CN202744906U - Concrete pouring equipment of ballastless track bed plate - Google Patents

Concrete pouring equipment of ballastless track bed plate Download PDF

Info

Publication number
CN202744906U
CN202744906U CN 201220297440 CN201220297440U CN202744906U CN 202744906 U CN202744906 U CN 202744906U CN 201220297440 CN201220297440 CN 201220297440 CN 201220297440 U CN201220297440 U CN 201220297440U CN 202744906 U CN202744906 U CN 202744906U
Authority
CN
China
Prior art keywords
bed plate
concrete
truss
track bed
ballastless track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220297440
Other languages
Chinese (zh)
Inventor
许爱军
许爱峻
周卫霞
高峰
贾常志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd filed Critical First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority to CN 201220297440 priority Critical patent/CN202744906U/en
Application granted granted Critical
Publication of CN202744906U publication Critical patent/CN202744906U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model relates to concrete pouring equipment of a ballastless track bed plate. The concrete pouring equipment comprises a truss, a walking device capable of walking on a protective wall for positioning is arranged at the lower part of one side of the truss, two rubber wheels capable of walking on a beam surface are arranged at the bottom of the other side of the truss, a concrete chute capable of leading the concrete to flow in a pouring position is arranged in the middle of the truss, and two discharge outlets are arranged on the concrete chute. According to the concrete pouring equipment of the ballastless track bed plate, the construction progress of the bed plate is greatly improved, teams using large equipment can be reduced, the labor cost can be lowered, the construction cost can be lowered, and the bed plate concrete construction quality can be effectively controlled.

Description

A kind of unballasted track bed plate concrete placing installation
Technical field
The utility model relates to a kind of unballasted track bed plate concrete placing installation
Background technology
Along with developing rapidly of the infrastructure projects such as China's high speed high-speed railway, the non-fragment orbit engineering is more and more, and unballasted track bed plate is the critical process of guaranteeing ballastless track bed board construction quality and the operation of non-fragment orbit later stage.Existing bed plate concrete placing installation exists efficiency of construction low, and construction cost is large, the concrete construction quality problem such as be difficult to be effectively controlled, and the equipment of building of inventing a kind of simple and effective seems particularly important.
The utility model content
The purpose of this utility model is exactly defective and the deficiency that exists for solving above-mentioned prior art, and a kind of quick, easy, efficient, unballasted track bed plate concrete placing installation of guaranteeing the quality is provided.
The technical scheme that adopts is:
A kind of unballasted track bed plate concrete placing installation, comprise truss, one side lower part of truss arranges one can be at protecting wall walking home row walking apparatus, the opposite side of truss bottom is equiped with two rubber tires can walking at the beam face, be provided with one at the truss middle part and supply concrete to flow into the concrete chute of building the position, at the concrete chute two feed openings are set.
The utility model has improved the bed plate construction speed greatly, has reduced main equipment and has used machine-team, has reduced labour cost, has reduced construction cost, can effectively control the bed plate concrete construction quality.
Description of drawings:
Fig. 1 is structural representation of the present utility model.
Fig. 2 is the left view of Fig. 1.
Specific embodiment
A kind of unballasted track bed plate concrete placing installation, comprise truss 1, one side lower part of truss 1 arranges one can be at protecting wall walking home row walking apparatus 4, the opposite side of truss 1 bottom is equiped with two rubber tires 5 can walking at the beam face, be provided with one at truss 1 middle part and supply concrete to flow into the concrete chute 2 of building the position, at concrete chute 2 two feed openings 3 are set.

Claims (1)

1. unballasted track bed plate concrete placing installation, comprise truss (1), a side lower part that it is characterized in that described truss (1) arranges one can be at the running gear (4) of protecting wall walking location, the opposite side of truss (1) bottom is equiped with two rubber tires (5) that can walk at the beam face, be provided with one at truss (1) middle part and supply concrete to flow into the concrete chute (2) of building the position, at concrete chute (2) two feed openings (3) are set.
CN 201220297440 2012-06-19 2012-06-19 Concrete pouring equipment of ballastless track bed plate Expired - Lifetime CN202744906U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220297440 CN202744906U (en) 2012-06-19 2012-06-19 Concrete pouring equipment of ballastless track bed plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220297440 CN202744906U (en) 2012-06-19 2012-06-19 Concrete pouring equipment of ballastless track bed plate

Publications (1)

Publication Number Publication Date
CN202744906U true CN202744906U (en) 2013-02-20

Family

ID=47704330

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220297440 Expired - Lifetime CN202744906U (en) 2012-06-19 2012-06-19 Concrete pouring equipment of ballastless track bed plate

Country Status (1)

Country Link
CN (1) CN202744906U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103510435A (en) * 2012-06-19 2014-01-15 中铁十九局集团第一工程有限公司 Concrete pouring device for ballastless track base board
CN103541306A (en) * 2013-09-30 2014-01-29 江苏省交通工程集团有限公司 Detachable adjustable and movable sliding chute

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103510435A (en) * 2012-06-19 2014-01-15 中铁十九局集团第一工程有限公司 Concrete pouring device for ballastless track base board
CN103541306A (en) * 2013-09-30 2014-01-29 江苏省交通工程集团有限公司 Detachable adjustable and movable sliding chute

Similar Documents

Publication Publication Date Title
CN104562863B (en) A kind of dual-purpose railway two-orbit
CN106702834A (en) Midline deviation rectifying method for sedimentary offset ballastless track
CN202480217U (en) Whole mouldboard of combined box girder
CN202744906U (en) Concrete pouring equipment of ballastless track bed plate
CN203531924U (en) Lifting type moving trolley provided with tracks, wheels and templates
CN203319248U (en) Automatic plate feeder
CN205000978U (en) Open type overlength tunnel concrete placement device
CN202945576U (en) Overall movement template device for subgrade drainage ditch construction
CN202964885U (en) Means for layout of split-type sleeper production line
CN207974520U (en) Double slope concrete regularization sliding moulds that incline
CN203127962U (en) Material transportation device for hot blast stove
CN206299163U (en) Mobile reinforcement processes factory building
CN202881928U (en) Sludge soft foundation solidifying machine
CN202702384U (en) Automatic circulating production system for wall plates
CN205934616U (en) A device for transportation of secret factory building driving rail
CN205127618U (en) Circulation sprays grid tray formula dust device
CN103510435A (en) Concrete pouring device for ballastless track base board
CN204059115U (en) For pouring into the template of non-fragment orbit self-compacting concrete layer
CN203702187U (en) Tunnel waterproof plate laying trolley
CN202878469U (en) Double-block type sleeper production line concrete delivery device
CN202882946U (en) Movable module used along with tunnel heightening section heightening template trolley
CN203371682U (en) Conveying device of horizontal solar foaming production line
CN202625204U (en) Chain disconnection preventing structure for scraper
CN204170652U (en) A kind of travelling mixer
CN203512669U (en) Walking mechanism of apron conveyor

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20130220

CX01 Expiry of patent term