CN1657718A - Method for repairing sewer using water-proof film lining - Google Patents

Method for repairing sewer using water-proof film lining Download PDF

Info

Publication number
CN1657718A
CN1657718A CN 200410016365 CN200410016365A CN1657718A CN 1657718 A CN1657718 A CN 1657718A CN 200410016365 CN200410016365 CN 200410016365 CN 200410016365 A CN200410016365 A CN 200410016365A CN 1657718 A CN1657718 A CN 1657718A
Authority
CN
China
Prior art keywords
water
criticize
sealing
grid cloth
repair
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200410016365
Other languages
Chinese (zh)
Other versions
CN1296577C (en
Inventor
李孝男
陶金龙
张阿林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI PUTUO MUNICIPAL ENGINEERING ADMINISTRATION
Original Assignee
SHANGHAI PUTUO MUNICIPAL ENGINEERING ADMINISTRATION
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI PUTUO MUNICIPAL ENGINEERING ADMINISTRATION filed Critical SHANGHAI PUTUO MUNICIPAL ENGINEERING ADMINISTRATION
Priority to CNB200410016365XA priority Critical patent/CN1296577C/en
Publication of CN1657718A publication Critical patent/CN1657718A/en
Application granted granted Critical
Publication of CN1296577C publication Critical patent/CN1296577C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

A method for repairing gulley drain with waterproof film, concretely including the following steps: stop water inject pulping and solidify soil; process with the destroyed point; set waterproof film; seal the edge; maintenance. During the process of repairing gulley drain in city and industrial area, the invention uses repairing technology in pipe, without need for digging largely on the road, less repairing cost, short term, simple operation, reliable quality, great practice, is suitable for being extended in gulley drain repairing in our country.

Description

A kind of method that adopts the waterproof film liner to repair sewer
Technical field
The present invention relates to the recovery technique of municipal engineering, specifically a kind of method that adopts the waterproof film liner to repair sewer.
Background technology
Generally all adopt excavation type comb job practices in the drainage pipe immersed tube of city, industrial occupancy is repaired, this job practices needs the road surface heavy excavation, and is time-consuming, influence traffic, especially in the city, this job practices is difficulty day by day, and the pressure that brings to urban traffic is too big.Also have at present and adopt external trenchless technology to repair sewer, though solved the problem that the road surface heavy excavation influences traffic, but this restorative procedure needs special construction machinery and the patching material of import, there is the repair cost height, complex operation, deficiencies such as long construction period are difficult to popularize in an all-round way in China's sewer is repaired and use.
Summary of the invention
A kind of method that adopts the waterproof film liner to repair sewer that the objective of the invention is to provide at the deficiencies in the prior art, it is repaired in pipe, do not need the road surface heavy excavation, repair cost is low, easy and simple to handle, short construction period, repairing quality is reliable, have very strong practicality, be convenient to China and in sewer is repaired, popularize use in an all-round way.
The concrete technical scheme that realizes the object of the invention is:
A kind of method that adopts the waterproof film liner to repair sewer, it comprises following concrete steps:
A, sealing leak stopping: with the sewer pipe shutoff, the desilting of drawing water with water under high pressure flush clean tube wall, is sought seepage, breaking point;
B, the solid soil of slip casting: open several grout holes from inside to outside at the pipe joint place, in managing, outwards the soil body outside the pipe joint pipe and the inspection shaft bottom soil body are carried out slip casting, the firm soil body;
C, breaking point are handled: adopt cement to accelerate to burn smart mode to the 1-3mm slit and repair; After adopting the water blockoff mortar to fill out embedding to the 4-10mm sealing, enrich sealing with the polyurethane injection; Adopt filleting technology to repair to the 11-30mm sealing;
D, the waterproof film liner is set: (1), pipe joint surfacing: the inwall with both sides, emery wheel hacking pipe joint center makes it have roughness; (2), implement the end and criticize: criticize at the bottom of scraping pasty state on the inwall of the both sides, pipe joint center of hacking batch, thickness remains on 2-3mm (3), lays grid cloth: treat the end criticize stiff after, lay grid cloth thereon; (4), face is criticized construction: criticize the pulpous state waterproof face of strike-ofing and criticize on grid cloth, thickness remains on 3-4mm;
E, edge sealing: with solvent-free epoxy resin to waterproof film liner both sides mouth edge sealing;
F, maintenance: natural curing water flowing after seven days.
Described slurry is made into cement, flyash, water glass.
Criticize and adopt polymer concrete dry-powder to add water furnishing pasty state at the described end.
Described grid cloth is fiberglass gridding cloth or chemical fibre grid cloth.
Described batch is adopted polymer concrete dry-powder addition polymerization compound cement based emulsion furnishing pasty state.
The present invention does not need the road surface heavy excavation just can repair immersed tube in repair in city, industrial occupancy sewer pipe, and it is low to have a rehabilitation expense, short construction period, easy and simple to handle, repairing quality is reliable, has very strong practicality, is convenient to China and popularizes use in an all-round way in sewer is repaired.
The specific embodiment:
1, sealing leak stopping:
At the pipeline section place blocking pipe that " immersed tube " phenomenon takes place, drain ponding in the pipe, poison gas situation in the detector tube, mud in the purge tube, with water under high pressure flush clean tube wall, enter then and seek the seepage breaking point in the pipeline, adopt the leak stopping of quick water blockoff mortar, that does not have obvious seepage breakage can carry out the construction of the grouting reinforcement soil body earlier in pipe.The emphasis of slip casting is fixed to the filling of the pipe joint place outer soil body of pipe and the inspection shaft bottom soil body, and plays the effect that water proof blocks water.Thereby the position of injected hole should be chosen in apart from per pass interface 0.30M place: require every pipe joint pipeline joint place is opened 4 injected holes up and down at least.Both sides grout hole about φ 800 following pipelines should be opened in pipe on the upper side; φ 1200 above pipelines should be opened in pipe position on the lower side, as the injected hole spacing excessive also should augment injected hole, do not produce phenomenon out of stock with the block water section of water proof consolidated earth mass of guarantee.1 of grout hole is offered in inspection shaft bottom, should control slurry denseness and by the required pressure of the grouting degree of depth during grouting well, and [following (containing φ 1000) the slip casting degree of depth of φ 1000 pipelines must not be less than 1.0M; φ 1200~φ 1800 slip casting degree of depth must not be less than 1.5M; The φ 2000 above slip casting degree of depth must not little 2.0M], answering pressure is done adjustment gradually from deep to shallow when grouting operation.Slip casting mixing ratio by weight [No. 525 cement: flyash: water glass, 0.9: 0.1: 30% (being radix promptly)] with concrete and coal ash weight sum.
2, breaking point is handled:
Adopting cement to accelerate to burn smart mode to 1~3mm slit repairs.
After adopting quick water blockoff mortar to fill out embedding to 4~10mm sealing, enrich sealing with the polyurethane injection again.
11~30mm sealing (interface does not misplace) employing filleting technology is repaired.
3, pipe joint is handled:
Waist hoop position exceeds the cement mortar of tube wall in cutting earlier, inwall with each 26-40 centimetre width of both sides, electric wheel hacking per pass interface center, and guaranteeing 52-80 centimetre width inner wall surface cleaning, flat, solid, the no greasy dirt of face, no loose and have certain roughness, the adhesion stress with tube wall is criticized at the enhancing end.(annotate: before the hacking in accordance with regulations width line location guarantee the profile standard.)
4, implementing the end criticizes:
Polyalcohol cement basis elastic water-proof film dry powder is added the thick pasty state of water furnishing, completely criticize surface, hacking place with the mud plate, width is each 0.25-0.4M of center with the interface, and thickness is not less than 2mm.(about 1: 4 of gouache ratio)
5, lay grid cloth
Criticize construction the end of at and promptly spread the wide fiberglass gridding cloth of one deck 48-78 centimetre or other chemical fibre grid cloth after about 5~6 hours.Grid cloth girth joining seam should be no less than 10 centimeters, and grid cloth is laid and must be close to the end and pull on, and rake angle can not be arranged, arches upward, phenomenon such as wrinkle, and the grid cloth of pipe top bit is used yoke and supported firmly, prevents sagging falling.
6, face is criticized construction:
Promptly carry out the waterproof face after grid cloth is laid and finished and criticize construction.Polymer concrete dry-powder and polymer cement base emulsion are pressed liquid: powder=4: 5, adopt special electric to stir instrument and constantly stir into uniform mortar shape, must not contain powder ball, grain piece in the mortar shape.Each charging must be removed clout foreign material in the bucket clean.Criticize with the mud plate and to scrape branch three roads and pull on, the fiber mesh cover is not had the end of at.After treating that one waterproof film surface is done, carry out second road again, the 3rd road is criticized and is scraped, this layer composite elastic grid cloth waterproof film thickness of inner lining should be no less than 4.5mm, criticize and add face and criticize about the about 6.5mm of gross thickness at the end, two limit mouths are made little chamfering.
7, edge sealing
With solvent-free epoxy resin to waterproof film liner both sides mouth edge sealing, to increase limit mouth adhesion stress and sealing.
8, maintenance
Natural curing water flowing after at least 7 days (with good conditionsi, curing time is longer better).
After above work progress enforcement, just form a kind of not only water-fast but also waterproof in the pipeline, and novel lining material with certain toughness and tensile strength, can resist structure, drainage pipe interface etc. because of the crack of expanding, shrinking or slight disturbance causing, phenomenon such as leak, easy construction, no seam, good integrity, rate of hardening is fast, can with multiple base material secure bond, be applicable to preventive overhaul engineering to drainage pipe.

Claims (5)

1, a kind of method that adopts the waterproof film liner to repair sewer is characterized in that it comprises following concrete steps:
A, sealing leak stopping: with the sewer pipe shutoff, the desilting of drawing water with water under high pressure flush clean tube wall, is sought seepage, breaking point;
B, the solid soil of slip casting: open several grout holes from inside to outside at the pipe joint place, in managing, outwards the soil body outside the pipe joint pipe and the inspection shaft bottom soil body are carried out slip casting, the firm soil body;
C, breaking point are handled: adopt cement to accelerate to burn smart mode to the 1-3mm slit and repair; After adopting the water blockoff mortar to fill out embedding to the 4-10mm sealing, enrich sealing with the polyurethane injection; Adopt filleting technology to repair to the 11-30mm sealing;
D, the waterproof film liner is set: (1), pipe joint surfacing: the inwall with both sides, emery wheel hacking pipe joint center makes it have roughness; (2), implement the end and criticize: criticize at the bottom of scraping pasty state on the inwall of the both sides, pipe joint center of hacking batch, thickness remains on 2-3mm; (3), lay grid cloth: treat the end criticize dry and hard after, lay grid cloth thereon; (4), face is criticized construction: criticize the pulpous state waterproof face of strike-ofing and criticize on grid cloth, thickness remains on 3-4mm;
E, edge sealing: with solvent-free epoxy resin to waterproof film liner both sides mouth edge sealing;
F, maintenance: natural curing water flowing after seven days.
2, restorative procedure according to claim 1 is characterized in that the slurry of being annotated is made into cement, flyash, water glass.
3, restorative procedure according to claim 1 is characterized in that the end criticizes to adopt polymer concrete dry-powder to add water furnishing pasty state.
4, repair method according to claim 1 is characterized in that grid cloth is fiberglass gridding cloth or chemical fibre grid cloth.
5, repair method according to claim 1 is characterized in that face is criticized to adopt polymer concrete dry-powder addition polymerization compound cement based emulsion furnishing pasty state.
CNB200410016365XA 2004-02-17 2004-02-17 Method for repairing sewer using water-proof film lining Expired - Fee Related CN1296577C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB200410016365XA CN1296577C (en) 2004-02-17 2004-02-17 Method for repairing sewer using water-proof film lining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB200410016365XA CN1296577C (en) 2004-02-17 2004-02-17 Method for repairing sewer using water-proof film lining

Publications (2)

Publication Number Publication Date
CN1657718A true CN1657718A (en) 2005-08-24
CN1296577C CN1296577C (en) 2007-01-24

Family

ID=35007409

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB200410016365XA Expired - Fee Related CN1296577C (en) 2004-02-17 2004-02-17 Method for repairing sewer using water-proof film lining

Country Status (1)

Country Link
CN (1) CN1296577C (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100532746C (en) * 2007-04-18 2009-08-26 上海龙日建设开发有限公司 Underground sewer repairing method
CN101235632B (en) * 2007-12-28 2010-06-02 中国水电顾问集团中南勘测设计研究院 Grouting leak-stopping technique
CN102486247A (en) * 2010-12-02 2012-06-06 杨兵 Water supply and drainage pipeline repair technique adopting size film lining method
CN103243801A (en) * 2013-04-25 2013-08-14 安徽建筑工业学院 Manhole repairing method
CN103437417A (en) * 2013-08-24 2013-12-11 无锡市政设计研究院有限公司 Part repair structure for steel lining of drainage pipeline
CN104060586A (en) * 2014-06-24 2014-09-24 大连市水利建筑设计院 Grouting anti-seepage method for lining steel pipe in reservoir water-supply tunnel
CN105363767A (en) * 2015-11-18 2016-03-02 同济大学 Extracting and injecting combined three-dimensional prevention and control method used for emergency treatment after soil pollution
CN109268624A (en) * 2018-10-19 2019-01-25 岭澳核电有限公司 Lengthen the life pipeline configuration and preparation method thereof
CN110617381A (en) * 2019-09-25 2019-12-27 郑州大学 Drainage pipeline cracking local plugging structure, plugging method and repairing method
CN111536362A (en) * 2020-04-28 2020-08-14 江苏绿材谷新材料科技发展有限公司 Method for grouting and reinforcing fiber grids of large-diameter concrete pipeline lining
CN112431990A (en) * 2020-12-11 2021-03-02 中国水利水电第七工程局成都水电建设工程有限公司 Method for repairing trenchless coating lining of large-diameter drainage pipeline
CN112746661A (en) * 2020-12-30 2021-05-04 北京城市排水集团有限责任公司 Small-sized drainage square ditch steel wire framework composite reinforcing and repairing system and construction method thereof

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1070568C (en) * 1992-08-11 2001-09-05 汉斯·穆勒 Method of repairing buried sewage pipes
JP3855096B2 (en) * 1999-10-18 2006-12-06 芦森工業株式会社 Pipeline lining method
KR100336372B1 (en) * 2000-01-26 2002-05-23 유정식 Inner Excavation Repairing

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100532746C (en) * 2007-04-18 2009-08-26 上海龙日建设开发有限公司 Underground sewer repairing method
CN101235632B (en) * 2007-12-28 2010-06-02 中国水电顾问集团中南勘测设计研究院 Grouting leak-stopping technique
CN102486247A (en) * 2010-12-02 2012-06-06 杨兵 Water supply and drainage pipeline repair technique adopting size film lining method
CN102486247B (en) * 2010-12-02 2014-04-09 杨兵 Water supply and drainage pipeline repair technique adopting size film lining method
CN103243801A (en) * 2013-04-25 2013-08-14 安徽建筑工业学院 Manhole repairing method
CN103437417A (en) * 2013-08-24 2013-12-11 无锡市政设计研究院有限公司 Part repair structure for steel lining of drainage pipeline
CN104060586A (en) * 2014-06-24 2014-09-24 大连市水利建筑设计院 Grouting anti-seepage method for lining steel pipe in reservoir water-supply tunnel
CN105363767A (en) * 2015-11-18 2016-03-02 同济大学 Extracting and injecting combined three-dimensional prevention and control method used for emergency treatment after soil pollution
CN109268624A (en) * 2018-10-19 2019-01-25 岭澳核电有限公司 Lengthen the life pipeline configuration and preparation method thereof
CN109268624B (en) * 2018-10-19 2021-06-11 岭澳核电有限公司 Life-prolonging pipeline structure and preparation method thereof
CN110617381A (en) * 2019-09-25 2019-12-27 郑州大学 Drainage pipeline cracking local plugging structure, plugging method and repairing method
CN111536362A (en) * 2020-04-28 2020-08-14 江苏绿材谷新材料科技发展有限公司 Method for grouting and reinforcing fiber grids of large-diameter concrete pipeline lining
CN111536362B (en) * 2020-04-28 2021-11-19 江苏绿材谷新材料科技发展有限公司 Method for grouting and reinforcing fiber grids of large-diameter concrete pipeline lining
CN112431990A (en) * 2020-12-11 2021-03-02 中国水利水电第七工程局成都水电建设工程有限公司 Method for repairing trenchless coating lining of large-diameter drainage pipeline
CN112746661A (en) * 2020-12-30 2021-05-04 北京城市排水集团有限责任公司 Small-sized drainage square ditch steel wire framework composite reinforcing and repairing system and construction method thereof

Also Published As

Publication number Publication date
CN1296577C (en) 2007-01-24

Similar Documents

Publication Publication Date Title
CN111485922B (en) Method for treating water leakage, block falling and slurry turning of ELF railway tunnel
CN110306616B (en) Construction method of sewage pipeline
CN1296577C (en) Method for repairing sewer using water-proof film lining
CN112431990B (en) Method for repairing trenchless coating lining of large-diameter drainage pipeline
CN1760455A (en) Method for treating collapsed road surface around inspection-pit for underground lines
CN102776897A (en) Wash apron anti-settling anti-cracking construction method and structure
CN104153371A (en) Grouting-to-stop-water construction method of underwater rubble bed
CN111424613A (en) Method for treating through cracks of roller compacted concrete dam
Morgado et al. Portuguese irrigation canals: lining solutions, anomalies, and rehabilitation
CN1317458C (en) Construction method for preventing seepage of channel joints
Lea et al. THE DETERIORATION OF CONCRETE IN STRUCTURES.
CN202148539U (en) Composite waterproof structure using underground engineering waterproof leaking stoppage treatment and construction method
CN102535493B (en) Method for constructing inverted type foundation beam
CN113374055A (en) Construction method of buried reinforced HDPE (high-density polyethylene) spiral corrugated pipe
CN104975623A (en) Non-excavation leaking inspection well repairing method and repairing structure
CN113833500B (en) Restoration method for waterproof and impermeable layer of mountain cave depot
RU2669302C1 (en) Method of repair and sealing of damage in concrete facings of channels
CN1195132C (en) Pipeline sinking process for use in tunnel foundation construction
CN1632288A (en) Method of vulcanized slurry synchronous slip casting for subway shield
CN113846695B (en) Reverse construction method basement construction method
CN218508504U (en) Composite impervious wall adapted to solid waste landfill
CN219527748U (en) Waterproof construction structure is synthesized to high water level area anti-floating anchor rod tip
CN210946357U (en) Horizontal double escape canal structure of motor vehicle way
Bauhan et al. Performance testing of trenchless wastewater line spot repairs
CN209397697U (en) Landscape pond bottom of pond that is a kind of while being built on ground library top plate and plain soil layer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20070124

Termination date: 20100217