CN117635057A - Building engineering construction monitoring method and system based on multidimensional data - Google Patents

Building engineering construction monitoring method and system based on multidimensional data Download PDF

Info

Publication number
CN117635057A
CN117635057A CN202311657959.8A CN202311657959A CN117635057A CN 117635057 A CN117635057 A CN 117635057A CN 202311657959 A CN202311657959 A CN 202311657959A CN 117635057 A CN117635057 A CN 117635057A
Authority
CN
China
Prior art keywords
sub
project
consumption
event
engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311657959.8A
Other languages
Chinese (zh)
Inventor
何冲
董文芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Pengyuan Construction Engineering Group Co ltd
Original Assignee
Shenzhen Pengyuan Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Pengyuan Construction Engineering Group Co ltd filed Critical Shenzhen Pengyuan Construction Engineering Group Co ltd
Priority to CN202311657959.8A priority Critical patent/CN117635057A/en
Publication of CN117635057A publication Critical patent/CN117635057A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention belongs to the technical field of RPA (remote procedure alliance), and provides a building engineering construction monitoring method and system based on multidimensional data, comprising the steps of obtaining engineering project information, disassembling the engineering project into a plurality of sub-projects, and determining material information required by the engineering project and total requirement of each material; determining the material types and the quantity of the sub-items and the types of the demand equipment based on the sub-items, and disassembling the sub-items into a plurality of events; the invention can complete the progress monitoring of the engineering project through the multidimensional data of the materials, optimize the progress of the engineering project based on the forward fluctuation reason of the consumption of each material every day, ensure the completion of the engineering project in the expected time and improve the completion efficiency of the engineering project to a certain extent.

Description

Building engineering construction monitoring method and system based on multidimensional data
Technical Field
The invention relates to the technical field of engineering project data processing, in particular to a building engineering construction monitoring method and system based on multidimensional data.
Background
Project progress prediction refers to predicting the progress status of a project in a future time period by comprehensively considering project budget, resources, progress status of each activity and other factors so as to perform effective project management and control, thereby highlighting the importance and necessity of project progress prediction.
At present, in the process of carrying out engineering projects, the progress information of the engineering projects can only be counted in a manual mode, and then the progress information is recorded into a computer for drawing and analyzing a table, because the engineering projects are long in time period and large in data quantity to be collected, when people draw and analyze the table, unified standards do not exist, the randomness is large, the specific progress condition of the projects cannot be objectively reflected, the labor and time spent in carrying out progress measurement on the large engineering projects are excessive, the monitoring efficiency is seriously reduced, the finally obtained result is inaccurate, and no help is provided for optimizing and improving the efficiency of the engineering projects.
Disclosure of Invention
(one) solving the technical problems
Aiming at the defects of the prior art, the invention provides a building engineering construction monitoring method and system based on multidimensional data, which are used for solving the problems in the background art.
(II) technical scheme
In order to achieve the above purpose, the invention is realized by the following technical scheme: a building engineering construction monitoring method based on multidimensional data comprises the following steps:
s1: acquiring engineering project information, decomposing the engineering project into a plurality of sub-projects, and determining material information required by the engineering project and total requirements of each material;
s2: determining the material types and the quantity of the sub-items and the types of the demand equipment based on the sub-items, and disassembling the sub-items into a plurality of events;
s3: arranging a plurality of events of the sub-items according to the sequence of the sub-item flow, calculating the accumulation amount of each material used in the completion process of the plurality of events, determining the individual total amount of each material required by each event, and marking the events of new materials or new equipment;
s4: counting the accumulated consumption of the materials and the consumption of the materials on a single day;
s5: determining a current project schedule based on the cumulative consumption of material, the single-day consumption of material, and the point in time when new material or new equipment is present;
s6: and predicting and early warning the project completion time based on the determined current project progress data.
As a preference of this embodiment, the specific steps of S4 are as follows:
carrying out time line statistics on the consumption of each material every day based on the construction of engineering projects;
and calculating the total consumption of each material based on the consumption of each material collected every day, and simultaneously calculating the daily average consumption of each material of the first sub-project to obtain daily average consumption data of each material.
As a preference of this embodiment, the specific flow in S5 is as follows:
judging whether new materials are consumed or new equipment works, comparing and calculating the accumulated consumption of each material of the first sub-project with the demand of each material of the event, and determining the event currently processed;
determining current sub-project construction data based on the determined current processing event and comparing the current daily material consumption with the average front material consumption;
and determining the progress of the current engineering project based on the determined current construction sub-project and the current processing time.
As a preferred embodiment, the process of determining whether new materials are consumed or new equipment is operated, comparing the accumulated consumption of each material of the sub-project with the demand of each material of the event, and determining the event currently processed includes:
determining whether new material usage or new equipment is in operation, determining an event based on the new material or new equipment;
determining the cumulative usage of each material of the first sub-item Nbeta j N=1, 2, 3,..n, N represents the label of each sub-item in the project, j represents the alternative label of each material in the project, several events in the first sub-itemRespective material requirements Nmu ij I=1, 2, 3,..and n, i representing the number of each event in the sub-item, determining the first sub-item event scheduleWhere m is the event that the first child item is in progress.
As a preferable mode of this embodiment, the process of determining the current sub-project construction data based on the determined current processing event and comparing the consumption amount of each material on the same day with the consumption data of each material on the same day includes:
m1: determining the accumulated usage amount alpha of each material of engineering projects j J represents the substitute label of each material in the engineering project, and the difference K between the cumulative usage of each material in the engineering project and the cumulative usage of each material determined to be subjected to the event sub-project is calculated j
M2: calculating the difference L between the consumption of each material on the same day and the consumption of each material on the same day of the determined event sub-project j
M3: based on K j Analyzing which two groups of marked events the event currently performed by the next sub-item is specifically between;
m4: difference K based on cumulative usage of each material j And the difference L of the consumption of each material on the same day j Determining the current event of the next sub-item;
m5: steps M1-M5 are repeated until all ongoing sub-items and events carried out by the sub-items are determined.
As a preference of this embodiment, the specific flow of S6 includes:
setting expected completion time for the first execution sub-item based on the disassembled sub-items;
counting the consumption of each material and the daily average consumption of each material of the first execution sub-project, calculating the fluctuation value of each material consumption per day, setting a fluctuation threshold, and analyzing the reason or carrying out early warning if the fluctuation of the daily consumption of the material is larger than the fluctuation threshold;
calculating the completion time of the sub-project based on the daily average consumption of each material of the sub-project and the total material demand of each sub-project event arranged in time;
based on the actual completion time of the first sub-project, the completion time of the subsequent sub-project is predicted, and meanwhile, monitoring and early warning are carried out on the engineering project based on the consumption of each material of each sub-project every day.
As a preferred embodiment, the multi-dimensional data-based construction monitoring system for construction of building engineering includes:
the information acquisition module is used for acquiring engineering project information and environment information;
the project disassembly module is used for splicing the engineering project into a plurality of sub-projects and disassembling the sub-projects into a plurality of events;
the data recording module is used for recording the engineering project, a plurality of sub projects and various material data required by a plurality of events, counting the accumulated consumption of various materials and the single-day material consumption data, and marking the events of new materials or new equipment based on the recorded various material data;
the analysis and calculation module is used for analyzing the data recorded by the data recording module and calculating the current detailed precision of the engineering project;
the monitoring and early warning module predicts and early warns the completion time of the engineering project based on the determined progress data of the current engineering project;
the memory module is used for storing all information of the engineering project and sending the engineering project information to the analysis and calculation module and the detection and early warning module.
As a preferred mode of this embodiment, the analysis and calculation module is configured to determine whether new material consumption or new equipment works, compare and calculate cumulative consumption of each material of the first sub-project with demand of each material of each event, determine a currently processed event, determine current sub-project construction data based on the determined currently processed event, compare current daily material consumption with average consumption of the front material, and determine current project progress based on the determined current construction sub-project and current processing time.
As a preferable mode of this embodiment, the flow of determining the progress of the current engineering project by the analysis and calculation module is specifically as follows:
determining whether new material usage or new equipment is in operation, determining an event based on the new material or new equipment;
determining the cumulative usage of each material of the first sub-item Nbeta j N=1, 2, 3,..n, N represents the label of each sub-item in the project, j represents the alternative label of each material in the project, and each material demand N μ for each of several events in the first sub-item ij I=1, 2, 3,..and n, i representing the number of each event in the sub-item, determining the first sub-item event scheduleWherein m is an ongoing event of the first sub-item;
determining the accumulated usage amount alpha of each material of engineering projects j J represents the substitute label of each material in the engineering project, and the difference K between the cumulative usage of each material in the engineering project and the cumulative usage of each material determined to be subjected to the event sub-project is calculated j
Calculating the difference L between the consumption of each material on the same day and the consumption of each material on the same day of the determined event sub-project j
Based on K j Analyzing which two groups of marked events the event currently performed by the next sub-item is specifically between;
difference K based on cumulative usage of each material j And the difference L of the consumption of each material on the same day j Determining the current event of the next sub-item;
the process of confirming the current event of the next sub-item is repeated until all the ongoing sub-items and the events carried out by the sub-items are determined.
As an preference of this embodiment, the specific process of predicting and pre-warning the completion time of the engineering project by the monitoring and pre-warning module includes:
setting expected completion time for the first execution sub-item based on the disassembled sub-items;
counting the consumption of each material and the daily average consumption of each material of the first execution sub-project, calculating the fluctuation value of each material consumption per day, setting a fluctuation threshold, and analyzing the reason or carrying out early warning if the fluctuation of the daily consumption of the material is larger than the fluctuation threshold;
calculating the completion time of the sub-project based on the daily average consumption of each material of the sub-project and the total material demand of each sub-project event arranged in time;
based on the actual completion time of the first sub-project, the completion time of the subsequent sub-project is predicted, and meanwhile, monitoring and early warning are carried out on the engineering project based on the consumption of each material of each sub-project every day.
(III) beneficial effects
The invention provides a building engineering construction monitoring method and system based on multidimensional data, which have the following beneficial effects:
the invention divides the project into a plurality of sub-projects, then divides the sub-projects into a plurality of events, sets a mark event according to the position of the occurrence of the materials in the plurality of events, calculates the ongoing event of the first sub-project by counting the accumulated usage of each material in the first sub-project and the daily usage of each material in the project, determines all the follow-up ongoing sub-projects and the ongoing events thereof by the difference value between the accumulated usage of each material in the project and the accumulated usage of each material in the determined event sub-project and the difference value between the current consumption of each material in the project and the current consumption of each material in the determined event sub-project, and the progress of the engineering project can be monitored through materials, meanwhile, the process of completion of the first sub-project is taken as reference data, the event similarity of the first sub-project and the subsequent sub-project, the consumption of each material every day and the total amount of each material required by the event of the subsequent sub-project are combined to push out the completion time of each subsequent sub-project, so that the completion time estimation of the engineering project is completed, and when the engineering project is performed, the progress of the engineering project is optimized based on the forward fluctuation reason of the consumption of each material every day, the completion of the engineering project in the expected time is ensured, and the completion efficiency of the engineering project can be improved to a certain extent.
Drawings
FIG. 1 is a flow chart of a method for monitoring construction of a building engineering based on multidimensional data;
fig. 2 is a block diagram of a construction monitoring system based on multidimensional data.
Detailed Description
Embodiments of the present invention are described in detail below, examples of which are illustrated in the accompanying drawings, wherein the same or similar reference numerals refer to the same or similar elements or elements having the same or similar functions throughout. The embodiments described below by referring to the drawings are exemplary only for explaining the present invention and are not to be construed as limiting the present invention.
Example 1
Referring to fig. 1, an embodiment of the present invention provides a method for monitoring construction of a building engineering based on multidimensional data, which is characterized in that: the method comprises the following steps:
s1: acquiring engineering project information, decomposing the engineering project into a plurality of sub-projects, and determining material information required by the engineering project and total requirements of each material;
specifically, the collected project information includes project locations, project types, budget totals, project amounts for each project category, budget amounts, number of deployment constructors, and planned construction period, wherein the project types include house construction, highway construction, railway laying, bridge construction, and the like.
S2: determining the material types and the quantity of the sub-items and the types of the demand equipment based on the sub-items, and disassembling the sub-items into a plurality of events;
specifically, the project, when disassembled, forms a plurality of sub-projects, each of which is independent and requires the use of a quantity of building material to complete, and the sub-projects use some building equipment during the process. Wherein each sub-item can be broken down into several events.
The project is to build a cell, the disassembled sub-project can be to build a building, and the event can be to build a layer in the building; if the engineering project is the construction of a section of long highway, the disassembled sub-project can be a section of long highway, and the event can be roadbed construction, pavement paving or roadside reinforcement in the construction process of a section of highway.
S3: arranging a plurality of events of the sub-items according to the sequence of the sub-item flow, calculating the accumulation amount of each material used in the completion process of the plurality of events, determining the individual total amount of each material required by each event, and marking the events of new materials or new equipment;
specifically, when each sub-item is disassembled into a plurality of events, the disassembly positions are engineering nodes of the sub-items, the events in each sub-item are ordered according to the flow of the sub-item, and different event types exist in the plurality of events of the sub-item, but the same event type exists in the plurality of events.
Wherein, the event that new material or new equipment appears is specifically split according to the node in the sub-project. And in addition to the first event in a plurality of events, if a material or new equipment which does not appear in the previous event appears in the subsequent events, the event is a mark event. For example, event 1 has materials such as cement, sand, and screw bars, event 2 uses cement and sand, event 2 is a non-marking event, and event 3 uses cement, sand, screw bars, and plain round bars, event 3 is a marking event.
Illustratively, when the sub-project is a highway construction, the event to which the sub-project is detachable is that the foundation of a partial area of the highway is flat, cement or asphalt is paved on the road, the road is flat after paving, the road edge is corrected, and the like, the events indicated by the foundation leveling of a partial area of a section of highway, the cement or asphalt paving of the road, the road leveling after paving and the road edge correction are all part of the same events, and the road paving is carried out along the road trend.
S4: counting the accumulated consumption of the materials and the consumption of the materials on a single day;
the statistical flow of the accumulated consumption and the single-day consumption of the material comprises the following steps: the type and consumption of daily consumable material is counted and the daily recorded material consumption is accumulated.
S5: determining a current project schedule based on the cumulative consumption of material, the single-day consumption of material, and the point in time when new material or new equipment is present;
s6: and predicting and early warning the project completion time based on the determined current project progress data.
Further, the specific steps of S4 are as follows:
carrying out time line statistics on the consumption of each material every day based on the construction of engineering projects;
and calculating the total consumption of each material based on the consumption of each material collected every day, and simultaneously calculating the daily average consumption of each material of the first sub-project to obtain daily average consumption data of each material.
When the daily average consumption of each material in the first sub-item is counted, the denominator is calculated specifically by counting the occurrence days of a certain material, all the daily average consumption of the material in the day is counted as a numerator, and the consumption of the material is obtained by the ratio of the two.
Further, the specific flow in S5 is as follows:
judging whether new materials are consumed or new equipment works, comparing and calculating the accumulated consumption of each material of the first sub-project with the demand of each material of the event, and determining the event currently processed;
determining current sub-project construction data based on the determined current processing event and comparing the current daily material consumption with the average front material consumption;
and determining the progress of the current engineering project based on the determined current construction sub-project and the current processing time.
Further, the determining whether new material consumption or new equipment works, comparing the accumulated consumption of each material of the sub-project with the demand of each material of the event, and determining the current event comprises:
determining whether new material usage or new equipment is in operation, determining an event based on the new material or new equipment;
determination of firstCumulative usage Nbeta of each material of sub-projects j N=1, 2, 3,..n, N represents the label of each sub-item in the project, j represents the alternative label of each material in the project, and each material demand N μ for each of several events in the first sub-item ij I=1, 2, 3,..and n, i representing the number of each event in the sub-item, determining the first sub-item event scheduleWhere m is the event that the first child item is in progress.
It will be appreciated that the cumulative amount of each material used in the first sub-item is specifically expressed as 1β j The cumulative usage of each material of the second sub-item is specifically expressed as 1 beta j The cement accumulation using amount of the first sub-item is specifically expressed as 1 beta Cement and its preparation method The respective material demand amounts Nmu of the first event in the first sub-item i1 Cement demand N mu for the first event in the first sub-item Cement 1
Specifically, the total amount of each material required by the event arranged in sequence with the first sub-item is gradually accumulated, and when the accumulated value of each material is greater than the accumulated usage amount of each material of the sub-item after a certain event is reached and the accumulated value of each material of the event before the event is less than or equal to the accumulated usage amount of each material of the sub-item, the event currently in progress with the first sub-item can be obtained.
Note that, nβ j Where j may replace the names of the materials to indicate the cumulative amount of use of a material, and j may refer to the use of a new device.
Further, the process of determining the current sub-project construction data based on the determined current processing event and comparing the consumption of each material on the same day with the consumption data of each material on the same day includes:
m1: determining the accumulated usage amount alpha of each material of engineering projects j J represents the substitute label of each material in the engineering project, and the difference K between the cumulative usage of each material in the engineering project and the cumulative usage of each material determined to be subjected to the event sub-project is calculated j
Specifically, the calculation formula is K j =α jj ,K j For the current usage of each material of the event sub-item which is not performed, the event sub-item is determined to be epsilon j
M2: calculating the difference L between the consumption of each material on the same day and the consumption of each material on the same day of the determined event sub-project j
Specifically, the calculation formula is L j =θ jj The consumption of each material is theta j It has been determined that the daily consumption of each material of the event sub-project is sigma j
M3: based on K j Analyzing which two groups of marked events the event currently performed by the next sub-item is specifically between;
specifically, after removing the sub-items for which the event has been determined to be performed, the respective amounts of material K currently used by the remaining sub-items are determined j Based on K j New material or new equipment is present in the sub-project, and the next sub-project can be directly determined between two sets of marking events.
M4: difference K based on cumulative usage of each material j And the difference L of the consumption of each material on the same day j Determining the current event of the next sub-item;
specifically, after determining which two marked events the next sub-item is between, which materials and L are used based on the events between the two sets of marked events, respectively j A currently ongoing event is determined.
Wherein the difference L of the consumption of each material on the same day j The type of the daily consumption material can be obtained, the specific consumption of each material is compared with the daily consumption of each material of the first sub-item, based on L j The type of material and the amount of consumption of the material to determine the event currently being performed.
It should be noted that, in the event between two adjacent marked events in the sub-item, the material type of each event is different.
M5: steps M1-M5 are repeated until all ongoing sub-items and events carried out by the sub-items are determined.
Further, the specific process of S6 includes:
setting expected completion time for the first execution sub-item based on the disassembled sub-items;
counting the consumption of each material and the daily average consumption of each material of the first execution sub-project, calculating the fluctuation value of each material consumption per day, setting a fluctuation threshold, and analyzing the reason or carrying out early warning if the fluctuation of the daily consumption of the material is larger than the fluctuation threshold;
specifically, the fluctuation threshold may be set to ±2%, i.e
-2% < (consumption value of a certain material on the day-average consumption value of the material)/average consumption value of the material 100% < 2%; and if the analysis and investigation cause is the waste of materials, the analysis and investigation cause is more than 2%, the engineering progress is accelerated, the cause of the engineering acceleration is determined, the engineering project efficiency is improved based on the cause, the early warning is carried out if the analysis and investigation cause is the waste of materials, and the analysis and investigation cause is less than 2%, and the early warning is carried out.
Calculating the completion time of the sub-project based on the daily average consumption of each material of the sub-project and the total material demand of each sub-project event arranged in time;
based on the actual completion time of the first sub-project, the completion time of the subsequent sub-project is predicted, and meanwhile, monitoring and early warning and time prediction are performed on the engineering project based on the consumption of each material of each sub-project every day.
Specifically, when the first sub-project is carried out, the subsequent sub-projects are carried out simultaneously, after the first sub-project is completed, events of the first sub-project are taken as reference data, the completion time of the subsequent sub-project events is calculated by analogy, meanwhile, the consumption of each material per day and the total amount of each material required by the subsequent sub-project events are combined, the completion time of each subsequent sub-project is comprehensively deduced, after fluctuation occurs in each material consumption of each subsequent sub-project day, the reason of fluctuation of consumable materials is checked, early warning is carried out through a project part, meanwhile, the progress of the project is optimized based on the forward fluctuation reason of each material consumption per day, and the project is guaranteed to be completed in the expected time.
It should be noted that, based on the monitored sub project completion time, the project completion time can be predicted, and when the project completion time is predicted, the project completion time can be increased by one day every working day which cannot be constructed by combining with the local meteorological data of the project. The project sets a predicted completion time for the project information before starting.
In the time prediction of the engineering project, the completion time of the engineering project is predicted based on the maximum simultaneous sub-project number set by the total material demand of the sub-project number set, and is used as the predicted reference time of the engineering project.
It should be understood that the calculation mode of the reference time is to classify the sub-projects according to the material types and the demand, find out a plurality of materials continuously penetrating through all sub-projects in the whole sub-project quantity set according to the material consumption fluctuation curve in the sub-project quantity set, calculate the time of reaching the demand of all the materials penetrating through the whole project through analog reasoning, and serve as the prediction time of the engineering project, and the two prediction times are mutually verified, so that the accuracy of the prediction time is greatly improved.
The maximum number of simultaneous sub-items, that is, the maximum number of simultaneous sub-items, is set for the engineering project to run.
In summary, the method for monitoring construction of the building engineering based on the multidimensional data provided by the invention comprises the steps of splitting an engineering project into a plurality of sub-projects, splitting the sub-projects into a plurality of events, setting a mark event according to the occurrence position of the materials in the plurality of events, calculating the ongoing event of the first sub-project by counting the accumulated usage of each material in the first sub-project and the daily usage of each material in the engineering project, and then estimating the completion time of each sub-project after the total breaking of each material in the first sub-project, by calculating the difference between the accumulated usage of each material in the engineering project and the accumulated usage of each material in the event and the difference between the current consumption of each material in the event and the current consumption of each material in the event, determining all subsequent sub-projects and the events carried out by the subsequent sub-projects, further completing the progress monitoring of the engineering project can be completed by the materials, and meanwhile, by taking the completed process of the first sub-project as reference data, and by combining the similarity of the event of the first sub-project and the consumption of each material in each day and the total consumption of each material required by the subsequent sub-project, the completion time of each sub-project can be estimated, thus the completion time of the engineering project can be completed, the engineering project can be completed in a certain forward time can be guaranteed, and the project can be completed in advance based on the expected forward progress of the project consumption, and the project consumption can be optimized.
Example 2
As shown in fig. 2, the present embodiment provides a building engineering construction monitoring system based on multidimensional data, including:
the information acquisition module is used for acquiring engineering project information and environment information;
the project disassembly module is used for splicing the engineering project into a plurality of sub-projects and disassembling the sub-projects into a plurality of events;
the data recording module is used for recording the engineering project, a plurality of sub projects and various material data required by a plurality of events, counting the accumulated consumption of various materials and the single-day material consumption data, and marking the events of new materials or new equipment based on the recorded various material data;
the analysis and calculation module is used for analyzing the data recorded by the data recording module and calculating the current detailed precision of the engineering project;
the monitoring and early warning module predicts and early warns the completion time of the engineering project based on the determined progress data of the current engineering project;
the memory module is used for storing all information of the engineering project and sending the engineering project information to the analysis and calculation module and the detection and early warning module.
Further, the analysis and calculation module is used for judging whether new materials are consumed or new equipment works, comparing and calculating the accumulated consumption of each material of the first sub-project with the demand of each material of the event, determining the event of current processing, comparing the current daily material consumption with the average consumption of the front materials based on the determined event of current processing, determining the construction data of the current sub-project, and determining the progress of the current project based on the determined current construction sub-project and the current processing time.
Further, the flow of determining the progress of the current engineering project by the analysis and calculation module is specifically as follows:
determining whether new material usage or new equipment is in operation, determining an event based on the new material or new equipment;
determining the cumulative usage of each material of the first sub-item Nbeta j N=1, 2, 3,..n, N represents the label of each sub-item in the project, j represents the alternative label of each material in the project, and each material demand N μ for each of several events in the first sub-item ij I=1, 2, 3,..and n, i representing the number of each event in the sub-item, determining the first sub-item event scheduleWherein m is an ongoing event of the first sub-item;
determining the accumulated usage amount alpha of each material of engineering projects j J represents the substitute label of each material in the engineering project, and the difference K between the cumulative usage of each material in the engineering project and the cumulative usage of each material determined to be subjected to the event sub-project is calculated j
Calculating the difference L between the consumption of each material on the same day and the consumption of each material on the same day of the determined event sub-project j
Based on K j Analyzing which two groups of marked events the event currently performed by the next sub-item is specifically between;
difference K based on cumulative usage of each material j And the difference L of the consumption of each material on the same day j Determining the current event of the next sub-item;
the process of confirming the current event of the next sub-item is repeated until all the ongoing sub-items and the events carried out by the sub-items are determined.
Further, the specific process of predicting and pre-warning the completion time of the engineering project by the monitoring and pre-warning module comprises the following steps:
setting expected completion time for the first execution sub-item based on the disassembled sub-items;
counting the consumption of each material and the daily average consumption of each material of the first execution sub-project, calculating the fluctuation value of each material consumption per day, setting a fluctuation threshold, and analyzing the reason or carrying out early warning if the fluctuation of the daily consumption of the material is larger than the fluctuation threshold;
calculating the completion time of the sub-project based on the daily average consumption of each material of the sub-project and the total material demand of each sub-project event arranged in time;
based on the actual completion time of the first sub-project, the completion time of the subsequent sub-project is predicted, and meanwhile, monitoring and early warning are carried out on the engineering project based on the consumption of each material of each sub-project every day.
Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (10)

1. A building engineering construction monitoring method based on multidimensional data is characterized in that: the method comprises the following steps:
s1: acquiring engineering project information, decomposing the engineering project into a plurality of sub-projects, and determining material information required by the engineering project and total requirements of each material;
s2: determining the material types and the quantity of the sub-items and the types of the demand equipment based on the sub-items, and disassembling the sub-items into a plurality of events;
s3: arranging a plurality of events of the sub-items according to the sequence of the sub-item flow, calculating the accumulation amount of each material used in the completion process of the plurality of events, determining the individual total amount of each material required by each event, and marking the events of new materials or new equipment;
s4: counting the accumulated consumption of the materials and the consumption of the materials on a single day;
s5: determining a current project schedule based on the cumulative consumption of material, the single-day consumption of material, and the point in time when new material or new equipment is present;
s6: and predicting and early warning the project completion time based on the determined current project progress data.
2. The multi-dimensional data based construction engineering construction monitoring method according to claim 1, wherein: the specific steps of the S4 are as follows:
carrying out time line statistics on the consumption of each material every day based on the construction of engineering projects;
and calculating the total consumption of each material based on the consumption of each material collected every day, and simultaneously calculating the daily average consumption of each material of the first sub-project to obtain daily average consumption data of each material.
3. The multi-dimensional data based construction engineering construction monitoring method according to claim 2, wherein: the specific flow in the step S5 is as follows:
judging whether new materials are consumed or new equipment works, comparing and calculating the accumulated consumption of each material of the first sub-project with the demand of each material of the event, and determining the event currently processed;
determining current sub-project construction data based on the determined current processing event and comparing the current daily material consumption with the average front material consumption;
and determining the progress of the current engineering project based on the determined current construction sub-project and the current processing time.
4. A multi-dimensional data based construction monitoring method according to claim 3, wherein: the process for determining whether new materials are consumed or new equipment works or not, comparing the accumulated consumption of each material of the sub-project with the demand of each material of the event, and determining the current event comprises the following steps:
determining whether new material usage or new equipment is in operation, determining an event based on the new material or new equipment;
determining the cumulative usage of each material of the first sub-item Nbeta j N=1, 2, 3,..n, N represents the label of each sub-item in the project, j represents the alternative label of each material in the project, and each material demand N μ for each of several events in the first sub-item ij I=1, 2, 3,..and n, i representing the number of each event in the sub-item, determining the first sub-item event scheduleWhere m is the event that the first child item is in progress.
5. A multi-dimensional data based construction monitoring method according to claim 3, wherein: the process for determining the current sub-project construction data based on the determined current processing event and comparing the consumption of each material on the same day with the consumption data of each material on the same day comprises the following steps:
m1: determining the accumulated usage amount alpha of each material of engineering projects j J represents the substitute label of each material in the engineering project, and the difference K between the cumulative usage of each material in the engineering project and the cumulative usage of each material determined to be subjected to the event sub-project is calculated j
M2: calculating the difference L between the consumption of each material on the same day and the consumption of each material on the same day of the determined event sub-project j
M3: based on K j Analyzing which two groups of marked events the event currently performed by the next sub-item is specifically between;
m4: difference K based on cumulative usage of each material j And the difference L of the consumption of each material on the same day j Determining the current event of the next sub-item;
m5: steps M1-M5 are repeated until all ongoing sub-items and events carried out by the sub-items are determined.
6. The multi-dimensional data based construction engineering construction monitoring method according to claim 1, wherein: the specific process of S6 includes:
setting expected completion time for the first execution sub-item based on the disassembled sub-items;
counting the consumption of each material and the daily average consumption of each material of the first execution sub-project, calculating the fluctuation value of each material consumption per day, setting a fluctuation threshold, and analyzing the reason or carrying out early warning if the fluctuation of the daily consumption of the material is larger than the fluctuation threshold;
calculating the completion time of the sub-project based on the daily average consumption of each material of the sub-project and the total material demand of each sub-project event arranged in time;
based on the actual completion time of the first sub-project, the completion time of the subsequent sub-project is predicted, and meanwhile, monitoring and early warning are carried out on the engineering project based on the consumption of each material of each sub-project every day.
7. The utility model provides a building engineering construction monitoring system based on multidimensional data which characterized in that: comprising the following steps:
the information acquisition module is used for acquiring engineering project information and environment information;
the project disassembly module is used for splicing the engineering project into a plurality of sub-projects and disassembling the sub-projects into a plurality of events;
the data recording module is used for recording the engineering project, a plurality of sub projects and various material data required by a plurality of events, counting the accumulated consumption of various materials and the single-day material consumption data, and marking the events of new materials or new equipment based on the recorded various material data;
the analysis and calculation module is used for analyzing the data recorded by the data recording module and calculating the current detailed precision of the engineering project;
the monitoring and early warning module predicts and early warns the completion time of the engineering project based on the determined progress data of the current engineering project;
the memory module is used for storing all information of the engineering project and sending the engineering project information to the analysis and calculation module and the detection and early warning module.
8. The multi-dimensional data based construction engineering construction monitoring system of claim 7, wherein: the analysis and calculation module is used for judging whether new materials are consumed or new equipment works, comparing and calculating the accumulated consumption of each material of the first sub-project with the demand of each material of the event, determining the event of current processing, comparing the current daily material consumption with the average consumption of the front materials based on the determined event of current processing, determining the construction data of the current sub-project, and determining the progress of the current engineering project based on the determined current construction sub-project and the current processing time.
9. The multi-dimensional data based construction engineering construction monitoring system of claim 8, wherein: the flow of determining the progress of the current engineering project by the analysis and calculation module is specifically as follows:
determining whether new material usage or new equipment is in operation, determining an event based on the new material or new equipment;
determining the cumulative usage of each material of the first sub-item Nbeta j N=1, 2, 3,..n, N represents the label of each sub-item in the project, j represents the alternative label of each material in the project, and each material demand N μ for each of several events in the first sub-item ij I=1, 2, 3,..and n, i representing the number of each event in the sub-item, determining the first sub-item event scheduleWherein m is an ongoing event of the first sub-item;
determining the accumulated usage amount alpha of each material of engineering projects j J represents the substitute label of each material in the engineering project, and the difference K between the cumulative usage of each material in the engineering project and the cumulative usage of each material determined to be subjected to the event sub-project is calculated j
Calculating the consumption of each material on the same day and determining the event to be carried outDifference L of consumption of materials on the same day of sub-project j
Based on K j Analyzing which two groups of marked events the event currently performed by the next sub-item is specifically between;
difference K based on cumulative usage of each material j And the difference L of the consumption of each material on the same day j Determining the current event of the next sub-item;
the process of confirming the current event of the next sub-item is repeated until all the ongoing sub-items and the events carried out by the sub-items are determined.
10. The multi-dimensional data based construction engineering construction monitoring system of claim 7, wherein: the specific flow of the monitoring and early warning module for predicting and early warning the completion time of the engineering project comprises the following steps:
setting expected completion time for the first execution sub-item based on the disassembled sub-items;
counting the consumption of each material and the daily average consumption of each material of the first execution sub-project, calculating the fluctuation value of each material consumption per day, setting a fluctuation threshold, and analyzing the reason or carrying out early warning if the fluctuation of the daily consumption of the material is larger than the fluctuation threshold;
calculating the completion time of the sub-project based on the daily average consumption of each material of the sub-project and the total material demand of each sub-project event arranged in time;
based on the actual completion time of the first sub-project, the completion time of the subsequent sub-project is predicted, and meanwhile, monitoring and early warning are carried out on the engineering project based on the consumption of each material of each sub-project every day.
CN202311657959.8A 2023-12-06 2023-12-06 Building engineering construction monitoring method and system based on multidimensional data Pending CN117635057A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311657959.8A CN117635057A (en) 2023-12-06 2023-12-06 Building engineering construction monitoring method and system based on multidimensional data

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311657959.8A CN117635057A (en) 2023-12-06 2023-12-06 Building engineering construction monitoring method and system based on multidimensional data

Publications (1)

Publication Number Publication Date
CN117635057A true CN117635057A (en) 2024-03-01

Family

ID=90017975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311657959.8A Pending CN117635057A (en) 2023-12-06 2023-12-06 Building engineering construction monitoring method and system based on multidimensional data

Country Status (1)

Country Link
CN (1) CN117635057A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020198755A1 (en) * 2001-06-22 2002-12-26 Birkner Charles Christian Integrated quality assurance control system to manage construction projects
US20130335413A1 (en) * 2012-06-13 2013-12-19 National Chiao Tung University System and method for estimating construction duration
CN107273587A (en) * 2017-05-26 2017-10-20 北京戴纳实验科技有限公司 A kind of Schedule monitoring method for laboratory engineering construction
CN112033375A (en) * 2020-09-11 2020-12-04 武汉市天佑宏图测绘科技有限公司 Internet-based monitoring system for engineering measurement
CN114219289A (en) * 2021-12-15 2022-03-22 四川沿江攀宁高速公路有限公司 Construction cost control method based on BIM and Internet of things technology
CN115496271A (en) * 2022-09-15 2022-12-20 合肥合锻智能制造股份有限公司 Multi-process dynamic scheduling optimization method based on integrated cooperative configuration

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020198755A1 (en) * 2001-06-22 2002-12-26 Birkner Charles Christian Integrated quality assurance control system to manage construction projects
US20130335413A1 (en) * 2012-06-13 2013-12-19 National Chiao Tung University System and method for estimating construction duration
CN107273587A (en) * 2017-05-26 2017-10-20 北京戴纳实验科技有限公司 A kind of Schedule monitoring method for laboratory engineering construction
CN112033375A (en) * 2020-09-11 2020-12-04 武汉市天佑宏图测绘科技有限公司 Internet-based monitoring system for engineering measurement
CN114219289A (en) * 2021-12-15 2022-03-22 四川沿江攀宁高速公路有限公司 Construction cost control method based on BIM and Internet of things technology
CN115496271A (en) * 2022-09-15 2022-12-20 合肥合锻智能制造股份有限公司 Multi-process dynamic scheduling optimization method based on integrated cooperative configuration

Similar Documents

Publication Publication Date Title
Wang et al. A hybrid Data Quality Indicator and statistical method for improving uncertainty analysis in LCA of complex system–application to the whole-building embodied energy analysis
JP6129028B2 (en) Energy consumption prediction method for building power equipment
Negahban Simulation-based estimation of the real demand in bike-sharing systems in the presence of censoring
CN109116444B (en) PCA-kNN-based air quality model PM2.5Forecasting method
CN117172556B (en) Construction risk early warning method and system for bridge engineering
CN110889088A (en) Enterprise pollution discharge supervision method assisted by electric model
CN109979193B (en) Data anomaly diagnosis method based on Markov model
US20140074797A1 (en) Methods and systems for generating a business process control chart for monitoring building processes
CN107957929A (en) A kind of software deficiency report based on topic model repairs personnel assignment method
CN111984705A (en) Precision evaluation management method and device for power quality monitoring device
Salimi et al. Sensitivity analysis of probabilistic occupancy prediction model using big data
CN116775672A (en) BIM-based engineering cost data dynamic correction method and system
JP2022154422A (en) energy management system
CN117077454B (en) Method for evaluating service life of road pavement under condition of missing road detection data
Frisén et al. Robust outbreak surveillance of epidemics in Sweden
CN117851908A (en) Improved on-line low-voltage transformer area electric energy meter misalignment monitoring method and device
CN117635057A (en) Building engineering construction monitoring method and system based on multidimensional data
CN116050624B (en) Comprehensive monitoring method and system for highway construction
Su et al. Considering critical building materials for embodied carbon emissions in buildings: A machine learning-based prediction model and tool
CN104462215A (en) Scientific and technical literature quoting number predicting method based on time sequence
WO2020105151A1 (en) Facility maintenance inspection assisting system and order of inspection determination method
Wang et al. Modeling and algorithms of VMT and AADT estimation for community area traffic networks
Kallen A comparison of statistical models for visual inspection data
CN117077968A (en) Enterprise target data management analysis processing system
CN118037135B (en) Qualitative analysis method for influence of vegetation coverage change on ecosystem service

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination