CN115288119A - Prefabricated bearing platform type miniature pile-anchor rod composite foundation and construction method thereof - Google Patents

Prefabricated bearing platform type miniature pile-anchor rod composite foundation and construction method thereof Download PDF

Info

Publication number
CN115288119A
CN115288119A CN202211063873.8A CN202211063873A CN115288119A CN 115288119 A CN115288119 A CN 115288119A CN 202211063873 A CN202211063873 A CN 202211063873A CN 115288119 A CN115288119 A CN 115288119A
Authority
CN
China
Prior art keywords
pile
anchor rod
bearing platform
foundation
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211063873.8A
Other languages
Chinese (zh)
Inventor
冯炳
黄剑
朱玛
吕庆
章剑光
谢天祥
王振峰
赏炜
沈鉴
孙志浩
周吉安
傅恒
李攀峰
徐兆欢
傅振阳
谢婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaoxing Jianyuan Electric Power Group Co ltd Daxing Electric Power Loading Branch
Shaoxing Daming Electric Power Design Institute Co ltd
Zhejiang University ZJU
Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Shaoxing Jianyuan Electric Power Group Co ltd Daxing Electric Power Loading Branch
Shaoxing Daming Electric Power Design Institute Co ltd
Zhejiang University ZJU
Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaoxing Jianyuan Electric Power Group Co ltd Daxing Electric Power Loading Branch, Shaoxing Daming Electric Power Design Institute Co ltd, Zhejiang University ZJU, Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical Shaoxing Jianyuan Electric Power Group Co ltd Daxing Electric Power Loading Branch
Priority to CN202211063873.8A priority Critical patent/CN115288119A/en
Publication of CN115288119A publication Critical patent/CN115288119A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to a prefabricated bearing platform type micro pile-anchor rod composite foundation and a construction method thereof, wherein the prefabricated bearing platform type micro pile-anchor rod composite foundation comprises a micro pile-anchor rod foundation and a steel truss bearing platform, wherein the steel truss bearing platform is fixed on a plurality of micro pile-anchor rod foundations; the micro pile-anchor rod foundation comprises a micro pile, a threaded steel rod and a grouting body, wherein the lower part of the threaded steel rod and the grouting body form an anchor rod, and the upper part of the threaded steel rod is used as a part of the micro pile; the construction steps are as follows: drilling; reaming; putting a threaded steel rod; injecting grouting body to the bottom of the hole expansion; placing the miniature pile reinforcement cage, and pouring concrete; installing a steel truss bearing platform; has the advantages that: the composite foundation has a simple structure and definite stress, can be used as a power transmission iron tower foundation in the soil and rock stratum on the mountainous area, and can be constructed in a light, mechanized and modularized manner; the problems that the bearing capacity of a single foundation is insufficient, large-scale foundation construction machinery cannot enter a field, and the construction cost is high are solved; a plurality of micro pile-anchor rod foundations are integrated through the steel truss bearing platform, and therefore large bearing capacity can be provided.

Description

Prefabricated bearing platform type miniature pile-anchor rod composite foundation and construction method thereof
Technical Field
The invention relates to the technical field of pile foundations, in particular to a prefabricated bearing platform type miniature pile-anchor rod composite foundation and a construction method thereof.
Background
With the rapid development of Chinese economy, the demand of society on electric power is increasing day by day, and in the process of fierce construction of power transmission lines with various voltage grades such as high voltage, ultrahigh voltage, extra-high voltage and the like, more and more power transmission lines inevitably span various complex strata, such as the upper and lower rock strata in mountainous areas. The foundation is used as an important component of the transmission line engineering, the form selection of the foundation is closely related to the stratum conditions, and the transmission iron tower can adopt a pile foundation or an anchor rod foundation for the soil-rock stratum above and below the mountain area.
If adopt pile foundation, it has following problem: 1. the uplift bearing capacity of the pile foundation is mainly provided by the side friction of the pile, and in order to provide enough uplift bearing capacity, the diameter of the pile needs to be made large, so that the cost is high, and meanwhile, the construction machinery of the large-diameter pile is large and difficult to transport to a mountain area; 2. drilling in rock, the pile forming efficiency is low, and the construction period is seriously prolonged; 3. because the pulling bearing capacity is mainly provided by the lateral resistance of the pile, the requirement of the pulling bearing capacity on the pile diameter under the condition of maximum hole forming of the existing mechanical equipment can not be met.
If adopt anchor rod basis, its cost is lower relatively, but the anchor rod level and the ability of pushing down load are relatively poor, often can appear the level and the not enough condition of bearing capacity of pushing down. Therefore, the anchor rod foundation often needs to be added with a bearing platform for providing horizontal and downward pressure bearing capacity. However, the addition of the bearing platform has the following two problems: 1. the bearing platform needs excavation construction, but large excavation machines such as excavators and the like which exist in large quantities in coastal mountain areas are difficult to enter a construction site; 2. if the soil layer on the upper part is thick, the bottom of the bearing platform is difficult to contact with the rock stratum, and the burial depth of the bearing platform is inevitably large at the moment, so that the manufacturing cost is high.
Based on this, the present application is thus proposed.
Disclosure of Invention
Aiming at the power transmission iron tower built in an upper-soil and lower-soil rock stratum, the invention provides a prefabricated bearing platform type miniature pile-anchor rod composite foundation which can meet the requirements of downward pressing, upward pulling and horizontal bearing capacity, is convenient to construct and is economical and reasonable and a construction method thereof.
A prefabricated bearing platform type miniature pile-anchor rod composite foundation comprises a miniature pile-anchor rod foundation and steel truss bearing platforms, wherein one steel truss bearing platform is fixed on a plurality of miniature pile-anchor rod foundations;
the micro pile-anchor rod foundation comprises a micro pile, a threaded steel rod and a grouting body, wherein the lower part of the threaded steel rod is wrapped by the grouting body to form a full-length bonding anchor rod, and the upper part of the threaded steel rod penetrates through the micro pile and serves as a part of the micro pile;
the miniature pile is a concrete cast-in-place pile, the diameter of the miniature pile is 150-400 mm, the pile length is 3-6 m, the pile body concrete strength is C25-C40, the thickness of the reinforcing steel bar protective layer is 35mm, the number of main reinforcing steel bars of the miniature pile is not less than 3, and the diameter of the main reinforcing steel bars is not less than 12mm;
the number of the deformed steel bars is 1-3, the deformed steel bars are arranged in the center of the micro pile, and the steel grade of the deformed steel bars adopts HRB335 and/or HRB400; if the screw-thread steel rods are multiple, the multiple screw-thread steel rods are arranged in a quincunx shape.
Further, the length of the full-length bonding type anchor rod is 6-12 m.
Further, the steel truss bearing platform and the miniature pile-anchor rod foundation are fixedly connected through bolts.
Furthermore, one steel truss bearing platform is fixed on 4-5 miniature pile-anchor rod foundations.
Furthermore, the grouting body is made of cement-based grouting materials, and for the working conditions of sulfate-corroded strata and underground water environment, sulfate-resistant cement is adopted, the pH value of water is not less than 4.0, insoluble substances are less than 2000mg/L, soluble substances are less than 2000mg/L, chlorides are less than 350mg/L, sulfates are less than 600mg/L, and sulfides are less than 100mg/L.
A construction method for the prefabricated bearing platform type miniature pile-anchor rod composite foundation comprises the following steps:
drilling a hole by using an anchor rod drilling machine, wherein the hole diameter is 90-130 mm, the specific drilling depth and the hole diameter of the drilled hole are determined after calculation according to the bearing capacity requirement, but the drilled hole is driven into a rock stratum to a certain depth, and a part of the full-length bonding anchor rod is ensured to be positioned in the rock;
using a hole expanding machine to expand the upper part of the drilled hole to form an expanded hole, wherein the diameter of the expanded hole is 300-400 mm, the height of the expanded hole is 3-6 m, and the specific numerical value is determined after calculation according to the bearing capacity requirement;
the method comprises the following steps of (1) using a deformed steel bar as a bar body, placing the deformed steel bar and a grouting pipe at the bottom of a drilled hole, locating the top of the deformed steel bar above the top of an enlarged hole by a certain height, then grouting, and injecting slurry to the bottom of the enlarged hole;
putting down the reinforcement cage of the miniature pile, pouring concrete, and loading when the strength of the concrete or cement paste of the miniature pile reaches the designed strength;
after a plurality of micro pile-anchor rod foundations are constructed, the micro pile-anchor rod foundations are integrated through a steel truss bearing platform to form a large foundation.
Further, the bottom of the enlarged hole contacts the top surface of the rock.
The invention has the advantages that:
1. the prefabricated bearing platform type miniature pile-anchor rod composite foundation is simple in structure and clear in stress, and can be used as a power transmission iron tower foundation for the upper and lower rock strata in the mountainous area;
2. the diameter of the miniature pile is only 300-400 mm, so that the miniature pile can be constructed in a light, mechanical and modular manner; the depth of the micro pile into the soil is 3-6 m, and the micro pile slightly enters the rock, so that the rapid construction can be realized;
3. the miniature pile and the anchor rod foundation are combined, the miniature pile foundation mainly provides downward pressing and horizontal bearing capacity, the anchor rod foundation mainly provides upward pulling bearing capacity, and the problems that the bearing capacity of a single foundation is insufficient, large foundation construction machinery cannot enter a field, and the construction cost is high can be solved;
4. a plurality of micro pile-anchor rod foundations are integrated through the steel truss bearing platform, and therefore large bearing capacity can be provided.
Drawings
FIG. 1 is a sectional view of a prefabricated bearing platform type micro pile-anchor rod composite foundation in the embodiment;
FIG. 2 is a top view of the precast pile cap type micro pile-anchor rod composite foundation in the embodiment;
FIG. 3 is a schematic view of drilling and reaming in an embodiment;
fig. 4 is a schematic connection diagram of the steel truss bearing platform, the tower foot and the miniature pile-anchor rod foundation in the embodiment.
Description of the reference symbols
1 is a micro pile; 2 is a full-length bonding type anchor rod; 3 is a screw-thread steel rod; 4 is grouting body; 5 is a main reinforcement of the micro pile; 6 is a concrete protective layer; 7, drilling an anchor rod; 8 is an enlarged hole; 9 is the upper soil layer thickness; 10 is the lower strata thickness; 11 is a steel truss bearing platform, 12 is a tower foot, and 13 is a bolt.
Detailed Description
The present invention is described in further detail below with reference to examples.
The embodiment provides a prefabricated bearing platform type micro pile-anchor rod composite foundation, as shown in fig. 1, fig. 2 and fig. 4, which comprises a micro pile-anchor rod foundation and a steel truss bearing platform 11, wherein one steel truss bearing platform 11 is fixed on a plurality of micro pile-anchor rod foundations, and a plurality of micro pile-anchor rod foundations can be combined into a large foundation through the steel truss bearing platform 11, so that greater bearing capacity can be provided. One power transmission iron tower is provided with 4 tower feet 12, 4-5 miniature pile-anchor rod foundations are arranged below each tower foot 12, and the miniature pile-anchor rod foundations are connected with the tower feet 12 through steel truss bearing platforms 11. The steel truss bearing platform 11 is fixedly connected with the tower legs 12 and the miniature pile-anchor rod foundation through bolts 13.
The miniature pile-anchor rod foundation comprises a miniature pile 1, a threaded steel rod 3 and a grouting body 4, wherein the lower part of the threaded steel rod 3 is wrapped by the grouting body 4 to jointly form a full-length bonding type anchor rod 2, and the upper part of the threaded steel rod 3 penetrates through the miniature pile 1 and serves as a part of the miniature pile 1. The micro pile 1 is a concrete cast-in-place pile, the length of the pile is 3-6 m, and the diameter is 150-400 mm. The strength of the pile body concrete is C25-C40, the thickness of the steel bar protection layer 6 is 35mm, the number of main bars 5 of the miniature pile is not less than 3, the diameter of each main bar is not less than 12mm, and the total sectional area of the steel bars meets the requirement of uplift force.
The upper part of the deformed steel bar 3 can be regarded as a part of the main reinforcement 5 of the miniature pile, the deformed steel bar 3 generally comprises 1-3, and is arranged at the central position of the miniature pile 1, if a plurality of deformed steel bars 3 are arranged in a quincunx shape, the length of the full-length bonding anchor rod 2 is 6-12 m, and the steel type of the deformed steel bar can adopt HRB335 and HRB400. The grouting body 4 is made of cement-based grouting material, and for the working conditions of sulfate corrosion stratum and underground water environment, sulfate-resistant cement should be adopted, the pH value of water is not less than 4.0, insoluble substances are less than 2000mg/L, soluble substances are less than 2000mg/L, chlorides are less than 350mg/L, sulfates are less than 600mg/L, and sulfides are less than 100mg/L.
The miniature pile-anchor rod foundation can provide the bearing capacity of pressing down, leveling and pulling up for the power transmission iron tower, wherein the bearing capacity of pressing down and leveling is mainly provided by the miniature pile 1, and the bearing capacity of pulling up is mainly provided by the full-length bonding type anchor rod 2.
The scheme is explained by combining the practical construction case.
The parameters of rock-soil layers of a certain upper and lower rock stratum are shown in table 1, the annual average underground water level is-1 m, and the highest water level can reach 0m. A single tower foot of a certain power transmission line corner tower needs to provide 3000kN uplift force, and because the miniature pile 1 is embedded into rocks during construction, the downward pressing bearing capacity can completely meet the requirement, the calculation of the downward pressing bearing capacity is not considered for the moment. 4 micro pile-anchor rod foundations are arranged under each tower foot, so that the single micro pile-anchor rod foundation needs to provide 750kN of uplift bearing capacity. The compressive strength of the grouting body is taken as 30kPa, the standard value of the bonding strength of the grouting body and the stroke basalt is 566.5kPa, and the micro pile is cast by C30 concrete.
Table 1: parameters of rock-soil layer of upper soil and lower rock stratum
Figure BDA0003827471480000051
The pile diameter, the pile length, the number of the deformed steel bars, the diameter of the deformed steel bars and the length of the deformed steel bars in the full-length bonding type anchor rod are continuously adjusted, the total upward pulling bearing capacity is calculated, the diameter of the pile is finally determined to be 400mm, the length of the pile is determined to be 6m, the number of the deformed steel bars is 3, the diameter of the deformed steel bars is 25mm, and the length of the deformed steel bars is 11m (6 m embedded in a miniature pile and 5m embedded in a rock mass).
The required minimum aperture of the deformed steel bar that three quincunx of transferring arranged is 54mm, for guaranteeing that the deformed steel bar transfers smoothly and there is sufficient slip casting body can wrap up the deformed steel bar, gets anchor rod drilling diameter 110mm.
The side friction force and the self weight of the miniature pile 1 can provide an upward pulling bearing force F1 as follows:
Figure BDA0003827471480000052
the anchor rod can provide the pull-up bearing force F 2 Is as follows F 2 = Π × 0.11 × 5 × 526.5 × 1=909.27kn; wherein 526.5kPa is the standard value of the bonding strength of the grouting body and the stroke basalt, and 0.11 is the diameter of the grouting body of 110mm.
The total pullout force was therefore 1093.27kN, which is greater than the pullout force value 750kN that needs to be provided.
The tensile resistance is calculated by continuously adjusting the number and the diameter of the main bars of the miniature pile, and finally 7 main bars of the miniature pile are taken, and three-grade steel with the diameter of 22mm is adopted. Tension F bearable by main reinforcement at the moment z Comprises the following steps:
F z =0.25×Π×22 2 ×7×360÷1000=957kN;
tensile force F capable of being borne by three threaded steel rods m Comprises the following steps:
F m =0.25×Π×25 2 ×3×360÷1000=530kN;
the main reinforcement can bear 957kN which is larger than 750kN, meanwhile, the three deformed steel bars can bear 530kN, and the partial resistance serves as a safety margin.
The anchor bar and the grouting body have strong bondingThe degree is 900kPa, and the binding power between the anchor rod and the grouting body is F mz The bonding strength of the grout and the surrounding soil is 909.27Kn, and is larger than 3 × Π × 0.025 × 5 × 900=1059.75kn, so that the anchor bars are not separated from the grout when the anchor bars are damaged.
With reference to fig. 1 to 4, the construction of the precast bearing platform type micro pile-anchor rod composite foundation includes the following steps:
1) The anchor rod is drilled 7, the hole diameter is 110mm, the drilling depth is 11m, and the drilling hole penetrates into the rock mass by 6m;
2) The hole expanding machine is used for carrying out hole expanding construction on the upper portion of the drilled hole to form an expanded hole 8, the diameter of the expanded hole 8 is 400mm, the height of the expanded hole 8 is 5m, and the bottom of the expanded hole 8 is in contact with the top surface of the rock, so that the micro pile 1 enters the rock;
3) Using the deformed steel bar 3 as a bar body, and putting the deformed steel bar 3, a grouting pipe and the like to the bottom of the drill hole 7;
4) Grouting slurry to the bottom of the enlarged hole 8 through a grouting pipe;
5) Placing the reinforcement cage of the miniature pile, and pouring concrete into the miniature pile 1;
6) When the strength of the concrete in the micro pile 1 reaches C30, the micro pile can bear load;
7) After 4 micro-pile-anchor rod foundations are constructed, the micro-pile-anchor rod foundations are integrated through the steel truss bearing platform 11 to form a large foundation. The steel truss bearing platform 11 is connected with the tower legs 12 and the miniature pile-anchor rod foundation through bolts 13.
In this embodiment, 4 micropile-anchor rod composite foundations are arranged under the foot of each power transmission tower, and each power transmission tower needs to be provided with 16 micropile-anchor rod foundations.
The above-mentioned embodiments are merely illustrative of the inventive concept and are not intended to limit the scope of the invention, which is defined by the claims and the insubstantial modifications of the inventive concept can be made without departing from the scope of the invention.

Claims (7)

1. The utility model provides a compound basis of prefabricated cushion cap formula micropile-stock which characterized in that: the steel truss pile comprises a micro pile-anchor rod foundation and steel truss bearing platforms, wherein one steel truss bearing platform is fixed on a plurality of micro pile-anchor rod foundations;
the miniature pile-anchor rod foundation comprises a miniature pile, a threaded steel rod and a grouting body, wherein the lower part of the threaded steel rod is wrapped by the grouting body to form a full-length bonding type anchor rod, and the upper part of the threaded steel rod penetrates through the miniature pile and serves as a part of the miniature pile;
the miniature pile is a concrete cast-in-place pile, the diameter of the miniature pile is 150-400 mm, the pile length is 3-6 m, the pile body concrete strength is C25-C40, the thickness of the reinforcing steel bar protective layer is 35mm, the number of main reinforcing steel bars of the miniature pile is not less than 3, and the diameter of the main reinforcing steel bars is not less than 12mm;
the number of the deformed steel bars is 1-3, the deformed steel bars are arranged in the center of the micro pile, and the steel grade of the deformed steel bars adopts HRB335 and/or HRB400; if the screw-thread steel rods are multiple, the multiple screw-thread steel rods are arranged in a quincunx shape.
2. The prefabricated bearing platform type miniature pile-anchor rod composite foundation as claimed in claim 1, wherein: the length of the full-length bonding type anchor rod is 6-12 m.
3. A prefabricated bearing platform type micropile-anchor rod composite foundation as claimed in claim 1, wherein: and the steel truss bearing platform and the miniature pile-anchor rod foundation are fixedly connected through bolts.
4. A prefabricated bearing platform type micropile-anchor rod composite foundation as claimed in claim 1, wherein: and one steel truss bearing platform is fixed on the 4-5 miniature pile-anchor rod bases.
5. A prefabricated bearing platform type micropile-anchor rod composite foundation as claimed in claim 1, wherein: the grouting body is made of cement-based grouting materials, and for the working conditions of sulfate corrosion stratums and underground water environments, sulfuric acid resistant cement is adopted, the pH value of water is not less than 4.0, insoluble substances are less than 2000mg/L, soluble substances are less than 2000mg/L, chlorides are less than 350mg/L, sulfates are less than 600mg/L, and sulfides are less than 100mg/L.
6. A construction method of a prefabricated bearing platform type miniature pile-anchor rod composite foundation based on any one of claims 1 to 7, which is characterized by comprising the following steps of:
drilling a hole with an anchor rod drilling machine, wherein the aperture is 90-130 mm, and the drilled hole is driven into a rock stratum;
using a hole expanding machine to expand the upper part of the drilled hole to form an expanded hole, wherein the diameter of the expanded hole is 300-400 mm, and the height of the expanded hole is 3-6 m;
placing a threaded steel rod and a grouting pipe at the bottom of the drilled hole, wherein the top of the threaded steel rod is positioned above the top of the enlarged hole, then grouting, and injecting slurry to the bottom of the enlarged hole;
putting down the mini pile reinforcement cage, and pouring concrete;
after a plurality of micro pile-anchor rod foundations are constructed, the micro pile-anchor rod foundations are integrated through a steel truss bearing platform to form a large foundation.
7. The construction method of the prefabricated bearing platform type micro pile-anchor rod composite foundation as claimed in claim 6, wherein: the bottom of the enlarged hole contacts the top surface of the rock.
CN202211063873.8A 2022-09-01 2022-09-01 Prefabricated bearing platform type miniature pile-anchor rod composite foundation and construction method thereof Pending CN115288119A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211063873.8A CN115288119A (en) 2022-09-01 2022-09-01 Prefabricated bearing platform type miniature pile-anchor rod composite foundation and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211063873.8A CN115288119A (en) 2022-09-01 2022-09-01 Prefabricated bearing platform type miniature pile-anchor rod composite foundation and construction method thereof

Publications (1)

Publication Number Publication Date
CN115288119A true CN115288119A (en) 2022-11-04

Family

ID=83831930

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211063873.8A Pending CN115288119A (en) 2022-09-01 2022-09-01 Prefabricated bearing platform type miniature pile-anchor rod composite foundation and construction method thereof

Country Status (1)

Country Link
CN (1) CN115288119A (en)

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3140159U (en) * 2007-12-26 2008-03-13 三協フロンテア株式会社 Steel frame foundation for unit house
KR20090006910A (en) * 2007-07-13 2009-01-16 김정인 Connection method of micropile cap to existing concrete footing structure, reinforced method using same and structure thereof
RU2008129395A (en) * 2008-07-18 2010-01-27 Общества с ограниченной ответственностью "МПО РИТА" (RU) METHOD FOR MANUFACTURING AN ASSEMBLY OF A PILE WITH A EXISTING FOUNDATION UNDER IT AMPLIFICATION (OPTIONS)
US20140161539A1 (en) * 2012-12-07 2014-06-12 Anoop Kumar Arya Soil anchor footing
CN106661856A (en) * 2014-09-17 2017-05-10 韩国电力公社 Transmission tower foundation using micropile
CN108560349A (en) * 2018-06-14 2018-09-21 中国电建集团成都勘测设计研究院有限公司 The high embankment retaining structure in soft clay area
CN108914961A (en) * 2018-08-03 2018-11-30 福州铭林钢塔钢构制造有限公司 Using the communication iron tower foundation and construction method of Screw Anchor
CN109930609A (en) * 2019-04-09 2019-06-25 大连交通大学 A kind of campshed composite supporting construction and its construction method for upper-soft lower-hard ground
CN210395410U (en) * 2019-06-24 2020-04-24 中国电力工程顾问集团西南电力设计院有限公司 Transmission tower pile foundation suitable for mountain area precipitous topography area horizontal stock
CN210395409U (en) * 2019-06-24 2020-04-24 中国电力工程顾问集团西南电力设计院有限公司 Transmission tower lotus-shaped pile foundation suitable for mountainous area steep terrain and combination thereof
CN211898463U (en) * 2020-03-20 2020-11-10 西安公路研究院 Reinforcing device combining micro-steel pipe pile and anchor rod
CN112459103A (en) * 2020-11-27 2021-03-09 中国电建集团贵州电力设计研究院有限公司 Iron tower pile foundation structure and preparation method thereof
CN113047329A (en) * 2021-05-17 2021-06-29 国网福建省电力有限公司泉州供电公司 Plum-blossom-shaped pile foundation anchor rod composite foundation structure and construction method thereof
CN114086576A (en) * 2021-12-02 2022-02-25 深圳市岩土综合勘察设计有限公司 Steel pipe micro pile and construction method for reinforcing filled slope by using micro pile
CN216893755U (en) * 2022-01-28 2022-07-05 湖北省电力勘测设计院有限公司 Mountain area combination formula transmission tower encloses anchor pier foundation structure
CN218233442U (en) * 2022-09-01 2023-01-06 绍兴大明电力设计院有限公司 Prefabricated bearing platform type miniature pile-anchor rod composite foundation

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090006910A (en) * 2007-07-13 2009-01-16 김정인 Connection method of micropile cap to existing concrete footing structure, reinforced method using same and structure thereof
JP3140159U (en) * 2007-12-26 2008-03-13 三協フロンテア株式会社 Steel frame foundation for unit house
RU2008129395A (en) * 2008-07-18 2010-01-27 Общества с ограниченной ответственностью "МПО РИТА" (RU) METHOD FOR MANUFACTURING AN ASSEMBLY OF A PILE WITH A EXISTING FOUNDATION UNDER IT AMPLIFICATION (OPTIONS)
US20140161539A1 (en) * 2012-12-07 2014-06-12 Anoop Kumar Arya Soil anchor footing
CN106661856A (en) * 2014-09-17 2017-05-10 韩国电力公社 Transmission tower foundation using micropile
CN108560349A (en) * 2018-06-14 2018-09-21 中国电建集团成都勘测设计研究院有限公司 The high embankment retaining structure in soft clay area
CN108914961A (en) * 2018-08-03 2018-11-30 福州铭林钢塔钢构制造有限公司 Using the communication iron tower foundation and construction method of Screw Anchor
CN109930609A (en) * 2019-04-09 2019-06-25 大连交通大学 A kind of campshed composite supporting construction and its construction method for upper-soft lower-hard ground
CN210395410U (en) * 2019-06-24 2020-04-24 中国电力工程顾问集团西南电力设计院有限公司 Transmission tower pile foundation suitable for mountain area precipitous topography area horizontal stock
CN210395409U (en) * 2019-06-24 2020-04-24 中国电力工程顾问集团西南电力设计院有限公司 Transmission tower lotus-shaped pile foundation suitable for mountainous area steep terrain and combination thereof
CN211898463U (en) * 2020-03-20 2020-11-10 西安公路研究院 Reinforcing device combining micro-steel pipe pile and anchor rod
CN112459103A (en) * 2020-11-27 2021-03-09 中国电建集团贵州电力设计研究院有限公司 Iron tower pile foundation structure and preparation method thereof
CN113047329A (en) * 2021-05-17 2021-06-29 国网福建省电力有限公司泉州供电公司 Plum-blossom-shaped pile foundation anchor rod composite foundation structure and construction method thereof
CN114086576A (en) * 2021-12-02 2022-02-25 深圳市岩土综合勘察设计有限公司 Steel pipe micro pile and construction method for reinforcing filled slope by using micro pile
CN216893755U (en) * 2022-01-28 2022-07-05 湖北省电力勘测设计院有限公司 Mountain area combination formula transmission tower encloses anchor pier foundation structure
CN218233442U (en) * 2022-09-01 2023-01-06 绍兴大明电力设计院有限公司 Prefabricated bearing platform type miniature pile-anchor rod composite foundation

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
吕庆: ""上拔-水平荷载作用下锚索承台基础受力变形特性"", 《湖南大学学报》, 25 July 2022 (2022-07-25) *
木林隆: "《基坑工程》", 机械工业出版社, pages: 84 *
李琴: ""新型基础在输电线路设计中的应用研究"", 《流体测量与控制》, 22 June 2022 (2022-06-22), pages 84 *

Similar Documents

Publication Publication Date Title
CN218233442U (en) Prefabricated bearing platform type miniature pile-anchor rod composite foundation
CN205225280U (en) A combined supporting structure that is used for steel -pipe pile bar planting tunnel composite lining of soft base
CN102561377A (en) Seismic-resistant-columned rock bolt foundation with enlarged toe and construction method of seismic-resistant-columned rock bolt foundation with enlarged toe
CN108842792B (en) Layered lifting and unloading type ground pulling anchor rod and construction method
CN111593757B (en) Line pole tower loop pile anchor composite foundation suitable for karst region and construction method thereof
CN201151920Y (en) Floating-resistant ground pit structure
CN113026760A (en) Combined type supporting pile for double-element foundation pit of soil and rock and construction method thereof
CN201502065U (en) Anchor rod joint excavation compound basis
CN205576957U (en) Stake end pilework
CN115288119A (en) Prefabricated bearing platform type miniature pile-anchor rod composite foundation and construction method thereof
CN102286971A (en) Concrete-filled steel tube core column socketed pile
CN113818474A (en) Assembly type bearing platform anchor cable foundation of power transmission tower and construction method
CN205205848U (en) Cavity gravity type marine wind power basis
CN107447775A (en) Landslide disaster body makes ground draining reinforced earth retaining wall structure
CN113431075A (en) Herringbone pile anchor assembly type foundation suitable for low-voltage power transmission line
CN111910671A (en) Prestressed anchor rod combined excavation composite foundation and construction method thereof
CN102444131B (en) Foundation pit support method
CN201495554U (en) Anchor bolt combination excavating compound base
CN220486413U (en) Microporous bored concrete pile rock anchor rod composite foundation of photovoltaic power station
CN106013216B (en) A kind of passive Stress Control deformation of wall formula barricade and its construction method
CN107642083A (en) Post-tensioned prestressing continuous underground wall structure and construction method with pull bar
CN212153412U (en) Anchor pulling anti-slide pile suitable for karst cavity
CN217299049U (en) Prestress pressure type anti-floating anchor rod with free section and anchoring section anchoring body
CN214831860U (en) Structure for improving bearing capacity of pier
CN216586523U (en) Multi-section head-expanding body-expanding anti-floating anchor rod

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination