CN201685997U - Shipbuilding tooling utilizing floating dock - Google Patents
Shipbuilding tooling utilizing floating dock Download PDFInfo
- Publication number
- CN201685997U CN201685997U CN201020162859XU CN201020162859U CN201685997U CN 201685997 U CN201685997 U CN 201685997U CN 201020162859X U CN201020162859X U CN 201020162859XU CN 201020162859 U CN201020162859 U CN 201020162859U CN 201685997 U CN201685997 U CN 201685997U
- Authority
- CN
- China
- Prior art keywords
- complete cross
- section
- floating drydock
- shipbuilding
- floating dock
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Ship Loading And Unloading (AREA)
Abstract
The utility model relates to a shipbuilding tooling utilizing a floating dock, which is characterized in that the tooling comprises the floating dock (1), various complete cross sections (2) of a new ship and a three-dimensional regulator (3), ballast water (6) is filled in a ballast tank of the floating dock (1), the complete cross sections (2) of the new ship are arranged on dock blocks (4) of the floating dock (1), and the three-dimensional regulator (3) is assembled on a pontoon deck (5) of the floating dock (1) and is padded at the bottoms of the complete cross sections (2) of the new ship. The shipbuilding tooling can resolve the problems of determining the ship reference line in the floating dock during shipbuilding and quickly adjusting and positioning complete cross sections of the new ship.
Description
(1) technical field
The utility model relates to a kind of frock of utilizing shiprepair to carry out shipbuilding with the floating drydock.Belong to the ship building technical field.
(2) background technology
Building berth, dry dock are ship closure and following drainage facility, are widely used in new shipbuilding; Floating drydock and dry dock are widely used in ship repair.These are critical facilitys of shipyard, and investment is big, and the cycle is long.
Along with the new ship demand in the world sharply enlarges, and new construction facilities can't increase in a short time fast, is to alleviate imbalance between supply and demand, and each shipyard will be used for being used for shipbuilding after the dry dock transformation of shiprepair one after another, but the floating drydock is adopted in shiprepair mostly.If the floating drydock also can be used for shipbuilding, then can realize shiprepair and shipbuilding resource sharing to a greater extent, be issued to the purpose that enlarges the shipbuilding production capacity in a short time to greatest extent in the situation that does not need very big fund input, thereby satisfy the demand of the world new ship.And when new ship demand reduced, the floating drydock still can be used for shiprepair, reduced idle facility.But the floating drydock is used for shipbuilding and has a following difficult problem:
Need definite datum line conduct when 1, closing up and close up benchmark, and the floating drydock can't provide the datum line as the land owing to new ship.Because:
1) floating drydock swims on the water surface, and its position and state change along with the variation of stormy waves, morning and evening tides and current.
2) when new ship segmentation (or complete cross section) when putting into the floating drydock, thereby the strained condition at floating drydock can change and produces distortion.
2, new ship segmentation (or complete cross section) is in floating drydock domestic demand quick adjusting location, to satisfy the requirement of shipbuilding period.
(3) summary of the invention
The purpose of this utility model is to overcome above-mentioned deficiency, provide a kind of can solve above-mentioned in the floating drydock the determining and the frock of utilizing the floating drydock shipbuilding of the quick adjusting orientation problem of new ship complete cross section of boats and ships datum line during shipbuilding.
The purpose of this utility model is to be achieved through the following technical solutions: a kind of frock of utilizing the floating drydock shipbuilding, comprise: each complete cross section and the three-dimensional adjustment machine of floating drydock, new ship, in the ballast tank at floating drydock, add ballast water, on the docking block at floating drydock, place each complete cross section of new ship, the three-dimensional adjustment machine of device on the pontoon deck at floating drydock, three-dimensional adjustment machine pad places the bottom of each complete cross section of described new ship.
The utility model has the advantages that:
1, this frock does not need the extensive new facility that increases, and only existing facility need be transformed.Can save input, instant effect greatly.
2, when not needing to adopt this method to build boats and ships, involved facilities and equipment can be used for shiprepair and building berth (or dry dock) shipbuilding, can not cause the idle of equipment, facility and place.Cut the waste.
3, realize shiprepair facility and construction facilities resource sharing, improved the alerting ability of factory operation greatly.
(4) description of drawings
Fig. 1 arranges scheme drawing for the complete cross section place that the utility model relates to.
Hydraulic trolley arrangement plan during complete cross section translation that Fig. 2 relates to for the utility model.
The layout scheme drawing (birds-eye view) of boats and ships in the floating drydock that Fig. 3 relates to for the utility model.
The layout scheme drawing (drawing in side sectional elevation) of boats and ships in the floating drydock that Fig. 4 relates to for the utility model.
The complete cross section lifting scheme drawing that Fig. 5 relates to for the utility model.
Reference numeral among the figure:
Floating drydock 1, boats and ships 2, three-dimensional adjustment machine 3, docking block 4, pontoon deck 5, ballast water 6.
The first complete cross section A, the second complete cross section B, the 3rd complete cross section C, the 4th complete cross section D, the 5th complete cross section E, the 6th complete cross section F.
(5) specific embodiment
Referring to Fig. 4, the layout scheme drawing (drawing in side sectional elevation) of boats and ships in the floating drydock that Fig. 4 relates to for the utility model.As seen from Figure 4, the utility model utilizes the frock of floating drydock shipbuilding, comprise: each complete cross section 2 and the three-dimensional adjustment machine 3 of floating drydock 1, new ship, in the ballast tank at floating drydock 1, add ballast water 6, on the docking block 4 at floating drydock 1, place each complete cross section 2 of new ship, the three-dimensional adjustment machine 3 of device on the pontoon deck 5 at floating drydock 1, three-dimensional adjustment machine 3 pads place the bottom of each complete cross section 2 of described new ship.Utilize the method for floating drydock shipbuilding as follows:
Step 4, will pump with the ballast water in the cooresponding ballast tank of first complete cross section, the weight of the ballast water that pumps equates substantially with the weight of first complete cross section.Utilize the described floating drydock of total station survey about in amount of deflection control line on the wing wall, and according to the ballast water in the measurement situation fine setting ballast tank, about making in the out-of-flat of amount of deflection control line on the wing wall less than 10mm.
Step 6, second complete cross section is lifted up into the floating drydock,, repeated for the 4th step then as Fig. 5.
Step 7, adjust the position of second complete cross section with three-dimensional adjustment machine, line of centers that surveying on first complete cross section drawn and height and position line are as the benchmark that closes up of second complete cross section.
Step 8, repeat above operation and close up the 3rd complete cross section, with the line of centers of first and second complete cross sections after the balance and height and position line the benchmark that closes up as the 3rd complete cross section.By that analogy, close up up to all complete cross sections and to finish, as Fig. 3.
Claims (1)
1. frock of utilizing the floating drydock shipbuilding, it is characterized in that: described frock comprises: each complete cross section (2) and the three-dimensional adjustment machine (3) of floating drydock (1), new ship, in the ballast tank of floating drydock (1), add ballast water (6), the docking block of (1) (4) is gone up each complete cross section (2) of placing new ship at the floating drydock, the pontoon deck of (1) (5) is gone up the three-dimensional adjustment machine (3) of device at the floating drydock, and three-dimensional adjustment machine (3) pad places the bottom of each complete cross section (2) of described new ship.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201020162859XU CN201685997U (en) | 2010-04-09 | 2010-04-09 | Shipbuilding tooling utilizing floating dock |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201020162859XU CN201685997U (en) | 2010-04-09 | 2010-04-09 | Shipbuilding tooling utilizing floating dock |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201685997U true CN201685997U (en) | 2010-12-29 |
Family
ID=43374283
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201020162859XU Expired - Fee Related CN201685997U (en) | 2010-04-09 | 2010-04-09 | Shipbuilding tooling utilizing floating dock |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201685997U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104802955A (en) * | 2014-12-05 | 2015-07-29 | 中集海洋工程研究院有限公司 | Floating dock |
CN107416131A (en) * | 2017-07-28 | 2017-12-01 | 广船国际有限公司 | A kind of dock positioner |
CN107416129A (en) * | 2017-07-28 | 2017-12-01 | 广船国际有限公司 | A kind of dock positioner and its installation method |
CN107719580A (en) * | 2017-08-15 | 2018-02-23 | 舟山长宏国际船舶修造有限公司 | A kind of horizontal building berth method on 10 ton ships |
CN108862093A (en) * | 2018-06-04 | 2018-11-23 | 芜湖恒安钢结构有限公司 | A kind of shipbuilding hull clamping lifting means |
CN111268060A (en) * | 2020-04-01 | 2020-06-12 | 扬帆集团股份有限公司 | Half ship folds device based on dock |
-
2010
- 2010-04-09 CN CN201020162859XU patent/CN201685997U/en not_active Expired - Fee Related
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104802955A (en) * | 2014-12-05 | 2015-07-29 | 中集海洋工程研究院有限公司 | Floating dock |
CN104802955B (en) * | 2014-12-05 | 2017-02-08 | 中集海洋工程研究院有限公司 | Floating dock |
CN107416131A (en) * | 2017-07-28 | 2017-12-01 | 广船国际有限公司 | A kind of dock positioner |
CN107416129A (en) * | 2017-07-28 | 2017-12-01 | 广船国际有限公司 | A kind of dock positioner and its installation method |
CN107719580A (en) * | 2017-08-15 | 2018-02-23 | 舟山长宏国际船舶修造有限公司 | A kind of horizontal building berth method on 10 ton ships |
CN107719580B (en) * | 2017-08-15 | 2019-05-31 | 舟山长宏国际船舶修造有限公司 | Horizontal building berth method on 10 10,000 tons ships of one kind |
CN108862093A (en) * | 2018-06-04 | 2018-11-23 | 芜湖恒安钢结构有限公司 | A kind of shipbuilding hull clamping lifting means |
CN111268060A (en) * | 2020-04-01 | 2020-06-12 | 扬帆集团股份有限公司 | Half ship folds device based on dock |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201685997U (en) | Shipbuilding tooling utilizing floating dock | |
CN204184555U (en) | A kind of novel floating drydock | |
CN101817393B (en) | Shipbuilding method by utilizing floating dock | |
CN105151236A (en) | Platform device for submerging, surfacing, moving and carrying floating piers and towers and working method thereof | |
CN203996823U (en) | Gravity swing ball formula following sea piston type hull self balancing device | |
CN105480380B (en) | Tension leg platform (TLP) upper module and the closure workmanship of lower float structure | |
CN103910044A (en) | Large-scale floating type ocean-structure semi-submersible lifting platform and application method thereof | |
CN104229099A (en) | Offshore engineering vessel loading and launching system and method | |
CN102114899A (en) | Extra-large float installation barge and design method thereof | |
CN104210627B (en) | Build the device and method of lower water for jack-up unit level land | |
CN103241668A (en) | Device and method for installing deep sea submarine storage tank | |
CN104743058A (en) | Floating installation method for upper assembling block of tension leg platform | |
CN106522275A (en) | Construction process for shipping large sinking pipes by self-propelled semi-submerged ship | |
CN203996826U (en) | Pontoon type following sea piston type hull self balancing device | |
CN204916099U (en) | Semi -submerged barge tilting dive stern deadwood | |
CN105586864A (en) | Method for folding self-lifting-type platform truss-type pile legs | |
CN109178225B (en) | Pull rod type undocking method for semi-submersible type ocean engineering platform | |
CN203902800U (en) | Semi-submersible type lifting platform for large floating offshore structure | |
CN103921905B (en) | Semi-submersible module for combining into large-scale floating body on the water and assembling method thereof | |
CN103569311A (en) | Propeller installing and positioning device and propeller underwater installing method | |
CN201685988U (en) | Height positioning device for afloat joining of main body of 1600-ton crane ship | |
CN202787291U (en) | Main pier steel cover box on-site two-abreast-machine hoisting construction structure | |
CN104802950A (en) | Self-elevating type underwater floater tension leg platform and establishing method thereof | |
CN206218146U (en) | Offshore operation at sea platform | |
CN204979158U (en) | Latent floating carrying platform device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20101229 Termination date: 20170409 |