting or dismounting pin-connected panel gutter
CN206554500U (en) Steel structure concrete, which is poured, uses adjustable transverse support bar
CN106284989B (en) The sliding form bracing system of double track and complete construction method
CN108005114A (en) A kind of piping lane pours mould
CN207775925U (en) A kind of piping lane pours mold
CN201367730Y (en) A die plate supporting device convenient for dismounting die plates
CN206299163U (en) Mobile reinforcement processes factory building
CN202990407U (en) Quick-release scaffold
CN205132926U (en) Special well word hoist of hydroelectric set tail water ell
CN204357118U (en) Form removal bracing frame behind a kind of beam slab ater-casting
CN203100853U (en) Foundation-free trunk scale
CN203514751U (en) Convenient-to-move scaffold for building interior wall construction
CN208122325U (en) A kind of assembled architecture Liftable type material distributing machine
CN208310404U (en) Unit type suspended moso bamboo ecological enclosing wall
CN201401013Y (en) Silo pump pumping concrete dividing hopper in slipform construction
CN105490233A (en) Highway crossing device for wire
CN206386131U (en) A kind of ditch cable trench formwork jumbo of significantly adjustment width

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20130220

CX01 Expiry of patent term