CN115369881A - Construction method of basement structure - Google Patents

Construction method of basement structure Download PDF

Info

Publication number
CN115369881A
CN115369881A CN202211151515.2A CN202211151515A CN115369881A CN 115369881 A CN115369881 A CN 115369881A CN 202211151515 A CN202211151515 A CN 202211151515A CN 115369881 A CN115369881 A CN 115369881A
Authority
CN
China
Prior art keywords
basement
construction
foundation
upper opening
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211151515.2A
Other languages
Chinese (zh)
Inventor
林科
龚盈寅
倪翊哲
周岗
龚倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jinlu Construction Group Co ltd
Original Assignee
Shanghai Jinlu Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jinlu Construction Group Co ltd filed Critical Shanghai Jinlu Construction Group Co ltd
Priority to CN202211151515.2A priority Critical patent/CN115369881A/en
Publication of CN115369881A publication Critical patent/CN115369881A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The application relates to the field of house construction, in particular to a construction method of a basement structure, which comprises the following steps: s1: constructing a foundation slab, namely dividing a construction area according to the position of a post-cast strip in the area of the foundation slab to be cast according to design requirements; s2: constructing a basement column, a wall and a top plate, and after pouring and forming a foundation bottom plate, sequentially constructing a structural column, the wall and the top plate on the foundation bottom plate; s3: performing waterproof construction outside the upper opening of the basement, performing waterproof construction at the position of the upper opening of the basement, and performing waterproof construction at the construction joint of the basement; s4: and backfilling the upper opening foundation of the basement, cleaning sundries in the foundation pit after the waterproof construction of the upper opening of the basement is finished, and filling a gap between the wall body of the basement and the side wall of the foundation pit. The method and the device have the effects of reducing construction cost, labor cost and construction period.

Description

Construction method of basement structure
Technical Field
The application relates to the field of house construction, in particular to a construction method of a basement structure.
Background
The existing basement is that the height of the ground of a room lower than the ground level of the outdoor is more than one half of the net height of the room, and a multi-storey and high-rise building needs a deeper foundation.
The basement in the building construction adopts the construction of jumping the storehouse, and the roof beam cantilever end that construct earlier are overlength, need carry out long-time back-jacking. The Chinese checkers method is characterized by that it fully utilizes the "resisting and releasing" characteristic principle of that the concrete is not stable in performance and can easily release internal stress before it is completely solidified in 5-10 days, and is characterized by that the building foundation or large-area concrete plane mechanism is divided into several zones, and constructed according to the principles of "block-dividing planning, block-separating construction, layer-pouring and integral forming", and its mode is identical to that of Chinese checkers, i.e. one section is poured at intervals. The interval time of two adjacent sections is not less than 7 days, so that the violent temperature difference and drying effect of the initial concrete construction part are avoided, and a post-cast strip is not required to be left.
With respect to the related art among the above, the inventors consider that the following drawbacks exist: in the prior art, the temporary column or the back jacking frame body is additionally arranged below the top plate for supporting, so that the construction cost is high, the temporary column or the outward-conveying frame body material needs to be chiseled after the subsequent top plate is connected, and the labor cost and the construction period are increased.
Disclosure of Invention
In order to overcome the problems in the prior art, the application provides a construction method of a basement structure.
The application provides a construction method of a basement structure, which adopts the following technical scheme:
a construction method of a basement structure comprises the following steps:
s1: constructing a foundation slab, namely dividing a construction area according to the position of a post-cast strip in the area of the foundation slab to be cast according to design requirements;
s2: constructing a basement column, a wall and a top plate, wherein after the foundation bottom plate is poured and molded, the construction of a structural column, the wall and the top plate is sequentially carried out on the foundation bottom plate;
s3: performing waterproof construction outside the upper opening of the basement, performing waterproof construction at the position of the upper opening of the basement, and performing waterproof construction at the construction joint of the basement;
s4: and backfilling the upper opening foundation of the basement, cleaning sundries in the foundation pit after the waterproof construction of the upper opening of the basement is finished, and filling a gap between the wall body of the basement and the side wall of the foundation pit.
By adopting the technical scheme, in the construction process of the basement structure, each link in the construction process can be effectively controlled, the efficiency in construction is improved through a standard operation flow, and the construction cost and the labor cost are reasonably reduced.
Optionally, in step S1, in the foundation slab construction, the foundation trench needs to be checked and accepted, the steel bars are bound on the poured slab, and the template engineering is performed on the periphery of the slab.
Through adopting above-mentioned technical scheme, before the construction bottom plate, the staff checks the acceptance to the foundation trench that excavates, makes the foundation trench accord with the requirement of design to the foundation trench bottom that excavates is close to levelly and smoothly, avoids appearing great pit, makes the foundation bottom plate construction come out can be more level and smooth, convenient subsequent construction operation.
Optionally, in step S2, the vertical steel bars in the structural column and the wall plate are fixed by three methods, i.e., threaded connection, welding and binding, according to different diameter specifications.
Through adopting above-mentioned technical scheme, because the diameter specification of structure post and the inside reinforcing bar of wall body is different, when connecting fixedly, need adopt different connected mode just can reach fixed requirement, to the great reinforcing bar of diameter, need adopt the sleeve to fix threaded connection between two adjacent reinforcing bars, to the reinforcing bar that the diameter is medium, adopt welded mode can conveniently be fixed with both, can adopt the mode of ligature to the less reinforcing bar of diameter, carry out quick fixed.
Optionally, in step S2, according to structural columns of different specifications, when concrete is poured, different formwork supporting modes are adopted, plywood with a thickness of 18mm is adopted when the cross section of the structural column is not greater than 600 × 600mm, and the plywood with the thickness of 18mm is fixed by surrounding purlins with steel pipes outside the plywood, plywood with the cross section of more than 600 × 600mm is also adopted, and the steel pipes surrounding purlins are arranged outside the plywood, and finally channel steel is arranged outside the steel pipes surrounding purlins for reinforcement.
Through adopting above-mentioned technical scheme, when processing preparation structure post on soleplate, because the structure post specification of different positions department is inequality, after the reinforcement is fixed to be accomplished, need strut the template at the external mounting of steel reinforcement cage, make things convenient for the concrete placement in later stage, owing to pour the concrete after, can be to strutting producing the extrusion force on the template, it can play reinforced effect to enclose the purlin at the outside of plywood to set up the steel pipe, under the bigger condition of structure post cross section, the channel-section steel that encloses the outside setting of purlin at the steel pipe can play reinforced effect once more.
Optionally, in step S2, a double-layer steel wire mesh is arranged on the reinforcement cage of the beam slab and at a position close to 500mm of the structural column and the wall body.
Through adopting above-mentioned technical scheme, when the concrete in pouring structure post, wall body, because the concrete composition on two kinds of positions is inequality, consequently, need strict separation when pouring, for guaranteeing that the concrete of two positions departments can not join in, the double-deck wire net piece that sets up can separate two positions punishment, avoids when pouring the concrete of two positions departments, and the concrete joins in together.
Optionally, in step S3, when the upper opening of the basement is subjected to construction waterproofing work, mortar or concrete is firstly used for leveling, so as to ensure the flatness of the surface of the base layer, and the deviation is not more than 5mm.
Through adopting above-mentioned technical scheme, when carrying out waterproofing, through the concrete to the basement suitable for reading the mouth the processing of making level, with the within range of the design requirement that the roughness keeps, follow-up when laying waterproofing membrane, the processing of carrying on water-proof that can be better.
Optionally, in step S3, waterproof rolls are laid on the leveled base layer, and two adjacent waterproof rolls are overlapped and sealed with each other.
Through adopting above-mentioned technical scheme, when carrying out water repellent, overlap joint each other between the adjacent waterproofing membrane, guarantee necessary sealed.
Optionally, in step S4, when backfilling is performed on the upper opening of the basement, the backfilled soil needs to be undisturbed soil, so that the construction waste cannot be used, and in the backfilling process, a layered backfilling manner should be adopted, and each layer of the backfilled soil is tamped.
Through adopting above-mentioned technical scheme, at the in-process of backfilling, need fill original state soil in the gap between basement wall body and the foundation ditch all around, make it better and the foundation ditch fuses all around, need the successive layer compaction at the in-process of backfilling, prevent that the later stage from appearing collapsing and appearing the pit.
In summary, the present application includes at least one of the following beneficial technical effects:
1. through adopting standardized construction flow, the construction progress of control basement structure construction to control construction cost and cost of labor, also more convenient for current basement structure construction, better implement.
Drawings
Fig. 1 is a schematic flow chart of an embodiment of the present application.
Detailed Description
The present application is described in further detail below with reference to fig. 1.
The embodiment of the application discloses a construction method of a basement structure. Referring to fig. 1, a construction method of a basement structure includes the steps of:
s1: constructing a foundation slab, wherein when the foundation slab is constructed, workers divide a construction area according to the position of a post-cast strip required by design;
before the construction of a foundation slab, workers firstly check and accept a foundation trench excavated in a basement, and construct cushion concrete on the bottom surface of the foundation trench, the construction of the cushion concrete should generally require that the exposed area of a foundation pit soil body is not more than 200m for reinforcement after following the excavation, and in the process of checking and accepting the foundation trench, the foundation trench should be checked and accepted in time with a supervision party and a design institute of basement structure construction according to the standard of design requirements, and after the check and acceptance is qualified, the cushion concrete begins to be poured, and the arranged cushion concrete can prevent the quality of the soil body at the bottom of the foundation pit from being influenced by rainwater erosion ears; before the pouring construction of the cushion concrete, the elevation of the cushion concrete is preset according to the design requirement, the cushion concrete is compacted by adopting a flat vibrator in the pouring process, and after the moisture in the cushion concrete is slightly dried, an iron trowel is used for polishing, flattening and compacting.
After the cushion concrete construction is finished, workers need to perform binding of bottom plate reinforcing steel bars on the surface of the cushion concrete, before the reinforcing steel bars are bound, the reinforcing steel bars need to be processed and formed in advance in a reinforcing steel bar processing factory according to the design requirements of a drawing, and the reinforcing steel bars are sent to a construction site after being processed; during steel bar binding, construction operators carry out binding according to the design requirements of drawings, in the binding process, all specifications, sizes, quantities and intervals of the steel bars must be checked accurately according to the design requirements of the drawings, the joint forms among the steel bars are constructed according to the requirements of the drawings, and after the steel bars are bound, a certain number of spot checks are carried out according to the specification; in the steel bar binding process, the binding is carried out strictly according to the standard requirements, two circles of the periphery of the steel bar of the bottom plate stressed in two directions must be bound by each cross node, and the steel bar at the middle section is bound by adopting a mode of one interval.
Constructing an outer enclosing wall formwork on the finished bottom plate, wherein the wall formwork at the periphery of the concrete bottom plate is shaped and assembled by adopting steel dies with 3 specifications according to the characteristics and quality targets of engineering, small steel dies and wood dies are locally adopted for assembly, vertical enclosing sandalwood on the formwork is arranged outside, transverse enclosing sandalwood is arranged inside, transverse and vertical box enclosing sandalwood all adopt phi 48 steel pipes, the distance between the phi 48 steel pipes and the transverse and vertical box enclosing sandalwood is not more than 600mm, a phi 14 single-head screw is fixedly adopted, the spot welding connection between the inner main rib and the bottom plate main rib is firm, phi 48 steel bars are used at the periphery, the horizontal distance is 100mm, and an upper inclined strut and a lower inclined strut are fixedly supported on the pit wall; pit formwork, elevartor shaft and local pit side form adopt combination steel mould, and the lower part is done the bracket with the 16 reinforcing bar of phi spacing, with 48 steel pipe support modes of phi with basic side fascia, the pit curb plate supports with the plank sheathing, makes things convenient for the later stage to demolish.
S2: constructing basement structure columns, walls and a top plate on a foundation bottom plate;
after the construction of the foundation slab is completed, workers sequentially construct a structural column, a wall body and a top plate on the surface of the foundation slab, the diameter of a vertical steel bar on the structural column and a vertical steel bar on the wall plate is not more than 22mm, a straight thread connection technology is adopted, electroslag pressure welding is adopted for the steel bar with the diameter of 18-22mm, and the steel bar with the diameter of less than 18mm is fixed in a binding mode; forming reinforcing steel bars for the lining wall, enabling workers to be familiar with construction drawings before binding the reinforcing steel bars for the lining wall, stripping the reinforcing steel bars pre-embedded in the underground continuous wall after checking the position to be installed, completing right angle, electrically welding and fixing the vertical reinforcing steel bars of the lining wall and the stripped reinforcing steel bars firmly, and rechecking and correcting the reinforcing steel bars; and 18mm thick plywood is adopted for the basement beam formwork. The beam bottom grating adopts 50 x 95mm wooden shelves; the distance between the vertical rods on the two sides of the basement beam is controlled within 1600mm, the longitudinal distance between the small transverse rods below the beam is 400mm, the platform grating adopts 20 multiplied by 40mm wooden shelves, the distance is 300mm, the distance between the bent frames is less than or equal to 800mm multiplied by 800mm, the step distance between the vertical rods is 1800mm, the distance between the sweeping rods and the ground is 200mm, the upward distance between the rest vertical rods is 1800mm, and the uppermost vertical rod is arranged at the bottom of the slab; in the process of arranging the bent frames, one scissor brace is arranged on four sides of the bent frames and every 4 rows of bent frame upright rods in the middle of the bent frames, the scissor braces are continuously arranged from bottom to top, and meanwhile, longitudinal and transverse scissor braces are arranged according to the construction distance between the structural columns.
Adopt the plywood that 18mm is thick at basement inner wall and interior welt template, the interior rib adopts 50 x 100's flitch, and vertical interval is 300mm, and horizontal interval is 450mm, and the purlin is enclosed to the level adopts double-barrelled 48 scaffold steel pipes of shuangpin phi, and vertical interval 400mm, to the horizontal interval 600mm of stay bolt phi 16, adopts plastic sleeve pipe to the stay bolt hole, and the convenience is to the installation and the dismantlement of stay bolt. When a structural column is constructed, a plywood with the thickness of 18mm is uniformly adopted for a rectangular column with the cross section less than or equal to 600 x 600mm, the column adopts a steel pipe surrounding purlin, phi 12 hook screws are fixed on templates to form a whole between the templates, and then phi 14 tightening screws are used for fixing; the method is characterized in that a plywood with the thickness of 18mm is adopted for a rectangular column with the cross section larger than 600 x 600mm, a column hoop of the rectangular column is made of channel steel with the distance of 450mm, two opposite-pull bolts with the diameter of 16 are respectively arranged in the length and width directions of the cross section, the vertical distance is 400mm, a structural column template vertical edge is made of square wood with the thickness of 50 x 95, and the side length distance is less than or equal to 250mm and the equal distance is arranged along the structural column; when the structural column template is fixed, the vertical split bolt distance of the column template is 500mm, and the distance between the center line of the lowest line and the terrace is 200mm.
The two ends of each of the opposite pulling screws of the concrete outer wall are provided with steel sheets and wood gaskets for limiting, the wallboard is fixed with the wallboard through two phi 48 steel pipe horizontal supports and shear supports, the distance is less than or equal to 1000mm, and the opposite pulling screws are connected with the platform bent frame to ensure the integral firmness of the opposite pulling screws.
When concrete is poured, all commercial concrete is adopted, a pump truck is adopted for pumping pouring, concrete pouring and vibrating are carried out on the underground two layers, a trestle from the first layer to the support is fully utilized as a pouring and tamping site, a basement wall top plate is constructed according to a post-pouring zone and construction joints in a partition mode, the trestle is divided into east and west parts according to the support to be dismantled, a first construction area on the west side of the wall top plate utilizes an east side and then dismantles the trestle as the concrete pouring and tamping site, and a first construction top plate with the west side reaching the strength grade is utilized as a concrete pouring and tamping site in a rear construction area on the east side of the wall top plate; in addition, in the concrete pouring process, according to the design amount of concrete of each layer of the basement, 40m of concrete is poured per hour according to each pump, and a concrete pump truck is arranged according to the principle that one regional pouring work is completed within 24 hours, so that the pouring process is uninterrupted until the continuous pouring is completed.
At the connecting nodes of the structural columns, the wall bodies and the beam plates, if the concrete labels are different, the beam plates are separated by double-layer steel wire meshes (the meshes are 5 multiplied by 5 mm) at the positions, close to the structural column walls, of 500mm, so that the quality of the structural columns and the wall bodies is ensured, the concrete must be conveyed according to the labels on the structural columns, and a specially-assigned person directs vehicles of the concrete with different labels to park so as to prevent confusion.
When pouring concrete, because the basement floor height is higher, the concrete should be poured and tamped by layering unloading, and the position that the reinforcing bar is denser at the connecting part of the structural column and the beam is provided with vibration holes to ensure that the concrete vibrates compactly.
S3: performing outer waterproof construction on the top plate after construction and at the upper opening of the basement;
and (3) on the basis of the step S2, waterproofing is required to be performed on the upper opening of the basement, during waterproofing construction, a mortar or concrete leveling layer is required to be leveled and polished, the surface is required to be solid and fully dried, phenomena such as concave-convex, looseness, bulges, peeling, cracks, pitted surface and the like are avoided, the flatness of the surface of the base layer is checked by using a 2M ruler, and the deviation is not more than 5mm.
The internal and external angles of the leveling layer and the protruding structure and the joint of the structure are made into circular arcs with the radius of 20mm or folded angles of 45 degrees (135 degrees); before the waterproof layer of the coiled material is laid, impurities such as dust, grease and the like on the base layer are removed, and the surface of the base layer must be kept clean; when a horizontal waterproof layer is laid, the coiled material is folded by a half, so that the bottom surface of the coiled material is exposed by a half, and the folded coiled material is smooth and has no wrinkles; when the vertical waterproof layer is laid, the vertical waterproof layer coiled material is laid from bottom to top, and the glue spreading and drying methods are the same as those of the plane.
To the bonding and the sealed operation of waterproofing membrane seam, the coiled material adopts the lapped mode with being connected of coiled material, and the overlap joint width is minor face 80mm, and the long limit is 80mm, and the overlap joint location between the adjacent coiled material is cleaned the overlap joint district with special cleaner after, evenly applies paint the overlap joint adhesive with a brush and carries out coiled material overlap joint bonding operation, gets rid of the air on one side with the hand pressfitting, makes what the overlap joint position can be firm bonds.
S4: performing foundation backfill at the upper opening of the basement; the foundation backfill construction at the upper opening of the basement is carried out alternately in the subsequent upper structure construction stage; during backfilling, all basic templates must be removed, sundries in a foundation pit must be cleaned, no water is accumulated in the foundation pit, a foundation surface axis or a related central control line must be well flicked and marked with red paint, and a foundation should be matched with a first party to timely contact an engineering quality supervision department to perform middle acceptance check work on a basic structure before backfilling.
When the upper opening of the basement is backfilled, workers adopt a mechanical and manual combined mode to backfill, and the backfilling efficiency is greatly improved; during backfilling, the backfilling quality is guaranteed constantly, collapse or depression is prevented after backfilling is finished, during backfilling, the backfilled soil is made of original state soil, building garbage and miscellaneous soil cannot be used, during backfilling, layering is conducted and layered tamping is conducted, the compaction coefficient is larger than or equal to 0.9, the backfilling thickness of each layer is 30-50cm, a cutting ring method is adopted for backfilling soil acceptance, a cutting ring sampling standard is that one group is taken every 500m indoors, one group is taken every 800m outdoors, next construction is conducted after acceptance is qualified, and backfilling operation is conducted again after acceptance is unqualified.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. A construction method of a basement structure is characterized in that: the method comprises the following steps:
s1: constructing a foundation slab, namely dividing a construction area according to the position of a post-cast strip in the area of the foundation slab to be cast according to design requirements;
s2: constructing a basement column, a wall and a top plate, and after pouring and forming a foundation bottom plate, sequentially constructing a structural column, the wall and the top plate on the foundation bottom plate;
s3: performing waterproof construction outside the upper opening of the basement, performing waterproof construction at the position of the upper opening of the basement, and performing waterproof construction at the construction joint of the basement;
s4: and backfilling the upper opening foundation of the basement, cleaning sundries in the foundation pit after the waterproof construction of the upper opening of the basement is finished, and filling a gap between the wall body of the basement and the side wall of the foundation pit.
2. The construction method of the basement structure according to claim 1, wherein: in the step S1, in the foundation slab construction, the foundation trench needs to be checked and accepted, the steel bars are bound on the poured slab, and the template engineering is performed on the periphery of the slab.
3. The construction method of the basement structure according to claim 1, wherein: and in the step S2, the vertical steel bars in the structural columns and the wall boards are fixed by adopting three modes of threaded connection, welding and binding according to different diameter specifications.
4. The construction method of the basement structure according to claim 1, wherein: in the step S2, according to structural columns of different specifications, different template supporting modes are adopted when concrete is poured, plywood with the thickness of 18mm is adopted when the cross section of each structural column is not more than 600 x 600mm, steel pipes are used for surrounding purlins outside the plywood for fixing, plywood with the thickness of 18mm is also adopted when the cross section of each structural column is more than 600 x 600mm, steel pipes are arranged outside the plywood for surrounding purlins, and finally channel steel is arranged outside the steel pipes for reinforcing.
5. The construction method of the basement structure according to claim 1, wherein: and in the step S2, double-layer steel wire meshes are arranged on the reinforcement cages of the beam slabs and close to 500mm positions of the structural columns and the wall body.
6. The construction method of the basement structure according to claim 1, wherein: in the step S3, when the upper opening of the basement is subjected to construction waterproof operation, mortar or concrete is firstly used for leveling, the flatness of the surface of the base layer is ensured, and the deviation is not more than 5mm.
7. The construction method of the basement structure according to claim 1, wherein: in the step S3, waterproof coiled materials are laid on the leveled base layer, and every two adjacent waterproof coiled materials are mutually lapped and sealed.
8. The construction method of the basement structure according to claim 1, wherein: in the step S4, when the backfill operation is performed on the upper opening of the basement, the backfill soil needs to adopt undisturbed soil, so that the construction waste cannot be used, and in the backfill process, a layered backfill mode should be adopted, and each layer of backfill soil is tamped.
CN202211151515.2A 2022-09-20 2022-09-20 Construction method of basement structure Pending CN115369881A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211151515.2A CN115369881A (en) 2022-09-20 2022-09-20 Construction method of basement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211151515.2A CN115369881A (en) 2022-09-20 2022-09-20 Construction method of basement structure

Publications (1)

Publication Number Publication Date
CN115369881A true CN115369881A (en) 2022-11-22

Family

ID=84071630

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211151515.2A Pending CN115369881A (en) 2022-09-20 2022-09-20 Construction method of basement structure

Country Status (1)

Country Link
CN (1) CN115369881A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017034633A1 (en) * 2015-08-21 2017-03-02 Parks Jody V Free-flowing waterproofing system
CN114482135A (en) * 2022-02-21 2022-05-13 中铁十六局集团城市建设发展有限公司 Advanced water stop structure of basement exterior wall post-cast strip and construction method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017034633A1 (en) * 2015-08-21 2017-03-02 Parks Jody V Free-flowing waterproofing system
CN114482135A (en) * 2022-02-21 2022-05-13 中铁十六局集团城市建设发展有限公司 Advanced water stop structure of basement exterior wall post-cast strip and construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
蒋新山: "上海世博村E地块甲级办公楼地下工程施工技术及措施", 建筑科学 *

Similar Documents

Publication Publication Date Title
US6434900B1 (en) Prefabricated concrete wall system
US20160340855A1 (en) Modular construction mold apparatus and method for constructing concrete buildings and structures
CN110777983A (en) Synchronous construction structure and method for concrete filled wall and cast-in-place structure
CN108265623A (en) A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct
CN108005254A (en) A kind of assembled architecture heat preserving exterior wall and its installation method
CN105714849A (en) Reverse construction method for adjacent high and low floors (bays) of basement
CN111188459B (en) Construction process for bonding prestressed reinforced concrete beam
KR100631365B1 (en) Steel Concrete Structure Using Angle Shapes
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
CN207110214U (en) A kind of prefabricated interior fill concrete wallboard
CN113697640A (en) Finished hoistway of integrally assembled elevator added in existing multi-story building and construction method
CN107237448A (en) A kind of prefabricated interior fill concrete wallboard and its manufacture method
CN109853803B (en) Assembled integral floor slab and manufacturing and installing method
CN208023735U (en) Assembly concrete-filled steel tube column-isolated footing-concrete collar tie beam T shape connecting nodes
CN110847065A (en) Prefabricated assembled box channel and construction method
CN107586068B (en) Upright column concrete and construction method of concrete upright column
CN115369881A (en) Construction method of basement structure
CN206457971U (en) A kind of prefabricated overlapped hollow plate of prestressing force
CN102767284B (en) Semi-prefabricating construction process for concrete thin-wall lower return eave
CN212506301U (en) Support system in combination assembled forever
CN111236631B (en) Semicircular concrete roof building supporting structure
CN114635503A (en) Fair-faced concrete wall flexibly connected with concrete frame column and construction method
CN114134927A (en) Device and method for embedding large power equipment foundation embedded pipe
CN105839824B (en) Shed deckhead construction method
CN208023734U (en) Assembly concrete-filled steel tube column-isolated footing-concrete collar tie beam linear type connecting node

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20221122

RJ01 Rejection of invention patent application after publication