CN202117341U - Template for embedding foundation bolts of steel structures of buildings - Google Patents

Template for embedding foundation bolts of steel structures of buildings Download PDF

Info

Publication number
CN202117341U
CN202117341U CN2011201931695U CN201120193169U CN202117341U CN 202117341 U CN202117341 U CN 202117341U CN 2011201931695 U CN2011201931695 U CN 2011201931695U CN 201120193169 U CN201120193169 U CN 201120193169U CN 202117341 U CN202117341 U CN 202117341U
Authority
CN
China
Prior art keywords
steel plate
template
steel
foundation bolts
embedding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011201931695U
Other languages
Chinese (zh)
Inventor
张彦卿
耿惠堂
邓荣江
王彦彬
侯永忠
赵宪勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei No2 Construction Engineering Co
Original Assignee
Hebei No2 Construction Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei No2 Construction Engineering Co filed Critical Hebei No2 Construction Engineering Co
Priority to CN2011201931695U priority Critical patent/CN202117341U/en
Application granted granted Critical
Publication of CN202117341U publication Critical patent/CN202117341U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a template for embedding foundation bolts of steel structures of buildings, which comprises a flat plate type steel plate, wherein a casting opening is arranged at the center of the steel plate, and the frame of the steel plate is provided with bolt holes for connecting the foundation bolts in penetrating mode. The steel plate is a rectangular flat plate, and the casting opening is a square with a 200-milimeter width and a 400-milimeter length. A center line for calibration is scored on the surface of the steel plate. The template for embedding foundation bolts of steel structures of buildings serves as a special template to be applied to construction of steel structure main bodies and concrete independent foundations, and not only can enable embedding of the foundation bolts to be accurate, but also is convenient to mount and reusable, thereby facilitating improvement of embedding quality of the foundation bolts of the structural engineering with small input.

Description

The template that the construction steel structure stone bolt is buried underground
Technical field
The utility model relates to a kind of a kind of template of burying underground of building engineering construction design field, particularly a kind ofly is used for the template that the construction steel structure stone bolt is buried underground.
Background technology
In building operations, concrete foundation and steel work main body are composite entities indispensable in the construction project, and be especially common in industrial premises, warehouse and commerce and trade building.Mix on the earth basis in order to be installed in the steel work main body, need before concrete foundation is built, preset a large amount of stone bolt.After completion was built, the lower end of stone bolt was embedded on the concrete foundation, and the upper end is then stretched out the upper surface of concrete foundation and passed the bolt hole that presets on the steel work main body, and concrete foundation and steel work main body are coupled together.Because the construction of concrete foundation need be by the steel bar framework of horizontal and vertical colligations such as reinforcing bar and the support shuttering that is erected at the steel bar framework both sides; Stone bolt is then mostly to be to adopt the method for welding or colligation that stone bolt is fixed the position by steel bar framework, carries out concrete building afterwards again.Mostly welding or colligation are to link with the reinforcing bar on basis, for example be welded on the vertical reinforcement of concrete foundation or colligation on vertical reinforcement and stirrup, be convenient to definite steel work stone bolt position.But the hole that is used to wear stone bolt on the steel work generally uses the machine drilling mode to confirm already in processing factory; Therefore must guarantee that when burying the steel work stone bolt underground the position of each stone bolt is accurate, the requirement that this is just high to being fixed with of every stone bolt.
Use the fixed form of colligation, although it has easy operating and the advantage that can often adjust, its solidness is not enough, and the displacement that bumps easily needs the running check correction to fix; Weld and use; Because stone bolt is general and the diameter difference distance of reinforcing bar is bigger, therefore also higher to welder's technical requirements, though welding is relatively firm; But the reinforcing bar that links to each other with it is when making colligation; With the link of ground be not immovable, in case the displacement that bumps after the machine-shaping can only be proofreaied and correct welding again with weld cutting.This has just caused the intensity heavy losses of reinforcing bar, and this is unconformable in construction.
The utility model content
The utility model technical issues that need to address provide a kind of stone bolt that not only can make and bury template accurate, easy for installation, that can reusable construction steel structure stone bolt bury underground underground.
For solving the problems of the technologies described above, the technical scheme that the utility model adopted is:
The template that the construction steel structure stone bolt is buried underground comprises plate steel plate, and the center of steel plate is provided with and builds mouth, and the frame of steel plate is provided with the bolt hole that is used for the cross-under stone bolt.
The further improvement of the utility model is: said steel plate is the rectangular flat plate of thickness greater than 8mm, builds mouth and is set to width 200mm, and length is square greater than 400mm's.
The further improvement of the utility model is: the surface delineation of said steel plate has the center line of calibration usefulness.
Because the technological progress of having adopted technique scheme, the utility model to obtain is:
The utility model in use; Stone bolt is passed bolt hole and is fixed on the template; During concreting the support shuttering of template and concrete foundation is fixed; By center line on the steel plate and measuring apparatus calibration positioning stone bolt, after concrete setting, get final product stripping and be used for next flowing water construction.Thickness that is provided with and the size of building mouth more help guaranteeing working strength and pouring quality.
The utility model is applied to as dedicated templates in the construction of steel work main body and concrete foundation (or other bases) stone bolt is buried underground accurately; And easy for installation, can reuse, the stone bolt that helps improving with less input structural steelwork is buried quality underground.
Description of drawings
Fig. 1 is the structural representation of the utility model.
Wherein, 1. steel plate is 2. built mouth, 3. bolt hole.
The specific embodiment
Below in conjunction with accompanying drawing the utility model is explained further details:
The template that a kind of building structure stone bolt as shown in Figure 1 is buried underground; The steel plate 1 that the matrix adopting of template is plate, the centre of steel plate has width 200mm, and length is greater than the square mouth 2 of building of 400mm; Steel plate frame position on demand is drilled with bolt hole 3, and steel plate thickness is greater than 8mm.The surface delineation center line of steel plate.
The utility model is applied in the construction of steel work main body and concrete foundation (or other bases); The stone bolt of during construction need being buried underground is through in the bolt hole of steel plate; The stone bolt that passes steel plate is provided with a nut in the both sides up and down of steel plate on each, and on fasten, after accomplishing concrete foundation (or other bases) reinforcing bar binding, support shuttering and installing; Steel plate is fixed on the concrete support shuttering; Make stone bolt be able to the location, can also cooperate transit and level gauge to check the position by the center line of delineating on the steel plate.

Claims (3)

1. the template buried underground of construction steel structure stone bolt, it is characterized in that: comprise plate steel plate (1), the center of steel plate is provided with builds mouthful (2), and the frame of steel plate is provided with the bolt hole (3) that is used for the cross-under stone bolt.
2. the template that construction steel structure stone bolt according to claim 1 is buried underground is characterized in that: said steel plate is the rectangular flat plate of thickness greater than 8mm, builds mouth and is set to width 200mm, and length is square greater than 400mm's.
3. the template that construction steel structure stone bolt according to claim 1 and 2 is buried underground is characterized in that: the surface delineation of said steel plate (1) has the center line of calibration usefulness.
CN2011201931695U 2011-06-09 2011-06-09 Template for embedding foundation bolts of steel structures of buildings Expired - Fee Related CN202117341U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201931695U CN202117341U (en) 2011-06-09 2011-06-09 Template for embedding foundation bolts of steel structures of buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201931695U CN202117341U (en) 2011-06-09 2011-06-09 Template for embedding foundation bolts of steel structures of buildings

Publications (1)

Publication Number Publication Date
CN202117341U true CN202117341U (en) 2012-01-18

Family

ID=45458415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201931695U Expired - Fee Related CN202117341U (en) 2011-06-09 2011-06-09 Template for embedding foundation bolts of steel structures of buildings

Country Status (1)

Country Link
CN (1) CN202117341U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102619235A (en) * 2012-04-17 2012-08-01 中国建筑第五工程局有限公司 Concrete foundation embedded bolt bracket and embedding method for concrete foundation embedded bolts
CN102797360A (en) * 2012-08-06 2012-11-28 华为技术有限公司 Positioning template used in cabinet installation
CN106352776A (en) * 2016-09-27 2017-01-25 中铁五局集团有限公司 Tool plate for embedded bolt assembly installation and checking
CN109853610A (en) * 2019-01-30 2019-06-07 山西三建集团有限公司 Steel pipe column concrete foundation pre-embedded anchoring bolts precise positioning mechanism and localization method
CN112127641A (en) * 2020-08-28 2020-12-25 上海二十冶建设有限公司 Accurate fixing method for anchor plate foundation bolt
CN113802697A (en) * 2021-08-31 2021-12-17 中冶(上海)钢结构科技有限公司 Machining and embedding method for steel structure embedded part in dense steel bar area
CN114809673A (en) * 2022-05-08 2022-07-29 山西三建集团有限公司 Rear-buried foundation bolt suspension positioning method in street lamp concrete foundation pouring

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102619235A (en) * 2012-04-17 2012-08-01 中国建筑第五工程局有限公司 Concrete foundation embedded bolt bracket and embedding method for concrete foundation embedded bolts
CN102797360A (en) * 2012-08-06 2012-11-28 华为技术有限公司 Positioning template used in cabinet installation
CN102797360B (en) * 2012-08-06 2016-08-10 华为技术有限公司 The locating template that a kind of rack is installed
CN106352776A (en) * 2016-09-27 2017-01-25 中铁五局集团有限公司 Tool plate for embedded bolt assembly installation and checking
CN109853610A (en) * 2019-01-30 2019-06-07 山西三建集团有限公司 Steel pipe column concrete foundation pre-embedded anchoring bolts precise positioning mechanism and localization method
CN112127641A (en) * 2020-08-28 2020-12-25 上海二十冶建设有限公司 Accurate fixing method for anchor plate foundation bolt
CN113802697A (en) * 2021-08-31 2021-12-17 中冶(上海)钢结构科技有限公司 Machining and embedding method for steel structure embedded part in dense steel bar area
CN114809673A (en) * 2022-05-08 2022-07-29 山西三建集团有限公司 Rear-buried foundation bolt suspension positioning method in street lamp concrete foundation pouring

Similar Documents

Publication Publication Date Title
CN202117341U (en) Template for embedding foundation bolts of steel structures of buildings
CN204054323U (en) Steel construction assembled beam making bench
CN102926504B (en) Construction method of steel and concrete overlapped beam combined part
CN108005401A (en) A kind of support and change method of the column of existing frame structure base isolation reinforcement
CN103334379A (en) Construction method for hanging part of anti-collision guardrail on expressway
CN207944708U (en) Assembled steel modular system for underground shear wall structure reverse construction
CN102518300A (en) Embedded conical bearing joint type steel structural support and construction method thereof
CN208733666U (en) A kind of fixing bolt preformed hole template tool
CN111218983A (en) Lattice formula structure concrete frame house
CN112302209B (en) Steel and concrete shear wall mixed structure and manufacturing method thereof
CN114215090A (en) Construction method of raft and compression pile in closed space
CN205296197U (en) Prefabricated cushion cap of anticorrosive industry factory building concrete rim of a cup formula
CN204173804U (en) A kind of inside-climbing tower crane of structural beams bearing-type is installed and climbing structure
CN111441513A (en) Cast-in-place concrete wall body combining truss reinforcing steel bars and steel plates and construction method
CN103132494A (en) Embedded anchor cone accurate positioning method
CN105275198B (en) A kind of shear-wall strengthening formwork structure and its construction method
CN201915420U (en) Foundation of temporary gate building
CN102454298B (en) Large-sized reinforced concrete construction of frame beam method
CN103898835B (en) The anti-back of the body of bridge draws load-bearing construction bracket and construction method
CN205224420U (en) Anticorrosive industry factory building precast concrete stand
CN209760295U (en) Pre-buried T type bolt fixed knot of underground pipe gallery electric power support constructs
CN113622328A (en) Box culvert construction assembly, application thereof and box culvert construction method
CN109826186B (en) General prefabricated reinforced concrete guide wall for underground diaphragm wall and implementation method
CN202323896U (en) Accurate positioning device for embedded anchor cone
CN112479027A (en) Gantry crane prefabricated foundation and installation method thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120118

Termination date: 20150609

EXPY Termination of patent right or utility model