CN201447323U - 高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置 - Google Patents

高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置 Download PDF

Info

Publication number
CN201447323U
CN201447323U CN2009200483340U CN200920048334U CN201447323U CN 201447323 U CN201447323 U CN 201447323U CN 2009200483340 U CN2009200483340 U CN 2009200483340U CN 200920048334 U CN200920048334 U CN 200920048334U CN 201447323 U CN201447323 U CN 201447323U
Authority
CN
China
Prior art keywords
tower crane
core tube
shear wall
tube shear
rise building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2009200483340U
Other languages
English (en)
Inventor
陈振明
戴立先
慈龙胜
熊涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Science and Industry Corp Ltd
Original Assignee
China Construction Steel Structure Jiangsu Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Steel Structure Jiangsu Corp Ltd filed Critical China Construction Steel Structure Jiangsu Corp Ltd
Priority to CN2009200483340U priority Critical patent/CN201447323U/zh
Application granted granted Critical
Publication of CN201447323U publication Critical patent/CN201447323U/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本实用新型涉及一种高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置,属于高层建筑施工技术领域。它包括核心筒剪力墙(1)和塔吊支撑架主梁(2),在所述核心筒剪力墙(1)设置预留孔洞,在该预留孔洞的底缘设置预埋钢板(3)和预埋锚栓(5),将塔吊支撑架主梁(2)与预埋钢板(3)用预埋锚栓(5)连成一体,并在塔吊支撑架主梁(2)与预埋钢板(3)之间设置调节垫片(4)。本实用新型通过将塔吊支撑架主梁直接放置在核心筒剪力墙上,与预埋钢板通过预埋锚栓连接在一起,不但不需要焊接,而且方便地调节垫片以使支撑架主梁上表面在同一水平高度。在荷载传递上这种支撑方式更加直接有效地保证了荷载的传递路径。

Description

高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置
(一)技术领域
本实用新型涉及一种高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置,属于高层建筑施工技术领域。
(二)背景技术
内爬式塔吊通常设置在高层建筑核心筒内塔吊支撑架上。塔吊支撑架主要由主梁、次梁及支撑组成。一般塔吊支撑架主梁与设置在核心筒剪力墙上的预埋件通过连接板焊接在一起以支撑塔吊,并将竖向荷载传递给核心筒剪力墙。通过这种支撑方法安置的塔吊为保证其安全正常地工作,一方面要求预埋件与连接板之间的焊接质量有充分的保证;另一方面为确保主梁上表面在同一水平高度对预埋件的埋植精度有很高要求,这对施工现场恶劣的作业环境来说具有非常大的难度。
(三)发明内容
本实用新型旨在解决塔吊现有支撑方法上存在的上述问题,提供一种既不用焊接也不需要严格控制预埋件精度的高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置。
本实用新型的目的是这样实现的:一种高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置,包括核心筒剪力墙和塔吊支撑架主梁,在所述核心筒剪力墙设置预留孔洞,在该预留孔洞的底缘设置预埋钢板和预埋锚栓,将塔吊支撑架主梁与预埋钢板用预埋锚栓连成一体,并在塔吊支撑架主梁与预埋钢板之间设置调节垫片。
本实用新型的有益效果是:
本实用新型通过将塔吊支撑架主梁直接放置在核心筒剪力墙上,与预埋钢板通过预埋锚栓连接在一起,不但不需要焊接,而且方便地调节垫片以使支撑架主梁上表面在同一水平高度。在荷载传递上这种支撑方式更加直接有效地保证了荷载的传递路径。
本实用新型解决了现场恶劣作业环境下塔吊支撑架主梁和预埋件之间焊接质量不易保证带来的安全隐患和难控制预埋件的精度以保证支撑架主梁上表面在同一水平高度的问题,有效地保证了施工现场塔吊的安全正常运转。
(四)附图说明
图1为本实用新型高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置的立体结构示意图。
图2为图1的侧立面图。
图中附图标记:
核心筒剪力墙1、塔吊支撑架主梁2、预埋钢板3、调节垫片4、预埋锚栓5。
(五)具体实施方式
参见图1和图2,图1为本实用新型高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置的立体结构示意图.图2为图1的侧立面图.由图1和图2可以看出,本实用新型高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置,包括核心筒剪力墙1和塔吊支撑架主梁2,在所述核心筒剪力墙1设置预留孔洞,在该预留孔洞的底缘设置预埋钢板3和预埋锚栓5,将塔吊支撑架主梁2与预埋钢板3用预埋锚栓5连成一体,并在塔吊支撑架主梁2与预埋钢板3之间设置调节垫片4.
其制作方法如下:在核心筒剪力墙1上设计预留孔洞的大小能方便塔吊支撑架主梁2的安装和拆除。在核心筒剪力墙1墙体混凝土浇灌前,用与预留孔洞大小相同的木制空心块与预埋钢板3及预埋锚栓5连成一体,将其预埋在塔吊支撑架主梁2对应的核心筒剪力墙1墙***置,与周边钢筋紧固连接,并对受压部位的钢筋进行局部加强处理;待混凝土浇注完成且达到一定强度后,将木制空心块取出形成塔吊支撑架主梁2的预留孔洞。塔吊支撑架主梁2与预埋钢板3用预埋锚栓5并通过调节垫片4以使塔吊支撑架主梁2的上表面在同一水平面上。通过这种支撑方式支撑起塔吊。当塔吊支撑架主梁使用完毕拆除后采用同样标号混凝土对剪力墙进行补强处理。

Claims (1)

1.一种高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置,包括核心筒剪力墙(1)和塔吊支撑架主梁(2),其特征在于:在所述核心筒剪力墙(1)设置预留孔洞,在该预留孔洞的底缘设置预埋钢板(3)和预埋锚栓(5),将塔吊支撑架主梁(2)与预埋钢板(3)用预埋锚栓(5)连成一体,并在塔吊支撑架主梁(2)与预埋钢板(3)之间设置调节垫片(4)。
CN2009200483340U 2009-09-04 2009-09-04 高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置 Expired - Lifetime CN201447323U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009200483340U CN201447323U (zh) 2009-09-04 2009-09-04 高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009200483340U CN201447323U (zh) 2009-09-04 2009-09-04 高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置

Publications (1)

Publication Number Publication Date
CN201447323U true CN201447323U (zh) 2010-05-05

Family

ID=42552040

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009200483340U Expired - Lifetime CN201447323U (zh) 2009-09-04 2009-09-04 高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置

Country Status (1)

Country Link
CN (1) CN201447323U (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112482561A (zh) * 2020-12-02 2021-03-12 上海席得建筑设计有限公司 一种核心筒内附墙结构
CN113529968A (zh) * 2021-07-16 2021-10-22 合肥工业大学 可适应构件间竖向变形差的钢梁与钢筋混凝土剪力墙节点

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112482561A (zh) * 2020-12-02 2021-03-12 上海席得建筑设计有限公司 一种核心筒内附墙结构
CN113529968A (zh) * 2021-07-16 2021-10-22 合肥工业大学 可适应构件间竖向变形差的钢梁与钢筋混凝土剪力墙节点

Similar Documents

Publication Publication Date Title
CN106703306B (zh) 一种预制混凝土女儿墙构件及其连接结构
CN108035594A (zh) 钢筋混凝土筒仓结构预制减压锥体施工方法
CN109577553A (zh) 一种新式装配式结构预制柱构件及梁柱节点施工方法
CN207863507U (zh) 一种用于高层建筑楼层的竖向构件置换装置
CN105649334A (zh) 一种混凝土剪力墙塔吊附墙施工方法及其装置
CN108678423A (zh) 钢筋混凝土结构逆向拆除竖向转换支撑结构
CN103821359A (zh) 大截面混凝土梁分层浇筑施工工法
CN110206144A (zh) 一种钢骨柱梁柱节点的施工方法
CN107988921B (zh) 一种上跨铁路、高速公路的跨线桥梁单点连续顶推施工方法
CN202481956U (zh) 附着爬升式定型化两用平台
CN201447323U (zh) 高层建筑核心筒剪力墙开洞型内爬式塔吊支撑装置
CN204173804U (zh) 一种结构梁承载式的内爬塔吊安装及顶升结构
CN110761562A (zh) 浇筑混凝土的辅助工具及使用方法
CN111648411A (zh) 下翻式后浇带换撑结构及施工方法、后浇带施工方法
CN203393637U (zh) 一种承重托架
CN213477639U (zh) 建筑混凝土楼板穿透式连续支撑
CN206174441U (zh) 一种电梯井操作平台
CN202273396U (zh) 移动式钢管柱内砼浇筑平台***
CN105480842B (zh) 一种后浇设备支撑梁及其施工方法
CN203924484U (zh) 一种预制梁及具有榫锚体系的钢筋混凝土结构
CN210685282U (zh) 一种预制轨顶风道装配结构
CN210282669U (zh) 钢筋混凝土预制构件生产用模具
CN102116052A (zh) 一种钢筋混凝土操作平台梁的浇筑方法
CN106759431B (zh) 一种悬空式塔吊钢平台基础
CN105314548A (zh) 一种结构梁承载式的内爬塔吊安装及顶升方法及结构

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA STATE CONSTRUCTION STEEL STRUCTURE CO., LTD.

Free format text: FORMER OWNER: CHINA CONSTRUCTION STEEL STRUCTURE JIANGSU CO., LTD.

Effective date: 20120224

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Wang Hong

Inventor after: Zhang Kun

Inventor after: Huang Gang

Inventor after: Chen Zhenming

Inventor after: Dai Lixian

Inventor after: Ci Longsheng

Inventor after: Xiong Tao

Inventor before: Chen Zhenming

Inventor before: Dai Lixian

Inventor before: Ci Longsheng

Inventor before: Xiong Tao

COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 214434 WUXI, JIANGSU PROVINCE TO: 518034 SHENZHEN, GUANGDONG PROVINCE

Free format text: CORRECT: INVENTOR; FROM: CHEN ZHENMING DAI LIXIAN CI LONGSHENG XIONG TAO TO: WANG HONG ZHANG KUN HUANG GANG CHEN ZHENMING DAI LIXIAN CI LONGSHENG XIONG TAO

TR01 Transfer of patent right

Effective date of registration: 20120224

Address after: 518034 Shenzhen City, Futian District Che Kung Temple Binhe industry Tairan 17 storey building No. 17A tipping

Patentee after: China Construction Steel Structure Corp., Ltd.

Address before: 214434 No. 6, Jingjiang Industrial Park, Jiangsu, Jiangyin

Patentee before: China Construction Steel Structure Jiangsu Co., Ltd.

CX01 Expiry of patent term

Granted publication date: 20100505

CX01 Expiry of patent term