CN117188780A - Steel stair hoisting method - Google Patents

Steel stair hoisting method Download PDF

Info

Publication number
CN117188780A
CN117188780A CN202311192734.XA CN202311192734A CN117188780A CN 117188780 A CN117188780 A CN 117188780A CN 202311192734 A CN202311192734 A CN 202311192734A CN 117188780 A CN117188780 A CN 117188780A
Authority
CN
China
Prior art keywords
steel
welding
stair
hoisting
assembling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311192734.XA
Other languages
Chinese (zh)
Inventor
罗威力
王楠
吕凯捷
崔杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou University
Original Assignee
Guangzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou University filed Critical Guangzhou University
Priority to CN202311192734.XA priority Critical patent/CN117188780A/en
Publication of CN117188780A publication Critical patent/CN117188780A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a steel stair hoisting method, which comprises the following steps: s1, lifting the steel stair by adopting an integral assembly and integral lifting construction method for installation construction. The invention can realize the hoisting precision of the steel stair.

Description

Steel stair hoisting method
Technical Field
The invention relates to the field of steel stair hoisting, in particular to a steel stair hoisting method.
Background
Along with the large-area application of the fabricated concrete structure, a large number of prefabricated components need to be hoisted and installed in the construction process of the prefabricated building, and as a large number of prefabricated components such as prefabricated stairways are made of reinforced concrete, the weight of the components is large, the hoisting is carried out by adopting a large-scale tower crane, the hoisting height is high, and the hoisting precision is lacking
Disclosure of Invention
The invention aims to provide a steel stair hoisting method, which aims to solve the problem of steel stair hoisting.
The invention provides a steel stair hoisting method, which comprises the following steps:
s1, lifting the steel stair by adopting an integral assembly and integral lifting construction method for installation construction.
By adopting the embodiment of the invention, the hoisting precision of the steel stair can be improved.
The foregoing description is only an overview of the present invention, and is intended to provide a more clear understanding of the technical means of the present invention, as it is embodied in accordance with the present invention, and to make the above and other objects, features and advantages of the present invention more apparent, as it is embodied in the following detailed description of the invention.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings that are needed in the description of the embodiments or the prior art will be briefly described, and it is obvious that the drawings in the description below are some embodiments of the present invention, and other drawings can be obtained according to the drawings without inventive effort for a person skilled in the art.
FIG. 1 is a schematic view of a steel stair construction of a method for lifting a steel stair according to an embodiment of the present invention;
fig. 2 is a schematic diagram of a steel cable and lifting points of a steel stair lifting method according to an embodiment of the present invention.
Detailed Description
The technical solutions of the present invention will be clearly and completely described in connection with the embodiments, and it is apparent that the described embodiments are some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Method embodiment
According to the embodiment of the invention, a steel stair hoisting method is provided, which specifically comprises the following steps:
s1, lifting the steel stair by adopting an integral assembly and integral lifting construction method for installation construction.
S1 specifically comprises: s11, after the steel member is transported to the site from a processing plant, welding and assembling the profile steel by matching with a welding method of submerged arc automatic welding;
s12, after the positioning axis, the foundation axis, the elevation and the like of the building are checked to meet the requirements, hoisting and installing the steel stair;
s13, using the positioning axis and elevation of the building, placing the GPS positioning device at the lifting position to implement the GPS positioning function on the steel stair, and monitoring whether the coordinates at the lifting point are identical with the original coordinates in real time after the GPS positioning device is connected with a computer until the steel stair is lifted to the set position, and finally connecting the steel stair with the embedded part.
S11 specifically comprises: after the steel member is transported to the site from a processing plant, welding and assembling the profiled steel, and prefabricating an assembling jig frame on the site before assembling the whole steel stair, wherein the steel stair is assembled on the jig frame, and the welding seam adopts fillet welding girth welding.
S12 specifically comprises the following steps: after the positioning axis, the foundation axis, the elevation and the like of the building are inspected to meet the requirements, the steel stairway is hoisted and installed, the hoisting is carried out in a mode of combining GPS positioning and hoisting processes, two steel ropes are pulled out from one end of the main structure frame column on the structural layer installed on the uppermost steel stairway, the steel ropes are connected with the other two ends of the frame column, two hoisting points are fixed on the two steel ropes, and the steel ropes enter the two hoists through the guiding of pulleys and are hoisted by the two hoists.
Welding and assembling the section steel specifically comprises the following steps: and welding and assembling the profile steel, and matching with a welding method of submerged arc automatic welding.
The upper and lower flange plates and the web splice should be offset a distance.
The specific implementation method is as follows:
FIG. 1 is a schematic view of a steel stair construction of a method for lifting a steel stair according to an embodiment of the present invention;
a large-span stairway with a semi-annular steel structure without an intermediate column adopts a mode that special-shaped rectangular steel beams are combined with channel steel as a main body stress structure (special-shaped rectangular steel beams). The column structure adopts Q345 steel, and the secondary structure adopts Q235 steel. The radius of the circle of the steel ladder beam center line of the outer ring of the steel stair is 9100mm, and the radius of the circle of the steel ladder beam center line of the inner ring is 7110mm.
The steel ladder beams 1 and 2 (GTL 1 and GTL 2) are main stress members of the steel stairs, and are required to resist lateral bending and torsion besides bearing stair loads and upper loads; the steel ladder beam 3 (GTL 3) transmits force to the GTL1 and the GTL2, and simultaneously the support of the compression flanges of the GTL1 and the GTL2 is increased to reduce the lateral free length of the steel ladder beam so as to improve the overall stability of the steel ladder; the use of the channel steel enables the loading of the ladder plate and the upper part to be better transferred to the GTL1 and the GTL2. The use of the GTL 1-GTL 3 special-shaped rectangular pipes increases the height of the web plate, and improves the strength and rigidity of the steel stair; the width of the flange is widened, and the overall stability of the steel stair is improved. The steel ladder beam and the channel steel are used as stress members to bear the external and transverse loads of the vertical load of the steel stairs.
Because the steel stairway is limited by the condition of the construction site, the steel stairway cannot be hoisted by adopting a hoisting machine, and the steel stairway is hoisted by adopting an integral assembly and integral hoisting construction method in combination with the actual condition of the construction site.
Firstly, after a steel member is transported to a site from a processing plant, welding and assembling are carried out on the profile steel by matching with a welding method of submerged arc automatic welding. Because the whole steel stair is semi-annular, an assembly jig frame is prefabricated on site before assembly, and the steel stair is assembled on the jig frame. The welding seam is full-length full-welded along the whole length of the member, the upper flange plate and the lower flange plate of the welded section steel are not provided with longitudinal splicing seams, only transverse splicing is allowed, and the web plates can be longitudinally and transversely spliced, but the splicing seams of the flange plates and the web plates are staggered by more than 200mm so as to avoid the intersection of the welding seam and the concentration of the defect of the welding seam.
And secondly, after the positioning axis, the foundation axis, the elevation and the like of the building are checked to meet the requirements, hoisting and installing the steel stair. Because the length of the steel stair is longer, the hoisting is performed in a mode of combining GPS positioning and lifting and hoisting technology in order to ensure the stability of the steel stair in the hoisting process. Two steel ropes are pulled out from one end of the main structure frame column on the structural layer installed on the uppermost steel stair by utilizing the main structure frame column, the steel ropes are connected with the other two ends of the frame column, two lifting points are fixed on the two steel ropes, and the two steel ropes enter two windlass through the guiding of pulleys and are lifted by the two windlass.
FIG. 2 is a schematic view of a steel cable and lifting points of a method of lifting a steel stair according to an embodiment of the present invention;
and (3) utilizing the positioning axis and elevation of the building, placing the GPS positioning device at a lifting position to implement a GPS positioning function on the steel stair, and monitoring whether coordinates at the lifting point are identical with original coordinates in real time after the GPS positioning device is connected with a GPS through a computer until the steel stair is lifted to a set position and finally connected with the embedded part.
The hoisting method improves the stability and the accuracy of hoisting.
Finally, it should be noted that: the above embodiments are only for illustrating the technical solution of the present invention, and not for limiting the same; although the invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some or all of the technical features thereof can be replaced by equivalents; and these modifications or substitutions may be made to the technical solutions of the embodiments of the present invention without departing from the spirit of the corresponding technical solutions.

Claims (6)

1. The steel stair hoisting method is characterized by comprising the following steps of:
s1, lifting the steel stair by adopting an integral assembly and integral lifting construction method for installation construction.
2. The method according to claim 1, wherein S1 specifically comprises: s11, after the steel member is transported to the site from a processing plant, welding and assembling the profile steel by matching with a welding method of submerged arc automatic welding;
s12, after the positioning axis, the foundation axis, the elevation and the like of the building are checked to meet the requirements, hoisting and installing the steel stair;
s13, using the positioning axis and elevation of the building, placing the GPS positioning device at the lifting position to implement the GPS positioning function on the steel stair, and monitoring whether the coordinates at the lifting point are identical with the original coordinates in real time after the GPS positioning device is connected with a computer until the steel stair is lifted to the set position, and finally connecting the steel stair with the embedded part.
3. The method according to claim 1, wherein S11 specifically comprises: after the steel member is transported to the site from a processing plant, welding and assembling the profiled steel, and prefabricating an assembling jig frame on the site before assembling the whole steel stair, wherein the steel stair is assembled on the jig frame, and the welding seam adopts fillet welding girth welding.
4. The method according to claim 1, wherein S12 specifically comprises: after the positioning axis, the foundation axis, the elevation and the like of the building are inspected to meet the requirements, the steel stairway is hoisted and installed, the hoisting is carried out in a mode of combining GPS positioning and hoisting processes, two steel ropes are pulled out from one end of the main structure frame column on the structural layer installed on the uppermost steel stairway, the steel ropes are connected with the other two ends of the frame column, two hoisting points are fixed on the two steel ropes, and the steel ropes enter the two hoists through the guiding of pulleys and are hoisted by the two hoists.
5. The method according to claim 1, wherein the welding and assembling of the section steel comprises: and welding and assembling the profile steel, and matching with a welding method of submerged arc automatic welding.
6. The method of claim 1 wherein said upper and lower flange plates and said web splice are offset by a distance.
CN202311192734.XA 2023-09-14 2023-09-14 Steel stair hoisting method Pending CN117188780A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311192734.XA CN117188780A (en) 2023-09-14 2023-09-14 Steel stair hoisting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311192734.XA CN117188780A (en) 2023-09-14 2023-09-14 Steel stair hoisting method

Publications (1)

Publication Number Publication Date
CN117188780A true CN117188780A (en) 2023-12-08

Family

ID=88986684

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311192734.XA Pending CN117188780A (en) 2023-09-14 2023-09-14 Steel stair hoisting method

Country Status (1)

Country Link
CN (1) CN117188780A (en)

Similar Documents

Publication Publication Date Title
US11280055B1 (en) Construction device and method for lateral bracing in ultra-deep foundation pit with silt
CN106930541B (en) Construction method of hanging type steel corridor
CN107013038A (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN113338333A (en) Quick mounting method for steel beam plate under cover-excavation top-down condition
CN117188780A (en) Steel stair hoisting method
CN218815294U (en) Steel construction platform of unloading
CN114908968B (en) Construction method of large-span fish-bellied pipe truss in gymnasium
CN114086770A (en) Hoisting and mounting method for steel frame structure
CN104818675B (en) The spelling method of reinforcing bar sections
CN113833126A (en) Roof installation method
CN113931068A (en) Bridge deck crane for mounting steel and concrete superposed beams and beam erecting method thereof
CN113006588A (en) Inverted construction method of chimney platform
CN108797350B (en) Tower column inner and outer stiff skeleton device and construction method thereof
CN112627355B (en) Petal-shaped large-span roof truss assembling method
CN115506604B (en) Method for installing first truss of large-span steel structure
WO2024148715A1 (en) Method for erecting continuous steel truss bridge
CN213114268U (en) Steel construction corridor bridge convenient to field assembly and mounting structure thereof
CN218757009U (en) Low-clearance steel support replacing structure below trestle bridge
CN109723231B (en) Steel structure construction process for oil storage tank
CN115289279A (en) Installation method of narrow-space pipe gallery multilayer pipeline
CN105314524A (en) Skylight truss hanger
CN108661189B (en) Box-type steel column splicing joint and installation method thereof
CN108842638B (en) Steel pipe truss girder rail type jig frame limiting assembling and cluster jack unloading construction method
CN115285850A (en) Method for installing steel rails of roof girder suspension transportation equipment
CN116856723A (en) Multi-layer steel structure slope-returning type installation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination