CN117114592A - Engineering progress control method and device - Google Patents

Engineering progress control method and device Download PDF

Info

Publication number
CN117114592A
CN117114592A CN202310699630.1A CN202310699630A CN117114592A CN 117114592 A CN117114592 A CN 117114592A CN 202310699630 A CN202310699630 A CN 202310699630A CN 117114592 A CN117114592 A CN 117114592A
Authority
CN
China
Prior art keywords
progress
management
regulation
identity
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202310699630.1A
Other languages
Chinese (zh)
Other versions
CN117114592B (en
Inventor
蔡志华
聂琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huateng Jianxin Technology Co ltd
Original Assignee
Huateng Jianxin Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huateng Jianxin Technology Co ltd filed Critical Huateng Jianxin Technology Co ltd
Priority to CN202310699630.1A priority Critical patent/CN117114592B/en
Publication of CN117114592A publication Critical patent/CN117114592A/en
Application granted granted Critical
Publication of CN117114592B publication Critical patent/CN117114592B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F21/00Security arrangements for protecting computers, components thereof, programs or data against unauthorised activity
    • G06F21/30Authentication, i.e. establishing the identity or authorisation of security principals
    • G06F21/31User authentication
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Computer Security & Cryptography (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Educational Administration (AREA)
  • Data Mining & Analysis (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Computer Hardware Design (AREA)
  • Software Systems (AREA)
  • General Engineering & Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application discloses a method and a device for controlling engineering progress, wherein the method comprises the following steps: receiving a progress adjustment instruction and an identity of a user; identifying a management authority set corresponding to the identity; comparing the management authority corresponding to the progress adjustment instruction with the management authority in the management authority set, determining legal management authority from the management authority corresponding to the progress adjustment instruction, and determining legal progress adjustment instruction corresponding to the legal management authority from the progress management; acquiring a progress management item corresponding to legal management authority, and displaying the current progress state of the progress management item; determining a progress regulation strategy of each progress management project according to the current progress state of the progress management project, legal progress regulation instructions and identity marks; and carrying out progress regulation operation on the corresponding progress management project according to the progress regulation strategy, and notifying a progress regulation notification object of a progress regulation operation result. The application can improve the management efficiency of the project progress of the user.

Description

Engineering progress control method and device
Technical Field
The application relates to the technical field of engineering data management, in particular to an engineering progress control method and an engineering progress control device.
Background
The engineering progress control is to make a plan for the working content, working program, duration and connection relation of engineering project construction, check the actual progress in the construction process and compare with the plan to judge whether the engineering progress is normal or not; and (3) taking corresponding measures or adjusting the original plan in time due to the early or late analysis progress of the deviation until the project is completed, so as to ensure the realization of project progress targets. In progress management, it is a key to smoothly perform management work to quickly grasp the actual progress of the project. When the progress of the engineering project deviates from the expected progress, the progress of the engineering project needs to be adjusted and optimized.
The current adjustment and optimization mode for the progress of the engineering project is generally as follows: logging in an engineering project progress management system by related engineering project management personnel, then clicking engineering nodes needing to be subjected to engineering project progress adjustment one by the management personnel, carrying out one-by-one manual progress adjustment by clicking the engineering nodes of each engineering project, and informing corresponding personnel one by one after the manual progress adjustment, wherein the whole operation process is complex and complicated and has low efficiency; meanwhile, a huge project has a plurality of managers, each manager has different progress management authorities for project nodes responsible for unified project progress management projects, in a project management system, project node contents of project progress management are various, the manager cannot intuitively and rapidly find project node parts responsible for project progress management, and the manager needs to read each project one by one to confirm whether project nodes need to perform progress management per se under the project, so that time and labor are consumed.
Disclosure of Invention
The embodiment of the application provides a method and a device for controlling engineering progress, which can improve the management efficiency of management personnel on engineering project progress.
The application discloses a project progress control method, which comprises the following steps:
receiving progress management information of a user, wherein the progress management information comprises a progress adjustment instruction and an identity mark; the progress adjustment instruction comprises progress adjustment demand information;
identifying a management authority set corresponding to the identity;
comparing the management authority corresponding to the progress adjustment instruction with the management authorities in the management authority set, determining legal management authorities from the management authorities corresponding to the progress adjustment instruction, and determining legal progress adjustment instructions corresponding to the legal management authorities from the progress management;
acquiring a progress management project corresponding to the legal management authority, and displaying the current progress state of the progress management project;
determining a progress regulation strategy of each progress management project according to the current progress state of the progress management project, the legal progress regulation instruction and the identity; the progress regulating strategy comprises the following steps: the progress adjustment parameters and the progress adjustment notification objects of each target engineering node of the progress management project;
and carrying out progress regulation operation on the corresponding progress management project according to the progress regulation strategy, and notifying a progress regulation operation result to the progress regulation notification object.
As an optional implementation manner, the determining the progress regulation policy of each progress management item according to the current progress status of the progress management item, the legal progress adjustment instruction and the identity includes:
determining the progress regulation style of each progress management project according to the identity; the progress regulation style is used for indicating the progress regulation amplitude of each target engineering node of the progress management project;
determining a progress adjustment parameter of each target engineering node of each progress management project according to the progress regulation style of the progress management project, the current progress state of the progress management project and the progress adjustment requirement information of the progress management project corresponding to the legal progress adjustment instruction;
and determining a progress adjustment notification object of each target engineering node of each progress management item according to the identity.
As an optional implementation manner, the determining the progress regulation style of each progress management item according to the identity identifier includes:
and finding the progress regulation style of each progress management project corresponding to the identity from the mapping table according to a mapping table of the pre-established identity and the progress regulation style of each progress management project, wherein the progress regulation style is obtained by training the history progress regulation data of the progress management project according to the user corresponding to the identity in advance.
As an optional implementation manner, the identifying the management authority set corresponding to the identity identifier includes:
identifying the position corresponding to the identity mark;
and acquiring a management authority set corresponding to the position.
As an optional implementation manner, the identity identifier includes a biometric feature of a user of the terminal that the user sends the progress management information, and the identifying the position corresponding to the identity identifier includes:
identifying identity information of a user through a biological identification method based on the biological characteristics;
and identifying the position corresponding to the user according to the identity information.
In a second aspect, the present application provides an engineering progress control device, the device comprising:
the information receiving module is used for receiving the progress management information of the user, wherein the progress management information comprises a progress adjustment instruction and an identity mark; the progress adjustment instruction comprises progress adjustment demand information;
the right identification module is used for identifying a management right set corresponding to the identity;
the permission comparison module is used for comparing the management permission corresponding to the progress adjustment instruction with the management permissions in the management permission set, determining legal management permissions from the management permissions corresponding to the progress adjustment instruction, and determining legal progress adjustment instructions corresponding to the legal management permissions from the progress management;
the project progress acquisition module is used for acquiring a progress management project corresponding to the legal management authority and displaying the current progress state of the progress management project;
the regulation and control strategy determining module is used for determining the progress regulation and control strategy of each progress management project according to the current progress state of the progress management project, the legal progress adjustment instruction and the identity; the progress regulating strategy comprises the following steps: the progress adjustment parameters and the progress adjustment notification objects of each target engineering node of the progress management project;
and the regulation and control operation module is used for carrying out the progress regulation and control operation on the corresponding progress management project according to the progress regulation and control strategy and notifying the progress regulation and control operation result to the progress regulation notifying object.
As an alternative embodiment, the regulation strategy determination module includes:
the regulation and control style determining unit is used for determining the progress regulation and control style of each progress management project according to the identity; the progress regulation style is used for indicating the progress regulation amplitude of each target engineering node of the progress management project;
the adjustment parameter determining unit is used for determining the progress adjustment parameter of each target engineering node of each progress management project according to the progress regulation style of the progress management project, the current progress state of the progress management project and the progress adjustment requirement information of the progress management project corresponding to the legal progress adjustment instruction;
and the notification object determining unit is used for determining a progress adjustment notification object of each target engineering node of each progress management item according to the identity.
As an optional implementation manner, the regulation style determining unit is specifically configured to:
and finding the progress regulation style of each progress management project corresponding to the identity from the mapping table according to a mapping table of the pre-established identity and the progress regulation style of each progress management project, wherein the progress regulation style is obtained by training the history progress regulation data of the progress management project according to the user corresponding to the identity in advance.
The third aspect of the present application discloses another engineering progress control electronic device, which includes:
a memory storing executable program code;
a processor coupled to the memory;
the processor invokes the executable program code stored in the memory to execute the engineering progress control method disclosed in the first aspect of the present application.
A fourth aspect of the present application discloses a computer storage medium storing computer instructions for executing the engineering progress control method disclosed in the first aspect of the present application when the computer instructions are called.
Compared with the prior art, the embodiment of the application has the following beneficial effects: the method comprises the steps that the management authority of a user on a progress management project is confirmed, the progress management project corresponding to legal management authority of the user is directly found, and the current progress state of the progress management project is displayed, so that the situation that the user can know the current progress state of the progress management project in charge of the user through complicated operation can be avoided; meanwhile, the progress regulation and control strategy of each progress management project is determined according to the current progress state of the progress management project, legal progress regulation instructions and the identity of a user, so that a proper progress regulation and control strategy can be quickly formulated according to the progress regulation and control needs of the user on target engineering nodes of the progress management project, the corresponding progress management project can be automatically subjected to progress regulation and control operation according to the progress regulation and control strategy, and after the progress regulation and control operation is carried out on the progress management project, corresponding personnel can be automatically notified. From the analysis, the embodiment of the application can automatically realize reasonable regulation and control of the progress of the project progress management project and automatically inform relevant personnel of the progress regulation result only by knowing the progress regulation instruction and the identity of the user, and the whole project progress regulation process is efficient and convenient.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for the description of the embodiments will be briefly described below, and it is apparent that the drawings in the following description are only some embodiments of the present application, and other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
FIG. 1 is a schematic flow chart of an engineering progress control method according to an embodiment of the present application;
FIG. 2 is a schematic structural diagram of an engineering progress control device according to a third embodiment of the present application;
fig. 3 is a schematic structural diagram of an engineering progress control electronic device according to a fourth embodiment of the present application.
Detailed Description
In order that those skilled in the art will better understand the present application, a technical solution in the embodiments of the present application will be clearly and completely described below with reference to the accompanying drawings in which it is apparent that the described embodiments are only some embodiments of the present application, not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the application without making any inventive effort, are intended to be within the scope of the application.
The terms first, second and the like in the description and in the claims and in the above-described figures are used for distinguishing between different objects and not necessarily for describing a sequential or chronological order. Furthermore, the terms "comprise" and "have," as well as any variations thereof, are intended to cover a non-exclusive inclusion. For example, a process, method, apparatus, article, or article that comprises a list of steps or elements is not limited to only those listed but may optionally include other steps or elements not listed or inherent to such process, method, article, or article.
Reference herein to "an embodiment" means that a particular feature, structure, or characteristic described in connection with the embodiment may be included in at least one embodiment of the application. The appearances of such phrases in various places in the specification are not necessarily all referring to the same embodiment, nor are separate or alternative embodiments mutually exclusive of other embodiments. Those of skill in the art will explicitly and implicitly appreciate that the embodiments described herein may be combined with other embodiments.
Referring to fig. 1, fig. 1 is a flow chart of an engineering progress control method according to an embodiment of the application. As shown in fig. 1, the engineering data management method may include the following operations:
s10, receiving progress management information of a user, wherein the progress management information comprises a progress adjustment instruction and an identity mark; the progress adjustment instruction comprises progress adjustment demand information;
specifically, when a user logs in the engineering progress management system, the system can acquire the identity information of the user and analyze and verify the identity of the user. After the user logs in the engineering progress management system, the user only needs to input the progress adjustment requirement information in a progress adjustment requirement input dialog box of the engineering progress management system, and no additional operation is needed. And the engineering progress management system generates the progress adjustment instruction after knowing the progress adjustment requirement information of the user and automatically executes the following steps. The schedule adjustment requirement information refers to requirement content of a user for adjusting the schedule of an engineering node responsible for management of the user of the target schedule management project, and as an example, the schedule adjustment requirement information input by the user may be: the method includes the steps of "uniformly speeding up the progress of A, B and the progress of the project node managed by the principal responsible for the progress management project of C", "finding out the project node of the progress management project of which the progress is more than 20% behind the expected one from the corresponding project nodes of the progress management project of A, B and the progress management project of C, speeding up the progress of the project nodes of the progress management project of which the progress is more than 20% behind the expected one from the current progress state (the purpose of speeding up may be to catch up the progress)", "finding out the project node of the progress management project of which the progress is more than 20% faster than the expected one from the corresponding project nodes of the progress management project of A, B and the progress management project of C, and slowing down the progress of the project nodes of the progress management project of which the progress is more than 20% faster than the expected one from the current progress state (the purpose of slowing down may be to avoid the progress being too fast to affect the quality)", and the like.
S11, identifying a management authority set corresponding to the identity;
after the progress management information of the user is received, identifying a management authority set corresponding to the user through an identity in the progress management information, wherein the identity of each user is preset with the corresponding management authority set of the relevant engineering node of the relevant progress management project.
S12, comparing the management authority corresponding to the progress adjustment instruction with the management authorities in the management authority set, determining legal management authorities from the management authorities corresponding to the progress adjustment instruction, and determining legal progress adjustment instructions corresponding to the legal management authorities from the progress management;
the user inputs a request content of the target progress management project, which is responsible for adjusting the progress of the managed engineering node, and may include the target progress management project which does not need to be managed by the user, and the user does not have management rights for the progress management of the relevant engineering node of the progress management project, so that the management rights corresponding to the progress adjustment instruction are required to be compared with the management rights in the management rights set, legal management rights are determined from the management rights corresponding to the progress adjustment instruction, and legal progress adjustment instructions corresponding to the legal management rights are determined from the progress management.
S13, acquiring a progress management project corresponding to the legal management authority, and displaying the current progress state of the progress management project;
s14, determining a progress regulation strategy of each progress management project according to the current progress state of the progress management project, the legal progress regulation instruction and the identity; the progress regulating strategy comprises the following steps: the progress adjustment parameters and the progress adjustment notification objects of each target engineering node of the progress management project;
and S15, performing progress regulation and control operation on the corresponding progress management project according to the progress regulation and control strategy, and notifying a progress regulation and control operation result to the progress regulation and control notification object.
In this embodiment, by confirming the management authority of the user on the progress management project by both the progress adjustment instruction and the identity identifier, the progress management project corresponding to the legal management authority of the user is directly found, and the current progress state of the progress management project is displayed, so that the user can be prevented from knowing the current progress state of the progress management project responsible for the user through complicated operations; meanwhile, the progress regulation and control strategy of each progress management project is determined according to the current progress state of the progress management project, legal progress regulation instructions and the identity of a user, so that a proper progress regulation and control strategy can be quickly formulated according to the progress regulation and control needs of the user on target engineering nodes of the progress management project, the corresponding progress management project can be automatically subjected to progress regulation and control operation according to the progress regulation and control strategy, and after the progress regulation and control operation is carried out on the progress management project, corresponding personnel can be automatically notified. From the analysis, the embodiment of the application can automatically realize reasonable regulation and control of the progress of the project progress management project and automatically inform relevant personnel of the progress regulation result only by knowing the progress regulation instruction and the identity of the user, and the whole project progress regulation process is efficient and convenient.
As an optional implementation manner, the determining the progress regulation policy of each progress management item according to the current progress status of the progress management item, the legal progress adjustment instruction and the identity includes:
determining the progress regulation style of each progress management project according to the identity; the progress regulation style is used for indicating the progress regulation amplitude of each target engineering node of the progress management project;
determining a progress adjustment parameter of each target engineering node of each progress management project according to the progress regulation style of the progress management project, the current progress state of the progress management project and the progress adjustment requirement information of the progress management project corresponding to the legal progress adjustment instruction;
and determining a progress adjustment notification object of each target engineering node of each progress management item according to the identity.
Specifically, the progress adjustment amplitude of each target engineering node of the progress management project may be different for different users, some managers may have a thunder line for the style of progress management, then the progress adjustment amplitude of the user for each target engineering node of the progress management project may be set to be larger (e.g., the progress is faster than the normal average of the industry), some managers may have a thunder line for the style of progress management, then the progress adjustment amplitude of the user for each target engineering node of the progress management project may be set to be smaller (e.g., the progress is slower than the normal average of the industry). The user can recognize the progress regulation style of the progress management project according to the identity, so that the subsequent progress regulation result can be more in line with the progress regulation habit and requirement of the user.
The corresponding relationship between the schedule regulation style of the schedule management project, the current schedule state of the schedule management project, and the schedule regulation requirement information of the schedule management project corresponding to the legal schedule regulation instruction and the schedule regulation parameter of each target engineering node of each schedule management project can be pre-established according to experience values (can be both the experience value of the industry and the experience value of the user).
In addition, after the progress of each target engineering node of the relevant progress management project of the user is adjusted, the relevant adjustment notification object can be notified according to the identity of the user. The corresponding relationship can be established in advance for the identity of the user, each target engineering node of the related progress management project, and the progress adjustment notification object after the progress adjustment of each target engineering node.
As an optional implementation manner, the determining the progress regulation style of each progress management item according to the identity identifier includes:
and finding the progress regulation style of each progress management project corresponding to the identity from the mapping table according to a mapping table of the pre-established identity and the progress regulation style of each progress management project, wherein the progress regulation style is obtained by training the history progress regulation data of the progress management project according to the user corresponding to the identity in advance.
Specifically, the progress regulation style is obtained by training the history progress regulation data of each target engineering node of the progress management project according to the user corresponding to the identity in advance, and the training process can be performed by using an existing training model method.
As an alternative embodiment, the S11 includes:
s111, identifying the position corresponding to the identity mark;
in the application, the progress management operation management system belongs to a construction management platform, and the construction management platform also comprises a human resource management system, and when the management authority set corresponding to the identity mark is identified, the position corresponding to the identity mark can be obtained from the human resource management system.
As an alternative embodiment, the S111 includes:
identifying identity information of a user through a biological identification method based on the biological characteristics; and identifying the position corresponding to the user according to the identity information.
Particularly, when the identity information of the user is identified by the biometric identification method based on the biometric feature, the identification mode of the biometric feature may be a combination of a plurality of types or may be a single mode.
For example, when the light intensity is lower than the preset threshold, the target multi-biometric mode includes a fingerprint recognition mode, but does not include a biometric mode dependent on the light intensity, such as an iris recognition mode, a face recognition mode, etc.; when cocoons are generated on the fingers of the user, the target multi-biometric module can comprise a biometric identification mode with high security level such as an iris identification mode, and does not comprise a fingerprint identification mode.
In a self embodiment, identifying identity information of the user through a biological identification method based on the biological characteristics; and recognizing the position corresponding to the user according to the identity information, and only giving each person one position without adjusting the authority once for each person, so that the authority is conveniently given.
Referring to fig. 2, fig. 2 is a schematic structural diagram of an engineering progress control device according to a third embodiment of the present application. As shown in fig. 2, in any other embodiment, the apparatus includes:
the information receiving module 10 is configured to receive progress management information of a user, where the progress management information includes a progress adjustment instruction and an identity; the progress adjustment instruction comprises progress adjustment demand information;
the right identification module 11 is used for identifying a management right set corresponding to the identity;
the permission comparison module 12 is configured to compare the management permission corresponding to the progress adjustment instruction with the management permissions in the management permission set, determine a legal management permission from the management permissions corresponding to the progress adjustment instruction, and determine a legal progress adjustment instruction corresponding to the legal management permission from the progress management;
the project progress obtaining module 13 is configured to obtain a progress management project corresponding to the legal management authority, and display a current progress state of the progress management project;
a regulation and control policy determining module 14, configured to determine a progress regulation and control policy of each progress management item according to a current progress status of the progress management item, the legal progress adjustment instruction, and the identity; the progress regulating strategy comprises the following steps: the progress adjustment parameters and the progress adjustment notification objects of each target engineering node of the progress management project;
and the regulation and control operation module 15 is used for carrying out the progress regulation and control operation on the corresponding progress management project according to the progress regulation and control strategy and notifying the progress regulation and control operation result to the progress regulation notifying object.
In this embodiment, by confirming the management authority of the user on the progress management project by both the progress adjustment instruction and the identity identifier, the progress management project corresponding to the legal management authority of the user is directly found, and the current progress state of the progress management project is displayed, so that the user can be prevented from knowing the current progress state of the progress management project responsible for the user through complicated operations; meanwhile, the progress regulation and control strategy of each progress management project is determined according to the current progress state of the progress management project, legal progress regulation instructions and the identity of a user, so that a proper progress regulation and control strategy can be quickly formulated according to the progress regulation and control needs of the user on target engineering nodes of the progress management project, the corresponding progress management project can be automatically subjected to progress regulation and control operation according to the progress regulation and control strategy, and after the progress regulation and control operation is carried out on the progress management project, corresponding personnel can be automatically notified. From the analysis, the embodiment of the application can automatically realize reasonable regulation and control of the progress of the project progress management project and automatically inform relevant personnel of the progress regulation result only by knowing the progress regulation instruction and the identity of the user, and the whole project progress regulation process is efficient and convenient.
As an alternative embodiment, the regulation strategy determination module includes:
the regulation and control style determining unit is used for determining the progress regulation and control style of each progress management project according to the identity; the progress regulation style is used for indicating the progress regulation amplitude of each target engineering node of the progress management project;
the adjustment parameter determining unit is used for determining the progress adjustment parameter of each target engineering node of each progress management project according to the progress regulation style of the progress management project, the current progress state of the progress management project and the progress adjustment requirement information of the progress management project corresponding to the legal progress adjustment instruction;
and the notification object determining unit is used for determining a progress adjustment notification object of each target engineering node of each progress management item according to the identity.
As an optional implementation manner, the regulation style determining unit is specifically configured to:
and finding the progress regulation style of each progress management project corresponding to the identity from the mapping table according to a mapping table of the pre-established identity and the progress regulation style of each progress management project, wherein the progress regulation style is obtained by training the history progress regulation data of the progress management project according to the user corresponding to the identity in advance.
It can be understood that the above-mentioned related device embodiments may correspond to the related content descriptions with reference to the above-mentioned method embodiments, and will not be described herein again.
The third aspect of the present application discloses another engineering progress control electronic device, which includes:
a memory storing executable program code;
a processor coupled to the memory;
the processor invokes the executable program code stored in the memory to execute the engineering progress control method disclosed in the first aspect of the present application.
A fourth aspect of the present application discloses a computer storage medium storing computer instructions for executing the engineering progress control method disclosed in the first aspect of the present application when the computer instructions are called.
Referring to fig. 3, fig. 3 is a schematic structural diagram of an engineering progress control electronic device according to a fourth embodiment of the present application. As shown in fig. 3, the engineering progress control electronic device may include:
a Processor 291, the apparatus further comprising a Memory 292 in which executable program code is stored; a communication interface (Communication Interface) 293 and bus 294 may also be included. The processor 291, the memory 292, and the communication interface 293 may communicate with each other via the bus 294. Communication interface 293 may be used for information transfer. The processor 291 is coupled to the memory 292, and the processor 291 may call logic instructions (executable program code) in the memory 292 to perform the engineering progress control method according to any of the above embodiments.
Further, the logic instructions in memory 292 described above may be implemented in the form of software functional units and stored in a computer-readable storage medium when sold or used as a stand-alone product.
The memory 292 is a computer readable storage medium, and may be used to store a software program, a computer executable program, and program instructions/modules corresponding to the methods in the embodiments of the present application. The processor 291 executes functional applications and data processing by running software programs, instructions and modules stored in the memory 292, i.e., implements the methods of the method embodiments described above.
Memory 292 may include a storage program area that may store an operating system, at least one application program required for functionality, and a storage data area; the storage data area may store data created according to the use of the terminal device, etc. Further, memory 292 may include high-speed random access memory, and may also include non-volatile memory.
Embodiments of the present application also provide a computer-readable storage medium having stored therein computer-executable instructions that, when invoked, are adapted to implement the method described in any of the embodiments.
Embodiments of the present application also disclose a computer program product comprising a non-transitory computer readable storage medium storing a computer program, and the computer program is operable to cause a computer to perform the steps of the engineering progress control method described in any of the embodiments.
The apparatus embodiments described above are merely illustrative, wherein the modules illustrated as separate components may or may not be physically separate, and the components shown as modules may or may not be physical, i.e., may be located in one place, or may be distributed over a plurality of network modules. Some or all of the modules may be selected according to actual needs to achieve the purpose of the solution of this embodiment. Those of ordinary skill in the art will understand and implement the present application without undue burden.
From the above detailed description of the embodiments, it will be apparent to those skilled in the art that the embodiments may be implemented by means of software plus necessary general hardware platforms, or of course by means of hardware. Based on such understanding, the foregoing technical solutions may be embodied essentially or in part in the form of a software product that may be stored in a computer-readable storage medium including Read-Only Memory (ROM), random-access Memory (Random Access Memory, RAM), programmable Read-Only Memory (Programmable Read-Only Memory, PROM), erasable programmable Read-Only Memory (Erasable Programmable Read Only Memory, EPROM), one-time programmable Read-Only Memory (OTPROM), electrically erasable programmable Read-Only Memory (EEPROM), compact disc Read-Only Memory (Compact Disc Read-Only Memory, CD-ROM) or other optical disc Memory, magnetic disc Memory, tape Memory, or any other medium that can be used for computer-readable carrying or storing data.
Finally, it should be noted that: the disclosed engineering progress control method and device are only the preferred embodiments of the present application, and are only used for illustrating the technical scheme of the present application, but not limiting the technical scheme; although the application has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art will understand that; the technical scheme recorded in the various embodiments can be modified or part of technical features in the technical scheme can be replaced equivalently; such modifications and substitutions do not depart from the spirit and scope of the corresponding technical solutions.

Claims (10)

1. An engineering progress control method, characterized in that the method comprises the following steps:
receiving progress management information of a user, wherein the progress management information comprises a progress adjustment instruction and an identity mark; the progress adjustment instruction comprises progress adjustment demand information;
identifying a management authority set corresponding to the identity;
comparing the management authority corresponding to the progress adjustment instruction with the management authorities in the management authority set, determining legal management authorities from the management authorities corresponding to the progress adjustment instruction, and determining legal progress adjustment instructions corresponding to the legal management authorities from the progress management;
acquiring a progress management project corresponding to the legal management authority, and displaying the current progress state of the progress management project;
determining a progress regulation strategy of each progress management project according to the current progress state of the progress management project, the legal progress regulation instruction and the identity; the progress regulating strategy comprises the following steps: the progress adjustment parameters and the progress adjustment notification objects of each target engineering node of the progress management project;
and carrying out progress regulation operation on the corresponding progress management project according to the progress regulation strategy, and notifying a progress regulation operation result to the progress regulation notification object.
2. The method of claim 1, wherein determining a schedule adjustment policy for each schedule management item based on a current schedule status of the schedule management item, the legal schedule adjustment instruction, and the identity comprises:
determining the progress regulation style of each progress management project according to the identity; the progress regulation style is used for indicating the progress regulation amplitude of each target engineering node of the progress management project;
determining a progress adjustment parameter of each target engineering node of each progress management project according to the progress regulation style of the progress management project, the current progress state of the progress management project and the progress adjustment requirement information of the progress management project corresponding to the legal progress adjustment instruction;
and determining a progress adjustment notification object of each target engineering node of each progress management item according to the identity.
3. The method of claim 2, wherein determining a progress style for each of the progress management projects based on the identity comprises:
and finding the progress regulation style of each progress management project corresponding to the identity from the mapping table according to a mapping table of the pre-established identity and the progress regulation style of each progress management project, wherein the progress regulation style is obtained by training the history progress regulation data of the progress management project according to the user corresponding to the identity in advance.
4. The method of claim 1, wherein the identifying the set of management rights corresponding to the identity comprises:
identifying the position corresponding to the identity mark;
and acquiring a management authority set corresponding to the position.
5. The method of claim 4, wherein the identity comprises a biometric of a user of the terminal from which the user sent the progress management information, and wherein identifying the identity corresponds to a job position comprises:
identifying identity information of a user through a biological identification method based on the biological characteristics;
and identifying the position corresponding to the user according to the identity information.
6. An engineering progress control device, characterized in that the device comprises:
the information receiving module is used for receiving the progress management information of the user, wherein the progress management information comprises a progress adjustment instruction and an identity mark; the progress adjustment instruction comprises progress adjustment demand information;
the right identification module is used for identifying a management right set corresponding to the identity;
the permission comparison module is used for comparing the management permission corresponding to the progress adjustment instruction with the management permissions in the management permission set, determining legal management permissions from the management permissions corresponding to the progress adjustment instruction, and determining legal progress adjustment instructions corresponding to the legal management permissions from the progress management;
the project progress acquisition module is used for acquiring a progress management project corresponding to the legal management authority and displaying the current progress state of the progress management project;
the regulation and control strategy determining module is used for determining the progress regulation and control strategy of each progress management project according to the current progress state of the progress management project, the legal progress adjustment instruction and the identity; the progress regulating strategy comprises the following steps: the progress adjustment parameters and the progress adjustment notification objects of each target engineering node of the progress management project;
and the regulation and control operation module is used for carrying out the progress regulation and control operation on the corresponding progress management project according to the progress regulation and control strategy and notifying the progress regulation and control operation result to the progress regulation notifying object.
7. The apparatus of claim 6, wherein the regulation strategy determination module comprises:
the regulation and control style determining unit is used for determining the progress regulation and control style of each progress management project according to the identity; the progress regulation style is used for indicating the progress regulation amplitude of each target engineering node of the progress management project;
the adjustment parameter determining unit is used for determining the progress adjustment parameter of each target engineering node of each progress management project according to the progress regulation style of the progress management project, the current progress state of the progress management project and the progress adjustment requirement information of the progress management project corresponding to the legal progress adjustment instruction;
and the notification object determining unit is used for determining a progress adjustment notification object of each target engineering node of each progress management item according to the identity.
8. The device according to claim 7, wherein the regulation style determination unit is specifically configured to:
and finding the progress regulation style of each progress management project corresponding to the identity from the mapping table according to a mapping table of the pre-established identity and the progress regulation style of each progress management project, wherein the progress regulation style is obtained by training the history progress regulation data of the progress management project according to the user corresponding to the identity in advance.
9. An engineering progress control electronic device, characterized in that the electronic device comprises:
a memory storing executable program code;
a processor coupled to the memory;
the processor invokes the executable program code stored in the memory to perform the engineering progress control method of any one of claims 1-5.
10. A computer storage medium storing computer instructions which, when invoked, are adapted to perform the engineering progress control method of any one of claims 1-5.
CN202310699630.1A 2023-06-13 2023-06-13 Engineering progress control method and device Active CN117114592B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310699630.1A CN117114592B (en) 2023-06-13 2023-06-13 Engineering progress control method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310699630.1A CN117114592B (en) 2023-06-13 2023-06-13 Engineering progress control method and device

Publications (2)

Publication Number Publication Date
CN117114592A true CN117114592A (en) 2023-11-24
CN117114592B CN117114592B (en) 2024-03-19

Family

ID=88795472

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310699630.1A Active CN117114592B (en) 2023-06-13 2023-06-13 Engineering progress control method and device

Country Status (1)

Country Link
CN (1) CN117114592B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1831855A (en) * 2006-04-04 2006-09-13 天津大学 Real-time analysing and control system and method for large underground hole group construction at network environment
CN111369220A (en) * 2020-03-06 2020-07-03 单俊平 Teacher's cloud platform is built to wisdom
CN111401765A (en) * 2020-03-24 2020-07-10 重庆德生鼎盛实业发展有限公司 Engineering progress supervisory systems based on big data
CN114548906A (en) * 2022-01-18 2022-05-27 山东恒诺信工程咨询有限公司 Engineering supervision and supervision method, system and device and storage medium

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1831855A (en) * 2006-04-04 2006-09-13 天津大学 Real-time analysing and control system and method for large underground hole group construction at network environment
CN111369220A (en) * 2020-03-06 2020-07-03 单俊平 Teacher's cloud platform is built to wisdom
CN111401765A (en) * 2020-03-24 2020-07-10 重庆德生鼎盛实业发展有限公司 Engineering progress supervisory systems based on big data
CN114548906A (en) * 2022-01-18 2022-05-27 山东恒诺信工程咨询有限公司 Engineering supervision and supervision method, system and device and storage medium

Also Published As

Publication number Publication date
CN117114592B (en) 2024-03-19

Similar Documents

Publication Publication Date Title
CN107451040B (en) Method and device for positioning fault reason and computer readable storage medium
CN107909330B (en) Workflow data processing method and device, storage medium and computer equipment
CN109145532B (en) Program white list management method and system supporting software online upgrade
CN112528251B (en) User account authority management method, device, equipment and readable medium
CN110619206B (en) Operation and maintenance risk control method, system, equipment and computer readable storage medium
CN107463839A (en) A kind of system and method for managing application program
CN106407203A (en) Method and device for identifying target terminal
CN110069925A (en) Software monitors method, system and computer readable storage medium
CN113918526A (en) Log processing method and device, computer equipment and storage medium
CN117114592B (en) Engineering progress control method and device
CN115017485A (en) Data authority management and control method and system
CN112650659B (en) Buried point setting method and device, computer equipment and storage medium
CN112163211B (en) Distribution network box management method and device, computer equipment and storage medium
CN109039714A (en) The management method and device of resource in cloud computing system
CN111061529B (en) Configuration software multi-label page management method, device and storage medium
CN111897843A (en) Configuration method and device of data transfer strategy of Internet of things and computer equipment
CN110457101A (en) A kind of information processing method, electronic equipment and storage medium
CN114443581B (en) Download control method, device, equipment and storage medium
CN109993421A (en) Apply the site safety risk recognition system and operating method in electricity power enterprise
CN112069377A (en) Session information data processing method and device, computer equipment and storage medium
CN109784675A (en) Task of supervision processing method, device, computer equipment and storage medium
CN106982433B (en) A kind of method and wireless controller making access terminal STA access WLAN
CN114553726B (en) Network security operation and maintenance method and system based on functions and resource levels
CN109872124A (en) Medical instrument research and development project management method and system
CN109814841A (en) A kind of resource information acquisition method and device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Country or region after: China

Address after: Room 3804, No. 660-1, Huangpu Avenue Middle, Tianhe District, Guangzhou City, Guangdong Province, 510665

Applicant after: Huateng Jianxin Technology Co.,Ltd.

Address before: Room 1301, 38 Zhongshan Avenue Middle, Tianhe District, Guangzhou, Guangdong 510000

Applicant before: Huateng Jianxin Technology Co.,Ltd.

Country or region before: China