CN1975112A - Shield tunnel subsidence control method based on exploring radar - Google Patents

Shield tunnel subsidence control method based on exploring radar Download PDF

Info

Publication number
CN1975112A
CN1975112A CN 200610147258 CN200610147258A CN1975112A CN 1975112 A CN1975112 A CN 1975112A CN 200610147258 CN200610147258 CN 200610147258 CN 200610147258 A CN200610147258 A CN 200610147258A CN 1975112 A CN1975112 A CN 1975112A
Authority
CN
China
Prior art keywords
tunnel
shield tunnel
grouting
neural network
detection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200610147258
Other languages
Chinese (zh)
Other versions
CN100445516C (en
Inventor
黄宏伟
谢雄耀
杜军
张丰收
田海洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CNB200610147258XA priority Critical patent/CN100445516C/en
Publication of CN1975112A publication Critical patent/CN1975112A/en
Application granted granted Critical
Publication of CN100445516C publication Critical patent/CN100445516C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention belongs to the field of tunnel and underground engineering technology. In the concrete, it relates to a shield tunnel settlement control method based on ground-detecting radar. Said control method includes the following steps: adopting ground-detecting radar equipment to make sectional and longitudinal detection of slurry injection after shield tunnel wall, determining and estimating dielectric constant of slurry injection material, making model testing detection to obtain data, extracting characteristic image and characteristic wave, utilizing wavelet neural network automatic identification method to obtain slurry injection layer distribution form, combining said slurry injection layer distribution form with ground settlement monitoring data and making analysis, then defining further construction measure for implementing settlement control according to the detected and analyzed result.

Description

Shield tunnel subsidence control method based on ground penetrating radar
Technical field
The invention belongs to tunnel and underground construction technical field, be specifically related to a kind of shield tunnel subsidence control method based on ground penetrating radar.
Background technology
Though shield Method has experienced the development of nearly two a century, it has been a quite ripe construction technology, still there are many problems in the posterior settlement control and the construction quality management that cause but it is constructed in soft soil layer, these cause the excessive deformation of stratum generation on every side, cause a lot of unnecessary engineering accidents.Cause mainly containing of subway engineering accident:
(1) vertical differential settlement of subway tunnel operation phase.Mainly comprise: duct piece connector opens even leaks, leaks mud and track rigidity railway roadbed and tunnel duct piece and breaks away from.
(2) double-O-tube shield settlement after construction problem.Sea-gull piece top produces the back of the body soil phenomenon of coming to nothing, and the stress of column is concentrated problems such as destruction.
(3) by-pass construction freezing method problem.Freeze in the construction freezing method process scope determine and the worker after the tunnel thaw collapse also be the problem that tunnel structure safety is produced a very large impact.
From the problem that subway work ran into, in the constructing tunnel process: in soft soil layer, adopt the shield construction tunnel,, must cause surface deformable even cause the distortion of tunnel structure itself because of stratum loss and soil disturbance.The ground settlement that causes with the engineering slurry balance shield construction of threaded list road, south, East Road, Yan'an, Fig. 1 Shanghai is an example.Since the shield tail haul out ground settlement that the back produces be the shield-tunneling construction disturbance produce final ground settlement about 60%.And the method that solves this key issue is exactly the structure void that generation is filled in slip casting timely after the shield tail is hauled out, and controls grouting amount, grouting pressure and slip casting position etc. accurately.
The problem that is run into from the tunnel operation process of present use: the vertical uneven subsidence of shield tunnel mainly is present in the built shield tunnel, is the influence of environment to shield tunnel.Because the variation of environment, the surrounding soil displacement, underground water runs off, the tunnel inhomogeneous deformation that factor such as liquefaction of soil for sleeping in causes under the tunnel that vibration causes.And big vertically inhomogeneous deformation all has certain potential threat to the safety and the comfortableness of tunnel structure safety, subway train operation.As above iron Line 1 in Haiti began to start building in 1989, be open to the traffic to nineteen ninety-five, and be article one subway tunnel in Shanghai.Owing to also lacked experience in the soft soil layer in Shanghai, building the subterranean railway tunnel at that time, build up from the tunnel, sedimentation in various degree just appears in running tunnel, after operation in a few years, and serious differential settlement and distortion that subway sectional tunnel produces.
At the above several problems that have a strong impact on the subway tunnel structural safety, a main way of solution is exactly slip casting.But at present, relatively blindly to the control measure of the vertical differential settlement in tunnel.Concrete way is the settlement observation data according to the face of land, in the big place of sedimentation, on the relevant position, carries out secondary or control slip casting by the injected hole of imbedding in early days in the tunnel.In this case, the force value of slip casting, slurries amount, range of grouting and a series of problems such as effect of finally controlling sedimentation all have certain uncertainty.Therefore, must detect the clay distribution after the tunnel wall, slip casting effect.
Owing to the disguise of tunnel wall grouting behind shaft or drift lining, the document from state's Neva is published does not still have solid detection means at present simultaneously.In the construction of current subway tunnel in Shanghai, only rely on the control device in the construction, comprise the slip casting time, grouting pressure, grouting amounts etc., the sedimentation and deformation in combined ground settlement observation, tunnel itself are monitored and are carried out quality control.Because the part characteristic of slurries, such as flowability, bleeding, permeability, gelation rate etc., and the characteristic on stratum of living in, tunnel, for example the tunnel degree of depth (goes up overburden layer thickness, be overlying burden), the concrete castability of soil layer, to phreatic permeability and phreatic flowability or the like factor, behind condition might not be uniformly to injecting cement paste in the section of jurisdiction, slurries may run off along some slurry path that overflows, cause grouting amount very big, grouting pressure does not increase.Carry out grouting behind shaft or drift lining in certain constructing tunnel and above-mentioned situation occurs,, still adhere to original grouting pressure standard because worry the TERM DEFORMATION in tunnel.Find that at last slurries flow in the discarded bomb shelter along the soil body slit of splitting.Such thing generation main cause is exactly the slip casting detection means that does not have corresponding maturation.
Summary of the invention
The object of the present invention is to provide a kind of shield tunnel subsidence control method based on ground penetrating radar.
The shield tunnel subsidence control method that the present invention proposes based on ground penetrating radar, adopting dynamic circulation feedback method DAC method (is D-detect; A-analyse; C-control) carry out shield tunnel subsidence control, be summarized as follows:
Mainly be to adopt ground penetrating radar equipment that the shield tunnel grouting behind shaft or drift lining is carried out full section and detection longitudinally in the D-detection process.
The A-analytic process mainly comprises: at first obtain the injecting paste material dielectric constant by measuring or estimating, and the model testing GPR that is applied to tunnel wall grouting behind shaft or drift lining layer surveys, GPR Forward modelling result and the on-the-spot data of surveying, therefrom extract characteristic image and characteristic wave by analysis, then it is imported sample as training, utilize the automatic identification procedure of wavelet neural network, obtain the distributional pattern of tunnel wall grouting behind shaft or drift lining layer; Analyze in conjunction with face of land settlement monitoring data in case of necessity.
C-determines next step Construction Control Measures according to above analysis result, and promptly the C process mainly is by adjusting construction parameter and carrying out the second compensation grouting method.For the effect of access control measure need be carried out on-the-spot detection, i.e. process D again.Form the circulation dynamic process, until control shield tunnel differential settlement distortion in full force and effect.(Fig. 1 is the flow process of this method).
The shield tunnel subsidence control method that the present invention proposes based on ground penetrating radar, its concrete steps are as follows:
(1) the shield tunnel grouting behind shaft or drift lining is carried out lossless detection: adopt ground penetrating radar equipment that full section in tunnel and detection are longitudinally carried out in the slip casting of shield tail, from described slip casting, obtain echo;
Ground penetrating radar, or title geological radar (Ground Penetrate/Probing Radar), being called for short GPR, is to utilize the reflection of high-frequency electromagnetic wave beam to survey invisible objective body or subsurface interface, to determine a kind of high-resolution electromagnetic scanning technology of its inner constructional form or position.
When the basic principle of ground penetrating radar utilizes electromagnetic wave to propagate exactly, on the interface that the dielectric constant of medium changes, produce the principle of reflection and refraction in medium, obtain the degree of depth of reflecting interface by analysis the emission echo.
(2) adopt Network Analyzer that shield tunnel grouting behind shaft or drift lining dielectric material characterisitic parameter is surveyed;
At present, permanent really for the electromagnetic wave velocity of wave often is to estimate velocity of electromagnetic waves according to the dielectric constant as constant.And the dielectricity feature of medium is unknown before detection behind the actual tunnel wall, and according to specific time and site changes because of the variation of frequency, in order to obtain being fit to the medium dielectric property parameter of frequency change, need measure the dielectric constant of grouting behind shaft or drift lining material.Can survey shield tunnel grouting behind shaft or drift lining dielectric material characterisitic parameter by the coaxial probe method.Instrument commonly used is the HP8753E Network Analyzer, and employings swept frequency range is 30KHz~6GHz, and this instrument can divide 401 sections automatically and carries out frequency sweep in the frequency range of needs detection, provides the relative dielectric constant value of the medium under the different frequency.
Can also estimate according to former empirical data surveying except utilizing Network Analyzer.The dielectric constant of gained is the call parameter that model testing ground penetrating radar, forward simulation and the on-the-spot data of surveying are handled.
(3) by to test of shield tunnel grouting behind shaft or drift lining detection model and forward simulation, the grouting layer lossless detection is demarcated characteristic image and characteristic wave;
Model testing: by can reach the purpose that instructs actual tunnel to survey to data analysis.The difference that model testing is mainly formed from injecting paste material, the difference of distributional pattern, different detection times and several main aspects such as structure void that may exist are analyzed.The signal of Fig. 2 model testing is surveyed characteristic image and the characteristic wave that obtains grouting layer by the ground penetrating radar to model testing, and imports sample as the training that the wavelet neural network image is discerned automatically.
Forward simulation:
Consider based on the characteristic that the shield tunnel grouting behind shaft or drift lining distributes, simulate the simulation that the ground penetrating radar electromagnetic wave is propagated in the medium behind the tunnel section of jurisdiction with Finite-Difference Time-Domain Method (FDTD).When the grouting behind shaft or drift lining model construction, suppose that firing angle is zero, do not consider the influence of magnetic conductivity, obtained the echo reflection model of GPR detection grouting behind shaft or drift lining according to the electromagnetic wave principle, several basic points according to the FDTD application, the forward simulation step that radar electromagnetic wave is propagated in the medium behind wall is summarized as follows: the basic parameter of medium behind the input tunnel duct piece wall, set up structural model, obtain and the input stimulus source discrete source is advanced diff, make it to become the point of corresponding time step, utilize Finite Difference-Time Domain branch principle to calculate electromagnetic wave propagation characteristic in medium, comprise reflection, resultant field and transmitted field are analyzed and calculated respectively to transmission and loss characteristic, calculate mirror field, the signal of output reflection ripple.According to above step, set up the program of the forward model that tunnel wall grouting behind shaft or drift lining distribution ground penetrating radar ripple propagates in dielectric layer, Fig. 3 is this flow chart.
Forward modelling result although there is repeatedly reflection interference ripple, still can demonstrate back wave position, three roads as shown in Figure 4 clearly from three groups of Simulation result images, first road is the air direct wave; Interface 1 is the reflection at layer of concrete and grouting layer interface; Interface 2 is the boundary reflection between grouting layer and the dry sand.For next step image recognition provides good directive function.
(4) based on the data of model-test data, forward simulation, shield tunnel ground penetrating radar image is discerned automatically, drawn tunnel wall grouting behind shaft or drift lining layer distributional pattern by Wavelet Neural Network Method.
A, extraction characteristic feature ripple
In order successfully underground target to be classified, the extraction of signal characteristic is crucial.The feature extraction of signal can be carried out from aspects such as time domain, frequency domain, auto-correlation, two spectrum, wavelet field, obtain through just drilling the checking of numerical simulation and model testing: the ground penetrating radar electromagnetic wave is on the interface between concrete and the injecting cement paste, and the phenomenon that has all occurred phasing back on the interface of the injecting cement paste and the soil body.Pursue waveform phase upset, and adjacent twice lineups position has the rule of similitude, cooperate power spectrumanalysis simultaneously, can obtain the distributional pattern and the thickness of grouting layer;
The automatic identification of B, wavelet neural network grouting behind shaft or drift lining layer
1) input of wavelet neural network training sample
The characteristic difference of in medium, propagating according to the ground penetrating radar electromagnetic wave, be the characteristics that medium interface is reflected in slurry layer generation polarity upset, from model testing result, Forward modelling result and on-the-spot result of detection that ground penetrating radar is surveyed, extract and comparatively typically contain of the input (as Fig. 5 is the characteristic wave of forward simulation) of the ground penetrating radar characteristic wave of grouting layer as the learning training sample of wavelet-neural network model.
2) the standard output of wavelet neural network training
The output sample of wavelet neural network is to determine according to the model testing result and the Forward modelling result in early stage.According to setting up the output collection on the artificial accurately comparison base of recognition, form the matrix of a specific size.Assignment 1 on the grouting layer position of identification, area assignment 0 beyond grouting layer, obtain the output sample matrix like this, adopt the MATLAB programmed process, value according to the zones of different in the matrix can obtain the colored grouting layer zone that shows, the mutual contrast verification that helps the wavelet neural network recognition result, Fig. 6 is that certain shield tunnel radar detection data is discerned automatically through wavelet neural network and carried out multi-scale wavelet transformation and handle the back coloured image, can very intuitively draw shield tunnel grouting behind shaft or drift lining distributional pattern from figure.
Wavelet neural network is discerned the accuracy of grouting layer automatically, largely depends on the quantity and the accuracy of the input and output data of training sample.Therefore need utilize existing a large amount of model testing detection data, the data and the field test data of forward simulation, therefrom extract the input set that typical waveform forms the wavelet neural network training sample, make sample have good representativeness and accuracy.
(5) control measure
The distributional pattern of the shield tunnel grouting behind shaft or drift lining layer that draws by the wavelet neural network automatic distinguishing method for image, analyze in conjunction with the monitored data of ground settlement in case of necessity, tunnel subsidence in constructing tunnel and the operation process is controlled, can be taked the method for in construction, adjusting constructing tunnel parameter (grouting pressure, grouting amount etc.) and carrying out second compensation slip casting.Need carry out on-the-spot detection again for the effect of access control measure, form the circulation dynamic process, until control shield tunnel differential settlement distortion in full force and effect.
Beneficial effect of the present invention:
Because the disguise of shield tunnel grouting behind shaft or drift lining, so mainly be to judge slip casting effect behind the wall up to now according to shield tunnel construction parameter (grouting pressure, grouting amount etc.), and on earth how actual effect, and existing recognition methods can not provide a concrete answer.And the application of DAC method of the present invention will address this problem well, and the effect that makes grouting behind shaft or drift lining makes shield tunnel subsidence control method more scientific from blindly determining concrete identification (effect as shown in Figure 6).
Description of drawings
Fig. 1 is the flow process diagram of DAC method of the present invention.
Fig. 2 is the schematic diagram of model testing.Wherein: (a) being simulation entity section of jurisdiction grouting behind shaft or drift lining device schematic diagram, (b) is device schematic diagram when behind the wall of simulation entity section of jurisdiction structure void being arranged.
Fig. 3 is the flow process diagram of forward simulation.
Fig. 4 is the Forward modelling result of certain thickness grouting layer.Wherein: (a) being forward model dielectric constant constant and size, (b) is Forward modelling result.
Fig. 5 is the characteristic wave of forward simulation.Wherein: (a) and (b) are respectively the characteristic wave of different-thickness grouting layer.
Fig. 6 discerns the grouting behind shaft or drift lining distributional pattern that obtains automatically for wavelet neural network.
Fig. 7 is a Shanghai subway tunnel wall grouting behind shaft or drift lining result of detection among the embodiment 1.
Fig. 8 is a simulation entity section of jurisdiction grouting behind shaft or drift lining device schematic diagram among the embodiment 1.
Fig. 9 is the characteristic wave that the model testing ground penetrating radar is surveyed among the embodiment 1.
Forward modelling result when Figure 10 is 20cm for grouting layer among the embodiment 1.Wherein: (a) being forward model dielectric constant constant and size, (b) is the Forward modelling result of embodiment 1.
Number in the figure: 1 is the section of jurisdiction, and 2 is arc formwork, and 3 is cross binding, and 4 is injecting cement paste, and 5 is structure void.
The specific embodiment
Further specify the present invention below by embodiment.
Embodiment 1: subway tunnel, Shanghai adopts the shield tunnel construction: the tunnel external diameter is φ 6200mm, and internal diameter is φ 5500mm, prefbricated tunnel lining section of jurisdiction through seam assembling, totally 855 rings, wherein steel pipe sheet 2 rings; Lining segment is a steel concrete, width 1200mm, and thick 350mm, lining segment concrete design strength is C55, impervious grade 〉=S10;
Adopt shield tail synchronous grouting mode in time to inject single liquid slurry, to fill the annular building space between excavation profile and the section of jurisdiction external diameter.After synchronous grouting is finished, utilize the section of jurisdiction hole for hoist to carry out secondary reinforcement slip casting to the place of not filling with.Injecting paste material comprises cement, swell soil, flyash, sand, Admixture and water.
The on-the-spot detection
At the scene uplink was carried out the detection of ground penetrating radar slip casting effect on July 25th, 2006,545 encircle that 835 rings carry out vertically and the hoop detection along the tunnel respectively.This test divides vertical survey line and loop wire survey line to survey: radar antenna frequency 250MHz, antenna step-length 0.025m.Antenna divides separation 0.003m.The time window 126ns, sampling number 316.Finish 8 of surveys line altogether, 6 of wherein vertical surveys line, 2 surveys line of hoop.This distance of testing longitudinal probing is 300 rings, and Fig. 7 is for wherein 793 encircling~797 rings along the vertical grouting behind shaft or drift lining distribution of tunnel bottom detection baseline results.The injecting paste material dielectric constant is measured and estimation:
Injecting paste material comprises cement, swell soil, flyash, sand, Admixture and water, and material usage is as shown in table 1.
Table 1 cement mortar material scale (unit: kg/m 3)
Cement Fine sand Flyash Swell soil Water Water reducing agent
125 260 1150 35 400 2.5
The slurries water content that adopts in this engineering is less than 20%.Therefore estimate that the dielectric constant (be 2 months the length of time, and look-in frequency is 250MHz) of slurries is: 22.
Model testing
Utilize a calibrated bolck in somewhere subway tunnel single targe structure construction section of jurisdiction commonly used to make as shown in Figure 8 test model.The section of jurisdiction diameter is 6.2m, and its width is 1m, and thickness is 350mm.An arc wooden form behind the section of jurisdiction, template and section of jurisdiction spacing are 200mm, form even slip casting thickness, fill single liquid slurry in the middle of template and section of jurisdiction.Utilize ground penetrating radar that this model testing is surveyed, drawn the characteristic wave (see figure 9) of grouting behind shaft or drift lining layer under the model testing situation.
Forward simulation
The thickness of this tunnel grouting layer is approximately 20cm, therefore adopts Finite-Difference Time-Domain Method (FDTD) method that grouting layer thickness is just being drilled numerical simulation for the 20cm model.
The discrete grid block planar dimension is 300 * 200 in the forward model; The maximum vertex of fillet is (300,200), and minimum vertex is (0,0); The center of antenna frequency is 200MHz, Δ x=Δ y=λ/20=0.025m.Wherein layer of concrete (simulation tunnel section of jurisdiction) is 14 grids, and 35cm is thick.If incidence wave is perpendicular to interface (θ=0), antenna branch separation is 6 grid=0.15m, and the step-length that antenna moves is 0.125m.Just drilling in the numerical model, the dielectric constant of each medium and thickness are as shown in figure 10.Layer of concrete ε=6.25, d=35cm, σ=0.001s/m; Dry sand ε=12, d=180cm, σ=0.002s/m.Fig. 5 is the characteristic wave of its Forward modelling result.
Wavelet neural network grouting behind shaft or drift lining layer is discerned automatically
Based on above-mentioned data, utilize wavelet neural network that 793 rings~797 ring result of detections are carried out grouting layer and discern automatically and carry out multi-scale wavelet transformation and handle back coloured image (shown in 6).The result shows that 795 rings~797 ring wall grouting behind shaft or drift lining amounts are less, and average thickness approximately has only 9.6cm, increases gradually from 793 rings~795 ring grouting amounts, and it is comparatively even to distribute, and average thickness reaches 19.1cm.
Control measure
Can intuitively obtain this shield tunnel grouting behind shaft or drift lining distributional pattern from Fig. 6, through checking with the site operation record, this section interval shield tail spillage occurred when construction, so grouting layer does not reach the thickness of design.So construction party has carried out slip casting control to it in time.

Claims (1)

1, a kind of shield tunnel subsidence control method based on ground penetrating radar adopts the dynamic circulation feedback method to carry out shield tunnel subsidence control, it is characterized in that concrete steps are as follows:
(1) the shield tunnel grouting behind shaft or drift lining is carried out lossless detection: adopt ground penetrating radar equipment that full section in tunnel and detection are longitudinally carried out in the slip casting of shield tail, from described slip casting, obtain echo;
(2) adopt Network Analyzer that shield tunnel grouting behind shaft or drift lining dielectric material characterisitic parameter is surveyed, the Network Analyzer swept frequency range is 30KHz~6GHz, and rule of thumb data are estimated simultaneously, obtain dielectric constant;
(3) by to test of shield tunnel grouting behind shaft or drift lining detection model and forward simulation, the grouting layer lossless detection is demarcated characteristic image and characteristic wave;
Model testing is the difference of forming from injecting paste material, the difference of distributional pattern, four aspects of different detection times and structure void are analyzed, survey characteristic image and the characteristic wave that obtains grouting layer by ground penetrating radar, and import sample as the training that the wavelet neural network image is discerned automatically to model testing;
The forward simulation step is: the basic parameter of medium behind the input tunnel duct piece wall, set up structural model, obtain and the input stimulus source, discrete source is advanced diff, make it to become the point of corresponding time step, utilize Finite Difference-Time Domain branch principle to calculate electromagnetic wave propagation characteristic in medium, comprise reflection, transmission and loss characteristic, analyze and calculate respectively the signal of resultant field and transmitted field, calculating mirror field, output reflection ripple;
(4) based on the data of model-test data, forward simulation, shield tunnel ground penetrating radar image is discerned automatically, drawn tunnel wall grouting behind shaft or drift lining layer distributional pattern by Wavelet Neural Network Method;
A, extraction characteristic feature ripple
The automatic identification of B, wavelet neural network grouting behind shaft or drift lining layer
1) input of wavelet neural network training sample
2) the standard output of wavelet neural network training
(5) control measure
The distributional pattern of the shield tunnel grouting behind shaft or drift lining layer that draws by the wavelet neural network automatic distinguishing method for image, monitored data in conjunction with ground settlement is analyzed, tunnel subsidence in constructing tunnel and the operation process is controlled, take in construction, to adjust constructing tunnel parameter and the method for carrying out second compensation slip casting, for the effect of access control measure need be carried out on-the-spot detection again, form the circulation dynamic process, until control shield tunnel differential settlement distortion in full force and effect.
CNB200610147258XA 2006-12-14 2006-12-14 Shield tunnel subsidence control method based on exploring radar Expired - Fee Related CN100445516C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB200610147258XA CN100445516C (en) 2006-12-14 2006-12-14 Shield tunnel subsidence control method based on exploring radar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB200610147258XA CN100445516C (en) 2006-12-14 2006-12-14 Shield tunnel subsidence control method based on exploring radar

Publications (2)

Publication Number Publication Date
CN1975112A true CN1975112A (en) 2007-06-06
CN100445516C CN100445516C (en) 2008-12-24

Family

ID=38125408

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB200610147258XA Expired - Fee Related CN100445516C (en) 2006-12-14 2006-12-14 Shield tunnel subsidence control method based on exploring radar

Country Status (1)

Country Link
CN (1) CN100445516C (en)

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100464155C (en) * 2007-07-13 2009-02-25 东南大学 Method for measuring complex foundation sedimentation and deformation by geological radar survey method
CN101364241B (en) * 2007-08-08 2010-06-02 同济大学 Computation method of shield tunnel liner continuous and nonuniform stiffness model structure
CN101299008B (en) * 2008-06-13 2010-06-23 同济大学 Trial model capable of simulating shield tunnel pipe slice joint and manufacturing method thereof
CN101943003A (en) * 2010-08-16 2011-01-12 上海地铁盾构设备工程有限公司 Shield construction system based on ground penetrating radar
CN101963507A (en) * 2010-08-16 2011-02-02 上海地铁盾构设备工程有限公司 Shield segment center detection system and shield posture determination method
CN102193515A (en) * 2011-01-27 2011-09-21 同济大学 Shield tunnel service channel freezing effect control method
CN102493424A (en) * 2011-11-24 2012-06-13 广州市地下铁道总公司 Prediction method for urban rail transit shield project
CN103343692A (en) * 2013-07-03 2013-10-09 上海建工集团股份有限公司 Radar antenna mounting device for cutter head of shield tunneling machine
CN103867208A (en) * 2014-03-12 2014-06-18 西安建筑科技大学 Method for controlling deformation of ground surface and pipelines in process of tunnel and underground works construction
CN103969627A (en) * 2014-05-26 2014-08-06 苏州市数字城市工程研究中心有限公司 Ground penetrating radar large-scale three-dimensional forward modeling method based on FDTD
CN104632244A (en) * 2014-12-16 2015-05-20 上海交通大学 Method for determining influences of land subsidence on subway tunnel settlement and protecting tunnel structure
CN104932025A (en) * 2015-06-11 2015-09-23 同济大学 Shield tunnel lifting hole wall penetration outward-extension type electromagnetic wave ground detecting system and application thereof
CN106545346A (en) * 2016-12-08 2017-03-29 中国地质大学(武汉) A kind of push pipe tunnel section optimization method
CN107120120A (en) * 2017-06-21 2017-09-01 同济大学 Vehicle frame walking shield tunnel grouting behind shaft or drift lining testing equipment
CN107386266A (en) * 2017-07-11 2017-11-24 中铁第勘察设计院集团有限公司 MJS reinforcing soft formation methods based on GPR
CN107402386A (en) * 2017-08-02 2017-11-28 中南大学 A kind of method of estimation of underground metalliferous pipe radius and buried depth based on BP neural network
CN108222952A (en) * 2017-12-18 2018-06-29 上海市基础工程集团有限公司 Airport taxi runway subsidence control method in shield crossing operation
CN108761449A (en) * 2018-06-11 2018-11-06 中国民航大学 A kind of disaster target imaging method under reinforcement echo interference
CN108933602A (en) * 2017-05-26 2018-12-04 爱思开海力士有限公司 Deep learning for ldpc decoding
CN109578020A (en) * 2018-11-26 2019-04-05 蓝传雯 Method is sprayed using the mould of electromagnetism template
CN111650584A (en) * 2020-05-14 2020-09-11 中国科学院武汉岩土力学研究所 Method and equipment for detecting reinforcement effect of shield tunnel through grouting behind wall
CN111706333A (en) * 2020-05-27 2020-09-25 上海市基础工程集团有限公司 Early warning and measuring system and method applied to shield tunnel interval construction settlement
CN112051570A (en) * 2020-09-09 2020-12-08 中铁二十局集团有限公司 Boulder detection method and apparatus, terminal device and storage medium
CN112287595A (en) * 2020-09-16 2021-01-29 同济大学 Method for predicting shield tunnel wall back grouting thickness based on ground penetrating radar detection and machine learning
CN112611332A (en) * 2020-09-28 2021-04-06 同济大学 Circumferential double-freedom-degree detection control device for shield wall back grouting
CN116413719A (en) * 2023-06-12 2023-07-11 深圳大学 Method and related equipment for exploration of lava pipeline below lunar subsurface

Cited By (42)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100464155C (en) * 2007-07-13 2009-02-25 东南大学 Method for measuring complex foundation sedimentation and deformation by geological radar survey method
CN101364241B (en) * 2007-08-08 2010-06-02 同济大学 Computation method of shield tunnel liner continuous and nonuniform stiffness model structure
CN101299008B (en) * 2008-06-13 2010-06-23 同济大学 Trial model capable of simulating shield tunnel pipe slice joint and manufacturing method thereof
CN101943003A (en) * 2010-08-16 2011-01-12 上海地铁盾构设备工程有限公司 Shield construction system based on ground penetrating radar
CN101963507A (en) * 2010-08-16 2011-02-02 上海地铁盾构设备工程有限公司 Shield segment center detection system and shield posture determination method
CN101963507B (en) * 2010-08-16 2012-02-01 上海地铁盾构设备工程有限公司 Shield segment center detection system and shield posture determination method
CN101943003B (en) * 2010-08-16 2012-07-11 上海地铁盾构设备工程有限公司 Shield construction system based on ground penetrating radar
CN102193515A (en) * 2011-01-27 2011-09-21 同济大学 Shield tunnel service channel freezing effect control method
CN102193515B (en) * 2011-01-27 2013-05-01 同济大学 Shield tunnel service channel freezing effect control method
CN102493424B (en) * 2011-11-24 2014-07-30 广州市地下铁道总公司 Prediction method for urban rail transit shield project
CN102493424A (en) * 2011-11-24 2012-06-13 广州市地下铁道总公司 Prediction method for urban rail transit shield project
CN103343692A (en) * 2013-07-03 2013-10-09 上海建工集团股份有限公司 Radar antenna mounting device for cutter head of shield tunneling machine
CN103343692B (en) * 2013-07-03 2015-05-13 上海建工集团股份有限公司 Radar antenna mounting device for cutter head of shield tunneling machine
CN103867208A (en) * 2014-03-12 2014-06-18 西安建筑科技大学 Method for controlling deformation of ground surface and pipelines in process of tunnel and underground works construction
CN103867208B (en) * 2014-03-12 2016-03-02 西安建筑科技大学 Control the method for earth's surface in tunnel and underground engineering construction process, pipeline distortion
CN103969627A (en) * 2014-05-26 2014-08-06 苏州市数字城市工程研究中心有限公司 Ground penetrating radar large-scale three-dimensional forward modeling method based on FDTD
CN103969627B (en) * 2014-05-26 2016-07-06 苏州市数字城市工程研究中心有限公司 The extensive D integral pin-fin tube analogy method of GPR based on FDTD
CN104632244A (en) * 2014-12-16 2015-05-20 上海交通大学 Method for determining influences of land subsidence on subway tunnel settlement and protecting tunnel structure
CN104932025A (en) * 2015-06-11 2015-09-23 同济大学 Shield tunnel lifting hole wall penetration outward-extension type electromagnetic wave ground detecting system and application thereof
CN104932025B (en) * 2015-06-11 2017-11-07 同济大学 Shield tunnel hole for hoist broken wall extending type electromagnetic wave visits ground system and its application
CN106545346B (en) * 2016-12-08 2017-08-25 中国地质大学(武汉) A kind of push pipe tunnel section optimization method
CN106545346A (en) * 2016-12-08 2017-03-29 中国地质大学(武汉) A kind of push pipe tunnel section optimization method
CN108933602A (en) * 2017-05-26 2018-12-04 爱思开海力士有限公司 Deep learning for ldpc decoding
CN108933602B (en) * 2017-05-26 2021-09-10 爱思开海力士有限公司 Deep learning for low density parity check decoding
CN107120120A (en) * 2017-06-21 2017-09-01 同济大学 Vehicle frame walking shield tunnel grouting behind shaft or drift lining testing equipment
CN107386266A (en) * 2017-07-11 2017-11-24 中铁第勘察设计院集团有限公司 MJS reinforcing soft formation methods based on GPR
CN107402386B (en) * 2017-08-02 2019-11-19 中南大学 A kind of estimation method of underground metalliferous round tube radius and buried depth based on BP neural network
CN107402386A (en) * 2017-08-02 2017-11-28 中南大学 A kind of method of estimation of underground metalliferous pipe radius and buried depth based on BP neural network
CN108222952A (en) * 2017-12-18 2018-06-29 上海市基础工程集团有限公司 Airport taxi runway subsidence control method in shield crossing operation
CN108761449A (en) * 2018-06-11 2018-11-06 中国民航大学 A kind of disaster target imaging method under reinforcement echo interference
CN108761449B (en) * 2018-06-11 2021-11-02 中国民航大学 Disaster target imaging method under interference of steel bar echo
CN109578020B (en) * 2018-11-26 2020-06-30 蓝传雯 Die spraying method using electromagnetic template
CN109578020A (en) * 2018-11-26 2019-04-05 蓝传雯 Method is sprayed using the mould of electromagnetism template
CN111650584A (en) * 2020-05-14 2020-09-11 中国科学院武汉岩土力学研究所 Method and equipment for detecting reinforcement effect of shield tunnel through grouting behind wall
CN111650584B (en) * 2020-05-14 2023-09-15 中国科学院武汉岩土力学研究所 Method and equipment for detecting grouting reinforcement effect behind shield tunnel wall
CN111706333A (en) * 2020-05-27 2020-09-25 上海市基础工程集团有限公司 Early warning and measuring system and method applied to shield tunnel interval construction settlement
CN112051570A (en) * 2020-09-09 2020-12-08 中铁二十局集团有限公司 Boulder detection method and apparatus, terminal device and storage medium
CN112287595A (en) * 2020-09-16 2021-01-29 同济大学 Method for predicting shield tunnel wall back grouting thickness based on ground penetrating radar detection and machine learning
CN112287595B (en) * 2020-09-16 2023-05-23 同济大学 Prediction method of post-grouting thickness of shield tunnel wall based on ground penetrating radar detection and machine learning
CN112611332A (en) * 2020-09-28 2021-04-06 同济大学 Circumferential double-freedom-degree detection control device for shield wall back grouting
CN116413719A (en) * 2023-06-12 2023-07-11 深圳大学 Method and related equipment for exploration of lava pipeline below lunar subsurface
CN116413719B (en) * 2023-06-12 2023-09-08 深圳大学 Method and related equipment for exploration of lava pipeline below lunar subsurface

Also Published As

Publication number Publication date
CN100445516C (en) 2008-12-24

Similar Documents

Publication Publication Date Title
CN100445516C (en) Shield tunnel subsidence control method based on exploring radar
Solla et al. A review of GPR application on transport infrastructures: Troubleshooting and best practices
CN111058855B (en) Deformation control method and evaluation system for shield underpassing structure
Solla et al. Ground-penetrating radar for the structural evaluation of masonry bridges: Results and interpretational tools
Yu et al. Quality monitoring of metro grouting behind segment using ground penetrating radar
Arede et al. Experimental characterization of the mechanical behaviour of components and materials of stone masonry railway bridges
CN101581701A (en) Method for detecting slip casting effect on ground surface
Karlovsek et al. Investigation of voids and cavities in bored tunnels using GPR
CN102980819B (en) The method of cement mixing soil intensity is detected with hardness test
CN106769753B (en) The trace structure column joint samples preparation method containing chisel for seepage tests
CN109188383A (en) Rich water gravel layer shield duct piece grouting behind shaft or drift lining geologic radar detection scheme
Chen et al. Study on the application of a comprehensive technique for geological prediction in tunneling
CN106149770A (en) Bored concrete pile pile foundation construction period synchronizes the large-section in-situ concrete pile hole wall Rock Mass Integrality detection method carried out
CN101581223A (en) Method for detecting slip casting effect of tunnel
Martini et al. Validation of nondestructive methods for assessing stone masonry using artificial neural networks
Huang et al. Research on void signal recognition algorithm of 3D ground-penetrating radar based on the digital image
Wang et al. Accurate detection technology of super long bored cast-in-place pile concrete pouring thickness based on ultrasonic inclined plane reflection measurement
Zhou et al. Application of ground penetrating radar in detecting deeply embedded reinforcing bars in pile foundation
CN110082758B (en) Pavement interlayer void detection and maintenance method
CN207366506U (en) The model test apparatus of concrete for hydraulic structure hidden defects detection
Liu et al. A system for inspecting karst voids during construction of cast-in-place pile foundations
KR101492117B1 (en) Method and System For Bore-hole Integrity Evaluation of Grouting in Umbrella Arch Methods Using Guided Ultrasonic Waves
Xie et al. Study on radargram characteristics of the backfill grouting quality evaluation of a shield tunnel using GPR
Li et al. Collaborative Methods for the Ground Settlement Control in Shield Tunnels: Based on Numerical Simulation, GPR Detection and Ground Monitoring
Anbazhagan Subsurface investigation—integrated and modern approach

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20081224

Termination date: 20111214