CN201252356Y - On-site disassembly overhaul special tool for high-voltage isolating switch - Google Patents

On-site disassembly overhaul special tool for high-voltage isolating switch Download PDF

Info

Publication number
CN201252356Y
CN201252356Y CNU2008200267120U CN200820026712U CN201252356Y CN 201252356 Y CN201252356 Y CN 201252356Y CN U2008200267120 U CNU2008200267120 U CN U2008200267120U CN 200820026712 U CN200820026712 U CN 200820026712U CN 201252356 Y CN201252356 Y CN 201252356Y
Authority
CN
China
Prior art keywords
isolating switch
overhaul
base support
supporting frame
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2008200267120U
Other languages
Chinese (zh)
Inventor
李志刚
王爱华
蒋涛
崔昌波
杨光伟
李峰
毛建波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
ZIBO POWER SUPPLY Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZIBO POWER SUPPLY Co filed Critical ZIBO POWER SUPPLY Co
Priority to CNU2008200267120U priority Critical patent/CN201252356Y/en
Application granted granted Critical
Publication of CN201252356Y publication Critical patent/CN201252356Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model relates to an on-site disassembly overhaul special tool for a high-voltage isolating switch, which comprises a base supporting frame. One side above the base supporting frame is provided with a working platform. The utility model is characterized in that the central position of the top part of the base supporting frame is provided with a center shaft in which a hanging arm is inserted; a movable pulley and a group of fixed pulleys are installed on the hanging arm; a hanging hook is installed on the movable pulley; and a cord is connected with the hanging hook through the fixed pulleys and the movable pulley; the bottom part of the base supporting frame is in a rectangle shape; and the two symmetrical sides are respectively connected with a clamp plate through retaining screws and can firmly fix the supporting frame on channel steel for supporting the isolating switch base. The on-site disassembly overhaul special tool for a high voltage isolating switch can be tightly abutted on repair equipment, has small working radius, simple structure, lightness, convenience and simple and easy assembly and use, can be independently assembled and used by one person, and brings great convenience to the repair work; and the utility model not only can realize split phase one-person operation but also can simultaneously carry out the disassembly and overhaul of three phases during use. The utility model thoroughly solves the overhaul problem of the GW6 type isolating switch.

Description

The on-the-spot disintegration overhaul of high voltage isolator specific purpose tool
Technical field
The utility model belongs to the service kit of converting equipment GW6 type isolating switch.
Background technology
Because characteristics such as the high voltage isolator volume is big, Heavy Weights, so at the turnover job of high voltage isolator, the scheme that generally adopts is to use crane and lift truck to cooperate to come the field overhaul of facilities and equipments at present.But the overhaul of some isolating switch often is subjected to the restriction of charging equipment on every side, and safe distance is not enough, though the load-carrying of crane and lift truck is very big, because its radius of clean-up is bigger, integral body takes up room also bigger, bump charging equipment very easily by mistake, electric shock accidents takes place; At this moment, crane, lift truck can't use; In addition, turnover job in the past, very big to the dependence of crane and lift truck, there is not their work to carry out, and also very expensive aspect the usage charges of vehicle and driver personnel's input, Jian Xiu cost has just increased greatly like this.At this moment, just need a kind of simple in structure, install and use convenient instrument and break through this restriction.
Summary of the invention
Technical problem to be solved in the utility model provides the on-the-spot disintegration overhaul of a kind of high voltage isolator specific purpose tool, to the dependence of crane and lift truck, reduces the vehicle cost of use when breaking away from the isolating switch overhaul, solves the difficult problem that three-phase can not disintegrate simultaneously and overhaul.
The on-the-spot disintegration overhaul of the utility model high voltage isolator specific purpose tool, comprise base support, base support top one side is provided with workbench, the center that it is characterized in that described base support top is provided with axis, insert arm on the axis, movable pulley and one group of fixed pulley are installed on the arm, suspension hook is installed on the movable pulley, rope is by fixed pulley and movable pulley connecting shackle.
Wherein optimized technical scheme is:
Described base support is the triangular prism shape, and workbench is positioned at a side position of base support.
The bottom of the described base support shape that is rectangle, the bottom on base two long limits connects clamping plate respectively, and clamping plate are connected by hold-down screw with base support.The purpose that clamping plate are set is to make things convenient for the utility model and repair apparatus to be installed together, convenient maintenance.
Operation principle of the present utility model is:
During hoisting heavy, the suspension hook of movable pulley catches on weight, and the staff is drawing rope, by the work-saving device of assembly pulley, weight is sling; When weight rises to when unsettled, the staff may stand on the workbench of base support one side, promotes position and direction that unsettled weight just can be adjusted the weight landing gently.Two groups of hold-down screws and clamping plate are arranged at the bottom of base support, can be fixed on support firmly on the channel-section steel that supports the isolating switch base, kit just can be near the equipment that will overhaul like this, the scope of work reduces widely, whole working region is within the safe distance fully, so overcome the not enough problem of safe distance fully, has broken away from the dependence to equipment such as crane and lift trucks simultaneously, greatly reduce recondition expense, and reached disintegrate the simultaneously purpose of overhaul of three-phase.
Advantage of the present utility model:
On the channel-section steel that is fixed on the plant bottom case junction that the utility model can be easily firm, abut against on the repair apparatus, the radius of clean-up is little, and simple in structure, light and handy convenient, install and use simple and easy, one people just can independently install and use, and brings great convenience to service work.
This product structure is simple, dismounting is simple and convenient, is easy to produce, and production single-piece specific purpose tool only needs 300 yuan, not only can produce in batches, and have promotional value.In use, not only can reach the phase-splitting one man operation, but also can finish the disintegration overhaul to three-phase simultaneously.Thoroughly solved a GW6 type isolating switch overhaul difficult problem.And change the difficult situation that the past does not have crane, lift truck just can't carry out the work.This specific purpose tool vertical tension reaches 400kg.Isolating switch is separated about the about 100kg of weight of body portion, satisfies the lifting safe requirement fully.
Description of drawings
Fig. 1 is a structural representation of the present utility model;
Fig. 2 is an arm part-structure schematic diagram;
Fig. 3 to be base support with the channel-section steel that supports the isolating switch base fixedly connected schematic diagram.
Among the figure: 1 base support, 2 arms, 3 axis, 4 clamping plate, 5 fixed pulleys, 6 movable pulleys, 7 ropes, 8 pillars, 9 workbenches, 10 suspension hooks, 11 hold-down screws, 12 channel-section steels, 13 fixed dams
Embodiment
Below in conjunction with description of drawings the utility model.
As Fig. 1, the on-the-spot disintegration overhaul of high voltage isolator specific purpose tool, the base support 1 that comprises a triangular prism that forms by three pillars 8, base support top one side is equipped with workbench 9, a center welding axis 3 (can adopt steel pipe manufacturing) at base support 1 top inserts one by one according to the arm 2 of on-the-spot actual design on the axis 3, and arm 2 bottoms are provided with fixed dam 13 (as shown in Figure 2), its effect is that the restriction arm inserts the degree of depth of axis 3, and arm is freely rotated; Movable pulley 6 and the one group of fixed pulley 5 that designs in the known technology mode is installed on the arm 2, suspension hook 10 is installed on the movable pulley 6, rope 7 drives the operation of suspension hook 10 by fixed pulley 5 and movable pulley 6.The bottom of the base support shape that is rectangle, the bottom on base two long limits connects clamping plate 4 (angle steel) respectively, and clamping plate 4 are connected by hold-down screw 11 with base support.
As Fig. 3, clamping plate 4 are threaded to the inside grooves of the channel-section steel 12 (known configurations) that supports the isolating switch base, and make it become nearly 90 degree angles with channel-section steel, tighten screw, make two long limits of base support 1 bottom symmetry step up the supporting surface of channel-section steel respectively with clamping plate 4, thereby base support 1 is fixed on the channel-section steel 12 firmly.Contrast for convenience, the bottom of base support represents that with fine line channel-section steel 12 and hold-down screw 11 usefulness heavy lines are represented.
During hoisting heavy, the suspension hook 10 of movable pulley 6 catches on weight, and the staff is drawing rope 7, by the force-reducing device of assembly pulley, weight is sling; When weight rises to when unsettled, the staff may stand on the workbench 9 on the shelf, promotes position and direction that unsettled weight just can be adjusted the weight landing gently; The hold-down screw 11 and the clamping plate 4 of base support 1 bottom, can be fixed on support firmly on the channel-section steel 12 that supports the isolating switch base, kit just can be near the equipment that will overhaul like this, the scope of work reduces widely, whole working region is within the safe distance fully, so overcome the not enough problem of safe distance fully, has broken away from the dependence to equipment such as crane and lift trucks simultaneously, greatly reduce recondition expense, and reached disintegrate the simultaneously purpose of overhaul of three-phase.

Claims (3)

1, the on-the-spot disintegration overhaul of a kind of high voltage isolator specific purpose tool, comprise base support (1), base support (1) top is provided with workbench (9), the center that it is characterized in that described base support top is provided with axis (3), axis (3) is gone up and is inserted arm (2), movable pulley (6) and one group of fixed pulley (5) are installed on the arm (2), and movable pulley (6) is gone up suspension hook (10) is installed, and rope (7) is by fixed pulley (5) and movable pulley (6) connecting shackle (10).
2, the on-the-spot disintegration overhaul of high voltage isolator according to claim 1 specific purpose tool is characterized in that described base support (1) is the triangular prism shape, and workbench (9) is positioned at a side position of base support.
3, the on-the-spot disintegration overhaul of high voltage isolator according to claim 1 specific purpose tool, the bottom that it is characterized in that described base support (1) shape that is rectangle, the bottom on base two long limits connects clamping plate (4) respectively, and clamping plate (4) are connected by hold-down screw (11) with base support.
CNU2008200267120U 2008-07-29 2008-07-29 On-site disassembly overhaul special tool for high-voltage isolating switch Expired - Lifetime CN201252356Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008200267120U CN201252356Y (en) 2008-07-29 2008-07-29 On-site disassembly overhaul special tool for high-voltage isolating switch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008200267120U CN201252356Y (en) 2008-07-29 2008-07-29 On-site disassembly overhaul special tool for high-voltage isolating switch

Publications (1)

Publication Number Publication Date
CN201252356Y true CN201252356Y (en) 2009-06-03

Family

ID=40748019

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008200267120U Expired - Lifetime CN201252356Y (en) 2008-07-29 2008-07-29 On-site disassembly overhaul special tool for high-voltage isolating switch

Country Status (1)

Country Link
CN (1) CN201252356Y (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101938093A (en) * 2010-08-26 2011-01-05 福建省电力有限公司福州电业局 Hard combined mask for changing disconnector
CN101997278A (en) * 2010-10-14 2011-03-30 黄道华 Bus uninterrupted isolator hoisting device
CN102826473A (en) * 2012-09-07 2012-12-19 鸡西电业局 Multi-functional electrical equipment lifting hold lever tool
CN103274324A (en) * 2013-05-22 2013-09-04 国家电网公司 Lift truck for replacing or overhauling disconnecting switch
CN105097366A (en) * 2015-08-19 2015-11-25 上海金盾消防智能科技有限公司 Mechanically-and-forcedly-connected contactor device
CN105645277A (en) * 2016-03-23 2016-06-08 国网山东省电力公司高唐县供电公司 Hanging bracket for folded isolating switch
CN107959252A (en) * 2017-12-05 2018-04-24 国网江苏省电力公司南通供电公司 A kind of special inspection platform of disconnecting switch

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101938093A (en) * 2010-08-26 2011-01-05 福建省电力有限公司福州电业局 Hard combined mask for changing disconnector
CN101938093B (en) * 2010-08-26 2012-09-05 福建省电力有限公司福州电业局 Hard combined mask for changing disconnector
CN101997278A (en) * 2010-10-14 2011-03-30 黄道华 Bus uninterrupted isolator hoisting device
CN102826473A (en) * 2012-09-07 2012-12-19 鸡西电业局 Multi-functional electrical equipment lifting hold lever tool
CN102826473B (en) * 2012-09-07 2015-02-18 鸡西电业局 Multi-functional electrical equipment lifting hold lever tool
CN103274324A (en) * 2013-05-22 2013-09-04 国家电网公司 Lift truck for replacing or overhauling disconnecting switch
CN103274324B (en) * 2013-05-22 2015-10-14 国家电网公司 A kind of disconnector changes overhaul lift car
CN105097366A (en) * 2015-08-19 2015-11-25 上海金盾消防智能科技有限公司 Mechanically-and-forcedly-connected contactor device
CN105645277A (en) * 2016-03-23 2016-06-08 国网山东省电力公司高唐县供电公司 Hanging bracket for folded isolating switch
CN107959252A (en) * 2017-12-05 2018-04-24 国网江苏省电力公司南通供电公司 A kind of special inspection platform of disconnecting switch

Similar Documents

Publication Publication Date Title
CN201252356Y (en) On-site disassembly overhaul special tool for high-voltage isolating switch
CN202186848U (en) Universal movable maintenance gantry crane
CN201882763U (en) Special carrying pole type beam of double-machine lifting crane
CN103730231B (en) A kind of head cover of transformer lowering or hoisting gear
CN109244912B (en) Special tool for replacing current transformer of 10kV middle-mounted switch cabinet
CN201817223U (en) Suspension device for on-load tapping switches of transformers
CN211078298U (en) Hoisting accessory is used in thermal power plant's maintenance
CN216706630U (en) Tank car inclined manhole cover dismounting tool
CN109244946A (en) A kind of electric integrated apparatus for examination and repair
CN202473589U (en) On-load tap-changer lifting frame
CN205500619U (en) Vapour is repaiied with portable jack -up shallow
CN202046833U (en) Lifting jack
CN210505382U (en) Lifting device for automobile recycling
CN203746609U (en) Transformer top cover lifting device
CN103373670A (en) Point switch machine hand-operated automobile installation specialized crane
CN202829393U (en) Multifunctional semi-automatic crane
CN109179244B (en) Hoisting frame for overhauling chemical equipment
CN205662284U (en) Two poles become platform ground jack
CN202333524U (en) Hoisting support for overhaul of isolating switch
CN202201650U (en) Four-supporting-column combined hoisting device for ultra-high voltage serial compensation platform
CN213085264U (en) Online dismouting auxiliary device of subway train unit brake
CN201458559U (en) Movable hoisting device
CN215262863U (en) Electro-hydraulic servo steel strand testing machine
CN211310595U (en) Low clearance electric hoist
CN216264241U (en) Welding tool for brake wheel of crane

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: ZIBO POWER SUPPLY COMPANY OF SHANDONG ELECTRIC POW

Effective date: 20130802

Owner name: STATE ELECTRIC NET CROP.

Free format text: FORMER OWNER: ZIBO POWER SUPPLY COMPANY OF SHANDONG ELECTRIC POWER CORPORATION

Effective date: 20130802

C41 Transfer of patent application or patent right or utility model
C56 Change in the name or address of the patentee

Owner name: ZIBO POWER SUPPLY COMPANY OF SHANDONG ELECTRIC POW

Free format text: FORMER NAME: ZIBO POWER SUPPLY COMPANY

COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 255032 ZIBO, SHANDONG PROVINCE TO: 100031 XICHENG, BEIJING

CP01 Change in the name or title of a patent holder

Address after: 100031 Xicheng District, Chang'an Avenue, No. 86,

Patentee after: State Grid Corporation of China

Patentee after: STATE GRID ZIBO POWER SUPPLY COMPANY OF SHANDONG PROVINCE

Address before: 100031 Xicheng District, Chang'an Avenue, No. 86,

Patentee before: State Grid Corporation of China

Patentee before: Zibo Power Supply Company of Shandong Electric Power Corp.

Address after: 255032 No. 61 West Village Road, Zhangdian District, Shandong, Zibo

Patentee after: Zibo Power Supply Company of Shandong Electric Power Corp.

Address before: 255032 No. 61 West Village Road, Zhangdian District, Shandong, Zibo

Patentee before: Zibo Power Supply Co.,Ltd.

TR01 Transfer of patent right

Effective date of registration: 20130802

Address after: 100031 Xicheng District, Chang'an Avenue, No. 86,

Patentee after: State Grid Corporation of China

Patentee after: Zibo Power Supply Company of Shandong Electric Power Corp.

Address before: 255032 No. 61 West Village Road, Zhangdian District, Shandong, Zibo

Patentee before: Zibo Power Supply Company of Shandong Electric Power Corp.

CX01 Expiry of patent term

Granted publication date: 20090603

CX01 Expiry of patent term