CN1704537A - Totally assembled type prefabricated concrete structure system - Google Patents

Totally assembled type prefabricated concrete structure system Download PDF

Info

Publication number
CN1704537A
CN1704537A CN 200410024722 CN200410024722A CN1704537A CN 1704537 A CN1704537 A CN 1704537A CN 200410024722 CN200410024722 CN 200410024722 CN 200410024722 A CN200410024722 A CN 200410024722A CN 1704537 A CN1704537 A CN 1704537A
Authority
CN
China
Prior art keywords
precast
concrete structure
short beam
structure system
short
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200410024722
Other languages
Chinese (zh)
Other versions
CN1316127C (en
Inventor
赵斌
吕西林
刘学剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CNB2004100247227A priority Critical patent/CN1316127C/en
Publication of CN1704537A publication Critical patent/CN1704537A/en
Application granted granted Critical
Publication of CN1316127C publication Critical patent/CN1316127C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

This invention discloses a total-prefabricated precast concrete structure system, comprising precast column, precast beam, short suspension beam forming precast-short beam assembly integral with precast column and matching with the connecting surface of precast beam and fixed, wherein, all the elements are built up on site. The invention makes the connection of precast beam and column can be adjusted according to the force to protect forced section rather than makes them directly locate on the column lateral. So is has the advantages of reasonable theory foundation, good structure and convenient execution.

Description

Complete prefabricated concrete structure system
Technical field
The present invention relates to precast concrete design and construction field, particularly complete prefabricated concrete structure system.
Background technology
At present, the common way of the bean column node of prefabricated concrete structure is that vertical posts directly is connected at position of joints with horizontal beam.The beam column juncture of the bent structure of common single storey industry workshop is: precast beam is sat put at vertical prefabricated column cap earlier, joint is positioned at the post upper surface, uses built-in fitting, bolt or reserved steel bar anchoring then; This connection way precast beam and prefabricated post can rotate relatively freely, thereby energy dissipation capability is relatively poor, and be unfavorable to opposing impact load or geological process.And to the prefabricated frame construction of general multilayer, the bonding land is positioned at beam-ends, and Liang Yuzhu makes rigidly connected form usually, but because joint is located immediately at the vertical posts side, this place often is the stressed cross section of least favorable, is easy to go beyond the limit of supporting capacity, causes destroying; Although structure has energy dissipation capability preferably, owing to a little less than the relative thin of bonding land, be easy to generate destruction than its position of Liangqi, thereby the bonding land is required height, corresponding cost improves, and is uneconomical.The bean column node of prestressing force prefabricated concrete structure normally applies prestressing force and forms the friction node, and beam column is formed integral body, and need apply prestressing force is one of principal character of this kind structural engagement method.
Summary of the invention
The object of the present invention is to provide a kind of connection reliable, stressed rationally have supporting capacity preferably, and the new structure system of good deformability and energy dissipation capability is particularly arranged under impact load or seismic loading.
For achieving the above object, the present invention is achieved in that
A kind of complete prefabricated concrete structure system, comprise prefabricated post, precast beam, also comprise the short beam of encorbelmenting, described prefabricated post and the described short beam of encorbelmenting constitute prefabricated post-short beam composite member integral body, and the bonding surface joint of described encorbelment short beam and described precast beam coincide and be fixing.
Preferable, the bonding surface joint of described encorbelment short beam and described precast beam is buried pre-embedded steel slab respectively underground.
Preferable, the bonding surface joint of described encorbelment short beam and described precast beam forms the stepped form that convex-concave interlaces, and implants engagement recesses relatively with engagement lugs.
Preferable, the bonding surface joint of described encorbelment short beam and described precast beam forms the sloping section of certain angle, overlaps mutually, and the angle of inclination of sloping section can be determined according to stressed and actual conditions.
Preferable, the bonding surface joint of described encorbelment short beam and described precast beam is fixed by bolt or pin or rivet.
The invention has the beneficial effects as follows: by the increase short beam of encorbelmenting, the junction surface that makes precast beam and prefabricated post no longer is to be located immediately at the prefabricated post side, but can change the position by adjusting precast beam length, thereby avoid the stressed cross section of least favorable according to concrete stressing conditions of when construction.Precast beam forms with the short beam of encorbelmenting, prefabricated post on-site consolidation, and the whole erection process all is to do operation, has improved working environment, has improved operating efficiency.It is reliable that the present invention has theoretical foundation, rational in infrastructure, easy construction, and required member is fit to advantages such as precast yard's large-scale production.
Description of drawings
Fig. 1 is the structural front view of first kind of juncture
Fig. 2 is the structure vertical view of first kind of juncture
Fig. 3 is the structural front view of second kind of juncture
Fig. 4 is the structure vertical view of second kind of juncture
Label declaration:
1 prefabricated post 2 short beam of encorbelmenting
3 bolts, 4 precast beams
5 pre-embedded steel slabs
The specific embodiment
The present invention will be further described below in conjunction with drawings and Examples.
Embodiment 1
As Fig. 1, Fig. 2, first kind of embodiment of the present invention is: the prefabricated post 1 and the short beam 2 of encorbelmenting are made prefabricated post-short beam composite member.Prefabricated post-short beam composite member, precast beam 4 are by precast yard's production and processing, the size that side, prefabricated post floor place has the short beam 2 of encorbelmenting is identical with precast beam 4 with the reinforcement placement mode, and the joint method of encorbelment short beam 2 and prefabricated post 4 adopts common rigid joint processing method.Form the concavo-convex stepped form that interlaces in the joint of the short beam 2 of encorbelmenting, in order to being connected with precast beam 4, precast beam 4 ends also are processed into the stepped form that the convex-concave corresponding to the short beam 2 of encorbelmenting interlaces, the equal pre-embedded steel slab 5 of all contact surfaces is strengthened, implant engagement recesses with engagement lugs, connect with bolt 3 then.Be convenient construction, the nut place of used bolt 3 forms the sulculus of appropriate depth, does not exceed precast beam 4 upper surfaces topmost with nut and is advisable.
Embodiment 2
As Fig. 3, Fig. 4, second kind of embodiment of the present invention is: the prefabricated post 1 and the short beam 2 of encorbelmenting are made prefabricated post-short beam composite member.Prefabricated post-short beam composite member, precast beam 4 are by precast yard's production and processing, side, prefabricated post floor place has the size of the short beam 2 of encorbelmenting, the reinforcement placement mode is identical with precast beam 4, and the joint method of encorbelment short beam 2 and prefabricated post 4 adopts common rigid joint processing method.Joint at the short beam 2 of encorbelmenting forms the sloping section with certain slope, and contact surface pre-embedded steel slab 5 is strengthened overlap joint, guarantees that closely the contact back connects with bolt 3, guarantees that bolt shaft is to vertical with the inclined-plane.Be convenient construction, the nut place of used bolt 3 forms the sulculus of appropriate depth, does not exceed precast beam 4 upper surfaces topmost with nut and is advisable.

Claims (5)

1. complete prefabricated concrete structure system, comprise prefabricated post, precast beam, it is characterized in that: also comprise the short beam of encorbelmenting, described prefabricated post and the described short beam of encorbelmenting constitute prefabricated post-short beam composite member integral body, and the bonding surface joint of described encorbelment short beam and described precast beam coincide and be fixing.
2. complete prefabricated concrete structure system according to claim 1 is characterized in that: the bonding surface joint of described encorbelment short beam and described precast beam is buried pre-embedded steel slab respectively underground.
3. complete prefabricated concrete structure system according to claim 1 and 2 is characterized in that: the bonding surface joint of described encorbelment short beam and described precast beam forms the stepped form that convex-concave interlaces, and implants engagement recesses relatively with engagement lugs.
4. complete prefabricated concrete structure system according to claim 1 and 2 is characterized in that: the bonding surface joint of described encorbelment short beam and described precast beam forms the sloping section of certain angle, mutually overlap joint.
5. complete prefabricated concrete structure system according to claim 1 and 2 is characterized in that: the bonding surface joint of described encorbelment short beam and described precast beam is fixed by bolt or pin or rivet.
CNB2004100247227A 2004-05-27 2004-05-27 Totally assembled type prefabricated concrete structure system Expired - Fee Related CN1316127C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2004100247227A CN1316127C (en) 2004-05-27 2004-05-27 Totally assembled type prefabricated concrete structure system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2004100247227A CN1316127C (en) 2004-05-27 2004-05-27 Totally assembled type prefabricated concrete structure system

Publications (2)

Publication Number Publication Date
CN1704537A true CN1704537A (en) 2005-12-07
CN1316127C CN1316127C (en) 2007-05-16

Family

ID=35576546

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2004100247227A Expired - Fee Related CN1316127C (en) 2004-05-27 2004-05-27 Totally assembled type prefabricated concrete structure system

Country Status (1)

Country Link
CN (1) CN1316127C (en)

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102661059A (en) * 2012-03-02 2012-09-12 同济大学 Unit-form residential building system of totally assembled type prefabricated concrete structure
CN102720304A (en) * 2012-06-15 2012-10-10 吴方伯 Reinforced concrete composite beam
CN101581114B (en) * 2008-05-16 2013-01-02 贵阳铝镁设计研究院有限公司 Reinforced concrete structural continuous beam with insulation property
CN102926463A (en) * 2012-11-09 2013-02-13 沈阳建筑大学 Plane external connection structure of cast-in-situ shear wall and prefabricated beam of assembly type concrete frame core tube structure
CN103104040A (en) * 2013-03-08 2013-05-15 郑州大学 Assembled framework beam-column joint adopting vertical connection and construction method thereof
CN103104041A (en) * 2013-03-08 2013-05-15 郑州大学 Assembled framework beam-column joint adopting transverse connection and construction method thereof
CN103104039A (en) * 2013-03-08 2013-05-15 郑州大学 Assembled framework beam-column joint adopting cover plate connection and construction method thereof
CN103290778A (en) * 2013-05-21 2013-09-11 北京交通大学 Method of improving bearing capacity of steel box girder joint
CN103541434A (en) * 2013-09-22 2014-01-29 沈阳建筑大学 Full-fabricated cross concrete combining joint
CN103541433A (en) * 2013-09-22 2014-01-29 沈阳建筑大学 Fabricated concrete hooking type joint
CN104532961A (en) * 2014-12-30 2015-04-22 中国电建集团贵阳勘测设计研究院有限公司 Connection method and structure for reinforced concrete cantilever beam and main body concrete
CN105863076A (en) * 2016-04-27 2016-08-17 重庆大学 Completely assembling type connecting structure for low-rise building
CN106013200A (en) * 2016-06-29 2016-10-12 山东远博建筑科技有限公司 Prefabricated assembly type strip foundation and construction technology
CN106149879A (en) * 2016-07-01 2016-11-23 四川省建筑科学研究院 The spelling dress floor system of spelling dress plate-column structure and composition thereof
CN106320164A (en) * 2016-08-22 2017-01-11 上海应用技术学院 Large prefabricated assembly cap beam with corbel structure and construction method
CN106320162A (en) * 2016-08-22 2017-01-11 上海应用技术学院 Prefabricated assembly cap beam structure with steel shear keys and construction method
CN107558311A (en) * 2017-09-14 2018-01-09 中铁第四勘察设计院集团有限公司 A kind of lateral connection component for straddle type monorail rail tracks
CN107620317A (en) * 2017-06-30 2018-01-23 中国冶集团有限公司 Piping lane construction foundation pit supporting supporting device
CN107882174A (en) * 2017-11-23 2018-04-06 厦门华旸建筑工程设计有限公司 A kind of suspended beam type steel structure frame
CN108755948A (en) * 2018-07-10 2018-11-06 福州大学 The assembled beam-column node structure and its construction method of tenon formula connection
CN109555232A (en) * 2018-12-20 2019-04-02 郑东华 Zheng Shi precast beam tenon connection connector
CN111206498A (en) * 2020-01-16 2020-05-29 姜江 Road bridge construction prefabricated plate connection structure
CN117840664A (en) * 2023-12-18 2024-04-09 中国科学院空间应用工程与技术中心 High-precision splicing structure and method for ultra-high-speed guide rail

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5024036A (en) * 1988-08-12 1991-06-18 Johnson David W Interlocking support structures
CH683931A5 (en) * 1991-11-05 1994-06-15 Daniel Erdin Support plate for post support - has nut with two flat sides, arranged in hole and on plate underside and has shaft screwing into it and which is attached to foundation
CN2390933Y (en) * 1999-06-04 2000-08-09 同济大学 Square steel pipe concrete beam and column jointing gusset
CN1079130C (en) * 1999-06-30 2002-02-13 张晶廷 Construction method of 3D architeccture system for house building
DE20013723U1 (en) * 1999-08-13 2000-12-07 Breit Sen Kit for a column
CN1263971A (en) * 2000-02-24 2000-08-23 施民 Technology for building house with centrifugal structural concrete members and frames without brick walls
CN1194150C (en) * 2001-07-26 2005-03-23 广东省建筑设计研究院 Storey steel pipe concrete column R.C joint

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101581114B (en) * 2008-05-16 2013-01-02 贵阳铝镁设计研究院有限公司 Reinforced concrete structural continuous beam with insulation property
CN102661059A (en) * 2012-03-02 2012-09-12 同济大学 Unit-form residential building system of totally assembled type prefabricated concrete structure
CN102661059B (en) * 2012-03-02 2014-09-17 同济大学 Unit-form residential building system of totally assembled type prefabricated concrete structure
CN102720304A (en) * 2012-06-15 2012-10-10 吴方伯 Reinforced concrete composite beam
CN102926463A (en) * 2012-11-09 2013-02-13 沈阳建筑大学 Plane external connection structure of cast-in-situ shear wall and prefabricated beam of assembly type concrete frame core tube structure
CN103104039B (en) * 2013-03-08 2015-07-22 郑州大学 Assembled framework beam-column joint adopting cover plate connection and construction method thereof
CN103104040A (en) * 2013-03-08 2013-05-15 郑州大学 Assembled framework beam-column joint adopting vertical connection and construction method thereof
CN103104041A (en) * 2013-03-08 2013-05-15 郑州大学 Assembled framework beam-column joint adopting transverse connection and construction method thereof
CN103104039A (en) * 2013-03-08 2013-05-15 郑州大学 Assembled framework beam-column joint adopting cover plate connection and construction method thereof
CN103104040B (en) * 2013-03-08 2015-10-14 郑州大学 A kind of assembling frame bean column node and construction method adopting vertical connection
CN103104041B (en) * 2013-03-08 2015-09-30 郑州大学 A kind of adopt cross bolts to connect assembled steel reinforced concrete frame bean column node and construction method
CN103290778A (en) * 2013-05-21 2013-09-11 北京交通大学 Method of improving bearing capacity of steel box girder joint
CN103541433A (en) * 2013-09-22 2014-01-29 沈阳建筑大学 Fabricated concrete hooking type joint
CN103541434A (en) * 2013-09-22 2014-01-29 沈阳建筑大学 Full-fabricated cross concrete combining joint
CN103541433B (en) * 2013-09-22 2015-12-09 沈阳建筑大学 Assembly concrete hook-hang type node
CN104532961A (en) * 2014-12-30 2015-04-22 中国电建集团贵阳勘测设计研究院有限公司 Connection method and structure for reinforced concrete cantilever beam and main body concrete
CN104532961B (en) * 2014-12-30 2017-02-22 中国电建集团贵阳勘测设计研究院有限公司 Connection method and structure for reinforced concrete cantilever beam and main body concrete
CN105863076A (en) * 2016-04-27 2016-08-17 重庆大学 Completely assembling type connecting structure for low-rise building
CN106013200A (en) * 2016-06-29 2016-10-12 山东远博建筑科技有限公司 Prefabricated assembly type strip foundation and construction technology
CN106149879A (en) * 2016-07-01 2016-11-23 四川省建筑科学研究院 The spelling dress floor system of spelling dress plate-column structure and composition thereof
CN106320162A (en) * 2016-08-22 2017-01-11 上海应用技术学院 Prefabricated assembly cap beam structure with steel shear keys and construction method
CN106320164A (en) * 2016-08-22 2017-01-11 上海应用技术学院 Large prefabricated assembly cap beam with corbel structure and construction method
CN107620317A (en) * 2017-06-30 2018-01-23 中国冶集团有限公司 Piping lane construction foundation pit supporting supporting device
CN107558311A (en) * 2017-09-14 2018-01-09 中铁第四勘察设计院集团有限公司 A kind of lateral connection component for straddle type monorail rail tracks
CN107882174A (en) * 2017-11-23 2018-04-06 厦门华旸建筑工程设计有限公司 A kind of suspended beam type steel structure frame
CN107882174B (en) * 2017-11-23 2023-11-07 厦门华旸建筑工程设计有限公司 Hanging beam type steel structure frame
CN108755948A (en) * 2018-07-10 2018-11-06 福州大学 The assembled beam-column node structure and its construction method of tenon formula connection
CN109555232A (en) * 2018-12-20 2019-04-02 郑东华 Zheng Shi precast beam tenon connection connector
CN111206498A (en) * 2020-01-16 2020-05-29 姜江 Road bridge construction prefabricated plate connection structure
CN117840664A (en) * 2023-12-18 2024-04-09 中国科学院空间应用工程与技术中心 High-precision splicing structure and method for ultra-high-speed guide rail

Also Published As

Publication number Publication date
CN1316127C (en) 2007-05-16

Similar Documents

Publication Publication Date Title
CN1704537A (en) Totally assembled type prefabricated concrete structure system
CN2685429Y (en) Precasted deformed column for integral prestress assembling plate-column structure
CN101029503A (en) Beam and pile assembled node of precast and prestressed concrete structure
CN101113604A (en) Full-prefabricated assembled concrete frame construction
CN107254925A (en) Vertical prestressing loam wall and its construction method
CN207211435U (en) A kind of vertical prestressing loam wall
CN1837527A (en) Profiled angle steel reinforced concrete structure, structure and member combination
CN103696429B (en) A kind of concrete of special-shaped foundation ditch supports the combined support system and the construction method that add fish belly sill
CN1873112A (en) New type base for mast type mechanical equipment
CN1326526A (en) Dome constructing method
CN2861328Y (en) Subsectional embedded structure of concrete steel column in reverse construction engineering
CN2701914Y (en) Concrete prefabricated and assembled multipurpose tower crane foundation
CN117248442A (en) Double-column pier and construction method thereof
EP1705313B1 (en) Reinforced console column and the method of its production
CN109914849B (en) FRP wall reinforcing device and reinforcing method
CN217975378U (en) Cast-in-place board template strutting arrangement of simple beam assembled
CN202610695U (en) Corrugated steel web type pre-tensioned prestressed concrete I-type beam
CN215594498U (en) Wall surface shear-resistant module for cluster low-rise steel structure
CN211874127U (en) Prefabricated enclosure and mounting structure thereof
CN112431436B (en) Anti-punching reinforcement construction method for flat slab
CN201794215U (en) Pretensioning method prestress reinforced concrete prefabricated beam
CN2583234Y (en) On site pouring reinforced concrete hollow cavity shearing wall
CN2752372Y (en) Finit cohesive steel strand for integrated prestress assembling plate-column structure
CN201053143Y (en) Whole-prefabricated assembling type concrete frame structure
CN111287555B (en) Prefabricated quickly-assembled enclosing wall structure and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20070516