CN201924089U - Aluminum electrolysis cell emergency short circuit power outage device - Google Patents

Aluminum electrolysis cell emergency short circuit power outage device Download PDF

Info

Publication number
CN201924089U
CN201924089U CN2010205040337U CN201020504033U CN201924089U CN 201924089 U CN201924089 U CN 201924089U CN 2010205040337 U CN2010205040337 U CN 2010205040337U CN 201020504033 U CN201020504033 U CN 201020504033U CN 201924089 U CN201924089 U CN 201924089U
Authority
CN
China
Prior art keywords
short circuit
bus
aluminum electrolysis
accident
short
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010205040337U
Other languages
Chinese (zh)
Inventor
阮绍勇
郭海龙
傅长宏
颜非亚
刘星桂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN2010205040337U priority Critical patent/CN201924089U/en
Application granted granted Critical
Publication of CN201924089U publication Critical patent/CN201924089U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Electrolytic Production Of Metals (AREA)

Abstract

The utility model discloses an aluminum electrolysis cell emergency short circuit power outage device. The device comprises a group of anode guide rods (1) which are connected with a cuboid bus bar (3) through a group of bus bar soft belts (2), and the cuboid bus bar (3) is connected with a short circuit block (5) through short circuit bus bar soft belts (4). During a cell leakage accident of an aluminum electrolysis cell, the device can serve as an emergency tool for the short circuit accident cell for a rapid power restoration of an aluminum electrolysis cell series within a short time, so as to minimize the influence of the cell leakage accident on production, and avoid the phenomenon that the breakdown of other aluminum electrolysis cells due to long-time power outage leads to larger loss.

Description

A kind of aluminium cell short circuit power cut device of meeting an urgent need
Technical field
The utility model relates to the emergent short circuit power cut device of a kind of aluminium cell, belongs to electrolyzer short circuit technology field.
Background technology
Electrolyzer is the major equipment of aluminium manufacturer.An electrolytic series generally is in series with more than 200 electrolyzer.When wherein an electrolyzer can not be kept ordinary production, its short circuit need be carried out large repairs so that withdraw to produce, be called and stop groove.The electrolyzer input energising operation of fixing greatly is called fluting.Electrolyzer is stopping groove and when fluting, generally all has the big electric current of kilo-amperes up to a hundred to be converted to the operation of another part bus from a part of bus.
Stop groove and relate to inside the plan groove and the groove that stops outside the plan of stopping.The inside the plan groove that stops is that brainchild stops groove and fluting and the time can allow whole pot line have a power failure or fell electric current about more than ten minutes, and the conversion operations of bus bar is finished in dismounting or the seal of busbar short-circuit mouth is installed.The groove that stops outside the plan is meant certain electrolyzer in the series bakie accident that meets accident, and the bus of rapid scour trough week of aluminium liquid that spills and ionogen and bottom land causes bus to thrust damage and haves no alternative but stop groove.
At present, take place outside the plan when stopping groove, must the have a power failure damage bus of this groove of repairing of pot line, generally impaired bus is electric current " the only way which must be passed ".Generally be to adopt the mode of welding of aluminum bus to rush to repair during repairing, purpose allows electric current recover through this circuit of short circuit mouth → this groove negative busbar → downstream slot riser bus bar → downstream slot anode, but because after the generation of on-the-spot bakie accident, work under bad environment danger, labour intensity is huge, repairing is difficulty quite, power off time long can influence the production run of other grooves, when serious even cause other groove " extremely groove ".
Summary of the invention
The purpose of this utility model is, a kind of aluminium cell short circuit power cut device of meeting an urgent need is provided.When aluminium cell generation bakie accident, as the Emergency Tool of short circuit accident groove, can allow interior the recovery rapidly of pot line short period of time switch on, make the bakie accident reduce to minimum to the influence of producing.
The technical solution of the utility model: a kind of aluminium cell short circuit power cut device of meeting an urgent need, constitute and comprise one group of anode rod, one group of anode rod is connected with the rectangular parallelepiped bus through one group of soft band of bus, and the rectangular parallelepiped bus is connected with short-circuit block through the soft band of short-circuit busbar.
In the emergent short circuit power cut device of aforesaid aluminium cell, described rectangular parallelepiped bus is provided with plural erection opening or hoisting ring.
Compared with prior art, the utility model is when aluminium cell generation bakie accident, can be used as the Emergency Tool of short circuit accident groove, allow interior the recovery rapidly of pot line short period of time switch on, make the bakie accident reduce to minimum to the influence of producing, and can avoid long-time the power failure to cause other electrolyzer " dead groove ", result in greater loss.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Being labeled as in the accompanying drawing: 1-anode rod, the soft band of 2-bus, 3-rectangular parallelepiped bus, the soft band of 4-short-circuit busbar, the 5-short-circuit block, 6-erection opening or hoisting ring, 7-accident groove riser bus bar, 8-accident groove positive bar, 9-accident groove balance bus, 10-downstream slot riser bus bar.
Embodiment
The utility model is described in further detail below in conjunction with drawings and Examples.
Embodiment.The utility model as shown in Figure 1, a kind of aluminium cell short circuit power cut device of meeting an urgent need constitutes and comprises that 1, one group of anode rod 1 of one group of anode rod is with 2 to be connected with rectangular parallelepiped bus 3 through one group of bus is soft, rectangular parallelepiped bus 3 is provided with plural erection opening or hoisting ring 6, so that lifting.Rectangular parallelepiped bus 3 is with 4 to be connected with short-circuit block 5 through short-circuit busbar is soft.
Working process of the present utility model
When in the pot line during certain platform trough generation bakie accident, the bus of rapid scour trough week of aluminium liquid that spills and ionogen and bottom land, cause the bus of groove week and bottom land to thrust damage, but the riser bus bar of this groove, positive bar, balance bus do not damage, by device of the present utility model, can allow electric current through accident groove riser bus bar 7, accident groove positive bar 8, accident groove balance bus 9 and device of the present utility model and 10 short circuits of downstream slot riser bus bar.
During concrete operations, available overhead traveling crane all proposes the positive bar 8 and the accident groove balance bus 9 of accident groove electricity output side earlier, lift this groove electricity output side that installs of the present utility model then, rectangular parallelepiped bus 3 is positioned on the operating surface pot shell side plate, anode rod 1 is fixed on the balance bus 9 by jig, the former short-circuit block that is fixed on the downstream slot riser bus bar 10 is alternative with the short-circuit block 5 of this device, finish the utility model Unit Installation.Can finish the short circuit operation of accident groove.The pot line operation of can resuming production rapidly.Every cell room is as long as several covers device of the present utility model of preparing can be tackled the bakie accident more.The utility model can be suitable for the electrolyzer of differing capacities, after the generation bakie accident, and can be to the rapid short circuit of accident groove.

Claims (2)

1. the emergent short circuit power cut device of an aluminium cell, it is characterized in that: formation comprises one group of anode rod (1), one group of anode rod (1) is connected with rectangular parallelepiped bus (3) through one group of soft band of bus (2), and rectangular parallelepiped bus (3) is connected with short-circuit block (5) through the soft band of short-circuit busbar (4).
2. the aluminium cell according to claim 1 short circuit power cut device of meeting an urgent need, it is characterized in that: described rectangular parallelepiped bus (3) is provided with plural erection opening or hoisting ring (6).
CN2010205040337U 2010-08-25 2010-08-25 Aluminum electrolysis cell emergency short circuit power outage device Expired - Lifetime CN201924089U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010205040337U CN201924089U (en) 2010-08-25 2010-08-25 Aluminum electrolysis cell emergency short circuit power outage device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010205040337U CN201924089U (en) 2010-08-25 2010-08-25 Aluminum electrolysis cell emergency short circuit power outage device

Publications (1)

Publication Number Publication Date
CN201924089U true CN201924089U (en) 2011-08-10

Family

ID=44427953

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010205040337U Expired - Lifetime CN201924089U (en) 2010-08-25 2010-08-25 Aluminum electrolysis cell emergency short circuit power outage device

Country Status (1)

Country Link
CN (1) CN201924089U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102677096A (en) * 2012-05-21 2012-09-19 中国铝业股份有限公司 Aluminium electrolytic cell emergency short-circuit bus
CN102953087A (en) * 2011-08-18 2013-03-06 贵阳铝镁设计研究院有限公司 Aluminum electrolytic end cell emergency short-circuit device
CN104674304A (en) * 2013-12-02 2015-06-03 贵阳铝镁设计研究院有限公司 Aluminum electrolytic cell emergency short circuit device
CN107893242A (en) * 2017-11-14 2018-04-10 中冶天工集团有限公司 The disconnection method of aluminium electroloysis central gangway bus

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102953087A (en) * 2011-08-18 2013-03-06 贵阳铝镁设计研究院有限公司 Aluminum electrolytic end cell emergency short-circuit device
CN102677096A (en) * 2012-05-21 2012-09-19 中国铝业股份有限公司 Aluminium electrolytic cell emergency short-circuit bus
CN102677096B (en) * 2012-05-21 2014-12-31 中国铝业股份有限公司 Aluminium electrolytic cell emergency short-circuit bus
CN104674304A (en) * 2013-12-02 2015-06-03 贵阳铝镁设计研究院有限公司 Aluminum electrolytic cell emergency short circuit device
CN104674304B (en) * 2013-12-02 2017-12-22 贵阳铝镁设计研究院有限公司 A kind of aluminium cell is met an urgent need short-circuiting means
CN107893242A (en) * 2017-11-14 2018-04-10 中冶天工集团有限公司 The disconnection method of aluminium electroloysis central gangway bus

Similar Documents

Publication Publication Date Title
CN201924089U (en) Aluminum electrolysis cell emergency short circuit power outage device
CN103904681B (en) High-power centralized parallel network power generation coordinated control system and method
CN104682431A (en) Self-starting method and self-starting system of energy storage converter
CN104242738A (en) Frequency conversion and energy saving control device and method for cluster well pumping units
CN204216804U (en) The distributed collecting and distributing frequency conversion control energy saving apparatus of cluster well oil extractor
CN102953087A (en) Aluminum electrolytic end cell emergency short-circuit device
CN202226937U (en) Emergency short-circuit device for aluminum electrolysis end socket cell
CN203270061U (en) Emergency short-circuit device for end-head groove of aluminium electrolysis cell
CN100507089C (en) Method for repairing liner on side of electrolytic tank without stopping the tank
CN204441905U (en) A kind of self-starting system of energy accumulation current converter
CN204529998U (en) The emergent short-circuit busbar device of aluminium cell
CN104022504B (en) Traction Substation of Electric Railway power supply based on SPWM technology
CN203613280U (en) Emergency short circuit device for aluminum electrolytic cell
CN201031256Y (en) No power-off aluminum cell short circuit power off and grooving device of aluminum electrolyze series
CN203261257U (en) Solar photovoltaic power generation single-phase grid-connected inverter
CN202334410U (en) Frequency conversion control system
CN203942277U (en) Traction Substation of Electric Railway power supply based on SPWM technology
CN204756756U (en) Complementary LED street lamp of scene
CN104467363A (en) High-power supply power converter
CN201390606Y (en) Vehicle-mounted transfer device for rubber-tyred container gantry crane
CN210380372U (en) Energy storage power supply system based on self energy storage electric power black start
CN202047148U (en) Emergency bus device for electrolytic cell
CN103580066A (en) Seamless switching control system of distributed power generation system
CN104674304B (en) A kind of aluminium cell is met an urgent need short-circuiting means
CN203645569U (en) Large-power photovoltaic grid connected inverter

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20110810