CN107447775A - Landslide disaster body makes ground draining reinforced earth retaining wall structure - Google Patents

Landslide disaster body makes ground draining reinforced earth retaining wall structure Download PDF

Info

Publication number
CN107447775A
CN107447775A CN201710677037.1A CN201710677037A CN107447775A CN 107447775 A CN107447775 A CN 107447775A CN 201710677037 A CN201710677037 A CN 201710677037A CN 107447775 A CN107447775 A CN 107447775A
Authority
CN
China
Prior art keywords
rib
draining
panel
drainage column
reinforced earth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710677037.1A
Other languages
Chinese (zh)
Inventor
殷跃平
王文沛
闫金凯
张楠
朱赛楠
魏云杰
高杨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA INSTITUTE FOR GEO-ENVIRONMENTAL MONITORING
Original Assignee
CHINA INSTITUTE FOR GEO-ENVIRONMENTAL MONITORING
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA INSTITUTE FOR GEO-ENVIRONMENTAL MONITORING filed Critical CHINA INSTITUTE FOR GEO-ENVIRONMENTAL MONITORING
Priority to CN201710677037.1A priority Critical patent/CN107447775A/en
Publication of CN107447775A publication Critical patent/CN107447775A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

Landslide disaster body makes ground draining reinforced earth retaining wall structure and is related to reinforced earth bulkhead support technology field.The present invention is one of two kinds of structural shapes;The first includes:Cap stone, rib post, draining panel, rib type rib tape, basis;Draining panel (3) contains osculum (3 1), and osculum is arranged in the middle and lower part of draining panel (3);Include for second:Cap stone (1), rib type rib tape (4), basic (5), drainage column (6), lattice plate (7), lattice girder (8);Drainage column contains draining floral tube (6 1), and draining floral tube (6 1) is arranged in the middle and lower part of drainage column.Rib type rib tape includes outer anchor head (4 1) and anchor cable (4 2).The present invention improves the drainability of reinforced earth bulkhead using draining panel or drainage column, reduces the water pressure increase because of caused by impeded drainage;Rigid rib band can resist certain differential settlement, and rib type structure and anchor cable in rib tape, further increase the pulling force of horizontal direction, prevent soil body slipping to deform.

Description

Landslide disaster body makes ground draining reinforced earth retaining wall structure
Technical field
The present invention relates to a kind of reinforced earth bulkhead support technology, is developed with making in particular for current landslide disaster body High roadbed, the super large earth volume of middle appearance and the draining reinforced earth retaining wall structure used, belong to hazards control safe practice Field, it is widely used in the preventing and treating that landslide disaster body makes tall earth fill in ground.
Background technology
In recent years, capacity wretched insufficiency in soil constrains the construction and development in city, in all parts of the country mostly by using " cutting Mountain, fill out ditch, make ground, build city " the methods of carry out the utilization in landslide disaster body soil to increase land used.But in engineering construction High embankment is frequently encountered, not only easily activates original natural geologic hazard, also newborn numerous artificial hazardous locations.This Outside, after primitive groove road is filled and led up, if charge for remittance row in upstream, which leads, not in time, also results in the serious subsidence of foundations, in addition slope instability, increase Geological disaster risk.It is general more using schemes such as barricade, friction piles to prevent above-mentioned calamity source.
Wherein, Construction of Reinforced Earth Retaining Walls is easy, quick, economical, has gradually applied to landslide disaster body and has made high roadbed in ground The preventing and treating of side slope, especially obtain significant comprehensive benefit in reservoir area of Three Gorges Deng Di high embankments area.However, the fortune for passing through the several years OK, traditional reinforced earth bulkhead deforms to some extent, or even destroys, and has threatened the safety of resident.
Impeded drainage tends to cause the water pressure in banketing to increase in reinforced earth bulkhead filler, in addition, filler and face Relative settlement between plate, bar strip with panel junction stress concentration, the actual tension of rib tape is far longer than its design Allowable tensile stress, then cause the rupture failure of rib tape, these are all the main originals for causing reinforced earth bulkhead deformation failure Cause.Therefore there is an urgent need to study a kind of new draining reinforced earth retaining wall structure, the draining and rib tape for lifting reinforced earth bulkhead resist Damage capability.
Landslide disaster body, which makes reduction geological disaster risk in ground, has important social effect and economic value.China Shan Ground pilot is made in the ground such as west, Zhejiang, Fujian, Hubei by landslide disaster body, has greatly expanded land used, but largely occur simultaneously High slope, high roadbed geological disaster risk should not also be ignored.In addition, landslide disaster body is used for the construction pair on airport, high ferro with making High slope, the deformation of high roadbed Rock And Soil propose more strict requirements.
The content of the invention
The purpose of the present invention aiming above mentioned problem existing for prior art, by set rib type rib tape, draining panel, The structures such as drainage column, a kind of new draining reinforced earth retaining wall structure is proposed, so as to lift the draining of reinforced earth bulkhead and rib tape Survivability.
The purpose of the present invention and solve its technical problem and can be achieved through the following technical solutions.
Ground draining reinforced earth retaining wall structure is made according to landslide disaster body proposed by the present invention, including:Two kinds of structural shapes.
Landslide disaster body makes ground draining reinforced earth retaining wall structure, it is characterised in that:For one of following two structural shapes;
The first structural shape includes:Cap stone (1), rib post (2), draining panel (3), rib type rib tape (4), basic (5);Rib type muscle Band (4) includes outer anchor head (4-1) and anchor cable (4-2);Draining panel (3) contains osculum (3-1), and osculum (3-1) is arranged In the middle and lower part of draining panel (3);Rib post (2) is located on the outside of draining panel (3), and rib type rib tape (4) stream line (4-2) passes through row Water panel (3) preformed hole, it is anchored on the outside of rib post (2), i.e., outer anchor head (4-1);
Second of structural shape includes:Cap stone (1), rib type rib tape (4), basic (5), drainage column (6), lattice plate (7), lattice Structure beam (8);Drainage column (6) contains draining floral tube (6-1), and draining floral tube (6-1) is arranged in the middle and lower part of drainage column (6);Its In, rib type rib tape (4) includes outer anchor head (4-1) and anchor cable (4-2);Rib type rib tape (4) stream line (4-2) is directly and drainage column (6) connect, outer anchor head (4-1) is on the hollow shaft inwall of drainage column (6);Drainage column (6) both sides are provided with lattice plate (7) and lattice Structure beam (8).Draining panel contains osculum, and drainage column contains draining floral tube, and osculum, draining floral tube are all respectively arranged in row The middle and lower part of water panel, drainage column.
In the first described structural shape, rib post is located at draining panels outside, and rib type rib tape stream line passes through draining face Plate preformed hole, it is anchored on the outside of rib post, i.e., outer anchor head, alloy sleeve can be disposed in advance in draining panel preformed hole.
In second described of structural shape, rib type rib tape stream line is directly connected with drainage column, and outer anchor head is in drainage column On hollow shaft inwall.Together with lattice plate, the lattice girder of drainage column both sides are cast-in-place with drainage column.
In rib type rib tape, rib tape is the rigid structure of shape with ribbing, can be precast concrete or reinforced concrete structure.Rib Type rib tape is divided into common section and rib type section, and the thickness of rib type section is generally common 3 times of section thickness, vertically upward, downwardly projecting Consistency of thickness.Anchor cable anchor ring is located in rib type section.In addition, the horizontal cross width of rib type rib tape is generally common section thickness 3~5 times.
Draining 5~10mm of bore dia of draining panel, and formula straggly is arranged.Osculum can be drilled with air drill.Panel is with filling out Grit loaded filter is set between soil.
Drainage column inner hollow, shaft inwall set draining floral tube, caliber 100mm, along the vertical spacing 1.0m of shaft.Row The section of water column can be that rectangle is alternatively circle.
The osculum of draining panel, the draining floral tube of drainage column, it is both needed to use permeable geotextiles.
Beneficial effect
Landslide disaster body of the present invention makes ground draining reinforced earth retaining wall structure, has the following effects that:
(1) drainability of reinforced earth bulkhead is improved using draining panel or drainage column, reduces and causes because of impeded drainage Water pressure increase;
(2) rigid rib band can resist certain differential settlement, and rib type structure and anchor cable in rib tape, further increase water Square to pulling force, prevent soil body slipping to deform.Steel strand wires can meet shearing strength and certain elongation percentage requirement in anchor cable.
(3) second of structural shape can also set up longer drainpipe in the present invention, drainpipe is connected with drainage pile, formation is matched somebody with somebody Cover drainage system.Wherein, the drainpipe other end, which is embedded in, makes ground sloping inner depths.
(4) alloy sleeve in draining panel preformed hole adds shear resistance of the rib tape between panel, prevents from protecting outside anchor cable Steel wire corrosion that sheath occurs by cutting, fracture.
(5) it is clear to administer program, it is workable;
In summary, the present invention technically has significant progress, and has obvious good effect, be really a novelty, Progressive, practical technical method.
Described above is only the general introduction of technical solution of the present invention, in order to better understand the technological means of the present invention, Simultaneously can be practiced according to the content of specification, and in order to allow the present invention above and other objects, features and advantages energy Enough become apparent, below especially exemplified by preferred embodiment, and coordinate accompanying drawing, describe in detail as follows.
Brief description of the drawings
Fig. 1 is that the landslide disaster body of the present invention makes ground draining reinforced earth bulkhead the first structural shape profile;
Fig. 2 is that the landslide disaster body of the present invention makes ground draining second of structural shape profile of reinforced earth bulkhead;
Fig. 3 is Fig. 1,2 middle rib type rib tape schematic diagrames;
Fig. 4 is the front elevation of the first structural shape of barricade in Fig. 1;
Fig. 5 is the front elevation of second of structural shape of barricade in Fig. 2.
1st, cap stone, 2, rib post, 3, draining panel, 4, rib type rib tape, 5, basis, 6, drainage column, 7, lattice plate, 8, lattice girder, 9, Banket, 3-1, osculum, 4-1, outer anchor head, 4-2, anchor cable, 6-1, draining floral tube
Embodiment
To further describe the present invention, ground draining reinforcement is made to landslide disaster body of the present invention with reference to the accompanying drawings and examples Native barricade and construction method are described in further detail.
Ground draining reinforced earth retaining wall structure profile is made as the landslide disaster body shown in Fig. 1,2 and is found out with reference to Fig. 3~5, The present invention includes two kinds of structural shapes, and the first structural shape includes:Cap stone, rib post, draining panel, rib type rib tape, basis;The Two kinds of structural shapes include:Cap stone, rib type rib tape, basis, drainage column, lattice plate, lattice girder.Wherein, rib type rib tape includes outer Anchor head, anchor cable.Draining panel contains osculum, and drainage column contains draining floral tube, and osculum, draining floral tube be all respectively arranged in The middle and lower part of draining panel, drainage column.In the first structural shape, rib post is located at draining panels outside, rib type rib tape stream line Through draining panel preformed hole, it is anchored on the outside of rib post, i.e., outer anchor head.In second described of structural shape, in rib type rib tape Anchor cable is directly connected with drainage column, and outer anchor head is on the hollow shaft inwall of drainage column.Lattice plate, the lattice girder of drainage column both sides Together with cast-in-place with drainage column.In rib type rib tape, rib tape is the rigid structure of shape with ribbing, can be that precast concrete or reinforcing bar mix Xtah Crude Clay structure.Rib type rib tape is divided into common section and rib type section, and the thickness of rib type section is generally common 3~4 times of section thickness, vertically to Upper, downwardly projecting consistency of thickness.Anchor cable anchor ring is located in rib type section.In addition, the horizontal cross width of rib type rib tape is general For 3~5 times of common section thickness.Draining 5~10mm of bore dia of draining panel, and formula straggly is arranged.Osculum can use air drill Drilling.Drainage column inner hollow, shaft inwall set draining floral tube, caliber 100mm, along the vertical spacing 1.0m of shaft.Draining Post can be that rectangle is alternatively circle.The osculum of draining panel, the draining floral tube of drainage column, it is both needed to use permeable geotextiles.
Embodiment 1:Construct regional situation:Certain landslide disaster Ti Zaodi new districts tall earth fill, basement rock are severely-weathered plaster Rock, filled slope 57m, fill material are angular limestone, the marl mass gravelly soil that excavation pick is abandoned, and design and are added using three-level Rib retaining wall structure, every grade of barricade is using the first type structure of the invention, i.e. drain bar+rib type rigid rib band structure.Specifically apply Work step is suddenly as follows.First step:Levelling of the land, foundation trench excavate;Second step:Construction lofting, basis pour;Third step:Peace Draining panel and rib post are filled, rib post is set every 5m, and panel is fixed using diagonal brace, and the level and inclination between strict control panel are missed Difference, and drilled by air drill, diameter 5mm osculum is formed, osculum sets double-deck permeable geotextiles by side of banketing;4th step Suddenly:Fill construction, maximum particle diameter of banketing must not exceed 15cm, and compaction in layers rolls;5th step:Lay rib type rib tape, rib Type rib tape can be prefabricated, keeps during installation rib tape horizontal, rib type section insertion compacted fill layer, and anchor cable is consolidated by panel preformed hole On the outside of rib post.Wherein the three~five step can be repeated in carrying out with elevation.
Embodiment 2:Construct regional situation:Certain landslide disaster body makes ground high ferro tall earth fill, and basement rock is fine sandstone, is filled out Soil thickness is 30m, and fill material is loess, and design uses multistage reinforced retaining wall structure, and every grade of barricade is using of the invention second Type structure, i.e. drainage column+rib type rigid rib band structure.Specific construction step is as follows.First step:Levelling of the land, foundation trench are opened Dig;Second step:Construction lofting, basis pour;Third step:Pour drainage column, lattice girder and lattice plate.Masterplate is disposed, is tied up Wire-tie, one-piece casting concrete, wherein in drainage column wall thickness 300mm, shaft sets draining floral tube, caliber 100mm, along post The vertical spacing 1.0m of body, is arranged in a circular formation, by first using air drill to drill, aperture 110mm, and then pre-buried aperture 100mm drainings Floral tube, permeable geotextiles are wrapped up in outside;Four steps:Fill construction, compaction in layers roll;5th step:Lay rib type rib tape, rib type Rib tape can be prefabricated, keeps during installation rib tape horizontal, rib type section insertion compacted fill layer, and anchor cable is fixed by panel preformed hole On the outside of rib post.Wherein the three~five step can be repeated in carrying out with elevation.
Content described in this specification embodiment is only enumerating to the way of realization of inventive concept, protection of the invention Scope is not construed as being only limitted to the concrete form that embodiment is stated, protection scope of the present invention is also and in art technology Personnel according to present inventive concept it is conceivable that equivalent technologies mean.
(1) drainability of reinforced earth bulkhead is improved using draining panel or drainage column, reduce because of impeded drainage and Caused water pressure increase;
(2) rigid rib band can resist certain differential settlement, and the angle of cut of rib tape and panel rises to about from destructible 45 ° 70 ° (wherein, 90 ° represent that rib tape is vertical with panel, and rib tape is without skew force).And rib type structure and anchor cable in rib tape, further The pulling force of horizontal direction is added, prevents soil body slipping to deform.Steel strand wires can meet that shearing strength is prolonged with certain in anchor cable Stretch rate requirement.
(3) second of structural shape can also set up longer drainpipe in the present invention, drainpipe is connected with drainage pile, formation is matched somebody with somebody Cover drainage system.Wherein, the drainpipe other end, which is embedded in, makes ground sloping inner depths.Drainage efficiency about 20~30% can be increased.
(4) alloy sleeve in draining panel preformed hole adds shear resistance of the rib tape between panel, prevents from protecting outside anchor cable Steel wire corrosion that sheath occurs by cutting, fracture so that originally the anchor cable life-span from possibility 1 year less than increasing to 10 years or so.

Claims (7)

1. landslide disaster body makes ground draining reinforced earth retaining wall structure, it is characterised in that:For one of following two structural shapes;
The first structural shape includes:Cap stone (1), rib post (2), draining panel (3), rib type rib tape (4), basic (5);Rib type muscle Band (4) includes outer anchor head (4-1) and anchor cable (4-2);Draining panel (3) contains osculum (3-1), and osculum (3-1) is arranged In the middle and lower part of draining panel (3);Rib post (2) is located on the outside of draining panel (3), and rib type rib tape (4) stream line (4-2) passes through row Water panel (3) preformed hole, it is anchored on the outside of rib post (2), i.e., outer anchor head (4-1);
Second of structural shape includes:Cap stone (1), rib type rib tape (4), basic (5), drainage column (6), lattice plate (7), lattice girder (8);Drainage column (6) contains draining floral tube (6-1), and draining floral tube (6-1) is arranged in the middle and lower part of drainage column (6);Wherein, rib Type rib tape (4) includes outer anchor head (4-1) and anchor cable (4-2);Rib type rib tape (4) stream line (4-2) directly connects with drainage column (6) Connect, outer anchor head (4-1) is on the hollow shaft inwall of drainage column (6);Drainage column (6) both sides are provided with lattice plate (7) and lattice girder (8)。
2. landslide disaster body according to claim 1 makes ground draining reinforced earth retaining wall structure, it is characterised in that:Described In a kind of structural shape, alloy sleeve is disposed in draining panel preformed hole in advance.
3. landslide disaster body according to claim 1 makes ground draining reinforced earth retaining wall structure, it is characterised in that:Described In two kinds of structural shapes, together with the lattice plate (7), lattice girder (8) of drainage column (6) both sides are cast-in-place with drainage column (6).
4. landslide disaster body according to claim 1 makes ground draining reinforced earth retaining wall structure, it is characterised in that:Described rib In type rib tape (4), rib tape is the rigid structure of shape with ribbing, is precast concrete or reinforced concrete structure;Rib type rib tape (4) It is divided into common section and rib type section, the thickness of rib type section is common 3 times of section thickness, consistency of thickness vertically upward, downwardly projecting;Anchor Rope (4-2) anchor ring is located in rib type section;The horizontal cross width of rib type rib tape (4) is 3~5 times of common section thickness.
5. landslide disaster body according to claim 1 makes ground draining reinforced earth retaining wall structure, it is characterised in that:Its feature exists In osculum (3-1) 5~10mm of diameter of described draining panel (3), and formula straggly is arranged;Draining panel and set between banketing Grit loaded filter.
6. landslide disaster body according to claim 1 makes ground draining reinforced earth retaining wall structure, it is characterised in that:Described row Water column (6) inner hollow, shaft inwall set draining floral tube (6-1), caliber 100mm, along the vertical spacing 1.0m of shaft;Draining Column section is rectangle or is circular.
7. landslide disaster body according to claim 1 makes ground draining reinforced earth retaining wall structure, it is characterised in that:Described row The osculum (3-1) of water panel (3), the draining floral tube (6-1) of drainage column (6), using permeable geotextiles.
CN201710677037.1A 2017-08-09 2017-08-09 Landslide disaster body makes ground draining reinforced earth retaining wall structure Pending CN107447775A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710677037.1A CN107447775A (en) 2017-08-09 2017-08-09 Landslide disaster body makes ground draining reinforced earth retaining wall structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710677037.1A CN107447775A (en) 2017-08-09 2017-08-09 Landslide disaster body makes ground draining reinforced earth retaining wall structure

Publications (1)

Publication Number Publication Date
CN107447775A true CN107447775A (en) 2017-12-08

Family

ID=60491929

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710677037.1A Pending CN107447775A (en) 2017-08-09 2017-08-09 Landslide disaster body makes ground draining reinforced earth retaining wall structure

Country Status (1)

Country Link
CN (1) CN107447775A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113982004A (en) * 2021-12-24 2022-01-28 太原理工大学 Anchor cable-reinforced soil combined soil retaining member and construction method thereof
WO2022247015A1 (en) * 2021-05-27 2022-12-01 中铁十九局集团第三工程有限公司 Retaining wall structure using corrugated plates and construction method therefor

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2470405Y (en) * 2001-03-02 2002-01-09 挡土墙结构有限公司 Anchored ribbed retaining wall
MY141660A (en) * 2004-06-07 2010-05-31 Angkatan Engineering Sdn Bhd Block panels and retaining walls constructed from such block panels
CN102016182A (en) * 2008-03-04 2011-04-13 泰瑞埃米国际公司 Flexible stabilizing strip intended to be used in reinforced soil constructions
CN103452130A (en) * 2013-08-20 2013-12-18 中铁第四勘察设计院集团有限公司 Prestressing force reinforcing mesh ribbing earth pillar plate type retaining wall
CN204590067U (en) * 2015-05-06 2015-08-26 黑龙江工程学院 A kind of novel reinforced earth bulkhead
CN205382507U (en) * 2016-01-29 2016-07-13 中冶集团武汉勘察研究院有限公司 Two -way anchored retaining wall by tie rods
CN106337434A (en) * 2016-08-30 2017-01-18 中国冶集团有限公司 Reinforced soil retaining wall and construction method thereof
CN106638673A (en) * 2016-09-22 2017-05-10 石家庄铁道大学 Construction method of combined supporting and retaining structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2470405Y (en) * 2001-03-02 2002-01-09 挡土墙结构有限公司 Anchored ribbed retaining wall
MY141660A (en) * 2004-06-07 2010-05-31 Angkatan Engineering Sdn Bhd Block panels and retaining walls constructed from such block panels
CN102016182A (en) * 2008-03-04 2011-04-13 泰瑞埃米国际公司 Flexible stabilizing strip intended to be used in reinforced soil constructions
CN103452130A (en) * 2013-08-20 2013-12-18 中铁第四勘察设计院集团有限公司 Prestressing force reinforcing mesh ribbing earth pillar plate type retaining wall
CN204590067U (en) * 2015-05-06 2015-08-26 黑龙江工程学院 A kind of novel reinforced earth bulkhead
CN205382507U (en) * 2016-01-29 2016-07-13 中冶集团武汉勘察研究院有限公司 Two -way anchored retaining wall by tie rods
CN106337434A (en) * 2016-08-30 2017-01-18 中国冶集团有限公司 Reinforced soil retaining wall and construction method thereof
CN106638673A (en) * 2016-09-22 2017-05-10 石家庄铁道大学 Construction method of combined supporting and retaining structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
上海市住房和城乡建设管理委员会科学技术委员会: "《公路与城市道路设计手册 下 第2版》", 31 March 2016 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022247015A1 (en) * 2021-05-27 2022-12-01 中铁十九局集团第三工程有限公司 Retaining wall structure using corrugated plates and construction method therefor
CN113982004A (en) * 2021-12-24 2022-01-28 太原理工大学 Anchor cable-reinforced soil combined soil retaining member and construction method thereof

Similar Documents

Publication Publication Date Title
CN103452147B (en) Self-balancing anchor counterweight broken pile forced-landing tilt correcting method
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN102518135B (en) Horizontal jet grouting soil anchor and castinplace pile Composite Foundation Pit supporting construction engineering method
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN106638673B (en) A kind of construction method of compound retaining structure
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN106759442A (en) A kind of single-pile elevated bearing-platform and anchor cable tower-crane foundation structure and its construction method
CN104631440B (en) A kind of existing large-section in-situ concrete pile strength core increases foundation pit supporting construction and constructional method
CN103031839A (en) Construction method of hand-dug piles
CN110685286A (en) Deep foundation pit supporting construction process for adjacent road under complex geological condition
CN105735345A (en) Composite type supporting and retaining structure and construction method adopting supporting and retaining structure
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN102330436A (en) Composite retaining structure and composite retaining method for half geotechnical layer ultradeep round spiral flow tank
CN107938685A (en) A kind of new diagonal brace composite support device
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN107447775A (en) Landslide disaster body makes ground draining reinforced earth retaining wall structure
CN109577322A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN205576957U (en) Stake end pilework
CN111042161A (en) Slope collapse high slope flexible processing structure and construction method thereof
CN110805049A (en) Construction method of mountain slope ultra-thickness spray anchor permanent supporting structure
CN206928296U (en) Pile pulling system
CN206376274U (en) A kind of single-pile elevated bearing-platform and anchor cable tower-crane foundation structure
CN206902710U (en) Retaining wall and counter-force open caisson platform pile pulling system
CN206902712U (en) Pile pulling recharge system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171208

WD01 Invention patent application deemed withdrawn after publication