CN114737789A - Combined structure dismantling and external wall temporary reinforcing construction method - Google Patents

Combined structure dismantling and external wall temporary reinforcing construction method Download PDF

Info

Publication number
CN114737789A
CN114737789A CN202210470477.0A CN202210470477A CN114737789A CN 114737789 A CN114737789 A CN 114737789A CN 202210470477 A CN202210470477 A CN 202210470477A CN 114737789 A CN114737789 A CN 114737789A
Authority
CN
China
Prior art keywords
wall
construction method
steel
external
reinforcement construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210470477.0A
Other languages
Chinese (zh)
Inventor
马磊
张洪涛
全有维
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd filed Critical Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority to CN202210470477.0A priority Critical patent/CN114737789A/en
Publication of CN114737789A publication Critical patent/CN114737789A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/08Wrecking of buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/02Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means
    • E04G1/04Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means the members being exclusively poles, rods, beams, or other members of similar form and simple cross-section
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/26Strutting means for wall parts; Supports or the like, e.g. for holding in position prefabricated walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G25/02Shores or struts; Chocks non-telescopic

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention provides a combined structure dismantling and external wall temporary reinforcement construction method, which designs a structure dismantling and reinforcement construction method combining a steel structure and a steel pipe scaffold according to different requirements of old building dismantling and external wall protection, can effectively ensure the stability of an external wall when the internal structure of a building is dismantled, has simple integral construction process, easily obtained materials, low construction cost and wide applicability, and meets the requirements of external wall protection and reinforcement.

Description

Combined structure dismantling and external wall temporary reinforcing construction method
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a combined structure dismantling and outer wall temporary reinforcing construction method.
Background
With the development of national economy, the problem of leaving a previous batch of old buildings in the building market is urgently to be solved, at the moment, a 'city updating' project is gradually brought up to schedule, the functions of the previous batch of old buildings cannot meet the current use requirements, but the external facade style of the buildings represents the characteristics of a period and even has important artistic value. In the urban renovation project, the problem is faced, namely how to reinforce and retain the external facade wall body while the internal structure of the old building is dismantled and newly built.
The existing structure dismantling scheme is mature, and when the structure is dismantled, two conventional schemes for reserving the outer decorative wall are available; one is a construction method based on the steel pipe scaffold, the method is simple to operate and low in cost, but the steel pipe scaffold is low in self rigidity and limited in application range; the other is a construction method based on a steel structure, although the steel structure has large self rigidity and wide application range, the method is complex to operate and has higher manufacturing cost.
Disclosure of Invention
Aiming at the defects in the prior art, the invention provides a combined structure dismantling and external wall temporary reinforcement construction method, which is based on a mode of combining a steel structure and a steel pipe scaffold, can effectively ensure the stability of an external wall when the internal structure of a building is dismantled, is safer and more reliable in construction, and has the advantages of simple integral construction process, easily obtained materials and low construction cost.
The present invention achieves the above-described object by the following technical means.
A combined structure dismantling and outer wall temporary reinforcement construction method comprises the following steps:
step 1: constructing anchor piles along the periphery of the building structure to be dismantled, and driving the anchor piles into a foundation;
step 2: building an outer protective frame around the building structure to be dismantled;
and 3, step 3: arranging steel structure protection devices in a grid shape on the inner side and the outer side of the outer wall to be protected, and mutually connecting the grids on the inner side and the outer side of the outer wall into a whole;
and 4, step 4: rigidly connecting an inclined support at the anchor pile, and then connecting the other end of the inclined support with an outer protection frame;
and 5: a plurality of wall connecting supports are uniformly arranged on the outer protection frame from bottom to top at intervals, one end of each wall connecting support is fixed with the outer protection frame, and the other end of each wall connecting support is connected with the steel structure protection device;
and 6: the indoor support is erected, a layer of full-hall support frame is firstly erected, a floor type steel pipe scaffold is adopted as a frame body of the full-hall support frame, and the top of the full-hall support frame is tightly attached to a floor plate;
and 7: repeating the step 6, and erecting other layers of full-hall supporting frames;
and 8: the structure is demolishd from last down, at first demolishs roof structure, then demolishs top floor board and vertical post, demolishs lower floor board and cylinder structure again, at this in-process, remains the outer wall structure throughout and does not move.
Further, the anchor pile is an uplift anchor rod with the diameter of 15 cm.
Furthermore, the outer protection frame adopts a double-row steel pipe floor scaffold, the diameter of a steel pipe of the outer protection frame is 3cm, and the wall thickness is 2 mm.
Furthermore, the steel structure protection device adopts 14# channel steel, grids on the inner side and the outer side of the outer wall are connected into a whole through the 14# channel steel, and the mesh size formed by the channel steel is 1 multiplied by 1 m.
Further, the diagonal brace is formed by welding a plurality of light rectangular small square pipes, the square pipes for manufacturing the diagonal brace have the cross-sectional dimension of 5 x 5cm, the wall thickness of 2mm, and the cross-sectional dimension of 1 x 1 m.
Further, the diameter of the steel pipe in the one-layer full-framing support frame is 3cm, and the wall thickness is 2 mm.
Further, the wall connecting support is a No. 14 channel steel.
The invention has the following beneficial effects:
the invention designs a structure dismantling and reinforcing construction method combining a steel structure and a steel pipe scaffold according to different requirements of old building dismantling and outer wall protection, has simple process, convenient construction and easily obtained materials, can save the cost by 40 percent compared with the traditional construction method, improves the quality safety by 30 percent, has wide applicability and meets the requirement of outer wall protection and reinforcement.
Drawings
Fig. 1 is a schematic view of a combined structure dismantling and external wall temporary reinforcement construction structure according to the present invention.
In the figure: 1-anchor pile; 2-an external protective frame; 3-inclined support; 4-connecting wall to support; 5-outer wall; 6-a layer of full supporting frame; 7-floor plate; 8-vertical columns; 9-roof.
Detailed Description
The invention will be further described with reference to the following figures and specific examples, but the scope of the invention is not limited thereto.
In the description of the present invention, it should be understood that the terms "mounted," "connected," "fixed," and the like are used broadly, and may be, for example, a fixed connection, a detachable connection, or an integral connection, which may be a direct connection, an indirect connection through an intermediate medium, or a communication between two elements; the specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
The combined structure dismantling and external wall temporary reinforcing structure is shown in figure 1, and the concrete construction method is as follows:
step 1: constructing an anchor pile;
constructing anchor piles 1 along the periphery of a building structure to be dismantled by adopting special machinery, driving the anchor piles 1 into a foundation, wherein the anchor piles 1 are uplift anchor rods with the diameter of 15 cm;
step 2: constructing an outer protection frame 2;
the outer protection frame 2 adopts a double-row steel pipe floor scaffold and is erected around a building structure to be dismantled, the diameter of a steel pipe of the outer protection frame 2 is 3cm, and the wall thickness is 2 mm;
and step 3: constructing a steel structure protection device;
the steel structure protection device adopts 14# channel steel to form latticed arrangement on the inner side and the outer side of the outer wall 5 to be protected, the inner grid and the outer grid are connected into a whole through the 14# channel steel, and the mesh size of the grid formed by the channel steel is 1 multiplied by 1 m; the steel structure protection device can effectively prevent the outer wall 5 from being unstable in the dismantling construction process;
and 4, step 4: constructing an inclined support 3;
a plurality of light rectangular small square tubes are welded in a factory in advance to form an inclined support 3, then the inclined support is transported to a site for construction, one end of the inclined support 3 is rigidly connected with an anchor pile 1, and the other end of the inclined support is connected with an outer protective frame 2; the cross section of the small square tube for manufacturing the diagonal bracing 3 is 5 multiplied by 5cm, the wall thickness is 2mm, and the cross section of the diagonal bracing 3 is 1 multiplied by 1 m;
and 5: constructing a wall connecting support 4;
the wall connecting supports 4 are 14# channel steel, a plurality of wall connecting supports 4 are uniformly arranged on the outer protection frame 2 from bottom to top at intervals, one end of each wall connecting support 4 is fixed with the outer protection frame 2, and the other end of each wall connecting support 4 is connected with the steel structure protection device;
step 6: constructing a layer of full-space support frame 6;
after all the wall-connected supports 4 are erected, the indoor supports are erected, a layer of full-hall support frames 6 are erected, a floor type steel pipe scaffold is adopted as a frame body of the full-hall support frames 6, the diameter of a steel pipe is 3cm, the wall thickness is 2mm, and the top of the full-hall support frames 6 is ensured to be tightly attached to a floor plate 7;
and 7: sequentially building two or more layers of full-hall supporting frame structures according to the step 6;
and 8: each layer full hall support frame sets up the completion back, from last down begin to carry out the structure demolish, at first demolish roof 9 structure, then demolish top floor board 7 and vertical post 8, demolish lower floor board 7 and cylinder structure again, in this in-process, it is motionless to remain outer wall 5 structure all the time, at steel construction protection device, even wall supports 4, under outer protection frame 2 and bearing diagonal 3's effect, can not exert an influence to outer wall 5 when building inner structure demolishs, outer wall 5 can remain stable state all the time, whole work progress safe and reliable more.
The present invention is not limited to the above-described embodiments, and any obvious improvements, substitutions or modifications can be made by those skilled in the art without departing from the spirit of the present invention.

Claims (7)

1. A combined structure dismantling and outer wall temporary reinforcement construction method is characterized by comprising the following steps:
step 1: constructing anchor piles (1) along the periphery of a building structure to be dismantled, and driving the anchor piles (1) into a foundation;
step 2: erecting an outer protective frame (2) around a building structure to be dismantled;
and step 3: arranging steel structure protection devices in a grid shape on the inner side and the outer side of an outer wall (5) to be protected, and mutually connecting grids on the inner side and the outer side of the outer wall (5) into a whole;
and 4, step 4: rigidly connecting an inclined support (3) at the anchor pile (1), and then connecting the other end of the inclined support (3) with an outer protection frame (2);
and 5: a plurality of wall connecting supports (4) are uniformly arranged on the outer protection frame (2) at intervals from bottom to top, one end of each wall connecting support (4) is fixed with the outer protection frame (2), and the other end of each wall connecting support (4) is connected with a steel structure protection device;
step 6: the indoor support is erected, a layer of full-hall support frames (6) are firstly erected, the frame bodies of the full-hall support frames (6) adopt floor type steel pipe scaffolds, and the tops of the full-hall support frames (6) are tightly attached to a floor plate (7);
and 7: repeating the step 6, and erecting other layers of full-hall supporting frames;
and 8: the structure is dismantled from top to bottom, at first demolishs roof (9) structure, then demolishs top floor board (7) and vertical post (8), demolishs lower floor board (7) and cylinder structure again, at this in-process, remains outer wall (5) structure motionless throughout.
2. The combined type structure demolition and exterior wall temporary reinforcement construction method according to claim 1, wherein the anchor piles (1) are uplift anchors having a diameter of 15 cm.
3. The combined type structure demolition and temporary external wall reinforcement construction method according to claim 1, wherein the external protection frame (2) adopts a double-row steel pipe floor scaffold, the diameter of the steel pipe of the external protection frame (2) is 3cm, and the wall thickness is 2 mm.
4. The combined structure demolition and external wall temporary reinforcement construction method according to claim 1, wherein the steel structure protection device is 14# channel steel, the inner and outer grids of the external wall (5) are integrally connected to each other by 14# channel steel, and the grid mesh size formed by the channel steel is 1 x 1 m.
5. The combined type structure demolition and external wall temporary reinforcement construction method according to claim 1, wherein the diagonal brace (3) is fabricated by welding a plurality of light rectangular small square pipes, the square pipes used for fabricating the diagonal brace (3) have a sectional size of 5 x 5cm, a wall thickness of 2mm, and a sectional size of the diagonal brace (3) is 1 x 1 m.
6. Combined structural demolition and temporary reinforcement construction method for external walls according to claim 1, characterized in that the steel pipes in the one-storey hall supporting frames (6) have a diameter of 3cm and a wall thickness of 2 mm.
7. Combined structural demolition and temporary reinforcement construction method for external walls according to claim 1, characterized in that the wall-connecting supports (4) are 14# channel steel.
CN202210470477.0A 2022-04-28 2022-04-28 Combined structure dismantling and external wall temporary reinforcing construction method Pending CN114737789A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210470477.0A CN114737789A (en) 2022-04-28 2022-04-28 Combined structure dismantling and external wall temporary reinforcing construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210470477.0A CN114737789A (en) 2022-04-28 2022-04-28 Combined structure dismantling and external wall temporary reinforcing construction method

Publications (1)

Publication Number Publication Date
CN114737789A true CN114737789A (en) 2022-07-12

Family

ID=82285903

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210470477.0A Pending CN114737789A (en) 2022-04-28 2022-04-28 Combined structure dismantling and external wall temporary reinforcing construction method

Country Status (1)

Country Link
CN (1) CN114737789A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118207884A (en) * 2024-05-22 2024-06-18 北京建工四建工程建设有限公司 Existing building dismantling and newly-built building foundation pit supporting cross comprehensive construction method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH144520A (en) * 1930-04-13 1931-01-15 Rietmann Hermann Dismountable framework.
CN201554236U (en) * 2009-11-05 2010-08-18 上海市第一建筑有限公司 Retained exterior wall strengthening device
CN101832034A (en) * 2010-04-22 2010-09-15 上海市第一建筑有限公司 Construction method of whole reverse replacement of structure
JP2014148845A (en) * 2013-02-01 2014-08-21 Takenaka Komuten Co Ltd Outer wall-holding method in construction work accompanied with preservation of existing outer wall
CN107419918A (en) * 2017-07-27 2017-12-01 上海二十冶建设有限公司 A kind of Historical Buildings periphery single-layer frame retains method for dismounting
CN109339479A (en) * 2018-10-29 2019-02-15 东南大学 A kind of the inside replacing structure and its method of existing reinforced concrete building
CN209040526U (en) * 2018-10-25 2019-06-28 山西大同大学 A kind of exterior wall scaffold
CN113027118A (en) * 2021-03-01 2021-06-25 中建二局第三建筑工程有限公司 Can have enough to meet need and loose unilateral formwork steel support of piece together formula
CN214401884U (en) * 2020-09-03 2021-10-15 浙江东横建筑工程有限公司 Basement outer wall unilateral formwork stress system
WO2022077892A1 (en) * 2020-10-16 2022-04-21 上海建工四建集团有限公司 Outer wall reinforcing device and method in building reconstruction

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH144520A (en) * 1930-04-13 1931-01-15 Rietmann Hermann Dismountable framework.
CN201554236U (en) * 2009-11-05 2010-08-18 上海市第一建筑有限公司 Retained exterior wall strengthening device
CN101832034A (en) * 2010-04-22 2010-09-15 上海市第一建筑有限公司 Construction method of whole reverse replacement of structure
JP2014148845A (en) * 2013-02-01 2014-08-21 Takenaka Komuten Co Ltd Outer wall-holding method in construction work accompanied with preservation of existing outer wall
CN107419918A (en) * 2017-07-27 2017-12-01 上海二十冶建设有限公司 A kind of Historical Buildings periphery single-layer frame retains method for dismounting
CN209040526U (en) * 2018-10-25 2019-06-28 山西大同大学 A kind of exterior wall scaffold
CN109339479A (en) * 2018-10-29 2019-02-15 东南大学 A kind of the inside replacing structure and its method of existing reinforced concrete building
CN214401884U (en) * 2020-09-03 2021-10-15 浙江东横建筑工程有限公司 Basement outer wall unilateral formwork stress system
WO2022077892A1 (en) * 2020-10-16 2022-04-21 上海建工四建集团有限公司 Outer wall reinforcing device and method in building reconstruction
CN113027118A (en) * 2021-03-01 2021-06-25 中建二局第三建筑工程有限公司 Can have enough to meet need and loose unilateral formwork steel support of piece together formula

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
徐杨斌;朱林辉;王宇;凌旭辉;: "历史保护建筑保留外墙改造加固技术", 建筑结构, no. 1 *
杨敏;: "临时核心筒支撑结构在历史保护建筑改建中的应用", 建筑施工, no. 11 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118207884A (en) * 2024-05-22 2024-06-18 北京建工四建工程建设有限公司 Existing building dismantling and newly-built building foundation pit supporting cross comprehensive construction method

Similar Documents

Publication Publication Date Title
CN204826308U (en) Structure assembly type structure is pieced together in advance to prefabricated shaped steel concrete shear force wall
CN108612110B (en) Combined type supporting construction method for deep foundation pit of subway station
CN210622376U (en) Cultural relics building emergency reinforcing apparatus
CN105089178A (en) Fabricated building of pre-assembling structure of prefabricated section steel concrete shear wall
CN113266017B (en) Regulation and storage tank construction method based on 'permanent-face integrated' inner support structure of deep foundation pit
CN103122691A (en) Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method
CN114737789A (en) Combined structure dismantling and external wall temporary reinforcing construction method
CN111395745A (en) Basement outer wall single-face formwork supporting system and construction method thereof
CN109403339B (en) Deep foundation pit composite supporting structure combining double-row piles with center island method and supporting method thereof
CN107326932B (en) Quasi-semi-reverse construction method for underground garage
CN217923621U (en) Combined multilayer vertical self-stabilizing enclosure structure
CN111778990A (en) Permanent-temporary combined assembly type inner support system and construction method
CN207847150U (en) A kind of temporary facility for being used for structural demolition and rebuilding
CN107675871A (en) One kind is building rise long-span outrigger wall-connecting piece construction method
CN217758840U (en) Multichannel multilayer self-stabilization type foundation pit supporting device
CN103711123B (en) The construction method of bamboo joint type mortar pile
CN216339582U (en) Combined inclined support for foundation pit support
CN210887229U (en) Irregular foundation pit assembled steel strutting arrangement
CN212506301U (en) Support system in combination assembled forever
CN214195653U (en) Supporting structure for reinforcing existing adobe wall-wood roof house by using profile steel
CN203096746U (en) Reinforced rib soil restraining composite supporting structure
CN116043921B (en) Construction method for steel-concrete combined structure retaining wall of water supply and drainage top pipe well
CN220686089U (en) Composite supporting structure of miniature steel pipe pile of deep foundation pit
CN217298943U (en) Underground rainwater regulation pond deep basal pit inner supporting structure
CN219732015U (en) Single-side formwork supporting device for outer wall of foundation pit adjacent to building enclosure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination