CN115726553A - Pre-assembling erection method for high and large disc buckle type scaffold - Google Patents

Pre-assembling erection method for high and large disc buckle type scaffold Download PDF

Info

Publication number
CN115726553A
CN115726553A CN202211513851.7A CN202211513851A CN115726553A CN 115726553 A CN115726553 A CN 115726553A CN 202211513851 A CN202211513851 A CN 202211513851A CN 115726553 A CN115726553 A CN 115726553A
Authority
CN
China
Prior art keywords
assembly
support
vertical
assembly method
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211513851.7A
Other languages
Chinese (zh)
Inventor
毛叔东
胡国谭
徐民刚
杨宗良
王天祺
吴志明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN202211513851.7A priority Critical patent/CN115726553A/en
Publication of CN115726553A publication Critical patent/CN115726553A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a method for pre-assembling and erecting a high and large disc buckle type scaffold; comprises a coiling buckle scaffold upright rod, a cross rod, an inclined pull rod and a pin; the method is characterized in that the erection method comprises the steps of judging a pre-assembly scheme which is specifically adopted according to the height of the support, preferably selecting a mixed pre-assembly method when the height of the support is more than 10 meters or the working condition is complex, preferably selecting a horizontal assembly method when the height of the support is 6 meters-10 meters, and preferably selecting a vertical pre-assembly method when the height of the support is not more than 6 meters; measuring and paying off on a construction site, and positioning the position of each upright rod of each unit module; and assembling the unit modules into a whole one by utilizing hoisting equipment. The method divides the original scaffold into a plurality of unit modules, pre-assembles the modules outside a construction site, and finally assembles the scaffold into an integral scaffold. The method can be carried out together with the preposed working procedures, can effectively shorten the construction period, improve the construction efficiency and reduce the construction cost.

Description

Pre-assembling erection method for high and large disc buckle type scaffold
Technical Field
The invention relates to the field of building construction, in particular to a method for pre-assembling and erecting a high and large disc buckle type scaffold.
Background
Generally, after the foundation construction of the scaffold is completed, the vertical rods and the cross rods are sequentially arranged from bottom to top according to the design combination of the vertical rods and the cross rods. The bottom upright posts and partial cross rods of one working face are completely installed, and then the bottom upright posts and the partial cross rods are installed layer by layer upwards, and the installation is finished by sequential connection from bottom to top. The scaffold erection operation generally needs to be carried out after foundation construction is completed, and construction progress is inevitably influenced when construction period is short. When the height of the support is high and the size of the support is large, a large amount of labor is consumed in carrying the support materials, construction cost is increased, construction efficiency is influenced, and meanwhile, the safety risks of falling from a high place, falling from a high place and the like are increased.
Disclosure of Invention
The invention aims to overcome the defects and provides a vertical pre-assembly erection method, a horizontal pre-assembly erection method and a mixed pre-assembly erection method, so that the construction efficiency is improved, the construction cost is reduced, and the construction safety is improved.
In order to achieve the above object, the present invention is realized by:
a method for pre-assembling and erecting a high and large coil buckle type scaffold comprises coil buckle scaffold upright rods, cross rods, diagonal draw rods and pins; the setting-up method comprises
Step 1, judging a pre-assembly scheme specifically adopted according to the height of a support, preferably selecting a mixed pre-assembly method when the height of the support is more than 10 meters or the working condition is complex, preferably selecting a horizontal assembly method when the height of the support is 6-10 meters, and preferably selecting a vertical pre-assembly method when the height of the support is not more than 6 meters;
step 2, dividing the whole support into unit modules according to the support scheme, wherein the unit modules are preferably rectangular and symmetrically designed, and the number of vertical cross rods and the number of rods on two sides of a central axis are kept consistent; the specific principle is related to which pre-assembly method is selected; when a vertical pre-assembly method is adopted, the length and the width of the vertical pre-assembly method are not more than 6m, and the pre-assembly height is not more than 6m; when a horizontal pre-assembly method is adopted, the width is not more than 6m, the height is not more than 5m, and the length in the vertical rod direction is not more than 10m; the diagonal draw bar arrangement of each unit module at least meets the requirement of interval one-span arrangement;
step 3, according to the design of the unit modules, pre-assembling the unit modules outside the construction site, numbering the unit modules in sequence according to the assembling sequence, and marking the orientation of the upright stanchion, the module number and the module number connected with the upright stanchion on four sides of the unit modules by arrows and letters;
step 4, measuring and setting out on a construction site, and positioning the position of each upright rod of each unit module;
step 5, utilizing hoisting equipment to assemble the unit modules into a whole one by one, hoisting the 1 st module to a specified position during assembly, ensuring the position of each upright of the 1 st module to be accurate, determining that the orientation of the upright sleeve is consistent with the scheme, and sequentially installing other modules after the 1 st module is installed; when the assembly is carried out horizontally, the distance between the 1 st module and the adjacent module is strictly controlled to be the distance between the coiling buckle cross rods, and after the position of the vertical rod is confirmed to be error-free, all the modules are connected into a whole by the cross rods.
The method for pre-assembling and erecting the tall and big disk buckle type scaffold,
the vertical pre-assembly method, the horizontal pre-assembly method and the mixed pre-assembly method in the step 1 respectively refer to
The vertical pre-assembly method comprises the following steps: the pre-assembly of the unit modules is basically consistent with the traditional erection method, the disc buckle upright rods are vertically arranged, then the cross rods and the diagonal rods are sequentially erected, and when the upright rods need to be lengthened, pins are arranged as required; when the support is integrally assembled, the support is assembled in the horizontal direction and the vertical direction, and when the integral height of the support is not more than 6m, a vertical pre-assembly method is preferably selected;
horizontal pre-assembly method: the pre-assembly of the unit modules is different from the traditional method for building the unit modules, the method is characterized in that a disc buckle vertical rod is transversely arranged, a transverse rod and a diagonal draw bar are sequentially built, a pin needs to be arranged for lengthening the vertical rod, when the support is integrally assembled, the support is mainly assembled in the horizontal direction, and when the height of the support is 6-10 m, a horizontal pre-assembly method is preferably adopted;
a mixed pre-assembly method: the method is a method using vertical and horizontal pre-assembly methods, when the support is complex or the overall height is more than 10m, the size of each module is confirmed according to the field conditions, and the pre-assembly method of each module is flexibly arranged.
The method is a method for building a pre-assembled scaffold, and comprises three methods of a vertical pre-assembly method, a horizontal pre-assembly method and a mixed pre-assembly method. The scaffold is mainly characterized in that an original scaffold is divided into a plurality of unit modules, pre-assembled outside a construction site according to the modules, and finally assembled into an integral scaffold. The method can be carried out together with the preposed working procedures, so that the construction period can be effectively shortened, the construction efficiency can be improved, and the construction cost can be reduced; the modular design is convenient for control once the height of setting up, utilizes hoisting equipment to carry out whole equipment, has saved the cost of labor that the material handling produced, improves material handling efficiency, has still reduced the safety risk that the aerial work brought simultaneously. In addition, the method comprises three forms, is suitable for various working conditions, and has wide application range.
Drawings
FIG. 1a is a plan view (vertical) of a unit module according to the present invention.
FIG. 1b is an elevation view (vertical) of the unit module of the present invention.
FIG. 1c is a schematic diagram of the unit module identifier (vertical type) in the present invention.
FIG. 2a is an elevation view (horizontal) of a unit module according to the present invention.
FIG. 2b isbase:Sub>A sectional view (horizontal type) ofbase:Sub>A unit module A-A according to the present invention.
FIG. 2c is a schematic diagram of the unit module identifier (horizontal type) in the present invention.
FIG. 3a is a schematic plan view of the whole assembly (vertical type) of the present invention.
FIG. 3b is a schematic vertical view of the whole assembly of the present invention.
FIG. 4 is a schematic view of the horizontal unit module of the present invention arranged vertically.
Detailed Description
The invention is further illustrated by the following specific examples.
A method for pre-assembling and erecting a high and large coil buckle type scaffold comprises coil buckle scaffold upright rods, cross rods, diagonal draw bars and pins; the setting-up method comprises
Step 1, judging a pre-assembly scheme specifically adopted according to the height of a support, preferably selecting a mixed pre-assembly method when the height of the support is more than 10 meters or the working condition is complex, preferably selecting a horizontal assembly method when the height of the support is 6-10 meters, and preferably selecting a vertical pre-assembly method when the height of the support is not more than 6 meters;
step 2, dividing the whole support into unit modules according to the support scheme, wherein the unit modules are preferably rectangular and symmetrically designed, and the number of vertical cross bars and the number of rods on two sides of the central axis are kept consistent; the specific principle is related to which pre-assembly method is selected; when a vertical pre-assembly method is adopted, the length and the width of the vertical pre-assembly method are not more than 6m, and the pre-assembly height is not more than 6m; when a horizontal pre-assembly method is adopted, the width is not more than 6m, the height is not more than 5m, and the length in the vertical rod direction is not more than 10m; the diagonal draw bar arrangement of each unit module at least meets the interval one-span arrangement;
step 3, according to the design of the unit modules, pre-assembling the unit modules outside the construction site, numbering the unit modules in sequence according to the assembling sequence, and marking the orientation of the upright stanchion, the module number and the module number connected with the upright stanchion on four sides of the unit modules by arrows and letters;
step 4, measuring and setting out on a construction site, and positioning the position of each upright rod of each unit module;
step 5, utilizing hoisting equipment to assemble the unit modules into a whole one by one, hoisting the 1 st module to a specified position during assembly, ensuring the position of each upright of the 1 st module to be accurate, determining that the orientation of the upright sleeve is consistent with the scheme, and sequentially installing other modules after the 1 st module is installed; when the assembly is carried out horizontally, the distance between the 1 st module and the adjacent module is strictly controlled to be the distance between the coiling buckle cross rods, and after the position of the vertical rod is confirmed to be error-free, all the modules are connected into a whole by the cross rods.
In the construction method, the unit module design of the vertical pre-assembly method is as follows:
the unit module consists of a plurality of vertical rods (11), a cross rod (12), an inclined pull rod (13) and a pin (14), as shown in figures 1a and 1 b. The size of the module is not too large or too small during module design. Should detain the pole setting by 4 dishes at least and 4 dishes detain the horizontal pole and constitute, its length, width, height all use to be no more than 6m as the fit, too big can increase the hoist and mount degree of difficulty and at hoist and mount in-process volatile steady, too high can reduce pre-assembly efficiency and increase the high altitude construction safety risk.
The coil buckle upright rod (11) used by the unit module is vertically arranged when being erected, and the arrangement of the inclined pull rod (13) at least meets the requirement of interval one-span arrangement for increasing the overall stability. The extension of the single module uprights must be done using a pin connection (14) to avoid the uprights falling off during the module transport. After the unit modules are assembled, the numbers Mn, the directions (marked by arrows) and the numbers Mk of adjacent modules are marked at the top and bottom ends of the four Zhou Li rods, and the numbers Mn, the directions (marked by the arrow and the direction by the letter S, N, E, W) and the numbers Mx of adjacent modules are marked on the cross rods on the periphery, so that the subsequent integral installation is facilitated, as shown in FIG. 1 c.
In the construction method, the horizontal pre-assembly method unit module is designed as follows:
the module is also composed of a plurality of vertical rods (21), a cross rod (22), a diagonal draw bar (23) and a pin (24), as shown in fig. 2a and 2 b. The design size of the module is different from that of a vertical pre-assembly method, the length of the module is not larger than 10m, the width of the module is not larger than 6m, and the height of the module is not larger than 5m. Too big length and width are unfavorable for whole assembly and the easy unstability of hoist and mount in-process, and high height can reduce pre-assembly efficiency and increase aerial work safety risk. The module should have 4 dish to detain the pole setting, 4 dish to detain the horizontal pole group at least.
The design of the unit module is a pre-assembly method for transversely arranging the disc buckle vertical rods, the arrangement of the diagonal draw bars for increasing the stability of the unit module at least meets the arrangement of 1 span at intervals, and the extension of the vertical rods must be connected by using pins so as to prevent the vertical rods from falling off in the module transportation process. After the unit modules are assembled, marks are made at corresponding positions of the vertical rods and the cross rods on the periphery, and the marking rules are consistent with those of the unit modules of the vertical pre-assembly method, as shown in fig. 2 c.
In the construction method, the vertical pre-assembly method is used for integral assembly:
the integral assembly is to assemble all the modules into a whole by utilizing machines such as a tower crane, a crane and the like on a construction site. The whole assembly of the method comprises horizontal assembly and vertical assembly, wherein the assembly is carried out according to the principle of firstly carrying out horizontal and then carrying out vertical, the assembly is carried out by firstly positioning the M1 module (the 1 st module), and the installation of other modules is carried out in sequence according to the logic numbers among the modules after repeatedly confirming the positions and elevations of the vertical rods on the periphery of the module. When other modules are horizontally installed, the distance between the four Zhou Ligan and the upright rods of the adjacent modules in place is determined to be the distance of a cross rod; when assembling in the vertical direction, the upper ends of the vertical rods around the lower unit module are provided with a guiding device so that the upper module can be positioned conveniently. As shown in fig. 3a and 3b, the modules are finally assembled into 1 unit.
In the construction method, the horizontal pre-assembly method is used for integral assembly:
because the vertical rod of the plate buckle under the horizontal pre-assembly method is placed horizontally, before the whole assembly, the required modules are firstly hoisted and vertically placed by using machines such as a tower crane, a truck crane and the like, and then the whole assembly can be completely referred to the vertical pre-assembly method in the installation sequence, as shown in fig. 4.

Claims (2)

1. A method for pre-assembling and erecting a high and large coil buckle type scaffold comprises coil buckle scaffold upright rods, cross rods, diagonal draw rods and pins; it is characterized in that the setting method comprises
Step 1, judging a pre-assembly scheme to be specifically adopted according to the height of a support, preferably selecting a mixed pre-assembly method when the height of the support is more than 10 meters or the working condition is complex, preferably selecting a horizontal assembly method when the height of the support is 6-10 meters, and preferably selecting a vertical pre-assembly method when the height of the support is not more than 6 meters;
step 2, dividing the whole support into unit modules according to the support scheme, wherein the unit modules are preferably rectangular and symmetrically designed, and the number of vertical cross bars and the number of rods on two sides of the central axis are kept consistent; the specific principle is related to which pre-assembly method is selected; when a vertical pre-assembly method is adopted, the length and the width of the vertical pre-assembly method are not more than 6m, and the pre-assembly height is not more than 6m; when a horizontal pre-assembly method is adopted, the width is not more than 6m, the height is not more than 5m, and the length in the vertical rod direction is not more than 10m; the diagonal draw bar arrangement of each unit module at least meets the interval one-span arrangement;
step 3, according to the design of the unit modules, pre-assembling the unit modules outside the construction site, numbering the unit modules in sequence according to the assembling sequence, and marking the orientation of the upright stanchion, the module number and the module number connected with the upright stanchion on four sides of the unit modules by arrows and letters;
step 4, carrying out measurement and paying-off on a construction site, and positioning the position of each upright rod of each unit module;
step 5, utilizing hoisting equipment to assemble the unit modules into a whole one by one, hoisting the 1 st module to a specified position during assembly, ensuring the position of each upright of the 1 st module to be accurate, determining that the orientation of the upright sleeve is consistent with the scheme, and sequentially installing other modules after the 1 st module is installed; when the assembly is carried out horizontally, the distance between the 1 st module and the adjacent module is strictly controlled to be the distance between the coiling buckle cross rods, and after the position of the vertical rod is confirmed to be error-free, all the modules are connected into a whole by the cross rods.
2. The pre-assembling erection method of the tall and big disc button scaffold according to claim 1, which is characterized in that:
the vertical pre-assembly method, the horizontal pre-assembly method and the mixed pre-assembly method in the step 1 are respectively referred to
The vertical pre-assembly method comprises the following steps: the pre-assembly of the unit modules is basically consistent with the traditional erection method, the plate buckle vertical rods are vertically arranged, then the cross rods and the diagonal rods are sequentially erected, and when the vertical rods need to be lengthened, pins are arranged as required; when the support is integrally assembled, the support is assembled in the horizontal direction and the vertical direction, and when the integral height of the support is not more than 6m, a vertical pre-assembly method is preferably selected;
horizontal pre-assembly method: the pre-assembly of the unit modules is different from the traditional method for building the unit modules, the method is characterized in that a disc buckle vertical rod is transversely arranged, a transverse rod and a diagonal draw bar are sequentially built, a pin needs to be arranged for lengthening the vertical rod, when the support is integrally assembled, the support is mainly assembled in the horizontal direction, and when the height of the support is 6-10 m, a horizontal pre-assembly method is preferably adopted;
the mixed pre-assembly method comprises the following steps: the method is a method which simultaneously uses a vertical and horizontal pre-assembly method, when the support is more complex or the whole height is more than 10m, the size of each module is confirmed according to the field condition, and the pre-assembly method of each module is flexibly arranged.
CN202211513851.7A 2022-11-30 2022-11-30 Pre-assembling erection method for high and large disc buckle type scaffold Pending CN115726553A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211513851.7A CN115726553A (en) 2022-11-30 2022-11-30 Pre-assembling erection method for high and large disc buckle type scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211513851.7A CN115726553A (en) 2022-11-30 2022-11-30 Pre-assembling erection method for high and large disc buckle type scaffold

Publications (1)

Publication Number Publication Date
CN115726553A true CN115726553A (en) 2023-03-03

Family

ID=85299154

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211513851.7A Pending CN115726553A (en) 2022-11-30 2022-11-30 Pre-assembling erection method for high and large disc buckle type scaffold

Country Status (1)

Country Link
CN (1) CN115726553A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205875654U (en) * 2016-08-05 2017-01-11 中建筑港集团有限公司 Novel scaffold frame device
CN206308988U (en) * 2016-11-15 2017-07-07 浙江横店建筑工程有限公司 Tool-type combination construction pylon
CN213234203U (en) * 2020-06-29 2021-05-18 中电建十一局工程有限公司 Disc buckle type upright column ladder cage scaffold
CN114673331A (en) * 2022-05-27 2022-06-28 天津鼎维固模架工程股份有限公司 Disc-buckling type tower and modular combined construction method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205875654U (en) * 2016-08-05 2017-01-11 中建筑港集团有限公司 Novel scaffold frame device
CN206308988U (en) * 2016-11-15 2017-07-07 浙江横店建筑工程有限公司 Tool-type combination construction pylon
CN213234203U (en) * 2020-06-29 2021-05-18 中电建十一局工程有限公司 Disc buckle type upright column ladder cage scaffold
CN114673331A (en) * 2022-05-27 2022-06-28 天津鼎维固模架工程股份有限公司 Disc-buckling type tower and modular combined construction method thereof

Similar Documents

Publication Publication Date Title
CN107090932B (en) Construction method of large-span thin-wall plane arch truss based on stiff ring beam
EP0654571A1 (en) Zone module construction method of steel structure construction
KR20110112228A (en) Method of building a hybrid tower for a wind generator
CN110805138B (en) Construction method for jacking two sides of large-span net rack
CN114458001A (en) Portable hanging flower basket suspension that construction was used is decorated to outdoor vestibule in high altitude
CN115726553A (en) Pre-assembling erection method for high and large disc buckle type scaffold
CN212771968U (en) Full-prefabricated assembled bridge bearing platform positioning system
CN110847691B (en) Mounting structure and mounting method of high-rise tower mast structure
CN112647719A (en) Modular hoisting method for embedded wall frame structure of steel structure factory building
CN111017696A (en) Hoisting method of integrally assembled prefabricated part
CN218495384U (en) Ladder beam on steel cable photovoltaic support
KR101372294B1 (en) Lifting method for meteorological mast using jacking system
CN113404199B (en) Installation method of umbrella-shaped roof structure
CN216196480U (en) Aerial work platform adopting Bailey beam structure
CN211113221U (en) Bent cap steel reinforcement framework shaping and binding rack
CN114673190A (en) Installation construction method for high-precision embedded bolt at column top
CN210825274U (en) Weather radar overhauls circulation jacking device
CN111827678A (en) Method for hoisting truss steel structure at top of silo
CN215330072U (en) Pay-off of three pile caps different stages in foundation construction
CN110847616A (en) Method for mounting large-volume steel frame flue
CN112683668A (en) Static load test device for communication support
CN116713629B (en) Assembling method for large pin wheel and supporting rod of portal crane
CN214462403U (en) Elevator shaft tool type steel platform
CN110685229A (en) Bent cap steel reinforcement framework shaping and binding rack
CN111305103A (en) Rapid construction method of ETC portal frame

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination