CN201307742Y - 66kv架空线路水平穿越式铁塔 - Google Patents
66kv架空线路水平穿越式铁塔 Download PDFInfo
- Publication number
- CN201307742Y CN201307742Y CNU2008202191747U CN200820219174U CN201307742Y CN 201307742 Y CN201307742 Y CN 201307742Y CN U2008202191747 U CNU2008202191747 U CN U2008202191747U CN 200820219174 U CN200820219174 U CN 200820219174U CN 201307742 Y CN201307742 Y CN 201307742Y
- Authority
- CN
- China
- Prior art keywords
- iron tower
- wires
- tower
- lines
- parallel frames
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
本实用新型涉及电力行业交压杆塔,尤其是66KV架空线路水平穿越式铁塔,由铁塔主材、被穿越线路、避雷针、穿越线路、上导线挂线点、下导线挂线点、导线过引横担组成。所述的导线过引横担上面有一组平面行架,在主材铁塔前后相同高度装有同样一组行架,三组平面行架与铁塔主材垂直,行架上导线与下导线齐平。本实用新型与现有门型电杆组比较,铁塔基础占地小,对线路路径选择没有特殊要求,塔身不易腐蚀,安装防盗螺栓后,更防止了人为破坏,电器安全性得到可靠保证,优化了线路整体投资。
Description
技术领域:
本实用新型涉及电力行业中的架空线路杆塔,尤其是66KV架空线路水平穿越式铁塔。
背景技术:
辽河油田的输电主干网络为66KV架空线路,架空线路又有单杆单回、单杆多回之分。在线路的设计施工中,根据电源和负荷位置、线路长短等设计要求,66KV架空线路与其它电压等级线路的交叉跨越是不可避免的。电力规程规定:低电压等级的架空线路禁止跨越高电压等级架空线路。当高电压等级线路的下导线距地高度较低时(如12m),66KV架空线路既要保证对220KV架空线路的安全距离,又要保证对地安全距离,穿越就很困难。在具体项目中,当一条66KV单杆双回路与220KV架空线路交叉,则设计难度更大。现有定型66KV双回电力铁塔的导线排列方式为鼓形排列,上导线最低高度为11.5m,不能满足穿越设计要求;对于第2种情况,设计部门通常采用3基门型电杆来实现穿越,门型电杆采用两根同径混凝土电杆作为主柱,配以角钢横担、叉梁、8根导(线)地(线)拉线,功能实现了,但缺点也很明显:其占地大,征地费用高,电杆易腐蚀,拉线易被人为损坏,安全性低。
实用新型内容:
本实用新型目的便是为了克服上述缺点,而提供的66KV架空线路水平穿越式铁塔,是对779(9)铁塔的改造,能实现三基铁塔连续两档穿越较低高度的高电压等级架空线路。
为了实现上述目的,本实用新型由铁塔主材、被穿越线路、避雷针、穿越线路、上导线挂线点、下导线挂线点、导线过引横担组成;所述的导线过引横担上面有一组平面行架,在主材铁塔前后相同高度装有同样一组行架,三组平面行架与铁塔主材垂直,行架上导线与下导线齐平。
本使用新型与现有技术相比具有显著的特点,779(9)铁塔经过改形后由于铁塔的两侧导线排列为水平排列,仅用一基此塔就能够实现连续穿越较低高度的(两条以上)高电压等级架空线路、能够保证对穿越线路、对地的安全距离,并且档距可达100m。与现有门型电杆组比较,铁塔基础占地小,对线路路径选择没有特殊要求,塔身不易腐蚀,安装防盗螺栓后,更防止了认为破坏,电器安全性得到可靠保证,优化了线路整体投资。
附图说明:
图1是本实用新型结构穿越示意图(中间铁塔为本实用新型)。
图2是本实用新型结构示意图。
图3是平面行架结构示意图。
具体实施方式:
本实用新型由以下实施例给出,下面结合附图予以说明:
图中1、被穿越线路,2、避雷针,3、穿越档线路,4、上导线挂线点,5、主材铁塔,6、下导线挂线点,7、导线过引横担,8、平面桁架。
铁塔的主材5为779(9)铁塔时一种耐张转角塔。被穿越线路1、穿越线路3、避雷针2(图1)、上导线挂线点4、下导线挂线点6、导线过引横担7(图2)组成了本实用新型主体。所述的导线过引横担7上面安装有一组平行桁架8(图3),在铁塔主材5前后同样高度也安装同样一组平行桁架8,三组平面桁架与铁塔主材垂直,平面桁架上导线与下导线齐平(图1)。
本实用新型的基础塔形为66KV架空线路铁塔779(9),保持导线排列形式为三角形排列,下导线高度9m,上导线高度11.5m。
铁塔两侧的上导线点与下导线挂点齐平。这样,铁塔两侧的导线排列形式就为水平排列了,三条导线的挂点高低为9m。
实际穿越时,被穿越线路1可以被看做几根平行避雷线来保护穿越档线路3,但保护范围有限,为降低66KV架空线路高度,可以取消铁塔穿越档一侧的避雷线,而塔顶安装避雷针2与被穿越线路1一同对穿越档线路3进行防雷保护(图2)。
铁塔导线过引横担有一组平面桁架,在铁塔的前后面同高度也安装了同样的桁架8各一组。这样,3组平面桁架就实现了上导线的前后过引,并与下导线齐平(图1)。
Claims (1)
1、66KV架空线路水平穿越式铁塔,是由铁塔主材(5)、被穿越线路(1)、避雷针(2)、穿越线路(3)、上导线挂线点(4)、下导线挂线点(6)、导线过引横担(7)组成;其特征在于:所述的导线过引横担(7)上面有一组平面行架(8),在主材铁塔前后相同高度装有同样一组行架(8),三组平面行架与铁塔主材垂直,行架上导线与下导线齐平。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2008202191747U CN201307742Y (zh) | 2008-11-14 | 2008-11-14 | 66kv架空线路水平穿越式铁塔 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2008202191747U CN201307742Y (zh) | 2008-11-14 | 2008-11-14 | 66kv架空线路水平穿越式铁塔 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201307742Y true CN201307742Y (zh) | 2009-09-09 |
Family
ID=41100208
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNU2008202191747U Expired - Fee Related CN201307742Y (zh) | 2008-11-14 | 2008-11-14 | 66kv架空线路水平穿越式铁塔 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201307742Y (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103972836A (zh) * | 2014-03-24 | 2014-08-06 | 于永洋 | 一种输电线路钻越方法 |
CN104901255A (zh) * | 2015-06-16 | 2015-09-09 | 国网山东省电力公司经济技术研究院 | 一种高压架空线路交叉钻越的方法及安全距离间隔装置 |
CN107706871A (zh) * | 2017-10-30 | 2018-02-16 | 江苏神马电力股份有限公司 | 架空配电线路 |
-
2008
- 2008-11-14 CN CNU2008202191747U patent/CN201307742Y/zh not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103972836A (zh) * | 2014-03-24 | 2014-08-06 | 于永洋 | 一种输电线路钻越方法 |
CN104901255A (zh) * | 2015-06-16 | 2015-09-09 | 国网山东省电力公司经济技术研究院 | 一种高压架空线路交叉钻越的方法及安全距离间隔装置 |
CN107706871A (zh) * | 2017-10-30 | 2018-02-16 | 江苏神马电力股份有限公司 | 架空配电线路 |
WO2019085706A1 (zh) * | 2017-10-30 | 2019-05-09 | 江苏神马电力股份有限公司 | 架空配电线路 |
US11322923B2 (en) | 2017-10-30 | 2022-05-03 | Jiangsu Shemar Electric Co., Ltd. | Overhead power distribution line |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203352100U (zh) | 输电线路防风拉线横担装置 | |
CN105406434A (zh) | 一种大风区输电线路防风偏的导线悬挂方法 | |
CN206128796U (zh) | 一种猫头直线塔 | |
CN202970091U (zh) | 一种220kV同杆双回路塔头全复合材料钢管杆 | |
CN201307742Y (zh) | 66kv架空线路水平穿越式铁塔 | |
CN103311844A (zh) | 山区地形跨越带电高压线路的架线方法 | |
CN201406865Y (zh) | 66kv架空输电线路双回水平穿越铁塔 | |
WO2011029311A1 (zh) | 一种复合材料杆塔外侧竖直接地引下方法及其杆塔 | |
CN207260730U (zh) | 一种双回路电缆终端塔 | |
CN201933831U (zh) | ±800kV直流线路与接地极线路共塔的输电铁塔 | |
CN209924555U (zh) | 一种220kV单回路耐张钻越塔 | |
CN207847235U (zh) | 无接地极直流输电线路杆塔 | |
CN203891557U (zh) | 紧凑型绝缘支架 | |
CN206769518U (zh) | 一种适用于覆冰区域的架空输电线路耐张塔 | |
CN203536911U (zh) | 双回高压线路穿越杆 | |
CN206071191U (zh) | 110kV同塔双回路钻越塔 | |
CN206636296U (zh) | 一种上字型e玻璃纤维环氧树脂横担塔 | |
CN204651846U (zh) | 风力发电厂电缆登塔平台 | |
CN204552239U (zh) | 交流五百千伏输电线路铁塔 | |
CN208347417U (zh) | 一种复合材料输电线路直线塔 | |
CN202012226U (zh) | 一种窄基铁塔 | |
CN207459403U (zh) | 一种紧凑型330kV变电站GIS的垂直出线结构 | |
CN202474705U (zh) | 一种驱鸟器带电安装工具 | |
CN206023151U (zh) | 10kv大档距终端电缆杆 | |
CN204793977U (zh) | 一种可悬挂避雷线的耐张杆 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20090909 Termination date: 20101114 |