CN108265623A - A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct - Google Patents

A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct Download PDF

Info

Publication number
CN108265623A
CN108265623A CN201810149475.5A CN201810149475A CN108265623A CN 108265623 A CN108265623 A CN 108265623A CN 201810149475 A CN201810149475 A CN 201810149475A CN 108265623 A CN108265623 A CN 108265623A
Authority
CN
China
Prior art keywords
collision wall
precast concrete
shingle nail
screw rod
prefabricated superposed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810149475.5A
Other languages
Chinese (zh)
Inventor
高强
张宇博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810149475.5A priority Critical patent/CN108265623A/en
Publication of CN108265623A publication Critical patent/CN108265623A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • E01D19/103Parapets, railings ; Guard barriers or road-bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to bridge structure technical field, specially a kind of prefabricated superposed type anti-collision walls and its construction method for urban viaduct.Anti-collision wall is made of two layers of precast concrete shingle nail inside and outside the connection of caged framework of steel reinforcement, and centre forms cavity.At the construction field (site), bridge floor plate surface reserves vertical connection reinforcing bar, prefabricated superposed type anti-collision wall is lifted from top to bottom to precalculated position, vertical connection reinforcing bar is reserved in hoisting process to stretch into the cavity of prefabricated superposed type anti-collision wall, overlap joint connection is realized with the vertical muscle of caged framework of steel reinforcement, and pass through the casting concrete into cavity, prefabricated superposed type anti-collision wall is made to form one with floorings.The present invention is prefabricated in the factory, and ensures the pouring quality of medial and lateral concrete walls panel, save live formwork, form removal process, and reduce most live reinforcing bar operation.Compared with traditional cast-in-situ construction method, site operation speed is greatly improved, shortens the construction period, while presentation quality and worker's personal safety are easier to be guaranteed.

Description

A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct
Technical field
The present invention relates to bridge structure technical fields, specially a kind of prefabricated superposed type anti-collision wall for urban viaduct And its construction method.
Background technology
At present, increasing with city vehicle, the unobstructed exception of urban transit system major trunk roads is important, and overpass is in city Link role is often played in city's traffic, carries very big traffic pressure, neat and artistic degree is also an appearance of city Important embodiment.
So in the newly-built or reconstruction and extension project of urban viaduct, construction period and construction quality are often policymaker The emphasis of concern.And traditional overpass both sides anti-collision wall needs reinforcing bar binding, installation pipeline to bury generally using cast-in-place engineering method The complicated procedures of forming such as template, casting concrete, maintenance, form removal inside and outside part, branch, low construction efficiency, the duration is longer, often results in The lasting congestion of traffic restricts local socio-economic development;And anti-collision wall is up-narrow and down-wide, cast in situs quality is not easy to ensure, The phenomenon that concrete surface voids and pits, often occurs, and seriously affects the aesthetic measure of anti-collision wall and the durability in later stage, needs It often safeguards and overhauls, larger manpower financial capacity is caused to waste;In addition, during site operation, worker is needed in high aerial peace installation and dismantling Template is unloaded, easily falls and causes safety accident, there are larger personal safety hidden danger.
Invention content
For above-mentioned technical problem, the purpose of the present invention is to provide a kind of for the prefabricated folded of urban viaduct Box-like anti-collision wall and its construction method, rational in infrastructure, connection is reliable, and site operation speed can be greatly improved, and shortens construction work Phase, while its presentation quality and worker's personal safety can be ensured more effectively.
In order to achieve the above object, the technical scheme is that:
A kind of prefabricated superposed type anti-collision wall for urban viaduct, the prefabricated superposed type anti-collision wall is by caged framework of steel reinforcement Two layers of precast concrete shingle nail composition, centre form cavity inside and outside connection;At the construction field (site), bridge floor plate surface reserves anti-collision wall Vertical connection reinforcing bar, prefabricated superposed type anti-collision wall are lifted from top to bottom to precalculated position, and vertical connection steel is reserved in hoisting process Muscle is stretched into the cavity of prefabricated superposed type anti-collision wall, and overlap joint connection is realized, and pass through to sky with the vertical muscle of caged framework of steel reinforcement Intracavitary casting concrete makes prefabricated superposed type anti-collision wall form one with floorings.
The framework of steel reinforcement is in caged, and the horizontal bar of caged framework of steel reinforcement is welded with vertical muscle infall using spot welding, steel Tendons skeleton be both anti-collision wall structure stress reinforcing bar and inside and outside precast concrete shingle nail, while meet component Globality requirement when demoulding, overturning, transport and lifting.
The interior outside pre-cast concrete walling panel is both a part and poured in place concrete for anticollision wall construction When interior outboard template, metope plate thickness be 60mm~150mm, length be 1.5m~3.0m;Wherein, inside pre-cast concrete walling Panel using corrosion resistant concrete for making or it is prefabricated when the corrosion resistant plane materiel of the embedding patch in surface, to cope with complexity residing for it, invade The working environment of corrosion.
The pre-buried L-type bracket in outside precast concrete shingle nail bottom, is evenly arranged along anti-collision wall spacing 1m~1.5m, Pre-buried vertical adjustment nut at corresponding floorings;Before anti-collision wall lifting, pre-buried vertical adjustment nut is first adjusted to design level mark Height, the horizonal base plate of L-type bracket is directly fallen on vertical adjustment nut during lifting, with support outside precast concrete shingle nail.
The pre-buried L-type bracket with holes in inside precast concrete shingle nail bottom, L-type bracket with holes is along anti-collision wall spacing 1m ~1.5m is evenly arranged;Pre-buried vertical screw rod at corresponding floorings, L-type bracket horizonal base plate with holes are provided with corresponding vertical screw rod Hole, and pacify a nut in advance on vertical screw rod;Before anti-collision wall lifting, first adjusting nut to design level absolute altitude, during lifting L-type bracket horizonal base plate with holes is inserted in screw rod, and falls on the nut pacified in advance, with support inside precast concrete shingle nail;It adjusts Behind the position of whole good anti-collision wall, a nut on vertical screw rod is installed again, L-type bracket with holes is fixed, and then fixed anticollision Wall prevents it from toppling, and removes extra support from.
The outside pre-cast concrete walling lower panels are equipped with lower hanging plate, and lower hanging plate is corresponding with the side of floorings.
The prefabricated superposed type anti-collision wall for urban viaduct, when anti-collision wall is located in the middle part of bridge, anti-collision wall Play the role of dividing strip, in caged framework of steel reinforcement both sides precast concrete shingle nail;Outside precast concrete shingle nail and interior The bottom of side precast concrete shingle nail, pre-buried L-type bracket with holes, the pre-buried vertical screw rod in floorings top, L-type ox with holes The bottom plate of leg is provided with the hole of corresponding pre-buried vertical screw rod, vertical screw rod top one nut of peace in advance, L-type bracket with holes during lifting Bottom plate be inserted in vertical screw rod, and fall on the nut pacified in advance below, the seam between precast concrete shingle nail bottom and floorings Gap is blocked using dry cement mortar.
The construction method of the prefabricated superposed type anti-collision wall for urban viaduct, includes the following steps:
(1) it is reserved at the top of floorings and vertically connects reinforcing bar and adjusting nut, vertical screw rod, the floorings in the range of anti-collision wall Chisel is picked into rough surface in surface, and cleans out no-sundries, watering wetting before lifting;
(2) nut on rotating adjusting nut and vertical screw rod, cooperation level meter are adjusted to predetermined absolute altitude;
(3) prefabricated anti-collision wall lifts in place from top to bottom, the sealing at the tongue and groove of outside precast concrete shingle nail middle and lower part Item squeezes to form outer side seal, and the bottom plate that adjusting nut withstands L-type bracket forms vertical supporting;Inside precast concrete shingle nail Under the hole on bottom sleeve-board with hole horizontal bracket enter vertical screw rod, and fall on following nut, formed vertical supporting;It adjusts Behind the position around of anti-collision wall, L-type bracket with holes with another nut from above is fixed again, forms reliable draw Knot, prevents component from toppling;
(4) gap under the precast concrete shingle nail of inside is blocked to form sealing with dry mortar, in the sky of anti-collision wall Intracavitary is interted, connecting pipeline and the related embedded part of installation, and then from top, into cavity, casting concrete, vibration compacting, top surface are smeared Light;
(5) mat formation bridge floor board finish, cover exposed vertical screw rod and L-type bracket with holes.
Compared with prior art, the present invention it has the following advantages and beneficial effect:
1. the present invention is formed hollow prefabricated folded by pre-cast concrete walling panel inside and outside the connection of caged framework of steel reinforcement Box-like anticollision wall member can save the complicated process such as outboard template, form removal in the branch of scene, and can reduce most scene Reinforcing bar operation greatly shortens the site operation duration.
The interior outside concrete wall surface plate 2. the present invention is prefabricated in the factory, concrete pouring quality are more guaranteed.Inside metope Corrosion resistant concrete for making or the embedding corrosion resistant plane materiel of patch can be used in plate, the durability of anti-collision wall is further improved, after reduction The maintenance cost of phase.
3. the present invention is by pre-buried adjusting nut, the spiral shell on the L-type bracket and floorings of precast concrete anti-collision wall bottom The built-in fittings such as bar, can adjust vertical elevation and the horizontal position of prefabricated superposed type anti-collision wall, and can effectively fixing component, prevent It topples, and above-mentioned work can be completed in construction personnel station on the inside of floorings, reduces risky operation, the effective people for ensureing worker Body safety.So as to reach and improve anti-collision wall quality and construction efficiency, shorten the construction period, ensure the purpose of construction personnel's safety.
Description of the drawings
Fig. 1 is the overlapping schematic diagram of the prefabricated superposed type anti-collision wall of the present invention.
Fig. 2 is the floorings reserved steel bar of the present invention and embedded part schematic diagram.
Fig. 3 is the side schematic view of the prefabricated superposed type anticollision wall member of the present invention.
Fig. 4 is the scheme of installation of the prefabricated superposed type anti-collision wall of the present invention.
Fig. 5 is the overlapping schematic diagram of the anti-collision wall without lower hanging plate of the present invention.
The anti-collision wall positioned at bridge median that Fig. 6 is the present invention overlaps schematic diagram.
In figure:1. caged framework of steel reinforcement, 2. outside precast concrete shingle nails, 3. inside precast concrete shingle nails, 4.L Type bracket, 5. L-type brackets with holes, 6. vertical screw rods, 7. vertical connection reinforcing bars, 8. adjusting nuts, 9. nuts, 10. sealing strips, 11. floorings, 12. dry mortars, 13. faces layer, 14. times hanging plates.
Specific embodiment
The present invention is specifically described with reference to the accompanying drawings and examples.
Embodiment 1:
As shown in Figure 1 to 4, the present invention is used for the prefabricated superposed type anti-collision wall of urban viaduct, by caged framework of steel reinforcement 1 Connection outside precast concrete shingle nail 2 and inside precast concrete shingle nail 3 are formed, and centre forms cavity.
The horizontal bar of cage-like framework of steel reinforcement 1 can be used spot welding with vertical muscle infall and weld, and make steel reinforcement cage more firm. It is both the effect of precast concrete shingle nail inside and outside the structure stress reinforcing bar and connection of anti-collision wall, while also should Meet globality requirement of the component in demoulding, overturning, transport and lifting.At the construction field (site), 11 surface of floorings is reserved vertically Reinforcing bar 7 is connected, prefabricated superposed type anti-collision wall is lifted from top to bottom to precalculated position, and vertical connection reinforcing bar 7 is reserved in hoisting process It stretches into the cavity of prefabricated superposed type anti-collision wall, overlap joint connection is realized, and pass through to cavity with the vertical muscle of caged framework of steel reinforcement 1 Interior casting concrete makes prefabricated superposed type anti-collision wall form one with floorings 11.
The outside precast concrete shingle nail 2, inside precast concrete shingle nail 3 are both one of anticollision wall construction Point, and interior outboard template when serving as poured in place concrete, metope plate thickness is 60mm~150mm, length for 1.5m~ 3.0m;Wherein, corrosion resistant concrete for making or the embedding corrosion resistant plane materiel of patch can be used in inside precast concrete shingle nail 3, with Cope with complicated, the rodent working environment residing for it.
The pre-buried L-type bracket 4 in 2 bottom of precast concrete shingle nail on the outside of the anti-collision wall, L-type bracket 4 is along anti-collision wall spacing 1m~1.5m is evenly arranged, pre-buried vertical adjustment nut 8 on the corresponding floorings 11 in 4 lower section of L-type bracket.Before anti-collision wall lifting first By the top levelling of floorings 11, adjusting nut 8 is adjusted to prescribed level absolute altitude, the bottom plate of L-type bracket 4 is directly fallen in during lifting On adjusting nut 8, play a supporting role.
The pre-buried L-type bracket 5 with holes in 3 bottom of inside precast concrete shingle nail, L-type bracket with holes is along anti-collision wall spacing 1m~1.5m is evenly arranged, pre-buried vertical screw rod 6 at corresponding floorings 11, and the bottom plate of L-type bracket 5 with holes, which is provided with, corresponds to pre-buried erect To the hole of screw rod 6, a nut 9 is pacified on vertical 6 top of screw rod in advance.Adjusting nut 8 is to prescribed level absolute altitude before anti-collision wall lifting, The bottom plate of L-type bracket 5 with holes is inserted in vertical screw rod 6 during lifting, and falls on the nut 9 pacified in advance below, plays a supporting role;It adjusts Behind the position of whole good anti-collision wall, nut 9 above is installed, L-type bracket 5 with holes is fixed, plays the role of fixed anti-collision wall, exempts from Go extra support.
As Figure 1-Figure 4, the work progress of the prefabricated superposed type anti-collision wall of the present invention is as follows:
1. the reserved vertical connection embedded parts such as reinforcing bar 7 and adjusting nut 8, vertical screw rod 6 in 11 top of floorings, anti-collision wall range Chisel is picked into rough surface in interior 11 surface of floorings, and cleans out no-sundries, watering wetting before lifting.
2. the nut 9 on rotating adjusting nut 8 and vertical screw rod 6, cooperation level meter are adjusted to predetermined absolute altitude.
3. prefabricated superposed type anti-collision wall lifts in place from top to bottom, the lower hanging plate of 2 lower part of outside precast concrete shingle nail 14 is corresponding with the side of floorings 11, and the sealing strip 10 at 2 middle and lower part tongue and groove of outside precast concrete shingle nail, which squeezes, to be formed Outer side seal, the bottom plate that adjusting nut 8 withstands L-type bracket 4 form vertical supporting;Band under inside precast concrete shingle nail 3 The hole on bottom sleeve-board of hole horizontal bracket 5 enters vertical screw rod 6, and falls on following nut 9, forms vertical supporting;It adjusts anti- After hitting the position around of wall, L-type bracket 5 with holes with another nut 9 from above is fixed again, forms reliable draw Knot, prevents component from toppling.
4. the gap under inside precast concrete shingle nail 3 is blocked with dry mortar 12 forms sealing, in anti-collision wall Intert in cavity, connecting pipeline and the related embedded part of installation, then from top into cavity casting concrete, vibration compacting, top surface Troweling.
5. bridge floor board finish 13 of mating formation covers exposed vertical screw rod 6 and L-type bracket 5 with holes.
Embodiment 2:
As shown in figure 5, as different from Example 1:Hanging plate, anticollision are not descended in precast concrete shingle nail 2 lower part in outside Wall is integrally fallen at 11 top of floorings, and the gap between 2 bottom of outside precast concrete shingle nail and floorings 11 is also using stiff Property cement mortar 12 blocks, remaining is the same as embodiment 1.
Embodiment 3:
As shown in fig. 6, as different from Example 1:The anti-collision wall is located in the middle part of bridge, plays the role of dividing strip, cage 1 both sides precast concrete shingle nail of shape framework of steel reinforcement (outside precast concrete shingle nail 2 and inside precast concrete shingle nail 3) Bottom, pre-buried L-type bracket 5 with holes, the pre-buried vertical screw rod 6 in the top of floorings 11, the bottom plate of L-type bracket 5 with holes is provided with The hole of corresponding pre-buried vertical screw rod 6, vertical 6 top of screw rod one nut 9 of peace in advance, the bottom plate set of L-type bracket 5 with holes during lifting Enter vertical screw rod 6, and fall on the nut 9 pacified in advance below.Gap between precast concrete shingle nail bottom and floorings 11 It being blocked using dry cement mortar 12, the face layer 13 of floorings 11 covers exposed vertical screw rod 6 and L-type bracket 5 with holes, Remaining is the same as embodiment 1.
Embodiment the result shows that, the present invention in anti-collision wall be prefabricated in the factory, it is ensured that medial and lateral concrete walls panel pours Build quality, save live formwork, form removal process, and most live reinforcing bar operation can be reduced.With traditional cast-in-place construction Engineering method is compared, and site operation speed can be greatly improved, and shortens the construction period, while presentation quality is easier to be guaranteed.
Obviously, as technological progress, those skilled in the art can variously implement the design of the present invention.Therefore, The present invention and its embodiment are not limited to example shown above, but can change in the frame of claim.

Claims (8)

1. a kind of prefabricated superposed type anti-collision wall for urban viaduct, which is characterized in that the prefabricated superposed type anti-collision wall is by cage Two layers of precast concrete shingle nail composition, centre form cavity inside and outside the connection of shape framework of steel reinforcement;At the construction field (site), bridge floor plate surface Reserved anti-collision wall vertically connects reinforcing bar, and prefabricated superposed type anti-collision wall is lifted from top to bottom to precalculated position, is reserved in hoisting process Vertical connection reinforcing bar is stretched into the cavity of prefabricated superposed type anti-collision wall, and overlap joint connection is realized with the vertical muscle of caged framework of steel reinforcement, And passing through the casting concrete into cavity makes prefabricated superposed type anti-collision wall form one with floorings.
2. the prefabricated superposed type anti-collision wall according to claim 1 for urban viaduct, which is characterized in that the reinforcing bar Skeleton is in caged, and the horizontal bar of caged framework of steel reinforcement is welded with vertical muscle infall using spot welding, and framework of steel reinforcement is both anti-collision wall Structure stress reinforcing bar, and precast concrete shingle nail inside and outside connecting, at the same meet the demoulding of component, overturning, transport and Globality requirement during lifting.
3. the prefabricated superposed type anti-collision wall according to claim 1 for urban viaduct, which is characterized in that described inside and outside Interior outboard template when side precast concrete shingle nail is both a part and poured in place concrete for anticollision wall construction, Metope plate thickness is 60mm~150mm, and length is 1.5m~3.0m;Wherein, precast concrete shingle nail in inside is using corrosion-resistant Concrete for making or it is prefabricated when the corrosion resistant plane materiel of the embedding patch in surface, to cope with complicated, the rodent working environment residing for it.
4. the prefabricated superposed type anti-collision wall according to claim 1 for urban viaduct, which is characterized in that the outside The pre-buried L-type bracket in precast concrete shingle nail bottom, is evenly arranged along anti-collision wall spacing 1m~1.5m, pre-buried at corresponding floorings Vertical adjustment nut;Before anti-collision wall lifting, pre-buried vertical adjustment nut is first adjusted to design level absolute altitude, L-type bracket during lifting Horizonal base plate directly fall on vertical adjustment nut, with support outside precast concrete shingle nail.
5. the prefabricated superposed type anti-collision wall according to claim 1 for urban viaduct, which is characterized in that the inside The pre-buried L-type bracket with holes in precast concrete shingle nail bottom, L-type bracket with holes are evenly arranged along anti-collision wall spacing 1m~1.5m; Pre-buried vertical screw rod at corresponding floorings, L-type bracket horizonal base plate with holes are provided with the hole of corresponding vertical screw rod, and in vertical spiral shell Pacify a nut on bar in advance;Before anti-collision wall lifting, first adjusting nut to design level absolute altitude, when lifting, L-type bracket with holes was horizontal Bottom plate is inserted in screw rod, and falls on the nut pacified in advance, with support inside precast concrete shingle nail;Adjust the position of anti-collision wall Afterwards, a nut on vertical screw rod is installed again, L-type bracket with holes is fixed, and then fixes anti-collision wall, prevent it from toppling, is exempted from Go extra support.
6. the prefabricated superposed type anti-collision wall according to claim 1 for urban viaduct, which is characterized in that the outside Pre-cast concrete walling lower panels are equipped with lower hanging plate, and lower hanging plate is corresponding with the side of floorings.
7. the prefabricated superposed type anti-collision wall described in accordance with the claim 1 for urban viaduct, which is characterized in that in anti-collision wall When in the middle part of bridge, anti-collision wall plays the role of dividing strip, in caged framework of steel reinforcement both sides precast concrete shingle nail;Outside The bottom of precast concrete shingle nail and inside precast concrete shingle nail, pre-buried L-type bracket with holes, floorings top are pre- Vertical screw rod is buried, the bottom plate of L-type bracket with holes is provided with the hole of corresponding pre-buried vertical screw rod, and a spiral shell is pacified on vertical screw rod top in advance Mother, the bottom plate of L-type bracket with holes is inserted in vertical screw rod during lifting, and falls on the nut pacified in advance below, precast concrete metope Gap between plate bottom and floorings is blocked using dry cement mortar.
8. the construction method of the prefabricated superposed type anti-collision wall for urban viaduct described in a kind of one of claim 1 to 7, It is characterized in that, includes the following steps:
(1) it is reserved at the top of floorings and vertically connects reinforcing bar and adjusting nut, vertical screw rod, the bridge floor plate surface in the range of anti-collision wall Chisel is picked into rough surface, and cleans out no-sundries, watering wetting before lifting;
(2) nut on rotating adjusting nut and vertical screw rod, cooperation level meter are adjusted to predetermined absolute altitude;
(3) prefabricated anti-collision wall lifts in place from top to bottom, and the sealing strip at the tongue and groove of outside precast concrete shingle nail middle and lower part squeezes For swaging into outer side seal, the bottom plate that adjusting nut withstands L-type bracket forms vertical supporting;Under the precast concrete shingle nail of inside Hole on bottom sleeve-board with hole horizontal bracket enters vertical screw rod, and falls on following nut, forms vertical supporting;Adjust anticollision Behind the position around of wall, L-type bracket with holes with another nut from above is fixed again, forms reliable drawknot, is prevented Only component topples;
(4) gap under the precast concrete shingle nail of inside is blocked to form sealing with dry mortar, in the cavity of anti-collision wall Interspersed, connecting pipeline and the related embedded part of installation, then from top into cavity casting concrete, vibration compacting, top surface troweling;
(5) mat formation bridge floor board finish, cover exposed vertical screw rod and L-type bracket with holes.
CN201810149475.5A 2018-02-13 2018-02-13 A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct Pending CN108265623A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810149475.5A CN108265623A (en) 2018-02-13 2018-02-13 A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810149475.5A CN108265623A (en) 2018-02-13 2018-02-13 A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct

Publications (1)

Publication Number Publication Date
CN108265623A true CN108265623A (en) 2018-07-10

Family

ID=62774108

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810149475.5A Pending CN108265623A (en) 2018-02-13 2018-02-13 A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct

Country Status (1)

Country Link
CN (1) CN108265623A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109137742A (en) * 2018-09-30 2019-01-04 中国建筑土木建设有限公司 The mounting device and installation method of prefabricated anti-collision wall linkage section
CN111364355A (en) * 2020-01-22 2020-07-03 华南理工大学 Assembled reinforced concrete side anti-collision guardrail for connecting bridges and construction method
CN111519824A (en) * 2020-04-14 2020-08-11 中铁第四勘察设计院集团有限公司 Prefabricated station platen, assembly type station and construction method of assembly type station
CN112504599A (en) * 2020-11-20 2021-03-16 陕西煤业化工技术研究院有限责任公司 Friction energy-absorbing plate collision test wall and prefabricating and construction installation process thereof
CN112538823A (en) * 2020-12-05 2021-03-23 中铁十九局集团第一工程有限公司 Construction method for mounting precast block of precast concrete protective wall
CN113832837A (en) * 2021-09-29 2021-12-24 广州机施建设集团有限公司 Fabricated anti-collision wall, welding device and construction method of fabricated anti-collision wall
CN113863132A (en) * 2021-09-26 2021-12-31 广州机施建设集团有限公司 Fabricated anti-collision wall and construction process

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0657717A (en) * 1992-08-13 1994-03-01 Onoda Cement Co Ltd Concrete guard fence
JPH06313304A (en) * 1993-04-30 1994-11-08 Keihan Concrete Kogyo Kk Structure of high balustrade in concrete structure having high balustrade and construction method for balustrade part
JPH0892923A (en) * 1994-09-22 1996-04-09 Chichibu Onoda Cement Corp Guard fence
CN201447879U (en) * 2009-08-24 2010-05-05 中建钢构江苏有限公司 Steel column base calibrating and fine adjusting device
CN102493350A (en) * 2011-12-19 2012-06-13 中国一冶集团有限公司 Construction method of landscape bridge outside-hanging crash barrier
CN103061267A (en) * 2013-01-15 2013-04-24 广州市市政工程设计研究院 Construction method of combined prefabricated bridge anti-collision wall
CN203200914U (en) * 2013-04-10 2013-09-18 上海嘉实(集团)有限公司 Steel structure socle outward exposed connecting structure
CN203256611U (en) * 2013-03-12 2013-10-30 长安大学 Height-adjustable bridge handrail base
CN203320700U (en) * 2013-07-19 2013-12-04 安徽富煌钢构股份有限公司 Steel structure column foot connecting structure
CN104563523A (en) * 2013-10-28 2015-04-29 五冶集团上海有限公司 Method for mounting pipe frame and door type light steel structure
CN205804170U (en) * 2016-06-17 2016-12-14 北京华路安交通科技有限公司 A kind of recycling bridge concrete guardrail
CN106567329A (en) * 2016-11-07 2017-04-19 上海市政工程设计研究总院(集团)有限公司 Semi-prefabricated reinforced concrete wall type guardrail
CN207944339U (en) * 2018-02-13 2018-10-09 高强 A kind of prefabricated superposed type anti-collision wall for urban viaduct

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0657717A (en) * 1992-08-13 1994-03-01 Onoda Cement Co Ltd Concrete guard fence
JPH06313304A (en) * 1993-04-30 1994-11-08 Keihan Concrete Kogyo Kk Structure of high balustrade in concrete structure having high balustrade and construction method for balustrade part
JPH0892923A (en) * 1994-09-22 1996-04-09 Chichibu Onoda Cement Corp Guard fence
CN201447879U (en) * 2009-08-24 2010-05-05 中建钢构江苏有限公司 Steel column base calibrating and fine adjusting device
CN102493350A (en) * 2011-12-19 2012-06-13 中国一冶集团有限公司 Construction method of landscape bridge outside-hanging crash barrier
CN103061267A (en) * 2013-01-15 2013-04-24 广州市市政工程设计研究院 Construction method of combined prefabricated bridge anti-collision wall
CN203256611U (en) * 2013-03-12 2013-10-30 长安大学 Height-adjustable bridge handrail base
CN203200914U (en) * 2013-04-10 2013-09-18 上海嘉实(集团)有限公司 Steel structure socle outward exposed connecting structure
CN203320700U (en) * 2013-07-19 2013-12-04 安徽富煌钢构股份有限公司 Steel structure column foot connecting structure
CN104563523A (en) * 2013-10-28 2015-04-29 五冶集团上海有限公司 Method for mounting pipe frame and door type light steel structure
CN205804170U (en) * 2016-06-17 2016-12-14 北京华路安交通科技有限公司 A kind of recycling bridge concrete guardrail
CN106567329A (en) * 2016-11-07 2017-04-19 上海市政工程设计研究总院(集团)有限公司 Semi-prefabricated reinforced concrete wall type guardrail
CN207944339U (en) * 2018-02-13 2018-10-09 高强 A kind of prefabricated superposed type anti-collision wall for urban viaduct

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109137742A (en) * 2018-09-30 2019-01-04 中国建筑土木建设有限公司 The mounting device and installation method of prefabricated anti-collision wall linkage section
CN111364355A (en) * 2020-01-22 2020-07-03 华南理工大学 Assembled reinforced concrete side anti-collision guardrail for connecting bridges and construction method
CN111519824A (en) * 2020-04-14 2020-08-11 中铁第四勘察设计院集团有限公司 Prefabricated station platen, assembly type station and construction method of assembly type station
CN112504599A (en) * 2020-11-20 2021-03-16 陕西煤业化工技术研究院有限责任公司 Friction energy-absorbing plate collision test wall and prefabricating and construction installation process thereof
CN112504599B (en) * 2020-11-20 2023-09-22 陕西煤业化工技术研究院有限责任公司 Friction energy absorption plate collision test wall and prefabrication and construction installation process thereof
CN112538823A (en) * 2020-12-05 2021-03-23 中铁十九局集团第一工程有限公司 Construction method for mounting precast block of precast concrete protective wall
CN113863132A (en) * 2021-09-26 2021-12-31 广州机施建设集团有限公司 Fabricated anti-collision wall and construction process
CN113832837A (en) * 2021-09-29 2021-12-24 广州机施建设集团有限公司 Fabricated anti-collision wall, welding device and construction method of fabricated anti-collision wall

Similar Documents

Publication Publication Date Title
CN108265623A (en) A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct
CN106869172B (en) In-situ deposited prefabricated split-mounting type subway underground station construction method
CN105178357B (en) Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition
CN102493603B (en) Prefabricated column of reserved concealed column channel, concealed column type complete assembled earthquake-resistant building and its method
CN106854873A (en) A kind of engineering method and garage parking in precast spliced sinking type garage parking
CN109811878A (en) The shell integrated structure of the cast-in-place coinsiding die of assembled architecture and construction method
CN106284412B (en) A kind of prefabricated pipe gallery and construction method
CN105040970A (en) Comprehensive gymnasium high formwork support system and construction method of comprehensive gymnasium high formwork support system
CN206545215U (en) A kind of precast spliced sinking type garage parking
CN103924525B (en) Urban interchange industrialization short-term precast assembly construction method
CN207944339U (en) A kind of prefabricated superposed type anti-collision wall for urban viaduct
CN206016309U (en) A kind of overall assembled building system
CN107476470A (en) Steel pipe built in assembled and GFRP pipe regeneration concrete compound shear walls and its construction method
CN108086353B (en) Hollow wall plate mixed prefabricated assembly type comprehensive pipe gallery spliced by cast-in-place hidden beams and construction method thereof
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN106120562A (en) Overpass rod iron bracket bent cap support for shuttering integral hoisting construction method
CN208072415U (en) Deep foundation pit reinforced concrete support part changes structure
CN107100083A (en) A kind of T-shaped high pier Cast-in-place Bent Cap formwork erecting structure and construction method
CN110409492A (en) The combination assembled piping lane of one kind more structures containing superposed member and its construction method
CN103452350A (en) Fabricated electronic workshop and construction method thereof
CN111188508A (en) Supplement plate of existing cantilever floor slab of building structure and construction method thereof
CN110512727A (en) A kind of pre-buried insulation board post stretching anchorage node construction of assembled architecture lotus rhizome beam and its construction method
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
CN207110214U (en) A kind of prefabricated interior fill concrete wallboard
CN111173042B (en) Advanced water stop post-cast strip of foundation slab and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination