CN201762702U - Drilling secant pile - Google Patents

Drilling secant pile Download PDF

Info

Publication number
CN201762702U
CN201762702U CN2010205321152U CN201020532115U CN201762702U CN 201762702 U CN201762702 U CN 201762702U CN 2010205321152 U CN2010205321152 U CN 2010205321152U CN 201020532115 U CN201020532115 U CN 201020532115U CN 201762702 U CN201762702 U CN 201762702U
Authority
CN
China
Prior art keywords
pile
stake
construction
adjacent
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010205321152U
Other languages
Chinese (zh)
Inventor
陈立成
***
樊忠祥
许国安
王栗山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 19th Bureau Group Co Ltd
Rail Transit Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Third Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
South China Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Original Assignee
China Railway 19th Bureau Group Co Ltd
Rail Transit Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Third Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
South China Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 19th Bureau Group Co Ltd, Rail Transit Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd, Third Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd, South China Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd filed Critical China Railway 19th Bureau Group Co Ltd
Priority to CN2010205321152U priority Critical patent/CN201762702U/en
Application granted granted Critical
Publication of CN201762702U publication Critical patent/CN201762702U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a drilling secant pile has solved under unfavorable geological conditions, and the bored concrete pile that prior art adopted has mud overflow to cause the influence to the surrounding environment to the construction site occupies greatly, and the construction period is long, technical problem with high costs. The retaining wall comprises a pile A and a pile B, wherein the pile A and the pile B are arranged at intervals to form a row of retaining walls, the pile B is arranged between every two adjacent pile A, and each pile B is meshed with the adjacent pile A. The horizontal cross section of the pile A is the same as that of the pile B. The utility model discloses having realized the segmentation construction purpose to subway deep basal pit enclosure, having overcome the interference that cross construction brought, reduced occuping of construction site, practiced thrift the construction cost.

Description

Boring interlock stake
Technical field
The utility model relates to a kind of space enclosing structure stake of Metro Deep Excavation.
Background technology
In the subway foundation pit civil engineering process of soft soil layer,, all can cause very big influence, even cause the sedimentation of ground high-rise building surrounding environment if the retaining of space enclosing structure soil and stagnant water effect are bad.Prior art generally is the method that adopts bored pile piling under unfavorable geological condition, and the defective that the used mud off of castinplace pile exists mud to overflow surrounding environment is impacted, and the construction plant takies greatly, and is long in time limit, the cost height.
Summary of the invention
The utility model provides a kind of boring interlock stake to solve under unfavorable geological condition, and the castinplace pile that prior art adopted exists mud to overflow surrounding environment is impacted, and the construction plant takies greatly, and is long in time limit, the technical problem that cost is high.
The utility model overcomes the above problems by following scheme:
A kind of boring interlock stake comprises A stake and B stake, it is characterized in that, A stake and B stake are arranged to a row formula retaining wall at interval, is provided with the B stake between per two adjacent A stakes, and each B stake all is interlocked with adjacent A stake.
Level cross-sectionn in described A stake is identical with the level cross-sectionn of B stake.
The utility model has been realized the section construction purpose to the subway Extra-Deep Foundation Pit, has overcome the interference that crossed construction brings, and has reduced taking of construction plant, has saved the construction funds.
Description of drawings:
Fig. 1 is a structural representation of the present utility model
Fig. 2 is a construction flow chart of the present utility model
Specific embodiment
A kind of boring interlock stake comprises A stake and B stake, it is characterized in that, A stake and B stake are arranged to a row formula retaining wall at interval, is provided with the B stake between per two adjacent A stakes, and each B stake all is interlocked with adjacent A stake.
Level cross-sectionn in described A stake is identical with the level cross-sectionn of B stake.
The all casing drill drilling construction is adopted in boring interlock stake, forms the foundation pit enclosure structure that mutual interlock is arranged between stake and stake.The arrangement mode of stake is that A stake and B stake are arranged at interval, construction B stake after the construction A stake earlier during construction, and require must finish before the super slow setting concrete initial set of A stake the construction of B stake.Adopt all casing drill to cut away the plain concrete of adjacent A stake intersection during the B pile driving construction, thereby realize interlock.
With the reinforced concrete pile is example, the construction technology process of single pile is led wall → drill machine with casing centering in place → lifting as: smooth place → measurement stake position → construction concrete and is laid first segment sleeve pipe → observing and controlling verticality → be pressed into first segment sleeve pipe → check and correction verticality → grab bucket to fetch earth, advance → measure hole depth → removing loosened soil with pipe bit, at the bottom of the inspection eye → B stake install reinforcing cage → put into concrete pouring conduit → perfusion concrete to pull out sleeve pipe → mensuration concrete face → stake machine displacement one by one.A type single pile construction technology and Type B pile foundation are originally identical, just do not have this operation of install reinforcing cage.

Claims (2)

1. a boring interlock stake comprises A stake and B stake, it is characterized in that A stake and B stake are arranged to a row formula retaining wall at interval, is provided with the B stake between per two adjacent A stakes, and each B stake all is interlocked with adjacent A stake.
2. a kind of boring interlock stake according to claim 1 is characterized in that, and is identical with the level cross-sectionn of B stake in the level cross-sectionn of described A stake.
CN2010205321152U 2010-09-17 2010-09-17 Drilling secant pile Expired - Fee Related CN201762702U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010205321152U CN201762702U (en) 2010-09-17 2010-09-17 Drilling secant pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010205321152U CN201762702U (en) 2010-09-17 2010-09-17 Drilling secant pile

Publications (1)

Publication Number Publication Date
CN201762702U true CN201762702U (en) 2011-03-16

Family

ID=43715313

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010205321152U Expired - Fee Related CN201762702U (en) 2010-09-17 2010-09-17 Drilling secant pile

Country Status (1)

Country Link
CN (1) CN201762702U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103255764A (en) * 2013-05-22 2013-08-21 浙江省地质矿产工程公司 Construction method for vibrating sunken tube construction secant pile wall
CN103276723A (en) * 2013-04-27 2013-09-04 瑞华建设集团有限公司 Construction method of concrete bored secant pile
CN104060613A (en) * 2013-03-22 2014-09-24 上海市城市建设设计研究总院 Directional secant pile grouting structure and directional secant pile grouting soil reinforcement method
CN104264662A (en) * 2014-10-17 2015-01-07 中亿丰建设集团股份有限公司 Construction method for deeply embedding hard rock secant pile in soil layer being rich in water
CN109056740A (en) * 2018-08-03 2018-12-21 浙江大学城市学院 A kind of construction method whether novel judgement interlocking pile is engaged
CN113866277A (en) * 2021-09-22 2021-12-31 合诚工程咨询集团股份有限公司 Nondestructive testing method for pile forming quality of large-diameter secant pile

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104060613A (en) * 2013-03-22 2014-09-24 上海市城市建设设计研究总院 Directional secant pile grouting structure and directional secant pile grouting soil reinforcement method
CN104060613B (en) * 2013-03-22 2016-04-20 上海市城市建设设计研究总院 The directed slip casting structure of interlocking pile and interlocking pile directed grouting and reinforcing soil body method
CN103276723A (en) * 2013-04-27 2013-09-04 瑞华建设集团有限公司 Construction method of concrete bored secant pile
CN103255764A (en) * 2013-05-22 2013-08-21 浙江省地质矿产工程公司 Construction method for vibrating sunken tube construction secant pile wall
CN104264662A (en) * 2014-10-17 2015-01-07 中亿丰建设集团股份有限公司 Construction method for deeply embedding hard rock secant pile in soil layer being rich in water
CN109056740A (en) * 2018-08-03 2018-12-21 浙江大学城市学院 A kind of construction method whether novel judgement interlocking pile is engaged
CN109056740B (en) * 2018-08-03 2020-04-07 浙江大学城市学院 Construction method for judging whether secant pile is secant or not
CN113866277A (en) * 2021-09-22 2021-12-31 合诚工程咨询集团股份有限公司 Nondestructive testing method for pile forming quality of large-diameter secant pile

Similar Documents

Publication Publication Date Title
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN104947690B (en) Grooving construction method for embedding underground continuous wall into rock
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN201762702U (en) Drilling secant pile
CN203846485U (en) Long pile percussion drill hole forming construction device
CN102286984A (en) Water-stop curtain and construction method thereof
CN104153352A (en) Karst geology rotary-drilling bored concrete pile hole forming process
CN101328712A (en) Construction method of interlocking pile for soft soil and soil layer with obstacle
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN103114599B (en) Deep basal pit sealing dewatering device and construction method thereof
CN102286981A (en) Waterproof curtain and construction method thereof
CN202194148U (en) Waterproof curtain
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN108532586A (en) A kind of construction method of garage parking diaphram wall
CN104612179A (en) Construction method for underground diaphragm wall penetrating through super-thick silt layer
CN202194149U (en) Water-proof curtain
CN105569051A (en) Foundation pit support system of sandy pebble boulder geological stratification and construction method
CN104264663A (en) Hard cutting construction technology for secant piles
CN106592605A (en) Construction method of foundation pit bracing with tri-axial stirring piles overlapped with reinforced concrete cast-in-place piles to be driven
CN104314071A (en) Construction method of underground diaphragm wall by employing rotary drilling rig
CN206428707U (en) A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation
CN110241836A (en) A kind of construction method of embedding rock water-stop curtain
CN105200994A (en) Construction method for reserved shield crossing composite foundation pit support device
CN102220764B (en) Construction method of deep foundation pit bracing system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110316