CN114753357A - Construction method of underwater drilled pile - Google Patents

Construction method of underwater drilled pile Download PDF

Info

Publication number
CN114753357A
CN114753357A CN202210365860.XA CN202210365860A CN114753357A CN 114753357 A CN114753357 A CN 114753357A CN 202210365860 A CN202210365860 A CN 202210365860A CN 114753357 A CN114753357 A CN 114753357A
Authority
CN
China
Prior art keywords
pile
drilling
steel casing
steel
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210365860.XA
Other languages
Chinese (zh)
Inventor
程相盼
陈春生
陈锋
杨好波
吴保伟
王军鹏
霍猛
李志国
张明明
宋永鑫
任延克
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Seventh Group Co Ltd
Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd
Original Assignee
China Railway Seventh Group Co Ltd
Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Seventh Group Co Ltd, Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd filed Critical China Railway Seventh Group Co Ltd
Priority to CN202210365860.XA priority Critical patent/CN114753357A/en
Publication of CN114753357A publication Critical patent/CN114753357A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/40Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/665Mould-pipes or other moulds for making piles
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B21/00Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor
    • E21B21/01Arrangements for handling drilling fluids or cuttings outside the borehole, e.g. mud boxes
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B21/00Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor
    • E21B21/06Arrangements for treating drilling fluids outside the borehole
    • E21B21/063Arrangements for treating drilling fluids outside the borehole by separating components
    • E21B21/065Separating solids from drilling fluids
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/12Underwater drilling

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Physics & Mathematics (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Earth Drilling (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a construction method of underwater drilling pile, which comprises constructing an above-water operation platform, arranging steel casing cylinders in platform mounting holes, fixing the steel casing cylinders, grouping the steel casing cylinders, arranging a communicating pipe at the top of the same group of steel casing cylinders, arranging a drilling machine, a slurry circulating pump, a sand separator and corresponding pipelines on each group of steel casing cylinders in a matching way, constructing a slurry circulating system for drilling, starting the drilling machine, drilling and forming holes on one of the steel casing cylinders, arranging a sounding pipe led to the top of the platform, then pouring pile foundation concrete, carrying out pile foundation quality detection after pile formation, replacing the operating objects of the drilling machine, the slurry circulating pump and the sand separator, drilling and forming holes on the other steel casing cylinder of each group according to the fifth step, arranging the sounding pipe, pouring pile foundation concrete and detecting pile foundation quality, and finishing construction. The invention can realize the simultaneous construction of a plurality of drilling machines, greatly improves the construction efficiency and shortens the construction period.

Description

Construction method of underwater drilled pile
Technical Field
The invention relates to the technical field of underwater bored pile construction, in particular to a construction method of an underwater bored pile.
Background
The bored pile is a pile formed by mechanically boring a pile hole in foundation soil, placing a steel reinforcement cage therein, and pouring concrete. The construction of cast-in-situ bored piles is divided into two types, namely a slurry wall protection method and a full casing construction method, according to the difference of the selected wall protection. Wherein, the work progress of mud dado drilled pile does: leveling field → slurry preparation → pile casing embedding → working platform laying → drilling machine installation and positioning → drilling hole forming → hole cleaning and hole forming quality inspection → steel reinforcement cage lowering → underwater concrete pouring → pile casing extraction → quality inspection. When using the percussion drill to creep into the pore-forming, need constantly add mud to downthehole and prevent the hole that collapses, simultaneously, supporting mud pond and the sedimentation tank of setting up on work platform carries out mud circulation and takes out the sediment operation. When a plurality of impact drills are adopted for simultaneous operation, in order to adjust slurry indexes in time and ensure the slag discharging effect, the volumes/occupied areas of a slurry tank and a sedimentation tank need to be correspondingly increased. However, when the drilled pile is located in a river or a sea area, the construction platform is an overwater platform, the operation surface of the construction platform is limited, the construction cost can be greatly increased by arranging more mud ponds and sedimentation tanks, the operation can be usually carried out by only adopting one percussion drill, and the overall construction progress of a project is seriously influenced. Secondly, because the sounding pipe height that carries out pile foundation quality inspection is located the pile bolck mostly, and need demolish construction platform, beat the steel sheet pile and just can survey the pile after deep basal pit excavation, if find the pile foundation has quality problems, then need demolish the cofferdam again and set up construction platform and carry out the pile foundation and beat again, will prolong construction period greatly, increase cost simultaneously, the risk factor is too high.
Disclosure of Invention
In order to solve the above problems, the invention provides a construction method of a bored pile in water, which specifically adopts the following technical scheme:
the construction method of the underwater drilled pile comprises the following steps:
firstly, constructing an overwater operation platform, and forming mounting holes in the overwater operation platform;
secondly, drilling a steel casing with the bottom embedded in the riverbed in the mounting hole, wherein the top of the steel casing extends to a position above the working surface of the platform;
fixing the steel casing and grouping the steel casing into groups, wherein each group comprises two steel casings which are a working cylinder and a slurry circulating cylinder, and the top of the steel casing in the same group is provided with a communicating pipe;
fourthly, mounting a drilling machine, a slurry circulating pump, a sand separator and corresponding pipelines on each group of steel casing in a matched manner, and constructing a slurry circulating system for drilling;
fifthly, starting a drilling machine, drilling one of each group of steel casing to form a hole, installing an acoustic pipe led to the top of the platform, then performing pile foundation concrete pouring, and performing pile foundation quality detection after pile forming;
and sixthly, replacing the operation objects of the drilling machine, the slurry circulating pump and the sand separating machine, drilling a hole, installing a sound detection pipe, performing pile foundation concrete pouring and pile foundation quality detection on the other one of each group of steel casing according to the fifth step, and finishing construction.
The drilling machine is a percussion drill, and a mode of jumping and beating pile foundations at intervals is adopted during simultaneous working.
And the bottom of the steel casing is welded with an integral edge covering with the edge width of 50 cm.
The steel casing and the platform are connected through a channel steel short section in a welding mode, and a connecting system is welded between the tops of the adjacent steel casings.
The mud circulating system for drilling comprises a drilling machine drill bit arranged in the working barrel, a communicating pipe arranged between the working barrel and the mud circulating barrel, and a mud circulating pump arranged in the mud circulating barrel, wherein an outlet pipe of the mud circulating pump is communicated to the working barrel, and a suction pipe and a mud discharge pipe which are arranged in the mud circulating barrel and communicated with the sand distributor.
The method for installing the sounding pipe comprises the steps of arranging a pile foundation reinforcement cage main cage in a steel casing after drilling to form a hole, then installing the sounding pipe on the pile foundation reinforcement cage main cage, and guiding the sounding pipe to the top of a platform by adopting a mode of arranging an auxiliary cage in the steel casing.
The auxiliary cage is formed by welding four main reinforcements and one stirrup, and the diameter of the auxiliary cage is the same as that of the pile foundation reinforcement cage main cage.
According to the construction method of the underwater bored pile, the connecting system is arranged between the platform and the steel casing, so that the overall stability of the steel casing and the platform is ensured, the vibration influence generated when a plurality of impact drills are constructed simultaneously is reduced, and the safety risk is reduced; the mode that steel casing is divided into groups, the steel casing is communicated between groups, and the steel casing are respectively a working cylinder and a slurry circulating cylinder is adopted, so that the slurry circulation during drilling and pore forming is ensured under the condition that a slurry pool and a sedimentation tank are not additionally added, and meanwhile, a sand separator is adopted to separate the slurry in the slurry circulating cylinder, so that the efficiency of slurry separation and the qualification of slurry quality are ensured, the measures are favorable for reducing the construction cost, and secondly, a plurality of drilling machines can be arranged on a platform to carry out simultaneous construction on the drilling machines, so that the construction efficiency is greatly improved, and the construction period is shortened; moreover, with the mode that the sounding pipe is introduced to the platform top by the pile top, can carry out the pile foundation before the platform is not demolishd and detect, avoid the later stage to take place the risk that quality accident caused time limit for a project and cost increase.
Drawings
Figure 1 is a schematic view of the arrangement of the apparatus on the marine work platform of the present invention.
FIG. 2 is a first construction state diagram of a #2 steel casing and a #5 steel casing in FIG. 1.
FIG. 3 is a second construction state diagram of the #2 steel casing and the #5 steel casing in FIG. 1.
Detailed Description
The following describes embodiments of the present invention in detail with reference to the drawings, which are implemented on the premise of the technical solution of the present invention, and give detailed implementation manners and specific working procedures, but the scope of the present invention is not limited to the following embodiments.
As shown in fig. 1 to 3, the construction method of the underwater bored pile according to the present invention includes the steps of:
firstly, constructing an overwater operation platform M and arranging a mounting hole on the overwater operation platform M. In this embodiment, there are 12 mounting holes, and the mounting holes are arranged in 4 rows of 3 mounting holes (see fig. 1).
And secondly, drilling steel protection cylinders 1 into the riverbed through mounting holes, wherein the bottom of each steel protection cylinder 1 is welded with a whole covered edge with the edge width of 50cm, so that the deformation of the edge feet of the steel protection cylinders 1 is prevented, and the top of each steel protection cylinder 1 extends to the position above the operation surface of the platform, so that a mud circulating system is conveniently fixed and constructed.
And thirdly, uniformly welding four channel steel short sections 21 at the joint of each steel casing 1 and the platform M for fixing, and further welding channel steel or steel pipes between the tops of adjacent steel casings to serve as a connection system 22, so that the overall stability of the steel casings 1 and the platform M is enhanced, the vibration influence generated when multiple impact drills are constructed simultaneously is reduced, and the safety risk is reduced.
In order to achieve the purpose of simultaneous construction of a plurality of percussion drills, the steel casing barrels 1 are divided into groups, the steel casing barrels 1 in the groups are mutually communicated and are respectively a working barrel and a mud circulation barrel, and therefore occupied area and investment of additionally arranging a mud pit and a sedimentation tank are avoided. Specifically, in the present embodiment, every two adjacent steel casings 1 are divided into one group, and the tops of the steel casings 1 in each group are connected by installing a communicating pipe 3 (which is generally located above the corresponding connecting system 22).
And fourthly, installing a drilling machine 4, a slurry circulating pump 5, a sand dividing machine 6 and corresponding pipelines on each group of steel casing 1 in a matched manner to construct a slurry circulating system for drilling. The mud circulating system for drilling comprises a drilling machine 4 (selected percussion drill) drill bit 41 arranged in a working barrel, a communicating pipe 3 arranged between the working barrel and the mud circulating barrel, a mud circulating pump 5 arranged in the mud circulating barrel, an outlet pipe 51 of the mud circulating pump 5 communicated to the working barrel, and a suction pipe 61 and a mud discharge pipe which are arranged in the mud circulating barrel and communicated with a sand distributor 6.
And fifthly, starting the drilling machine 4, drilling a hole in one of the steel casing barrels 1 of each group, installing the sounding pipe 7 leading to the top of the platform, then pouring concrete into the pile foundation 8, and detecting the quality of the pile foundation 8 after the pile is formed.
Taking a #2 steel casing 1 and a #5 steel casing 1 in the same group as an example, wherein the #2 steel casing 1 is used as a working cylinder, and the #5 steel casing 1 is used as a slurry circulating cylinder, and the slurry circulating system for drilling adopted by the same is specifically as follows: the drill bit 41 is installed in the #2 steel protective cylinder 1, the sand distributor 6 is installed on one side of the #5 steel protective cylinder 1, the slurry circulating pump 5 is installed in the #5 steel protective cylinder 1, the communicating pipe 3 is arranged between the two steel protective cylinders 1, the outlet pipe 51 of the slurry circulating pump 5 is communicated into the #2 steel protective cylinder 1, and the suction pipe 61 and the slurry discharge pipe of the sand distributor 6 are communicated into the #5 steel protective cylinder 1 (see fig. 2).
When drilling and pore forming are carried out, slurry generated during drilling in the #2 steel protective cylinder 1 is conveyed to the #5 steel protective cylinder 1 through a communicating pipe 3 between the #5 steel protective cylinder and the #2 steel protective cylinder, a sand distributor 6 carries out suction separation on the slurry in the #5 steel protective cylinder 1 through a suction pipe 61, the discharged slag is discharged to a slag box, the standard-reaching slurry is conveyed back to the #5 steel protective cylinder 1 through a slurry discharge pipe, and then the standard-reaching slurry is conveyed back to the #2 steel protective cylinder 1 through an outlet pipe 51 of a slurry circulating pump 5 to complete slurry circulation.
After the #2 steel casing 1 finishes drilling and forming holes, the pile foundation reinforcement cage main cage 9 is arranged in the casing, then the acoustic pipe 7 is installed on the pile foundation reinforcement cage main cage 9, and the acoustic pipe 7 is led to the top of the platform M by adopting a mode of arranging the auxiliary cage 10 in the #2 steel casing 1. The auxiliary cage 10 is formed by welding four main ribs and one stirrup, and the diameter of the auxiliary cage 10 is the same as that of the pile foundation reinforcement cage main cage 9.
The mode of above-mentioned leading sounding pipe 7 to the platform top by the pile bolck can carry out the pile foundation before the platform is not demolishd and detect, avoids the risk that the quality accident caused time limit for a project and cost-push in the later stage.
And sixthly, replacing operation objects of the drilling machine 4, the slurry circulating pump 5 and the sand separating machine 6, drilling another one of each group of steel casing 1 to form a hole, installing the sounding pipe 7, and performing pile foundation concrete pouring and pile foundation quality detection to complete construction.
The above working process is illustrated by taking the #2 steel casing 1 and the #5 steel casing 1 of the same group as an example.
In the drilling hole forming operation, the #5 steel protective cylinder 1 is used as a working cylinder, and the #2 steel protective cylinder 1 is used as a slurry circulating cylinder, wherein the adopted slurry circulating system for drilling specifically comprises the following steps: the drill bit 41 is installed in the #5 steel casing 1, the sand distributor 6 is installed on one side of the #2 steel casing 1, the slurry circulating pump 5 is installed in the #2 steel casing 1, a communicating pipe 3 is arranged between the two steel casings 1, an outlet pipe 51 of the slurry circulating pump 5 is communicated into the #5 steel casing 1, and a suction pipe 61 and a slurry discharge pipe of the sand distributor 6 are communicated into the #2 steel casing 1 (see fig. 3).
When drilling and pore forming are carried out, slurry generated during drilling in the #5 steel protective cylinder 1 is conveyed to the #2 steel protective cylinder 1 through a communicating pipe 3 between the #5 steel protective cylinder and the #2 steel protective cylinder 1, a sand distributor 6 carries out suction separation on the slurry in the #2 steel protective cylinder 1 through a suction pipe 61, the discharged slag is discharged to a slag box, the standard-reaching slurry is conveyed back to the #2 steel protective cylinder 1 through a slurry discharge pipe, and then the standard-reaching slurry is conveyed back to the #5 steel protective cylinder 1 through an outlet pipe 51 of a slurry circulating pump 5 to complete slurry circulation.
When the six drilling machines 4 on the platform M work simultaneously, the drilling sequence should be planned in advance, and a mode of pile foundation interval jumping is adopted, so that not only is the construction of the next pile hole not influenced by the previous pile hole ensured, but also the moving distances of the drilling machines 4 are not too far and not interfered with each other.
It should be noted that in the description of the present invention, terms such as "front", "rear", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.

Claims (7)

1. A construction method of a bored pile in water is characterized by comprising the following steps:
firstly, constructing an overwater operation platform, and forming mounting holes in the overwater operation platform;
secondly, drilling a steel casing with the bottom embedded in the riverbed in the mounting hole, wherein the top of the steel casing extends to a position above the working surface of the platform;
thirdly, fixing the steel pile casings and grouping the steel pile casings, wherein each group comprises two steel pile casings which are a working cylinder and a slurry circulating cylinder, and a communicating pipe is arranged at the top of the steel pile casings in the same group;
Fourthly, installing a drilling machine, a slurry circulating pump, a sand separator and corresponding pipelines on each group of steel casing in a matched manner to construct a slurry circulating system for drilling;
fifthly, starting a drilling machine, drilling one of each group of steel casing to form a hole, installing a sounding pipe led to the top of the platform, then performing pile foundation concrete pouring, and performing pile foundation quality detection after pile forming;
and sixthly, replacing operation objects of the drilling machine, the slurry circulating pump and the sand separating machine, drilling and forming holes, installing the sounding pipe, performing pile foundation concrete pouring and pile foundation quality detection on the other one of each group of steel casing according to the fifth step, and completing construction.
2. The method for constructing a bored pile in water according to claim 1, wherein: the drilling machine is a percussion drill, and a mode of alternately jumping and beating pile foundations is adopted when the drilling machine works simultaneously.
3. The method for constructing a bored pile in water according to claim 1, wherein: and the bottom of the steel casing is welded with an integral edge covering with the edge width of 50 cm.
4. The method for constructing a bored pile in water according to claim 1, wherein: the steel casing and the platform are connected through channel steel short sections in a welded mode, and a connecting system is welded between the tops of the adjacent steel casings.
5. The method for constructing a bored pile in water according to claim 1, wherein: the mud circulating system for drilling comprises a drilling machine drill bit arranged in the working barrel, a communicating pipe arranged between the working barrel and the mud circulating barrel, and a mud circulating pump arranged in the mud circulating barrel, wherein an outlet pipe of the mud circulating pump is communicated to the working barrel, and a suction pipe and a mud discharge pipe which are arranged in the mud circulating barrel and communicated with the sand distributor.
6. The method for constructing a bored pile in water according to claim 1, wherein: the method for installing the sounding pipe comprises the steps of arranging a pile foundation reinforcement cage main cage in a steel casing after drilling to form a hole, then installing the sounding pipe on the pile foundation reinforcement cage main cage, and guiding the sounding pipe to the top of a platform by adopting a mode of arranging an auxiliary cage in the steel casing.
7. The method of constructing a bored pile in water according to claim 6, wherein: the auxiliary cage is formed by welding four main reinforcements and one stirrup, and the diameter of the auxiliary cage is the same as that of the pile foundation reinforcement cage main cage.
CN202210365860.XA 2022-04-08 2022-04-08 Construction method of underwater drilled pile Pending CN114753357A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210365860.XA CN114753357A (en) 2022-04-08 2022-04-08 Construction method of underwater drilled pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210365860.XA CN114753357A (en) 2022-04-08 2022-04-08 Construction method of underwater drilled pile

Publications (1)

Publication Number Publication Date
CN114753357A true CN114753357A (en) 2022-07-15

Family

ID=82328964

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210365860.XA Pending CN114753357A (en) 2022-04-08 2022-04-08 Construction method of underwater drilled pile

Country Status (1)

Country Link
CN (1) CN114753357A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116733392A (en) * 2023-08-15 2023-09-12 吉林市政建设集团有限公司 Pile foundation slurry circulation system of water platform

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002285555A (en) * 2001-03-26 2002-10-03 Toyo Constr Co Ltd Underwater concrete placing method and underwater concrete placing apparatus
CN106320333A (en) * 2016-09-27 2017-01-11 中交天航南方交通建设有限公司 Row type water cast-in-place pile device and construction method
CN107386285A (en) * 2017-08-03 2017-11-24 中铁六局集团有限公司 A kind of novel steel tube pile foundation rock borehole anchorage method
CN206917624U (en) * 2017-06-16 2018-01-23 武汉市市政建设集团有限公司 A kind of mud circulating system for water Bridge bored pile construction
WO2018045772A1 (en) * 2016-09-09 2018-03-15 中交第二航务工程局有限公司 Construction method and construction system for overwater bored piles based on incremental launching movement platform
CN109914399A (en) * 2019-03-21 2019-06-21 杭州公路工程监理咨询有限公司 A kind of pile base construction method of environmental protection
CN110359476A (en) * 2019-07-04 2019-10-22 中铁七局集团有限公司 A kind of construction method of steel sheet-pile cofferdam inner support and drilled pile steel pile casting installation operation platform
CN210918937U (en) * 2019-10-08 2020-07-03 中交第二航务工程局有限公司 Quick purification of drilling stake mud on water, cyclic utilization system
CN213233461U (en) * 2020-06-24 2021-05-18 中建四局土木工程有限公司 Slurry circulation system
CN113235576A (en) * 2021-04-29 2021-08-10 上海宝冶集团有限公司 Construction method for inner and outer casing of cast-in-situ bored pile in water source protected area

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002285555A (en) * 2001-03-26 2002-10-03 Toyo Constr Co Ltd Underwater concrete placing method and underwater concrete placing apparatus
WO2018045772A1 (en) * 2016-09-09 2018-03-15 中交第二航务工程局有限公司 Construction method and construction system for overwater bored piles based on incremental launching movement platform
CN106320333A (en) * 2016-09-27 2017-01-11 中交天航南方交通建设有限公司 Row type water cast-in-place pile device and construction method
CN206917624U (en) * 2017-06-16 2018-01-23 武汉市市政建设集团有限公司 A kind of mud circulating system for water Bridge bored pile construction
CN107386285A (en) * 2017-08-03 2017-11-24 中铁六局集团有限公司 A kind of novel steel tube pile foundation rock borehole anchorage method
CN109914399A (en) * 2019-03-21 2019-06-21 杭州公路工程监理咨询有限公司 A kind of pile base construction method of environmental protection
CN110359476A (en) * 2019-07-04 2019-10-22 中铁七局集团有限公司 A kind of construction method of steel sheet-pile cofferdam inner support and drilled pile steel pile casting installation operation platform
CN210918937U (en) * 2019-10-08 2020-07-03 中交第二航务工程局有限公司 Quick purification of drilling stake mud on water, cyclic utilization system
CN213233461U (en) * 2020-06-24 2021-05-18 中建四局土木工程有限公司 Slurry circulation system
CN113235576A (en) * 2021-04-29 2021-08-10 上海宝冶集团有限公司 Construction method for inner and outer casing of cast-in-situ bored pile in water source protected area

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
厉泽逸 等: "《港口工程桩基涉及与施工关键技术研究》", 华南理工大学出版社, pages: 279 - 280 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116733392A (en) * 2023-08-15 2023-09-12 吉林市政建设集团有限公司 Pile foundation slurry circulation system of water platform
CN116733392B (en) * 2023-08-15 2023-10-27 吉林市政建设集团有限公司 Pile foundation slurry circulation system of water platform

Similar Documents

Publication Publication Date Title
CN109487807B (en) Steel pipe pile cofferdam hole leading and replacement construction method
CN110528511A (en) A kind of the impact drilling pile construction method
CN109914399B (en) Environment-friendly pile foundation construction method
CN108842807A (en) A kind of construction technology of the embedding rock single pile of offshore wind power foundation embedded type
CN110359476B (en) Construction method of construction platform for mounting steel sheet pile cofferdam inner support and bored pile steel casing
CN210918937U (en) Quick purification of drilling stake mud on water, cyclic utilization system
CN114753357A (en) Construction method of underwater drilled pile
CN113737780A (en) Underwater rock-socketed concrete pile and construction method thereof
CN113550340A (en) Construction method of deepwater foundation of double-wall steel cofferdam without sealing bottom under deepwater rock entering condition
CN112761644A (en) Suspension sinking vertical shaft well completion process
CN113123388A (en) Grooving construction method
CN114108611B (en) Construction method of large-diameter concrete filled steel tube reducing pile foundation
CN110593258B (en) Reinforcing construction method and reinforcing structure for steel sleeve pile of existing building pile foundation
CN111236208A (en) Underground diaphragm wall foundation pit construction method
CN111827130A (en) Construction method of water bridge pile foundation and bearing platform without trestle
CN217105086U (en) Construction device for underwater pier drilling pile
CN114991668A (en) Construction device and method for open-circuit surface drilling of shallow gas drilling well of development well
CN114687749A (en) Tunnel full-section one-step forming construction method based on advanced pre-reinforcement
CN103015433A (en) Method for constructing super-large diameter round and square combination deep foundation pit
CN114482107A (en) Construction method of impervious wall
CN114183069A (en) Pile group drilling construction method for efficiently utilizing mud slurry
CN215290044U (en) Movable offshore oil fixing platform
CN113684889B (en) Structural system for pipe-jacking water taking in deep water area and construction method thereof
CN214738266U (en) Vertical jacking implementation structure in underwater tunnel suitable for hard stratum
CN218148449U (en) Fore shaft steel-pipe pile cofferdam suitable for rich water sand bed

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination