CN201116803Y - Ground source heat pump imbedded pipe heat-exchanging pile device - Google Patents

Ground source heat pump imbedded pipe heat-exchanging pile device Download PDF

Info

Publication number
CN201116803Y
CN201116803Y CNU2007200883842U CN200720088384U CN201116803Y CN 201116803 Y CN201116803 Y CN 201116803Y CN U2007200883842 U CNU2007200883842 U CN U2007200883842U CN 200720088384 U CN200720088384 U CN 200720088384U CN 201116803 Y CN201116803 Y CN 201116803Y
Authority
CN
China
Prior art keywords
pipe
heat exchange
double
tube
pipe laying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2007200883842U
Other languages
Chinese (zh)
Inventor
郁松涛
郁云涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUBEI FENGSHEN CLEAN AIR-CONDITIONING EQUIPMENT ENGINEERING Co Ltd
Original Assignee
HUBEI FENGSHEN CLEAN AIR-CONDITIONING EQUIPMENT ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUBEI FENGSHEN CLEAN AIR-CONDITIONING EQUIPMENT ENGINEERING Co Ltd filed Critical HUBEI FENGSHEN CLEAN AIR-CONDITIONING EQUIPMENT ENGINEERING Co Ltd
Priority to CNU2007200883842U priority Critical patent/CN201116803Y/en
Application granted granted Critical
Publication of CN201116803Y publication Critical patent/CN201116803Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

The utility model relates to a groundwater source heat pump pipe laying heat exchanging pile device, belonging to the groundwater heat pump warm-cold resource access device field. The pipe laying heat exchange pipe of the device is formed by a building foundation well, a cushion cap reinforcement frame, a double U-shape pipe, a reinforcement cage, a steel sleeve and a ring bracket, wherein the reinforcement cage is arranged in the building foundation well, the double U-shape pipe is arranged in the reinforcement cage, and the upper portion of the double U-shape pipe is provided with the steel sleeve, the bending portion of the lower portion is provided with the ring bracket, the two pipe port ends are extended out of the surface of the cushion cap reinforcement frame upwards, and are respectively converged to connect with the relative general water pipe. The foundation well of the pipe laying heat exchanging pipe and the inner components thereof are integrated into a pile through casting concrete on the foundation well. The utility model integrates the underground underwater heat pump U-shape pipe heat exchanging with the building foundation pile, realizes the water circulation geothermal heat usage in the underground pipe U-shape pipe, which not only saves time and cost for extra drilling projects which are required by the current single arranged groundwater heat pump warm-cold resource device, but also increases the heat exchange quantity and the heat exchange efficiency of the heat pump.

Description

Earth source heat pump pipe laying heat exchange stake device
Technical field
The utility model earth source heat pump pipe laying heat exchange stake device, source, possession heat pump Cooling and Heat Source is taken apparatus field.
Background technology
Existing earth source heat pump cold and heat source apparatus mainly is conventional holing in the soil the inside, and the inside, hole is provided with single U type pipe laying, takes underground heat by the circulation of the water in the U type pipe, though this heat-exchanger rig is comparatively ripe, has following limitation:
1. the limitation of single hole heat exchange amount.General single hole heat dissipation capacity<60W/ linear meter(lin.m.), heat-obtaining amount<40W/ linear meter(lin.m.) is difficult to improve;
2. drilling depth limitation.When quantities is big, add gun drilling, influenced by geological conditions, difficulty of construction is very big, and investment cost will increase a lot, and the duration can not guarantee;
3. the place limitation of holing.General job site must be vacated or spare the tract area as the boring place, and this makes other professional crossed constructions be a greater impact.
4. drilling time limitation.When quantities was big, the time of general independent boring when geological conditions is abominable, changed drilling technique all more than 3 months, and institute's time-consuming is longer.
5. the buried pipe construction of prior art generally the some months after civil engineering carry out, therefore must prolong engineering between high man-hour.
Therefore, other heat-exchanger rig of development and use earth source heat pump becomes the major issue that people pay close attention to.
The utility model content
The purpose of this utility model provides a kind of earth source heat pump pipe laying heat exchange stake device, by earth source heat pump U type pipe laying is set in the bored concrete pile of building foundation self, make the earth source heat pump pipe laying heat exchange stake that is combined as a whole of pipe heat exchange of underground earth source heat pump U type and building foundation pile, realize that the water circulation in the underground stake U type pipe takes underground heat, not only save existing time and the expense that the required extra borehole engineering of earth source heat pump cold and heat source apparatus is set separately, improve heat pump heat exchange amount and heat exchange efficiency simultaneously.
The utility model purpose is achieved by the following technical solution:
A kind of earth source heat pump pipe laying of the utility model heat exchange stake device, comprise source pump, water pump, water-main and pipe laying heat exchange stake, be characterized in that pipe laying heat exchange stake is by the building foundation well, the cushion cap reinforced frame, double u-tube, steel reinforcement cage, steel bushing, circle ring rack is formed, in building foundation well 1, place steel reinforcement cage 2, double u-tube 3 vertically is set in the steel reinforcement cage 2, double u-tube 3 is made up of through short tube 3-1 and elbow 3-2 serial or parallel connection two single U type PE pipes, steel bushing 6 is equipped with at straight tube position, double u-tube 3 top respectively, circle ring rack 7 is made up of annulus 7-1 and draw-in groove support 7-2, draw-in groove support 7-2 has draw-in groove 7-3, by its support draw-in groove 7-3 circle ring rack 7 is installed on double u-tube 3 lower knuckle positions, cushion cap reinforced frame 4 is arranged on the top of basic well 1, two nose ends 9 on double u-tube top stretch out cushion cap reinforced frame 4 surfaces straight up, by cast concrete 8 in basic well 1, basic well 1 and inner each member thereof of pipe laying heat exchange stake are connected as one pipe laying heat exchange stake admittedly with fixed attention, two nose ends 9 on double u-tube 3 tops compile respectively and the connection of corresponding water-main.
Said U type pipe is a polymer pipe, below all U type polymer pipe representativeness is expressed as U type polyethylene pipe, and abbreviates U type PE pipe as.
Conduit 10 is provided with back taper type stop 11, is used for auxiliary pipe down and past from bottom to up basic well 1 cast concrete, after fulfiling assignment conduit 10 is taken out, and is used further to other pile foundation construction.
According to design, prefabricated two single U type PE pipes transfer steel reinforcement cage 2 to the shaft bottom of building foundation well 1, again by the conduit 10 that is provided with back taper type stop 11, circle ring rack 7 is enclosed within on the conduit 10, the crooked position of two U type pipes is stuck among the draw-in groove 7-3 of draw-in groove support, by conduit 10 and circle ring rack 7 two U type pipes are vertically put into steel reinforcement cage 2 bottoms, with four about 3 meters steel bushings 6 of length, be enclosed within PE pipe straight tube upper end respectively, at this moment, begin cast concrete 8 in basic well 1 by conduit 10 by bottom, conduit 10 promptly can rise, lifting gradually along with conduit 10, until taking out conduit 10, the then corresponding well head that is poured into from the bottom to top of concrete, thereby basic well 1 and inner each member thereof of pipe laying heat exchange stake are connected as one pipe laying heat exchange stake admittedly with fixed attention, cut stake again and become unified horizontal absolute altitude, annular cutting steel bushing 6, expose 4 PE pipes, with elbow 3-2 two single U type pipe serial or parallel connections are become double u-tube 3 with short tube 3-1 then, pour into a mould cushion cap reinforced frame 4 this moment again, form cushion cap, two nose ends 9 on double u-tube 3 tops of reserving compile respectively and the connection of corresponding water-main.
The utility model technological merit is obvious: by earth source heat pump U type pipe laying is set in the bored concrete pile of building foundation self, make the earth source heat pump pipe laying heat exchange stake that is combined as a whole of pipe heat exchange of underground earth source heat pump U type and building foundation pile, realize that the water circulation in the underground stake U type pipe takes underground heat, the position of civil engineering bored concrete pile, be the place of pipe laying heat exchange stake, therefore do not account for site area, not only save existing time and the expense that the required extra borehole engineering of earth source heat pump cold and heat source apparatus is set separately, improve heat pump heat exchange amount and heat exchange efficiency simultaneously, adopt the single hole heat exchange amount of this device to increase, the heat exchange amount is more than 1.5 times of pipe laying of prior art boring.
Description of drawings
Fig. 1 the utility model series connection double u-tube structural representation
Fig. 2 the utility model double u-tube structural representation in parallel
Fig. 3 the utility model circle ring rack elevational schematic view
Fig. 4 the utility model circle ring rack floor map
Fig. 5 the utility model adopts subsidiary conduit to implement schematic diagram
The specific embodiment
How now further specify the utility model in conjunction with the accompanying drawings implements:
One, at first according to structure fabrication the utility model pipe laying heat exchange stake of the present utility model,
According to design, prefabricated two single U type PE pipes, steel reinforcement cage 2 is transferred to the shaft bottom of building foundation well 1, again by the conduit 10 that is provided with back taper type stop 11, circle ring rack 7 is enclosed within on the conduit 10, the crooked position of two U type pipes is stuck among the draw-in groove 7-3 of draw-in groove support, by conduit 10 and circle ring rack 7 two U type pipes are vertically put into steel reinforcement cage 2 bottoms, with four about 3 meters steel bushings 6 of length, be enclosed within PE pipe straight tube upper end respectively, at this moment, begin cast concrete 8 in basic well 1 by conduit 10 by bottom, conduit 10 promptly can rise, lifting gradually along with conduit 10, until taking out conduit 10, the then corresponding well head that is poured into from the bottom to top of concrete, thereby basic well 1 and inner each member thereof of pipe laying heat exchange stake are connected as one pipe laying heat exchange stake admittedly with fixed attention, cut stake again and become unified horizontal absolute altitude, annular cutting steel bushing 6 exposes 4 PE pipes, with elbow 3-2 two single U type pipe serial or parallel connections are become double u-tube 3 with short tube 3-1 then, pour into a mould cushion cap reinforced frame 4 this moment again, form cushion cap, two nose ends 9 on double u-tube 3 tops of reservation, compile respectively and the connection of corresponding water-main, promptly be made into pipe laying heat exchange stake.
Two, make the preceding correlation test of operation
With the above-mentioned pipe laying heat exchange stake that completes, carry out following correlation test
1. at first the pipe laying inside the heat exchange stake is carried out pressure test, test pressure is 1.5 times of operating pressure, after pressure testing is qualified, keeps operating pressure in the pipeline;
2. 2 PE nose ends 9 that each pipe laying heat exchange stake reserved are connected with horizontal house steward in setting pipe trench.
3. be connected with total pipeline finish after, pour water, be forced into 1.0Mpa then, stable back checks whether each junction has seepage.
4. after the passed examination, the backfill pipe trench is to designed elevation, and the total pipe joint of the level of reservation advances machine room, and is standby.
So far, the setting of the utility model earth source heat pump pipe laying heat exchange stake device is all finished, and after source pump and control system UNICOM, can implement the operation of earth source heat pump pile foundation heat transfer process.

Claims (3)

1, a kind of earth source heat pump pipe laying heat exchange stake device, comprise source pump, water pump, water-main and pipe laying heat exchange stake, it is characterized in that pipe laying heat exchange stake is by the building foundation well, the cushion cap reinforced frame, double u-tube, steel reinforcement cage, steel bushing, circle ring rack is formed, in basic well (1), place steel reinforcement cage (2), double u-tube (3) vertically is provided with in the steel reinforcement cage (2), steel bushing (6) is equipped with at straight tube position, double u-tube (3) top respectively, circle ring rack (7) is installed on double u-tube (3) lower knuckle position, cushion cap reinforced frame (4) is arranged on the top of basic well (1), two nose ends (9) on double u-tube (3) top stretch out cushion cap reinforced frame (4) surface straight up, by cast concrete (8) in basic well (1), basic well (1) and inner each member thereof of pipe laying heat exchange stake are connected as one pipe laying heat exchange stake admittedly with fixed attention, two nose ends (9) on double u-tube (3) top compile respectively and the connection of corresponding water-main.
2,, it is characterized in that double u-tube (3) is made up of through short tube (3-1) and elbow (3-2) serial or parallel connection two single U type PE pipes according to a kind of earth source heat pump pipe laying heat exchange stake device of claim power 1.
3, according to a kind of earth source heat pump pipe laying heat exchange stake device of claim power 1, it is characterized in that circle ring rack (7) is made up of annulus (7-1) and draw-in groove support (7-2), draw-in groove support (7-2) has draw-in groove (7-3).
CNU2007200883842U 2007-11-22 2007-11-22 Ground source heat pump imbedded pipe heat-exchanging pile device Expired - Lifetime CN201116803Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200883842U CN201116803Y (en) 2007-11-22 2007-11-22 Ground source heat pump imbedded pipe heat-exchanging pile device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200883842U CN201116803Y (en) 2007-11-22 2007-11-22 Ground source heat pump imbedded pipe heat-exchanging pile device

Publications (1)

Publication Number Publication Date
CN201116803Y true CN201116803Y (en) 2008-09-17

Family

ID=39991377

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200883842U Expired - Lifetime CN201116803Y (en) 2007-11-22 2007-11-22 Ground source heat pump imbedded pipe heat-exchanging pile device

Country Status (1)

Country Link
CN (1) CN201116803Y (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182206A (en) * 2011-01-21 2011-09-14 余戈平 Building foundation
CN102733375A (en) * 2012-06-29 2012-10-17 上海建工二建集团有限公司 Pipe pile cap joint of cast-in-place pile pre-buried ground source heat pump
CN103383018A (en) * 2013-07-18 2013-11-06 河海大学 Construction method for embedding pipe in ground source heat pump pouring pile reinforcement cage
CN103498470A (en) * 2013-09-26 2014-01-08 河海大学 Prefabricated hexagonal energy pile and manufacturing method thereof
CN104278670A (en) * 2014-10-23 2015-01-14 南京工业大学 Precast reinforced concrete pipe pile with spiral tube heat exchanger of ground source heat pump
CN104278669A (en) * 2014-10-23 2015-01-14 南京工业大学 Prefabricated reinforced concrete pipe pile with double-semicircle W-shaped parallel heat exchanger for ground source heat pump
CN104695432A (en) * 2015-03-18 2015-06-10 北京思创佳德桩工机械制造有限公司 Screw pile
CN105698437A (en) * 2016-01-29 2016-06-22 上海诺佛尔生态科技股份有限公司 U-shaped joint for ground source heat pump, ground source heat pump and ground source heat pump construction method
CN105951745A (en) * 2016-06-30 2016-09-21 青岛理工大学 Prefabricated geothermic energy pipe pile
CN106049507A (en) * 2016-07-15 2016-10-26 山东省鲁南地质工程勘察院 Ground source well heat exchanger integrating ground temperature monitoring function and construction method of ground source well heat exchanger
CN106016837B (en) * 2016-07-12 2018-06-15 三峡大学 A kind of energy acquisition and energy storage equipment based on pile-raft foundation
CN108966966A (en) * 2018-09-13 2018-12-11 吉林省三和清洁能源开发有限公司 A kind of greenhouse storing energy and supplying hot irrigation system
CN111733800A (en) * 2020-06-24 2020-10-02 河南居安供热技术有限公司 Self-winding energy pile

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182206A (en) * 2011-01-21 2011-09-14 余戈平 Building foundation
CN102733375B (en) * 2012-06-29 2014-07-30 上海建工二建集团有限公司 Pipe pile cap joint of cast-in-place pile pre-buried ground source heat pump
CN102733375A (en) * 2012-06-29 2012-10-17 上海建工二建集团有限公司 Pipe pile cap joint of cast-in-place pile pre-buried ground source heat pump
CN103383018A (en) * 2013-07-18 2013-11-06 河海大学 Construction method for embedding pipe in ground source heat pump pouring pile reinforcement cage
CN103498470B (en) * 2013-09-26 2015-08-19 河海大学 A kind of hexagon precast energy pile and preparation method thereof
CN103498470A (en) * 2013-09-26 2014-01-08 河海大学 Prefabricated hexagonal energy pile and manufacturing method thereof
CN104278670A (en) * 2014-10-23 2015-01-14 南京工业大学 Precast reinforced concrete pipe pile with spiral tube heat exchanger of ground source heat pump
CN104278669A (en) * 2014-10-23 2015-01-14 南京工业大学 Prefabricated reinforced concrete pipe pile with double-semicircle W-shaped parallel heat exchanger for ground source heat pump
CN104695432A (en) * 2015-03-18 2015-06-10 北京思创佳德桩工机械制造有限公司 Screw pile
CN107917552A (en) * 2016-01-29 2018-04-17 上海诺佛尔生态科技有限公司 It is easy to fix, prevent the construction method of the earth source heat pump of heat-transfer pipe deformation
CN105698437B (en) * 2016-01-29 2017-11-10 上海诺佛尔生态科技股份有限公司 A kind of U-joint used for geothermal heat pump, earth source heat pump and earth source heat pump construction method
CN105698437A (en) * 2016-01-29 2016-06-22 上海诺佛尔生态科技股份有限公司 U-shaped joint for ground source heat pump, ground source heat pump and ground source heat pump construction method
CN105951745A (en) * 2016-06-30 2016-09-21 青岛理工大学 Prefabricated geothermic energy pipe pile
CN105951745B (en) * 2016-06-30 2017-10-20 青岛理工大学 A kind of prefabricated geothermal energy pile tube
CN106016837B (en) * 2016-07-12 2018-06-15 三峡大学 A kind of energy acquisition and energy storage equipment based on pile-raft foundation
CN106049507A (en) * 2016-07-15 2016-10-26 山东省鲁南地质工程勘察院 Ground source well heat exchanger integrating ground temperature monitoring function and construction method of ground source well heat exchanger
CN108966966A (en) * 2018-09-13 2018-12-11 吉林省三和清洁能源开发有限公司 A kind of greenhouse storing energy and supplying hot irrigation system
CN111733800A (en) * 2020-06-24 2020-10-02 河南居安供热技术有限公司 Self-winding energy pile

Similar Documents

Publication Publication Date Title
CN201116803Y (en) Ground source heat pump imbedded pipe heat-exchanging pile device
CN102587365B (en) Method for embedding precession-type backfill grouting ground source thermal energy conversion precast pile device into stratum
CN102808405B (en) PCC (Large Diameter Pipe Pile by using Cast-in-place Concrete) energy pile and manufacturing method thereof
CN202543904U (en) Screw-in wall-post-grouting precast pile device for ground-source heat energy conversion
CN108166486B (en) Deep buried pipe type prefabricated energy pipe pile and construction process thereof
CN102995627B (en) Geothermal energy collecting pile foundation
CN109458757B (en) Static drilling root planting energy pile and production method and construction method thereof
CN101182711A (en) Shallow layer geothermal energy converting anchor rod
CN110453676B (en) Prefabricated energy pile structure design and construction method
CN103016842B (en) Mud soft soil foundation earth source heat pump direct-burried heat exchanger reverse construction engineering method
CN103134236A (en) Construction method of tilted burying of underground heat exchanger of ground source heat pump
CN203569561U (en) Novel pile forming device of steel pipe protection wall cast-in-place piles following up drill
CN207904917U (en) Deep layer buried tube type prefabrication type energy pile pile
CN1945165A (en) Direct buried underground heat exchanger of engineering abandored water lowering well
CN107447749A (en) A kind of heat-exchange system and construction technology based on deep layer pipe laying and energy pile
CN103322832A (en) Ground source heat pump efficient heat exchanger and construction method thereof
CN108589708A (en) A kind of Multifunctional cast-in-situ major diameter foundation pit support pipe pile and ground temperature exchange system
CN111102765A (en) Novel prefabricated energy pile system and construction method thereof
CN205742161U (en) A kind of novel high-strength prefabricated geothermal energy concrete tubular pile
KR101303575B1 (en) Combined type geothermal system and construction method using large aperture punchung
CN1944806A (en) Low temperature geothermal energy converting cement and earth wet stirring pile
CN201412991Y (en) Temperature collecting well device for ground temperature heat and cold supply
CN211650816U (en) Prefabricated energy pile application structure
CN210441697U (en) Water well type spiral ground heat exchanger and heat exchange system
Liu et al. Vertical U-shaped heat exchangers for construction engineering: New promises and future challenges

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Nanjing Fengsheng New Energy Technology Co., Ltd.

Assignor: Hubei Fengshen Clean Air-conditioning Equipment Engineering Co., Ltd.

Contract record no.: 2010320000982

Denomination of utility model: Ground source heat pump imbedded pipe heat-exchanging pile device

Granted publication date: 20080917

License type: Exclusive License

Record date: 20100720

CX01 Expiry of patent term

Granted publication date: 20080917