CN115369858B - Construction process of concrete filled steel tubular column - Google Patents

Construction process of concrete filled steel tubular column Download PDF

Info

Publication number
CN115369858B
CN115369858B CN202210909034.7A CN202210909034A CN115369858B CN 115369858 B CN115369858 B CN 115369858B CN 202210909034 A CN202210909034 A CN 202210909034A CN 115369858 B CN115369858 B CN 115369858B
Authority
CN
China
Prior art keywords
steel
steel pipe
concrete
casing
pouring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210909034.7A
Other languages
Chinese (zh)
Other versions
CN115369858A (en
Inventor
王伟
索亚迪
刘�东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Chemical Engineering Sixth Construction Co Ltd
Original Assignee
China National Chemical Engineering Sixth Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Chemical Engineering Sixth Construction Co Ltd filed Critical China National Chemical Engineering Sixth Construction Co Ltd
Priority to CN202210909034.7A priority Critical patent/CN115369858B/en
Publication of CN115369858A publication Critical patent/CN115369858A/en
Application granted granted Critical
Publication of CN115369858B publication Critical patent/CN115369858B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/40Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds in open water
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a construction process of a concrete filled steel tubular column, which comprises the following steps: the steel pipe is sleeved with a steel protection cylinder, and the steel pipe and the steel protection cylinder are assembled into a whole by adopting a positioning bracket and an auxiliary device; lifting the assembled structure, lowering, and installing a drilling machine on the construction surface at the bottom of the steel casing; controlling the steel pipe and the steel casing to sink to the designed elevation synchronously through the rotary digging of the drilling machine; s4, taking out the drilling machine and evacuating slurry and water in the steel casing; removing the positioning support after pouring the bottom layer concrete, pulling up the steel pile casing layer by layer, and synchronously pouring the steel pipe concrete of the corresponding stratum; and continuously pulling up the steel protective cylinder until the steel protective cylinder is separated from the steel pipe, and pouring the residual steel pipe concrete. According to the invention, the steel pile casing is assembled with the steel pipe, and the integral sinking of the assembled structure is realized by synchronously digging downwards in cooperation with the drilling machine, so that the influence of external factors on positioning accuracy is reduced; and after the steel pipe is sunk in place, the steel pile casing is gradually pulled out according to the stratum structure, and meanwhile, the steel pipe concrete pouring is completed in a layered mode, so that the construction stability and the construction quality are ensured.

Description

Construction process of concrete filled steel tubular column
Technical Field
The invention relates to the technical field of steel structure construction. More particularly, the invention relates to a construction process of a concrete filled steel tubular column.
Background
With the rapid development of the steel structure industry in China, the design, manufacturing and installation technology of the steel structure engineering is gradually oriented to the promotion and development of large and complex constructional engineering. The concrete filled steel tubular column is widely used because of its good compression resistance, bearing strength and deformation resistance. Compared with a pure steel structure, the steel pipe concrete structure has the advantages of steel saving, high rigidity, good stability, strong rust prevention and fire resistance, and the like; compared with the reinforced concrete structure, the steel pipe concrete structure has the advantages of light dead weight, high strength, excellent anti-seismic performance, energy saving, land saving, short construction period and the like.
The common construction method of the concrete filled steel tube column comprises the following steps: firstly, inserting the steel pipe into a pre-dug pile hole, and then filling concrete into the steel pipe to solidify the steel pipe and the pile bottom structure and form a column. The construction process is simple to operate, the pile forming quality of concrete is good, but when facing a complex or severe geological environment (such as underwater or soft geology), the pile hole is insufficient in supporting force, the problems of collapse, collapse and the like easily occur before the steel pipe is placed and in the installation process, the positioning accuracy and the installation efficiency of the steel pipe are affected, the external impact force which can be born by the thin-wall steel pipe before filling the concrete is small, the pile forming quality of the steel pipe concrete column is seriously affected by the damage or deformation easily occurring under the condition that the external environment is severe or the pile hole is unstable.
In order to solve the problems, a construction process of the concrete filled steel tubular column needs to be designed, and the construction efficiency and the construction quality are ensured while the construction process is suitable for various geological environments.
Disclosure of Invention
The invention aims to provide a construction process of a concrete filled steel tubular column, which realizes the integral sinking of a spliced structure by splicing a steel casing and a steel tube and synchronously digging downwards by matching with a drilling machine, thereby reducing the influence of external factors on positioning accuracy; and after the steel pipe is sunk in place, the steel pile casing is gradually pulled out according to the stratum structure, and meanwhile, the steel pipe concrete pouring is completed in a layered mode, so that the construction stability and the construction quality are ensured.
To achieve these objects and other advantages and in accordance with the purpose of the invention, there is provided a concrete filled steel tubular column construction process comprising:
s1, sleeving a steel protection cylinder on the outer side of a steel pipe, fixedly connecting the steel pipe and the top of the steel protection cylinder by adopting a positioning bracket, and filling a bottom gap between the steel pipe and the steel protection cylinder by adopting an auxiliary device so that the steel pipe and the steel protection cylinder form a spliced structure, and the bottom end of the steel protection cylinder is lower than the bottom end of the steel pipe;
s2, integrally hoisting the assembled structure by using hoisting equipment, lowering the assembled structure according to the designed position of the steel pipe, and then lowering a drilling machine to the bottom construction surface of the steel casing along the inner part of the steel pipe;
s3, driving the drilling machine to vertically dig a construction surface downwards in a rotary mode, and controlling the steel pipe and the steel casing to synchronously sink along the vertical direction until the bottom end of the steel pipe reaches a designed elevation;
s4, taking out the drilling machine and evacuating slurry and water in the steel casing;
s5, pouring concrete to the bottom of the steel pipe to the bottom of the steel pile casing, removing the positioning support after the concrete is solidified, pulling the steel pile casing layer by layer in the vertical direction by adopting hoisting equipment, and synchronously pouring the steel pipe concrete of the corresponding layer until the steel pipe concrete pouring in all the layers is completed;
s6, adopting hoisting equipment to continuously pull up the steel casing until the steel casing is separated from the steel pipe, and simultaneously pouring the steel pipe concrete of the remaining sections.
Preferably, in the construction process of the concrete filled steel tube column, in S1, the steel tube is pretreated before the steel tube and the steel casing are assembled, and the method comprises the following steps:
s11, coaxially sleeving a pouring inner template in a steel pipe body, closing gaps between the pouring inner template and two ends of the steel pipe body, pouring pre-filled concrete between the steel pipe body and the pouring inner template, and removing the pouring inner template after the concrete is solidified to form a pre-filled steel pipe;
s12, arranging a plurality of layers of grouting holes at the lower part of the pre-filled steel tube according to the distribution condition of the construction stratum, wherein the grouting holes are in one-to-one correspondence with a plurality of strata, each layer of grouting holes comprises a plurality of grouting holes, the grouting holes are arranged at intervals along the circumferential direction of the steel tube body, and each grouting hole is communicated with the pre-filled steel tube and the steel casing.
Preferably, in the construction process of the concrete filled steel tubular column, the positioning bracket comprises a hoisting platform which is fixed on the outer side wall of the top of the steel casing; the steel pile casing lifting lug is arranged at the top of the lifting platform; the collet chuck comprises two jackets, the intrados of the collet chucks are oppositely arranged and sleeved on the outer side wall of the top of the steel pipe, the two jackets are connected through bolts and clamp the steel pipe inwards, and the steel pipe is erected on the hoisting platform through the collet chuck; the steel pipe lifting lug is arranged at the top of the collet chuck; and the positioning bolt is fixedly connected with the collet chuck and the hoisting platform.
Preferably, in the construction process of the concrete filled steel tubular column, the auxiliary device comprises a cutting edge foot, wherein the cutting edge foot is continuously arranged along the inner periphery of the steel casing and fixed at the bottom end of the steel casing, and the tip end of the cutting edge foot is vertically downwards arranged; the water stop ring is horizontally fixed at the top of the cutting edge, the outer side wall of the water stop ring is fixedly connected with the inner side wall of the steel casing, and the inner side wall of the water stop ring is abutted to the outer side wall of the steel pipe and is in sliding connection along the height direction of the steel pipe.
Preferably, in the construction process of the concrete filled steel tubular column, in S4, after the slurry and water in the steel casing are evacuated, the positioning of the steel tubular column is adjusted, and the adjustment method is as follows:
firstly, the connection of the positioning bolts to the collet chuck and the hoisting platform is released, then the hoisting equipment is used for adjusting the relative position of the collet chuck on the hoisting platform, and after the steel pipe moves to the designed position, the temporary fixing device is used for fixing the collet chuck on the hoisting platform again.
Preferably, in the construction process of the steel pipe concrete column, in S5, the number of pull-up layers and the single-layer pull-up distance of the steel casing are set according to stratum distribution and stratum thickness, and the construction method for pouring the multilayer steel pipe concrete comprises the following steps:
s51, pulling up the steel pile casing until the bottom end of the steel pile casing is flush with the current stratum surface, synchronously pouring concrete to the bottom of the steel pipe in the process of pulling up the steel pile casing, enabling the concrete in the steel pipe to enter a gap between the steel pipe and the steel pile casing through an opening on the side wall of the steel pipe and fill the gap, wherein the height position of the concrete in the steel pipe in the poured single-layer steel pipe concrete is the same as the height position of the concrete between the steel pipe and the steel pile casing;
s52, after the steel pipe concrete of the current stratum is solidified, repeating the step S51 to continue pouring the upper layer of steel pipe concrete until the pouring of the steel pipe concrete in all the strata is completed.
In the construction process of the concrete filled steel tubular column, in S51, the poured single-layer concrete filled steel tubular column is matched with the strength of the rock in the corresponding stratum.
The invention at least comprises the following beneficial effects:
1. according to the invention, the steel pile casing and the steel pipe are assembled, the integral sinking of the assembled structure is realized by synchronously digging down the steel pipe in cooperation with the drilling machine, the gap between the steel pipe and the steel pile casing is relatively closed, the sinking posture and the axis coordinate of the inner steel pipe are used as positioning references, the influence of external factors on the positioning accuracy of the steel pipe concrete column is reduced, the synchronous sinking of the steel pile casing and the steel pipe simplifies the construction process, and the construction efficiency is improved; gradually pulling out the steel casing according to the stratum structure after the steel pipe is sunk in place, and layering according to geological conditions to finish concrete pouring of the steel pipe, so that external supporting stability in the concrete pouring is guaranteed, a layered reinforcing structure connected with an external stratum is formed at the bottom of the steel pipe concrete column, and construction stability and construction quality are improved;
2. according to the invention, concrete filling is performed on the inner wall of the steel pipe in advance before assembly, so that the strength and bearing capacity of the steel pipe are improved, the steel pipe can be further protected from external impact force in the synchronous sinking process along with the steel casing, and the concrete filled in the subsequent concrete pouring process can fully fill the concrete gaps on the damaged inner wall of the steel pipe, so that the piling quality of the steel pipe concrete column is not affected.
Additional advantages, objects, and features of the invention will be set forth in part in the description which follows and in part will become apparent to those having ordinary skill in the art upon examination of the following or may be learned from practice of the invention.
Drawings
FIG. 1 is a schematic view of the construction structure of S3 of the construction process of a concrete filled steel tubular column according to one embodiment of the present invention;
FIG. 2 is a schematic plan view of the assembly structure of S3 in the above embodiment;
fig. 3 is a schematic view of the construction structure of S4 in the above embodiment;
fig. 4 is a schematic view of a construction structure for pouring the bottom concrete in the above embodiment;
fig. 5 is a schematic view of a construction structure of concrete filled steel tube for casting an underwater rock layer in the above embodiment;
fig. 6 is a schematic view of a construction structure of concrete filled steel tube for casting an underwater soil layer in the above embodiment;
fig. 7 is a schematic view of the construction structure of S6 in the above embodiment.
Reference numerals illustrate:
11. a steel pipe body; 12. pre-filling concrete; 13. grouting holes; 2. a steel pile casing; 31. hoisting the platform; 32. a collet; 33. steel pile casing lifting lug; 34. a steel pipe lifting lug; 35. a bolt; 36. positioning bolts; 37. temporary fixing means; 41. a blade foot; 42. a water stop ring; 5. hoisting equipment; 6. a drilling machine; 71. bottom layer concrete; 72. single-layer steel pipe concrete; 81. an underwater rock formation; 82. an underwater soil layer; 83. the water surface.
Detailed Description
The present invention is described in further detail below with reference to the drawings to enable those skilled in the art to practice the invention by referring to the description.
It should be noted that the experimental methods described in the following embodiments, unless otherwise specified, are all conventional methods, and the reagents and materials, unless otherwise specified, are all commercially available; in the description of the present invention, the terms "transverse", "longitudinal", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, are merely for convenience in describing the present invention and simplifying the description, and do not indicate or imply that the devices or elements referred to must have a specific orientation, be configured and operated in a specific orientation, and thus are not to be construed as limiting the present invention.
As shown in fig. 1 to 7, the present invention provides a concrete filled steel tubular column construction process, comprising:
s1, sleeving a steel protection cylinder 2 on the outer side of a steel pipe, fixedly connecting the steel pipe and the top of the steel protection cylinder 2 by adopting a positioning bracket, and filling a bottom gap between the steel pipe and the steel protection cylinder by adopting an auxiliary device so that the steel pipe and the steel protection cylinder form a spliced structure, and the bottom end of the steel protection cylinder is lower than the bottom end of the steel pipe;
s2, integrally lifting the assembled structure by using lifting equipment 5, lowering the assembled structure according to a designed position, and then lowering a drilling machine 5 to the construction surface at the bottom of the steel casing along the inner part of the steel pipe;
s3, driving the drilling machine 5 to vertically dig a construction surface downwards in a rotary mode, and controlling the steel pipe and the steel casing to synchronously sink along the vertical direction until the bottom end of the steel pipe reaches a designed elevation;
s4, taking out the drilling machine and evacuating slurry and water in the steel casing;
s5, pouring concrete to the bottom of the steel pipe to the bottom of the steel pile casing, removing the positioning support after the concrete is solidified, pulling the steel pile casing layer by layer in the vertical direction by adopting hoisting equipment, and synchronously pouring the steel pipe concrete of the corresponding layer until the steel pipe concrete pouring in all the layers is completed;
s6, adopting hoisting equipment to continuously pull up the steel casing until the steel casing is separated from the steel pipe, and simultaneously pouring the steel pipe concrete of the remaining sections.
In the above technical scheme, in S1, the steel pipe and the steel casing are initially assembled and connected through the positioning bracket at the top, the steel casing and the steel pipe are coaxially sleeved and are downwards arranged at a distance from one end relative to the bottom end of the steel pipe (namely, the bottom end of the steel casing is lower than the bottom end of the steel pipe), and the auxiliary device at the bottom can further fix the relative position of the steel pipe and the steel casing and form a relatively closed annular cavity between the steel pipe and the steel casing. The positioning bracket and the auxiliary device are arranged on the outer side of the steel pipe, a cavity which is penetrated up and down is formed in the steel pipe, and the drill rig in S2 is prevented from being lowered along the inner side of the steel pipe and the subsequent rotary digging construction is prevented from being influenced; the hoisting equipment is arranged on a water surface fixing structure or a temporary construction platform, the hoisting equipment can comprise a plurality of cranes, the S2 adopts a crane integral hoisting assembly structure, after sinking to a certain height (the structure cannot continue sinking by self gravity), another crane is adopted to lower the drilling machine to the bottom of the steel protection cylinder along the steel pipe (the space between the bottom of the steel protection cylinder and the bottom of the steel pipe), the drilling machine can adopt a conventional rotary drilling rig, the drill bit size of the drilling machine is adaptive to the inner diameter of the steel pipe, and the drilling machine can smoothly lower or lift the drilling machine along the inside of the steel pipe. S3, as the drilling machine is continuously dug down, the soil layer below the assembly structure is damaged, so that the assembly structure can continue to sink until the bottom end of the steel pipe reaches the designed elevation H; in the above process, the two cranes respectively control the digging speed of the drilling machine and the sinking speed of the assembly structure, so that the two cranes sink synchronously, meanwhile, the sinking posture of the assembly structure is controlled, the steel pipe and the steel pile casing are ensured to be vertically inserted into the underwater soil layer/rock stratum, in addition, the external acting force of the assembly structure is mainly applied to the outer steel pile casing in the sinking process, the internal impact force is small (mainly the acting force of the slurry floating up to the inner wall of the steel pipe brought up in the sinking process), the steel pipe and the steel pile casing are synchronously sunk at one time, the steel pipe quality is protected, the steel pipe is not easy to be damaged, and the construction quality is ensured while the construction efficiency is ensured. The rotary digging construction is provided with devices such as water injection, a slurry pump, a conveying pipeline and the like in a matching way, high-pressure water can be continuously injected to the construction surface in the rotary digging process, the construction surface is flushed and soil and crushed rock are taken away, and slurry generated in the rotary digging process is discharged through the conveying pipeline; after the drilling machine is constructed, the drilling machine is lifted by using the crane and separated from the inside of the steel pipe, the matched slurry pump and the conveying pipeline for rotary excavation construction are not removed, and in S5, reverse grouting can be continuously performed by using the conveying pipeline and the slurry pump, so that concrete pouring construction is performed. In this embodiment, the concrete filled steel tubular column construction process is applied to an underwater pile foundation construction, wherein the underwater soil layer 82 (lower in strength) is arranged in a certain depth range below the water surface 83, and the underwater rock layer 81 (higher in strength) is arranged below the underwater soil layer. Specifically, the stratum comprises two layers (an underwater soil layer and an underwater rock layer), and the steel casing is pulled up twice to perform concrete filled steel tube pouring in the stratum. In S5, pouring the bottom layer concrete 71 (namely, concrete between the bottom end of the steel casing and the bottom end of the steel pipe in the initial installation position) firstly, and when the concrete is actually poured, after filling the height gap between the bottom end of the steel casing and the bottom end of the steel pipe, pouring a section of concrete in the steel pipe upwards continuously so as to ensure the foundation positioning and fixing effect of the bottom layer concrete on the steel pipe and the underwater rock stratum. The single-layer steel pipe concrete 72 comprises concrete in a steel pipe, concrete between the steel pipe and the steel pile casing, the steel pile casing is upwards grouted from the bottom of the current steel pipe (namely the concrete plane in the steel pipe) in a single-time pulling process, and integrated pouring molding of the concrete in the steel pipe, the steel pipe and the concrete between the steel pipe and the steel pile casing in a corresponding stratum (height range) can be realized through the opening of the side wall of the steel pipe, wherein the pulling of the steel pile casing and the pouring of the concrete are synchronously carried out, and the poured concrete is filled in the gap between the original position of the steel pile casing and the stratum after the steel pile casing is pulled out, so that the supporting stability of the external environment in the concrete pouring process is ensured, the pile foundation drilling is not easy to collapse, and the current stratum and the steel pipe concrete are connected into a whole through the integrally poured concrete, so that the connection stability of the steel pipe concrete column and the lower foundation is further ensured. And S6, after the pouring of the steel pipe concrete in all the strata is completed, the steel pile casing is not required to maintain the supporting stability between the strata and the steel pipe, the steel pile casing can be directly pulled up and removed, meanwhile, the concrete in the steel pipe of the rest sections (namely the steel pipe concrete on the strata) can be continuously poured, and the construction of the single-pile steel pipe concrete column is completed after capping and solidification.
According to the invention, the steel pile casing and the steel pipe are assembled, the integral sinking of the assembled structure is realized by synchronously digging down the steel pipe in cooperation with the drilling machine, the gap between the steel pipe and the steel pile casing is relatively closed, the sinking posture and the axis coordinate of the inner steel pipe are used as positioning references, the influence of external factors on the positioning accuracy of the steel pipe concrete column is reduced, the synchronous sinking of the steel pile casing and the steel pipe simplifies the construction process, and the construction efficiency is improved; the steel pipe is sunk in place, the steel pile casing is gradually pulled out according to the stratum structure, meanwhile, steel pipe concrete pouring is completed in a layered mode according to geological conditions, external supporting stability in the concrete pouring is guaranteed, a layered reinforcing structure connected with an external stratum is formed at the bottom of the steel pipe concrete column, and construction stability and construction quality are improved.
In another technical scheme, in the construction process of the concrete filled steel tubular column, in S1, the steel tube is pretreated before the steel tube and the steel casing are assembled, and the method comprises the following steps:
s11, coaxially sleeving a pouring inner template in a steel pipe body 11, closing gaps between the pouring inner template and two ends of the steel pipe body, pouring pre-filled concrete 12 between the steel pipe body and the pouring inner template, and removing the pouring inner template after the concrete is solidified to form a pre-filled steel pipe;
s12, arranging a plurality of layers of grouting holes at the lower part of the pre-filled steel tube according to the distribution condition of the construction stratum, wherein the grouting holes are in one-to-one correspondence with a plurality of strata, each layer of grouting holes comprises a plurality of grouting holes 13 which are arranged at intervals along the circumferential direction of the steel tube body, and each grouting hole is communicated with the pre-filled steel tube and the steel casing.
According to the technical scheme, the steel pipe body is a cylindrical hollow thin-wall steel pipe, the pouring inner template is a cylindrical template with the diameter smaller than that of the steel pipe body, the cylindrical template is sleeved in the steel pipe and forms an annular cavity together with the steel pipe, the bottom end and the top end of the steel pipe body are respectively provided with a bottom die and a top die for sealing the upper end and the lower end of the annular cavity, the top die is also provided with a grouting opening and an air vent, and after pouring is completed, the pouring inner template is removed after concrete solidification, namely the pre-filled steel pipe with the inner side wall uniformly covered with a concrete layer is formed. Meanwhile, as the steel pipe concrete of the corresponding layer is pulled up in a layered manner and synchronously poured in the S5, in order to realize the integrated pouring of the single-layer steel pipe concrete, grouting holes are correspondingly formed in the steel pipe sections of the corresponding layer (the height range), a plurality of grouting holes in the same layer can be formed in the bottom of the steel pipe concrete section of the current pouring, when the steel pipe concrete of the previous layer (solidified) is poured upwards, the concrete in the steel pipe flows into the space between the steel pipe and the steel pipe through the grouting holes, and as the steel pipe is synchronously moved upwards, the concrete flowing out of the grouting holes fills the gap between the outer side of the steel pipe and the current stratum, so that the connection reliability of the bottom of the steel pipe concrete column and the stratum is further improved. The concrete filling is carried out on the inner wall of the steel pipe in advance before assembly, so that the strength and the bearing capacity of the steel pipe are improved, the steel pipe can be further protected from being influenced by external impact force in the synchronous sinking process along with the steel casing, and the concrete filled in the subsequent concrete pouring process can fully fill the concrete gaps on the damaged inner wall of the steel pipe, so that the piling quality of the steel pipe concrete column is not influenced.
In another technical scheme, in the construction process of the concrete filled steel tubular column, the positioning bracket comprises a hoisting platform 31 which is fixed on the outer side wall of the top of the steel casing; a steel casing lifting lug 33 arranged on the top of the hoisting platform; the collet 32 comprises two jackets, the intrados of which are oppositely arranged and sleeved on the outer side wall of the top of the steel pipe, the two jackets are connected through bolts 35 and clamp the steel pipe inwards, and the steel pipe is erected on the hoisting platform through the collet; a steel pipe lifting lug 34 arranged on the top of the collet; and a positioning bolt 36 fixedly connecting the collet and the hoisting platform. The positioning support is of a split structure, the collet and the hoisting platform are respectively connected with the steel pipe and the steel protection barrel, and the detachable connection of the steel pipe and the steel protection barrel can be realized by controlling the connection relation between the collet and the hoisting platform. The collet is supported at the top of the hoisting platform, corresponding vertical perforations are arranged on the collet and the hoisting platform in advance, two vertical perforations are penetrated downwards in sequence by using positioning bolts and are respectively locked from two ends, so that the relative fixation of the collet and the hoisting platform can be realized, on one hand, the relative installation position (vertical position and transverse position) of the steel pipe and the steel protection barrel can be controlled, and on the other hand, after the connection of the positioning bolts is released, the position of the collet on the hoisting platform can be adjusted, and therefore, the fine adjustment of the setting state (the verticality) and the positioning (the transverse position) of the steel pipe can be realized through the adjustment of the internal structure of the positioning bracket after the assembly structure is wholly sunk in place. The steel pile casing lifting lugs and the steel pipe lifting lugs are staggered in the plane, so that mutual interference during lifting is avoided. When the collet chuck is fixed relative to the hoisting platform, the steel pipe and the steel casing are connected into a whole, and the hoisting assembly structure can be integrally hoisted through the steel pipe lifting lug or the steel casing lifting lug; when the collet chuck is separated from the hoisting platform, the collet chuck can be quickly dismantled by removing the bolt connection between the collet chuck and the hoisting platform, and then the steel casing is independently hoisted by the steel casing lifting lugs so as to perform single-layer steel pipe concrete pouring, at the moment, the position of the steel pipe in the ground is initially stabilized after the bottom layer concrete is poured, and the support stability in water can be maintained without additional control of hoisting equipment.
In another technical scheme, in the construction process of the concrete filled steel tubular column, the auxiliary device comprises a cutting edge 41, wherein the cutting edge 41 is continuously arranged along the inner periphery of the steel casing and fixed at the bottom end of the steel casing, and the tip end of the cutting edge is vertically downwards arranged; and the water stop ring 42 is horizontally fixed at the top of the blade foot, the outer side wall of the water stop ring is fixedly connected with the inner side wall of the steel casing, and the inner side wall of the water stop ring is abutted to the outer side wall of the steel pipe and is in sliding connection along the height direction of the steel pipe. Specifically, the cutting edge foot is fixed in the bottom of steel casing along circumference, can cooperate the rig to dig the supplementary integral quick decline of group of construction and piece together the structure soon, improves the efficiency of construction. The water stop ring is fixed at the top of the cutting edge and is flush with the bottom end of the steel pipe, the steel protection barrel is filled with slurry and water in the sinking process, the water stop ring swells when meeting water, the bottom end of the steel pipe is circumferentially fixed at the bottom end, the steel pipe bottom end is prevented from shaking in the steel protection barrel in the sinking process, meanwhile, the water stop ring seals the gap between the bottom end of the steel pipe and the steel protection barrel, and a sealed pouring space can be formed below the cutting edge in the bottom concrete construction or the single-layer steel pipe concrete construction, so that the pouring and solidification of the single-layer steel pipe concrete are facilitated. In addition, the water stop ring has certain shrinkage elasticity, and after the mud and water in the steel pile casing are evacuated in S4, the position of the steel pipe in the steel pile casing is conveniently fine-tuned, and the installation quality of the steel pipe concrete column is further guaranteed.
In another technical scheme, in the construction process of the concrete filled steel tubular column, in S4, after the slurry and water in the steel casing are evacuated, the positioning of the steel tubular column is adjusted, and the adjusting method is as follows:
firstly, the connection of the collet chuck to the hoisting platform by the positioning bolts is released, then the relative position of the collet chuck on the hoisting platform is adjusted by using hoisting equipment, and after the steel pipe moves to the designed position, the collet chuck 32 is re-fixed on the hoisting platform by adopting a temporary fixing device 37. The steel pipe lifting lug on the lifting device connecting collet chuck finely adjusts the position of the steel pipe in the steel protection barrel, the collet chuck and the lifting platform are re-fixed by using a temporary fixing device after adjustment, the temporary fixing device can select a opposite-pull clamping plate, and the two clamping pieces respectively press the middle positioning bracket from the top surface of the collet chuck and the bottom surface of the lifting platform relatively, so that the collet chuck and the lifting platform are relatively fixed, and the steel pipe is prevented from being positioned to deviate in the concrete pouring process. After the connection of the positioning support is released, the steel pipe and the outer steel casing are supported in the underwater stratum relatively independently, impact force generated by the external environment mainly acts on the steel casing, and in the subsequent concrete pouring process, the construction environment of the steel pipe is stable, so that the positioning accuracy and the pouring quality of the steel pipe concrete column after pouring is further ensured.
In another technical scheme, in the construction process of the steel pipe concrete column, in S5, the number of pull-up layers and the single-layer pull-up distance of the steel casing are set according to stratum distribution and stratum thickness, and the construction method for pouring the multilayer steel pipe concrete comprises the following steps:
s51, pulling up the steel pile casing 2 until the bottom end of the steel pile casing is flush with the current stratum surface, synchronously pouring concrete to the bottom of the steel pipe in the process of pulling up the steel pile casing, enabling the concrete in the steel pipe to enter a gap between the steel pipe and the steel pile casing through a side wall opening of the steel pipe and fill the gap, wherein the height position of the concrete in the steel pipe in the poured single-layer steel pipe concrete 72 is the same as the height position of the concrete between the steel pipe and the steel pile casing;
s52, after the steel pipe concrete of the current stratum is solidified, repeating the step S51 to continue pouring the upper layer of steel pipe concrete until the pouring of the steel pipe concrete in all the strata is completed.
In this embodiment, the formation comprises two layers (underwater soil layer 82 and underwater rock layer 81), and the steel casing is pulled up twice to perform concrete filled steel tube casting in the formation. Because the bottom of the steel pile casing is pulled up to be flush with the surface of the current stratum in construction and concrete solidification is carried out at the position, after the single-layer steel pipe concrete 72 is poured, the current stratum and the steel pipe concrete column in the corresponding height range are connected into a whole, a round table-shaped reinforcing structure is formed at the joint of the bottom of the previous stratum and the steel pipe, the overall stability of supporting and connecting the steel pipe concrete column among different strata is further improved, and particularly, for unfavorable environments such as soft geological layers, the supporting stability between the reinforced steel pipe concrete column and the ground layer can be assisted by the structure, and the supporting quality of the steel pipe concrete column is prevented from being influenced by stratum change.
In another technical scheme, in the construction process of the concrete filled steel tubular column, in S51, the poured single-layer concrete filled steel tubular column is matched with the rock and soil strength in the corresponding stratum. Specifically, in this embodiment, the stratum includes the underwater rock stratum and the underwater soil layer from bottom to top, the bottom concrete and the first layer of steel pipe concrete are all poured in the underwater rock stratum, the high-performance concrete (HPC) is selected to adapt to (approach) the rock-soil strength of the underwater rock stratum, the second layer of steel pipe concrete is poured in the underground soil layer, the ordinary concrete is selected to adapt to the rock-soil strength of the underwater soil layer, and the connection integrity and stability of the steel pipe concrete column lower structure and the foundation are better. The pre-filled concrete and the steel tube concrete (the upper concrete in the steel tube) of the rest sections in the S6 can be high-performance concrete, so that the overall strength and the bearing capacity of the steel tube concrete column are improved, and the supporting stability of the steel tube concrete column in various environments is further ensured.
Although embodiments of the present invention have been disclosed above, it is not limited to the details and embodiments shown and described, it is well suited to various fields of use for which the invention would be readily apparent to those skilled in the art, and accordingly, the invention is not limited to the specific details and illustrations shown and described herein, without departing from the general concepts defined in the claims and their equivalents.

Claims (5)

1. The construction process of the concrete filled steel tube column is characterized by comprising the following steps of:
s1, sleeving a steel protection cylinder on the outer side of a steel pipe, fixedly connecting the steel pipe and the top of the steel protection cylinder by adopting a positioning bracket, and filling a bottom gap between the steel pipe and the steel protection cylinder by adopting an auxiliary device so that the steel pipe and the steel protection cylinder form a spliced structure, and the bottom end of the steel protection cylinder is lower than the bottom end of the steel pipe;
the auxiliary device comprises a cutting edge foot which is continuously arranged along the inner periphery of the steel protective cylinder and fixed at the bottom end of the steel protective cylinder, and the tip end of the cutting edge foot is vertically downwards arranged; the water stop ring is horizontally fixed at the top of the cutting edge, the outer side wall of the water stop ring is fixedly connected with the inner side wall of the steel casing, and the inner side wall of the water stop ring is abutted to the outer side wall of the steel pipe and is in sliding connection along the height direction of the steel pipe;
s2, integrally hoisting the assembled structure by using hoisting equipment, lowering the assembled structure according to the designed position of the steel pipe, and then lowering a drilling machine to the bottom construction surface of the steel casing along the inner part of the steel pipe;
s3, driving the drilling machine to vertically dig a construction surface downwards in a rotary mode, and controlling the steel pipe and the steel casing to synchronously sink along the vertical direction until the bottom end of the steel pipe reaches a designed elevation;
s4, taking out the drilling machine and evacuating slurry and water in the steel casing;
s5, pouring concrete to the bottom of the steel pipe to the bottom of the steel pile casing, removing the positioning support after the concrete is solidified, pulling the steel pile casing layer by layer in the vertical direction by adopting hoisting equipment, and synchronously pouring the steel pipe concrete of the corresponding layer until the steel pipe concrete pouring in all the layers is completed; the construction method for pouring the multilayer steel pipe concrete comprises the following steps of:
s51, pulling up the steel pile casing until the bottom end of the steel pile casing is flush with the current stratum surface, synchronously pouring concrete to the bottom of the steel pipe in the process of pulling up the steel pile casing, enabling the concrete in the steel pipe to enter a gap between the steel pipe and the steel pile casing through an opening on the side wall of the steel pipe and fill the gap, wherein the height position of the concrete in the steel pipe in the poured single-layer steel pipe concrete is the same as the height position of the concrete between the steel pipe and the steel pile casing;
s52, after the steel pipe concrete of the current stratum is solidified, repeating the step S51 to continue pouring the upper layer of steel pipe concrete until the pouring of the steel pipe concrete in all the strata is completed;
s6, adopting hoisting equipment to continuously pull up the steel casing until the steel casing is separated from the steel pipe, and simultaneously pouring the steel pipe concrete of the remaining sections.
2. A concrete filled steel tubular column construction process according to claim 1, wherein in S1, the steel pipe is pretreated before being assembled with the steel casing, and the method comprises:
s11, coaxially sleeving a pouring inner template in a steel pipe body, closing gaps between the pouring inner template and two ends of the steel pipe body, pouring pre-filled concrete between the steel pipe body and the pouring inner template, and removing the pouring inner template after the concrete is solidified to form a pre-filled steel pipe;
s12, arranging a plurality of layers of grouting holes at the lower part of the pre-filled steel tube according to the distribution condition of the construction stratum, wherein the grouting holes are in one-to-one correspondence with a plurality of strata, each layer of grouting holes comprises a plurality of grouting holes, the grouting holes are arranged at intervals along the circumferential direction of the steel tube body, and each grouting hole is communicated with the pre-filled steel tube and the steel casing.
3. A concrete filled steel tubular column construction process as recited in claim 1 wherein said positioning bracket comprises a lifting platform secured to the top outer sidewall of said steel casing; the steel pile casing lifting lug is arranged at the top of the lifting platform; the collet chuck comprises two jackets, the intrados of the collet chucks are oppositely arranged and sleeved on the outer side wall of the top of the steel pipe, the two jackets are connected through bolts and clamp the steel pipe inwards, and the steel pipe is erected on the hoisting platform through the collet chuck; the steel pipe lifting lug is arranged at the top of the collet chuck; and the positioning bolt is fixedly connected with the collet chuck and the hoisting platform.
4. A steel pipe concrete column construction process according to claim 3, wherein in S4, the positioning of the steel pipe is adjusted after the slurry and water in the steel casing are evacuated, the adjustment method is:
firstly, the connection of the positioning bolts to the collet chuck and the hoisting platform is released, then the hoisting equipment is used for adjusting the relative position of the collet chuck on the hoisting platform, and after the steel pipe moves to the designed position, the temporary fixing device is used for fixing the collet chuck on the hoisting platform again.
5. A steel pipe concrete column construction process according to claim 1, wherein in S51, the poured single layer steel pipe concrete is matched with the strength of the rock in the corresponding formation.
CN202210909034.7A 2022-07-29 2022-07-29 Construction process of concrete filled steel tubular column Active CN115369858B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210909034.7A CN115369858B (en) 2022-07-29 2022-07-29 Construction process of concrete filled steel tubular column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210909034.7A CN115369858B (en) 2022-07-29 2022-07-29 Construction process of concrete filled steel tubular column

Publications (2)

Publication Number Publication Date
CN115369858A CN115369858A (en) 2022-11-22
CN115369858B true CN115369858B (en) 2023-12-12

Family

ID=84064568

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210909034.7A Active CN115369858B (en) 2022-07-29 2022-07-29 Construction process of concrete filled steel tubular column

Country Status (1)

Country Link
CN (1) CN115369858B (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202347516U (en) * 2011-06-01 2012-07-25 常雷 Pore-forming device for linked composite piling wall
CN102644275A (en) * 2012-05-22 2012-08-22 中国建筑第二工程局有限公司 Rotary-digging combined pile-forming construction method in complicated geological conditions
KR101194594B1 (en) * 2012-04-30 2012-10-25 주식회사 씨엠파트너스건축사사무소 Construction method of the concrete filled steel tube column
WO2012157829A1 (en) * 2011-05-13 2012-11-22 (주)코아지질 Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same
CN104153384A (en) * 2014-08-22 2014-11-19 熊翱 On-sea sandwich steel pipe pile foundation and construction method
CN108374418A (en) * 2018-03-26 2018-08-07 中铁五局集团有限公司 Steel pipe column precise positioning Fast Installation construction technology in a kind of sheltered reverse excavation
JP2019078106A (en) * 2017-10-26 2019-05-23 株式会社イチケン Pile head processing apparatus
CN109914399A (en) * 2019-03-21 2019-06-21 杭州公路工程监理咨询有限公司 A kind of pile base construction method of environmental protection
CN111827274A (en) * 2020-07-22 2020-10-27 浙江大学 High-strength grouting method for marine wind power weakly-weathered bedrock single-pile socketed foundation
CN112227357A (en) * 2020-08-31 2021-01-15 重庆建工第九建设有限公司 Construction method for double steel pile casings of rotary excavation pile foundation
CN213358591U (en) * 2020-07-31 2021-06-04 中国建筑土木建设有限公司 Detachable protects a structure

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104912045B (en) * 2014-03-14 2019-09-10 广东海上城建控股发展有限公司 Pier constitution water bottom is fixed to use hollow cylinder pier and its construction method of installation
CN111395346A (en) * 2020-03-19 2020-07-10 广州市建筑科学研究院有限公司 Construction method for pouring concrete into karst cave

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012157829A1 (en) * 2011-05-13 2012-11-22 (주)코아지질 Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same
CN202347516U (en) * 2011-06-01 2012-07-25 常雷 Pore-forming device for linked composite piling wall
KR101194594B1 (en) * 2012-04-30 2012-10-25 주식회사 씨엠파트너스건축사사무소 Construction method of the concrete filled steel tube column
CN102644275A (en) * 2012-05-22 2012-08-22 中国建筑第二工程局有限公司 Rotary-digging combined pile-forming construction method in complicated geological conditions
CN104153384A (en) * 2014-08-22 2014-11-19 熊翱 On-sea sandwich steel pipe pile foundation and construction method
JP2019078106A (en) * 2017-10-26 2019-05-23 株式会社イチケン Pile head processing apparatus
CN108374418A (en) * 2018-03-26 2018-08-07 中铁五局集团有限公司 Steel pipe column precise positioning Fast Installation construction technology in a kind of sheltered reverse excavation
CN109914399A (en) * 2019-03-21 2019-06-21 杭州公路工程监理咨询有限公司 A kind of pile base construction method of environmental protection
CN111827274A (en) * 2020-07-22 2020-10-27 浙江大学 High-strength grouting method for marine wind power weakly-weathered bedrock single-pile socketed foundation
CN213358591U (en) * 2020-07-31 2021-06-04 中国建筑土木建设有限公司 Detachable protects a structure
CN112227357A (en) * 2020-08-31 2021-01-15 重庆建工第九建设有限公司 Construction method for double steel pile casings of rotary excavation pile foundation

Also Published As

Publication number Publication date
CN115369858A (en) 2022-11-22

Similar Documents

Publication Publication Date Title
CN105735251B (en) Cutting type full-casing follow-up pile-forming construction method and system of bridge pile foundation rotary drilling rig
CN108086340B (en) Open caisson construction structure and construction method thereof
CN105569560B (en) A full set of tubular type long auger stake machine and the method for utilizing the ram machine construction
CN113550340A (en) Construction method of deepwater foundation of double-wall steel cofferdam without sealing bottom under deepwater rock entering condition
CN114215049A (en) Construction method for main steel casing of bored pile under deep water foundation and bare rock environment
CN109680702A (en) Suction cartridge type single-pile foundation structure and its construction method
WO2024007591A1 (en) Rock-socketed monopile construction method based on double-casing pile stabilizing platform
CN112627172A (en) Pile forming system and construction method for large-diameter cast-in-situ bored pile in karst area
CN112878375A (en) Vertical jacking implementation method and structure in underwater tunnel suitable for hard stratum
CN112281880A (en) Construction method of complex stratum long spiral hole-leading inserting-driving locking opening steel pipe pile cofferdam
CN100374656C (en) Construction method for large-diameter tilted socketed pile
CN214245694U (en) Pile forming system for large-diameter cast-in-situ bored pile in karst area
CN115369858B (en) Construction process of concrete filled steel tubular column
CN109989346B (en) Bridge large-diameter precast concrete tubular column foundation and construction method thereof
CN115584722A (en) Construction method of secant pile in water-rich rock-filling layer-containing soft soil area
CN114134822A (en) Bridge cast-in-situ bored pile retaining wall structure and construction method thereof
CN114635450A (en) Construction method for permanent steel pipe structural column of covered and excavated station
CN108316288A (en) Half casing guncreting pile construction equipment and construction method
CN114319412A (en) Single-pile foundation supported by inclined piles and construction method thereof
CN113481971A (en) Construction method for forming hole of cast-in-place pile under complex geological condition
CN111188339A (en) Ultra-long steel pile casing sinking system of large-diameter ultra-deep cast-in-place pile
CN212001091U (en) Ultra-long steel pile casing sinking system of large-diameter ultra-deep cast-in-place pile
CN112431195B (en) Pile planting and grouting construction method for tubular piles
CN219061506U (en) Arrangement structure of comprehensive pile forming construction equipment for low-clearance filling pile under foundation pit bottom supporting beam
CN217231820U (en) Be favorable to retrieving and manage bored concrete pile structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant