CN108265623A - A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct - Google Patents
A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct Download PDFInfo
- Publication number
- CN108265623A CN108265623A CN201810149475.5A CN201810149475A CN108265623A CN 108265623 A CN108265623 A CN 108265623A CN 201810149475 A CN201810149475 A CN 201810149475A CN 108265623 A CN108265623 A CN 108265623A
- Authority
- CN
- China
- Prior art keywords
- collision wall
- precast concrete
- shingle nail
- screw rod
- prefabricated superposed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 26
- 239000011178 precast concrete Substances 0.000 claims abstract description 55
- 238000009408 flooring Methods 0.000 claims abstract description 33
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 22
- 239000010959 steel Substances 0.000 claims abstract description 22
- 239000004567 concrete Substances 0.000 claims abstract description 20
- 230000002787 reinforcement Effects 0.000 claims abstract description 19
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 19
- 238000005266 casting Methods 0.000 claims abstract description 8
- 238000000034 method Methods 0.000 claims abstract description 8
- 210000003205 muscle Anatomy 0.000 claims abstract description 8
- 238000005260 corrosion Methods 0.000 claims description 9
- 230000007797 corrosion Effects 0.000 claims description 9
- 238000007789 sealing Methods 0.000 claims description 7
- 238000009434 installation Methods 0.000 claims description 6
- 238000013461 design Methods 0.000 claims description 5
- 239000011083 cement mortar Substances 0.000 claims description 4
- 239000004570 mortar (masonry) Substances 0.000 claims description 4
- 230000015572 biosynthetic process Effects 0.000 claims description 3
- 238000003466 welding Methods 0.000 claims description 3
- 238000009736 wetting Methods 0.000 claims description 3
- 241000283984 Rodentia Species 0.000 claims description 2
- 239000000203 mixture Substances 0.000 claims description 2
- 238000009415 formwork Methods 0.000 abstract description 2
- 238000011065 in-situ storage Methods 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 4
- 238000012407 engineering method Methods 0.000 description 2
- 238000012423 maintenance Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000002045 lasting effect Effects 0.000 description 1
- 230000013011 mating Effects 0.000 description 1
- 210000002435 tendon Anatomy 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/10—Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
- E01D19/103—Parapets, railings ; Guard barriers or road-bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The present invention relates to bridge structure technical field, specially a kind of prefabricated superposed type anti-collision walls and its construction method for urban viaduct.Anti-collision wall is made of two layers of precast concrete shingle nail inside and outside the connection of caged framework of steel reinforcement, and centre forms cavity.At the construction field (site), bridge floor plate surface reserves vertical connection reinforcing bar, prefabricated superposed type anti-collision wall is lifted from top to bottom to precalculated position, vertical connection reinforcing bar is reserved in hoisting process to stretch into the cavity of prefabricated superposed type anti-collision wall, overlap joint connection is realized with the vertical muscle of caged framework of steel reinforcement, and pass through the casting concrete into cavity, prefabricated superposed type anti-collision wall is made to form one with floorings.The present invention is prefabricated in the factory, and ensures the pouring quality of medial and lateral concrete walls panel, save live formwork, form removal process, and reduce most live reinforcing bar operation.Compared with traditional cast-in-situ construction method, site operation speed is greatly improved, shortens the construction period, while presentation quality and worker's personal safety are easier to be guaranteed.
Description
Technical field
The present invention relates to bridge structure technical fields, specially a kind of prefabricated superposed type anti-collision wall for urban viaduct
And its construction method.
Background technology
At present, increasing with city vehicle, the unobstructed exception of urban transit system major trunk roads is important, and overpass is in city
Link role is often played in city's traffic, carries very big traffic pressure, neat and artistic degree is also an appearance of city
Important embodiment.
So in the newly-built or reconstruction and extension project of urban viaduct, construction period and construction quality are often policymaker
The emphasis of concern.And traditional overpass both sides anti-collision wall needs reinforcing bar binding, installation pipeline to bury generally using cast-in-place engineering method
The complicated procedures of forming such as template, casting concrete, maintenance, form removal inside and outside part, branch, low construction efficiency, the duration is longer, often results in
The lasting congestion of traffic restricts local socio-economic development;And anti-collision wall is up-narrow and down-wide, cast in situs quality is not easy to ensure,
The phenomenon that concrete surface voids and pits, often occurs, and seriously affects the aesthetic measure of anti-collision wall and the durability in later stage, needs
It often safeguards and overhauls, larger manpower financial capacity is caused to waste;In addition, during site operation, worker is needed in high aerial peace installation and dismantling
Template is unloaded, easily falls and causes safety accident, there are larger personal safety hidden danger.
Invention content
For above-mentioned technical problem, the purpose of the present invention is to provide a kind of for the prefabricated folded of urban viaduct
Box-like anti-collision wall and its construction method, rational in infrastructure, connection is reliable, and site operation speed can be greatly improved, and shortens construction work
Phase, while its presentation quality and worker's personal safety can be ensured more effectively.
In order to achieve the above object, the technical scheme is that:
A kind of prefabricated superposed type anti-collision wall for urban viaduct, the prefabricated superposed type anti-collision wall is by caged framework of steel reinforcement
Two layers of precast concrete shingle nail composition, centre form cavity inside and outside connection;At the construction field (site), bridge floor plate surface reserves anti-collision wall
Vertical connection reinforcing bar, prefabricated superposed type anti-collision wall are lifted from top to bottom to precalculated position, and vertical connection steel is reserved in hoisting process
Muscle is stretched into the cavity of prefabricated superposed type anti-collision wall, and overlap joint connection is realized, and pass through to sky with the vertical muscle of caged framework of steel reinforcement
Intracavitary casting concrete makes prefabricated superposed type anti-collision wall form one with floorings.
The framework of steel reinforcement is in caged, and the horizontal bar of caged framework of steel reinforcement is welded with vertical muscle infall using spot welding, steel
Tendons skeleton be both anti-collision wall structure stress reinforcing bar and inside and outside precast concrete shingle nail, while meet component
Globality requirement when demoulding, overturning, transport and lifting.
The interior outside pre-cast concrete walling panel is both a part and poured in place concrete for anticollision wall construction
When interior outboard template, metope plate thickness be 60mm~150mm, length be 1.5m~3.0m;Wherein, inside pre-cast concrete walling
Panel using corrosion resistant concrete for making or it is prefabricated when the corrosion resistant plane materiel of the embedding patch in surface, to cope with complexity residing for it, invade
The working environment of corrosion.
The pre-buried L-type bracket in outside precast concrete shingle nail bottom, is evenly arranged along anti-collision wall spacing 1m~1.5m,
Pre-buried vertical adjustment nut at corresponding floorings;Before anti-collision wall lifting, pre-buried vertical adjustment nut is first adjusted to design level mark
Height, the horizonal base plate of L-type bracket is directly fallen on vertical adjustment nut during lifting, with support outside precast concrete shingle nail.
The pre-buried L-type bracket with holes in inside precast concrete shingle nail bottom, L-type bracket with holes is along anti-collision wall spacing 1m
~1.5m is evenly arranged;Pre-buried vertical screw rod at corresponding floorings, L-type bracket horizonal base plate with holes are provided with corresponding vertical screw rod
Hole, and pacify a nut in advance on vertical screw rod;Before anti-collision wall lifting, first adjusting nut to design level absolute altitude, during lifting
L-type bracket horizonal base plate with holes is inserted in screw rod, and falls on the nut pacified in advance, with support inside precast concrete shingle nail;It adjusts
Behind the position of whole good anti-collision wall, a nut on vertical screw rod is installed again, L-type bracket with holes is fixed, and then fixed anticollision
Wall prevents it from toppling, and removes extra support from.
The outside pre-cast concrete walling lower panels are equipped with lower hanging plate, and lower hanging plate is corresponding with the side of floorings.
The prefabricated superposed type anti-collision wall for urban viaduct, when anti-collision wall is located in the middle part of bridge, anti-collision wall
Play the role of dividing strip, in caged framework of steel reinforcement both sides precast concrete shingle nail;Outside precast concrete shingle nail and interior
The bottom of side precast concrete shingle nail, pre-buried L-type bracket with holes, the pre-buried vertical screw rod in floorings top, L-type ox with holes
The bottom plate of leg is provided with the hole of corresponding pre-buried vertical screw rod, vertical screw rod top one nut of peace in advance, L-type bracket with holes during lifting
Bottom plate be inserted in vertical screw rod, and fall on the nut pacified in advance below, the seam between precast concrete shingle nail bottom and floorings
Gap is blocked using dry cement mortar.
The construction method of the prefabricated superposed type anti-collision wall for urban viaduct, includes the following steps:
(1) it is reserved at the top of floorings and vertically connects reinforcing bar and adjusting nut, vertical screw rod, the floorings in the range of anti-collision wall
Chisel is picked into rough surface in surface, and cleans out no-sundries, watering wetting before lifting;
(2) nut on rotating adjusting nut and vertical screw rod, cooperation level meter are adjusted to predetermined absolute altitude;
(3) prefabricated anti-collision wall lifts in place from top to bottom, the sealing at the tongue and groove of outside precast concrete shingle nail middle and lower part
Item squeezes to form outer side seal, and the bottom plate that adjusting nut withstands L-type bracket forms vertical supporting;Inside precast concrete shingle nail
Under the hole on bottom sleeve-board with hole horizontal bracket enter vertical screw rod, and fall on following nut, formed vertical supporting;It adjusts
Behind the position around of anti-collision wall, L-type bracket with holes with another nut from above is fixed again, forms reliable draw
Knot, prevents component from toppling;
(4) gap under the precast concrete shingle nail of inside is blocked to form sealing with dry mortar, in the sky of anti-collision wall
Intracavitary is interted, connecting pipeline and the related embedded part of installation, and then from top, into cavity, casting concrete, vibration compacting, top surface are smeared
Light;
(5) mat formation bridge floor board finish, cover exposed vertical screw rod and L-type bracket with holes.
Compared with prior art, the present invention it has the following advantages and beneficial effect:
1. the present invention is formed hollow prefabricated folded by pre-cast concrete walling panel inside and outside the connection of caged framework of steel reinforcement
Box-like anticollision wall member can save the complicated process such as outboard template, form removal in the branch of scene, and can reduce most scene
Reinforcing bar operation greatly shortens the site operation duration.
The interior outside concrete wall surface plate 2. the present invention is prefabricated in the factory, concrete pouring quality are more guaranteed.Inside metope
Corrosion resistant concrete for making or the embedding corrosion resistant plane materiel of patch can be used in plate, the durability of anti-collision wall is further improved, after reduction
The maintenance cost of phase.
3. the present invention is by pre-buried adjusting nut, the spiral shell on the L-type bracket and floorings of precast concrete anti-collision wall bottom
The built-in fittings such as bar, can adjust vertical elevation and the horizontal position of prefabricated superposed type anti-collision wall, and can effectively fixing component, prevent
It topples, and above-mentioned work can be completed in construction personnel station on the inside of floorings, reduces risky operation, the effective people for ensureing worker
Body safety.So as to reach and improve anti-collision wall quality and construction efficiency, shorten the construction period, ensure the purpose of construction personnel's safety.
Description of the drawings
Fig. 1 is the overlapping schematic diagram of the prefabricated superposed type anti-collision wall of the present invention.
Fig. 2 is the floorings reserved steel bar of the present invention and embedded part schematic diagram.
Fig. 3 is the side schematic view of the prefabricated superposed type anticollision wall member of the present invention.
Fig. 4 is the scheme of installation of the prefabricated superposed type anti-collision wall of the present invention.
Fig. 5 is the overlapping schematic diagram of the anti-collision wall without lower hanging plate of the present invention.
The anti-collision wall positioned at bridge median that Fig. 6 is the present invention overlaps schematic diagram.
In figure:1. caged framework of steel reinforcement, 2. outside precast concrete shingle nails, 3. inside precast concrete shingle nails, 4.L
Type bracket, 5. L-type brackets with holes, 6. vertical screw rods, 7. vertical connection reinforcing bars, 8. adjusting nuts, 9. nuts, 10. sealing strips,
11. floorings, 12. dry mortars, 13. faces layer, 14. times hanging plates.
Specific embodiment
The present invention is specifically described with reference to the accompanying drawings and examples.
Embodiment 1:
As shown in Figure 1 to 4, the present invention is used for the prefabricated superposed type anti-collision wall of urban viaduct, by caged framework of steel reinforcement 1
Connection outside precast concrete shingle nail 2 and inside precast concrete shingle nail 3 are formed, and centre forms cavity.
The horizontal bar of cage-like framework of steel reinforcement 1 can be used spot welding with vertical muscle infall and weld, and make steel reinforcement cage more firm.
It is both the effect of precast concrete shingle nail inside and outside the structure stress reinforcing bar and connection of anti-collision wall, while also should
Meet globality requirement of the component in demoulding, overturning, transport and lifting.At the construction field (site), 11 surface of floorings is reserved vertically
Reinforcing bar 7 is connected, prefabricated superposed type anti-collision wall is lifted from top to bottom to precalculated position, and vertical connection reinforcing bar 7 is reserved in hoisting process
It stretches into the cavity of prefabricated superposed type anti-collision wall, overlap joint connection is realized, and pass through to cavity with the vertical muscle of caged framework of steel reinforcement 1
Interior casting concrete makes prefabricated superposed type anti-collision wall form one with floorings 11.
The outside precast concrete shingle nail 2, inside precast concrete shingle nail 3 are both one of anticollision wall construction
Point, and interior outboard template when serving as poured in place concrete, metope plate thickness is 60mm~150mm, length for 1.5m~
3.0m;Wherein, corrosion resistant concrete for making or the embedding corrosion resistant plane materiel of patch can be used in inside precast concrete shingle nail 3, with
Cope with complicated, the rodent working environment residing for it.
The pre-buried L-type bracket 4 in 2 bottom of precast concrete shingle nail on the outside of the anti-collision wall, L-type bracket 4 is along anti-collision wall spacing
1m~1.5m is evenly arranged, pre-buried vertical adjustment nut 8 on the corresponding floorings 11 in 4 lower section of L-type bracket.Before anti-collision wall lifting first
By the top levelling of floorings 11, adjusting nut 8 is adjusted to prescribed level absolute altitude, the bottom plate of L-type bracket 4 is directly fallen in during lifting
On adjusting nut 8, play a supporting role.
The pre-buried L-type bracket 5 with holes in 3 bottom of inside precast concrete shingle nail, L-type bracket with holes is along anti-collision wall spacing
1m~1.5m is evenly arranged, pre-buried vertical screw rod 6 at corresponding floorings 11, and the bottom plate of L-type bracket 5 with holes, which is provided with, corresponds to pre-buried erect
To the hole of screw rod 6, a nut 9 is pacified on vertical 6 top of screw rod in advance.Adjusting nut 8 is to prescribed level absolute altitude before anti-collision wall lifting,
The bottom plate of L-type bracket 5 with holes is inserted in vertical screw rod 6 during lifting, and falls on the nut 9 pacified in advance below, plays a supporting role;It adjusts
Behind the position of whole good anti-collision wall, nut 9 above is installed, L-type bracket 5 with holes is fixed, plays the role of fixed anti-collision wall, exempts from
Go extra support.
As Figure 1-Figure 4, the work progress of the prefabricated superposed type anti-collision wall of the present invention is as follows:
1. the reserved vertical connection embedded parts such as reinforcing bar 7 and adjusting nut 8, vertical screw rod 6 in 11 top of floorings, anti-collision wall range
Chisel is picked into rough surface in interior 11 surface of floorings, and cleans out no-sundries, watering wetting before lifting.
2. the nut 9 on rotating adjusting nut 8 and vertical screw rod 6, cooperation level meter are adjusted to predetermined absolute altitude.
3. prefabricated superposed type anti-collision wall lifts in place from top to bottom, the lower hanging plate of 2 lower part of outside precast concrete shingle nail
14 is corresponding with the side of floorings 11, and the sealing strip 10 at 2 middle and lower part tongue and groove of outside precast concrete shingle nail, which squeezes, to be formed
Outer side seal, the bottom plate that adjusting nut 8 withstands L-type bracket 4 form vertical supporting;Band under inside precast concrete shingle nail 3
The hole on bottom sleeve-board of hole horizontal bracket 5 enters vertical screw rod 6, and falls on following nut 9, forms vertical supporting;It adjusts anti-
After hitting the position around of wall, L-type bracket 5 with holes with another nut 9 from above is fixed again, forms reliable draw
Knot, prevents component from toppling.
4. the gap under inside precast concrete shingle nail 3 is blocked with dry mortar 12 forms sealing, in anti-collision wall
Intert in cavity, connecting pipeline and the related embedded part of installation, then from top into cavity casting concrete, vibration compacting, top surface
Troweling.
5. bridge floor board finish 13 of mating formation covers exposed vertical screw rod 6 and L-type bracket 5 with holes.
Embodiment 2:
As shown in figure 5, as different from Example 1:Hanging plate, anticollision are not descended in precast concrete shingle nail 2 lower part in outside
Wall is integrally fallen at 11 top of floorings, and the gap between 2 bottom of outside precast concrete shingle nail and floorings 11 is also using stiff
Property cement mortar 12 blocks, remaining is the same as embodiment 1.
Embodiment 3:
As shown in fig. 6, as different from Example 1:The anti-collision wall is located in the middle part of bridge, plays the role of dividing strip, cage
1 both sides precast concrete shingle nail of shape framework of steel reinforcement (outside precast concrete shingle nail 2 and inside precast concrete shingle nail 3)
Bottom, pre-buried L-type bracket 5 with holes, the pre-buried vertical screw rod 6 in the top of floorings 11, the bottom plate of L-type bracket 5 with holes is provided with
The hole of corresponding pre-buried vertical screw rod 6, vertical 6 top of screw rod one nut 9 of peace in advance, the bottom plate set of L-type bracket 5 with holes during lifting
Enter vertical screw rod 6, and fall on the nut 9 pacified in advance below.Gap between precast concrete shingle nail bottom and floorings 11
It being blocked using dry cement mortar 12, the face layer 13 of floorings 11 covers exposed vertical screw rod 6 and L-type bracket 5 with holes,
Remaining is the same as embodiment 1.
Embodiment the result shows that, the present invention in anti-collision wall be prefabricated in the factory, it is ensured that medial and lateral concrete walls panel pours
Build quality, save live formwork, form removal process, and most live reinforcing bar operation can be reduced.With traditional cast-in-place construction
Engineering method is compared, and site operation speed can be greatly improved, and shortens the construction period, while presentation quality is easier to be guaranteed.
Obviously, as technological progress, those skilled in the art can variously implement the design of the present invention.Therefore,
The present invention and its embodiment are not limited to example shown above, but can change in the frame of claim.
Claims (8)
1. a kind of prefabricated superposed type anti-collision wall for urban viaduct, which is characterized in that the prefabricated superposed type anti-collision wall is by cage
Two layers of precast concrete shingle nail composition, centre form cavity inside and outside the connection of shape framework of steel reinforcement;At the construction field (site), bridge floor plate surface
Reserved anti-collision wall vertically connects reinforcing bar, and prefabricated superposed type anti-collision wall is lifted from top to bottom to precalculated position, is reserved in hoisting process
Vertical connection reinforcing bar is stretched into the cavity of prefabricated superposed type anti-collision wall, and overlap joint connection is realized with the vertical muscle of caged framework of steel reinforcement,
And passing through the casting concrete into cavity makes prefabricated superposed type anti-collision wall form one with floorings.
2. the prefabricated superposed type anti-collision wall according to claim 1 for urban viaduct, which is characterized in that the reinforcing bar
Skeleton is in caged, and the horizontal bar of caged framework of steel reinforcement is welded with vertical muscle infall using spot welding, and framework of steel reinforcement is both anti-collision wall
Structure stress reinforcing bar, and precast concrete shingle nail inside and outside connecting, at the same meet the demoulding of component, overturning, transport and
Globality requirement during lifting.
3. the prefabricated superposed type anti-collision wall according to claim 1 for urban viaduct, which is characterized in that described inside and outside
Interior outboard template when side precast concrete shingle nail is both a part and poured in place concrete for anticollision wall construction,
Metope plate thickness is 60mm~150mm, and length is 1.5m~3.0m;Wherein, precast concrete shingle nail in inside is using corrosion-resistant
Concrete for making or it is prefabricated when the corrosion resistant plane materiel of the embedding patch in surface, to cope with complicated, the rodent working environment residing for it.
4. the prefabricated superposed type anti-collision wall according to claim 1 for urban viaduct, which is characterized in that the outside
The pre-buried L-type bracket in precast concrete shingle nail bottom, is evenly arranged along anti-collision wall spacing 1m~1.5m, pre-buried at corresponding floorings
Vertical adjustment nut;Before anti-collision wall lifting, pre-buried vertical adjustment nut is first adjusted to design level absolute altitude, L-type bracket during lifting
Horizonal base plate directly fall on vertical adjustment nut, with support outside precast concrete shingle nail.
5. the prefabricated superposed type anti-collision wall according to claim 1 for urban viaduct, which is characterized in that the inside
The pre-buried L-type bracket with holes in precast concrete shingle nail bottom, L-type bracket with holes are evenly arranged along anti-collision wall spacing 1m~1.5m;
Pre-buried vertical screw rod at corresponding floorings, L-type bracket horizonal base plate with holes are provided with the hole of corresponding vertical screw rod, and in vertical spiral shell
Pacify a nut on bar in advance;Before anti-collision wall lifting, first adjusting nut to design level absolute altitude, when lifting, L-type bracket with holes was horizontal
Bottom plate is inserted in screw rod, and falls on the nut pacified in advance, with support inside precast concrete shingle nail;Adjust the position of anti-collision wall
Afterwards, a nut on vertical screw rod is installed again, L-type bracket with holes is fixed, and then fixes anti-collision wall, prevent it from toppling, is exempted from
Go extra support.
6. the prefabricated superposed type anti-collision wall according to claim 1 for urban viaduct, which is characterized in that the outside
Pre-cast concrete walling lower panels are equipped with lower hanging plate, and lower hanging plate is corresponding with the side of floorings.
7. the prefabricated superposed type anti-collision wall described in accordance with the claim 1 for urban viaduct, which is characterized in that in anti-collision wall
When in the middle part of bridge, anti-collision wall plays the role of dividing strip, in caged framework of steel reinforcement both sides precast concrete shingle nail;Outside
The bottom of precast concrete shingle nail and inside precast concrete shingle nail, pre-buried L-type bracket with holes, floorings top are pre-
Vertical screw rod is buried, the bottom plate of L-type bracket with holes is provided with the hole of corresponding pre-buried vertical screw rod, and a spiral shell is pacified on vertical screw rod top in advance
Mother, the bottom plate of L-type bracket with holes is inserted in vertical screw rod during lifting, and falls on the nut pacified in advance below, precast concrete metope
Gap between plate bottom and floorings is blocked using dry cement mortar.
8. the construction method of the prefabricated superposed type anti-collision wall for urban viaduct described in a kind of one of claim 1 to 7,
It is characterized in that, includes the following steps:
(1) it is reserved at the top of floorings and vertically connects reinforcing bar and adjusting nut, vertical screw rod, the bridge floor plate surface in the range of anti-collision wall
Chisel is picked into rough surface, and cleans out no-sundries, watering wetting before lifting;
(2) nut on rotating adjusting nut and vertical screw rod, cooperation level meter are adjusted to predetermined absolute altitude;
(3) prefabricated anti-collision wall lifts in place from top to bottom, and the sealing strip at the tongue and groove of outside precast concrete shingle nail middle and lower part squeezes
For swaging into outer side seal, the bottom plate that adjusting nut withstands L-type bracket forms vertical supporting;Under the precast concrete shingle nail of inside
Hole on bottom sleeve-board with hole horizontal bracket enters vertical screw rod, and falls on following nut, forms vertical supporting;Adjust anticollision
Behind the position around of wall, L-type bracket with holes with another nut from above is fixed again, forms reliable drawknot, is prevented
Only component topples;
(4) gap under the precast concrete shingle nail of inside is blocked to form sealing with dry mortar, in the cavity of anti-collision wall
Interspersed, connecting pipeline and the related embedded part of installation, then from top into cavity casting concrete, vibration compacting, top surface troweling;
(5) mat formation bridge floor board finish, cover exposed vertical screw rod and L-type bracket with holes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810149475.5A CN108265623A (en) | 2018-02-13 | 2018-02-13 | A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810149475.5A CN108265623A (en) | 2018-02-13 | 2018-02-13 | A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108265623A true CN108265623A (en) | 2018-07-10 |
Family
ID=62774108
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810149475.5A Pending CN108265623A (en) | 2018-02-13 | 2018-02-13 | A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108265623A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109137742A (en) * | 2018-09-30 | 2019-01-04 | 中国建筑土木建设有限公司 | The mounting device and installation method of prefabricated anti-collision wall linkage section |
CN111364355A (en) * | 2020-01-22 | 2020-07-03 | 华南理工大学 | Assembled reinforced concrete side anti-collision guardrail for connecting bridges and construction method |
CN111519824A (en) * | 2020-04-14 | 2020-08-11 | 中铁第四勘察设计院集团有限公司 | Prefabricated station platen, assembly type station and construction method of assembly type station |
CN112504599A (en) * | 2020-11-20 | 2021-03-16 | 陕西煤业化工技术研究院有限责任公司 | Friction energy-absorbing plate collision test wall and prefabricating and construction installation process thereof |
CN112538823A (en) * | 2020-12-05 | 2021-03-23 | 中铁十九局集团第一工程有限公司 | Construction method for mounting precast block of precast concrete protective wall |
CN113832837A (en) * | 2021-09-29 | 2021-12-24 | 广州机施建设集团有限公司 | Fabricated anti-collision wall, welding device and construction method of fabricated anti-collision wall |
CN113863132A (en) * | 2021-09-26 | 2021-12-31 | 广州机施建设集团有限公司 | Fabricated anti-collision wall and construction process |
Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0657717A (en) * | 1992-08-13 | 1994-03-01 | Onoda Cement Co Ltd | Concrete guard fence |
JPH06313304A (en) * | 1993-04-30 | 1994-11-08 | Keihan Concrete Kogyo Kk | Structure of high balustrade in concrete structure having high balustrade and construction method for balustrade part |
JPH0892923A (en) * | 1994-09-22 | 1996-04-09 | Chichibu Onoda Cement Corp | Guard fence |
CN201447879U (en) * | 2009-08-24 | 2010-05-05 | 中建钢构江苏有限公司 | Steel column base calibrating and fine adjusting device |
CN102493350A (en) * | 2011-12-19 | 2012-06-13 | 中国一冶集团有限公司 | Construction method of landscape bridge outside-hanging crash barrier |
CN103061267A (en) * | 2013-01-15 | 2013-04-24 | 广州市市政工程设计研究院 | Construction method of combined prefabricated bridge anti-collision wall |
CN203200914U (en) * | 2013-04-10 | 2013-09-18 | 上海嘉实(集团)有限公司 | Steel structure socle outward exposed connecting structure |
CN203256611U (en) * | 2013-03-12 | 2013-10-30 | 长安大学 | Height-adjustable bridge handrail base |
CN203320700U (en) * | 2013-07-19 | 2013-12-04 | 安徽富煌钢构股份有限公司 | Steel structure column foot connecting structure |
CN104563523A (en) * | 2013-10-28 | 2015-04-29 | 五冶集团上海有限公司 | Method for mounting pipe frame and door type light steel structure |
CN205804170U (en) * | 2016-06-17 | 2016-12-14 | 北京华路安交通科技有限公司 | A kind of recycling bridge concrete guardrail |
CN106567329A (en) * | 2016-11-07 | 2017-04-19 | 上海市政工程设计研究总院(集团)有限公司 | Semi-prefabricated reinforced concrete wall type guardrail |
CN207944339U (en) * | 2018-02-13 | 2018-10-09 | 高强 | A kind of prefabricated superposed type anti-collision wall for urban viaduct |
-
2018
- 2018-02-13 CN CN201810149475.5A patent/CN108265623A/en active Pending
Patent Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0657717A (en) * | 1992-08-13 | 1994-03-01 | Onoda Cement Co Ltd | Concrete guard fence |
JPH06313304A (en) * | 1993-04-30 | 1994-11-08 | Keihan Concrete Kogyo Kk | Structure of high balustrade in concrete structure having high balustrade and construction method for balustrade part |
JPH0892923A (en) * | 1994-09-22 | 1996-04-09 | Chichibu Onoda Cement Corp | Guard fence |
CN201447879U (en) * | 2009-08-24 | 2010-05-05 | 中建钢构江苏有限公司 | Steel column base calibrating and fine adjusting device |
CN102493350A (en) * | 2011-12-19 | 2012-06-13 | 中国一冶集团有限公司 | Construction method of landscape bridge outside-hanging crash barrier |
CN103061267A (en) * | 2013-01-15 | 2013-04-24 | 广州市市政工程设计研究院 | Construction method of combined prefabricated bridge anti-collision wall |
CN203256611U (en) * | 2013-03-12 | 2013-10-30 | 长安大学 | Height-adjustable bridge handrail base |
CN203200914U (en) * | 2013-04-10 | 2013-09-18 | 上海嘉实(集团)有限公司 | Steel structure socle outward exposed connecting structure |
CN203320700U (en) * | 2013-07-19 | 2013-12-04 | 安徽富煌钢构股份有限公司 | Steel structure column foot connecting structure |
CN104563523A (en) * | 2013-10-28 | 2015-04-29 | 五冶集团上海有限公司 | Method for mounting pipe frame and door type light steel structure |
CN205804170U (en) * | 2016-06-17 | 2016-12-14 | 北京华路安交通科技有限公司 | A kind of recycling bridge concrete guardrail |
CN106567329A (en) * | 2016-11-07 | 2017-04-19 | 上海市政工程设计研究总院(集团)有限公司 | Semi-prefabricated reinforced concrete wall type guardrail |
CN207944339U (en) * | 2018-02-13 | 2018-10-09 | 高强 | A kind of prefabricated superposed type anti-collision wall for urban viaduct |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109137742A (en) * | 2018-09-30 | 2019-01-04 | 中国建筑土木建设有限公司 | The mounting device and installation method of prefabricated anti-collision wall linkage section |
CN111364355A (en) * | 2020-01-22 | 2020-07-03 | 华南理工大学 | Assembled reinforced concrete side anti-collision guardrail for connecting bridges and construction method |
CN111519824A (en) * | 2020-04-14 | 2020-08-11 | 中铁第四勘察设计院集团有限公司 | Prefabricated station platen, assembly type station and construction method of assembly type station |
CN112504599A (en) * | 2020-11-20 | 2021-03-16 | 陕西煤业化工技术研究院有限责任公司 | Friction energy-absorbing plate collision test wall and prefabricating and construction installation process thereof |
CN112504599B (en) * | 2020-11-20 | 2023-09-22 | 陕西煤业化工技术研究院有限责任公司 | Friction energy absorption plate collision test wall and prefabrication and construction installation process thereof |
CN112538823A (en) * | 2020-12-05 | 2021-03-23 | 中铁十九局集团第一工程有限公司 | Construction method for mounting precast block of precast concrete protective wall |
CN113863132A (en) * | 2021-09-26 | 2021-12-31 | 广州机施建设集团有限公司 | Fabricated anti-collision wall and construction process |
CN113832837A (en) * | 2021-09-29 | 2021-12-24 | 广州机施建设集团有限公司 | Fabricated anti-collision wall, welding device and construction method of fabricated anti-collision wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108265623A (en) | A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct | |
CN106869172B (en) | In-situ deposited prefabricated split-mounting type subway underground station construction method | |
CN105178357B (en) | Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition | |
CN102493603B (en) | Prefabricated column of reserved concealed column channel, concealed column type complete assembled earthquake-resistant building and its method | |
CN106854873A (en) | A kind of engineering method and garage parking in precast spliced sinking type garage parking | |
CN109811878A (en) | The shell integrated structure of the cast-in-place coinsiding die of assembled architecture and construction method | |
CN106284412B (en) | A kind of prefabricated pipe gallery and construction method | |
CN105040970A (en) | Comprehensive gymnasium high formwork support system and construction method of comprehensive gymnasium high formwork support system | |
CN206545215U (en) | A kind of precast spliced sinking type garage parking | |
CN103924525B (en) | Urban interchange industrialization short-term precast assembly construction method | |
CN207944339U (en) | A kind of prefabricated superposed type anti-collision wall for urban viaduct | |
CN206016309U (en) | A kind of overall assembled building system | |
CN107476470A (en) | Steel pipe built in assembled and GFRP pipe regeneration concrete compound shear walls and its construction method | |
CN108086353B (en) | Hollow wall plate mixed prefabricated assembly type comprehensive pipe gallery spliced by cast-in-place hidden beams and construction method thereof | |
CN113638304B (en) | Concrete beam type bridge hidden cover beam structure system and construction method thereof | |
CN106120562A (en) | Overpass rod iron bracket bent cap support for shuttering integral hoisting construction method | |
CN208072415U (en) | Deep foundation pit reinforced concrete support part changes structure | |
CN107100083A (en) | A kind of T-shaped high pier Cast-in-place Bent Cap formwork erecting structure and construction method | |
CN110409492A (en) | The combination assembled piping lane of one kind more structures containing superposed member and its construction method | |
CN103452350A (en) | Fabricated electronic workshop and construction method thereof | |
CN111188508A (en) | Supplement plate of existing cantilever floor slab of building structure and construction method thereof | |
CN110512727A (en) | A kind of pre-buried insulation board post stretching anchorage node construction of assembled architecture lotus rhizome beam and its construction method | |
CN110106915A (en) | One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure | |
CN207110214U (en) | A kind of prefabricated interior fill concrete wallboard | |
CN111173042B (en) | Advanced water stop post-cast strip of foundation slab and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |