CN114482562A - Installation method of embedded part of nuclear chemical storage well - Google Patents

Installation method of embedded part of nuclear chemical storage well Download PDF

Info

Publication number
CN114482562A
CN114482562A CN202210013341.7A CN202210013341A CN114482562A CN 114482562 A CN114482562 A CN 114482562A CN 202210013341 A CN202210013341 A CN 202210013341A CN 114482562 A CN114482562 A CN 114482562A
Authority
CN
China
Prior art keywords
installing
positioning steel
penetrating
embedded
storage well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210013341.7A
Other languages
Chinese (zh)
Other versions
CN114482562B (en
Inventor
余绪俊
梁超
陈水森
徐敬
吴闯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Nuclear Industry 24 Construction Co Ltd
Original Assignee
China Nuclear Industry 24 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Nuclear Industry 24 Construction Co Ltd filed Critical China Nuclear Industry 24 Construction Co Ltd
Priority to CN202210013341.7A priority Critical patent/CN114482562B/en
Publication of CN114482562A publication Critical patent/CN114482562A/en
Application granted granted Critical
Publication of CN114482562B publication Critical patent/CN114482562B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/41Connecting devices specially adapted for embedding in concrete or masonry

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a method for installing embedded parts of a nuclear chemical storage well, wherein the embedded parts used in the installation method comprise a bottom plate, penetrating parts, positioning steel plates, truss structures and a detection cover plate, the bottom plate is connected to the bottoms of the penetrating parts, the truss structures are erected among the penetrating parts, and the installation method comprises the following steps: a penetration mount, wherein the penetration mount comprises: manufacturing and installing a positioning steel plate; installing a penetrating piece; installing a bottom shaft; mounting an angle steel bracket; and measuring the penetration piece, namely measuring the central position and the elevation of the penetration piece one by one and adjusting the central position and the elevation one by one. The invention analyzes each part of the storage well, adopts a series of safe and reliable measures to ensure the high-precision installation of the upper embedded penetration piece, the lower shaft and the bottom plate, improves the efficiency and ensures the construction quality.

Description

Installation method of embedded part of nuclear chemical storage well
Technical Field
The invention relates to the technical field of nuclear power station construction, in particular to a method for installing embedded parts of a nuclear chemical storage well.
Background
At present, a storage well mainly comprises an upper embedded penetrating piece, a lower shaft, a bottom plate and a shielding plug, and has the advantages of large number of parts, large scale and high installation precision; wherein the whole installation process of the upper embedded penetration piece is crossed with the civil engineering depth; and (3) hoisting the lower shaft, if a conventional installation method is adopted, the working procedures are multiple, the efficiency is low, a large amount of labor is consumed, the construction period cannot be guaranteed, and the quality is not easy to control.
Disclosure of Invention
The invention provides a method for installing embedded parts of a nuclear chemical storage well, which aims to solve the technical problems of complex and complicated assembling process, difficult quality control and low assembling efficiency of the existing method for installing the storage well.
In order to achieve the purpose, the invention provides an embedded part installation method of a nuclear chemical storage well, the embedded part used in the installation method comprises a bottom plate, penetrating parts, a positioning steel plate, a truss structure and a detection cover plate, the bottom plate is connected to the bottoms of the penetrating parts, the truss structure is erected among the penetrating parts,
the installation method comprises the following steps:
S1: penetration installation
Wherein the penetration mount comprises:
S11: manufacturing and installing a positioning steel plate;
after the positioning steel plates are transported to the site, the positioning steel plates are directly laid on the primary and secondary keels, and the peripheries of the positioning steel plates are welded and fixed at the bottoms of the vertical ribs of the wall body by adopting carbon steel flat irons;
controlling a gap between the positioning steel plate and a lower flange of the penetrating piece, wherein the mounting gap is controlled to be 1-1.5 mm;
S12: installing a penetrating piece;
S2: installing a bottom shaft;
the foundation bolt is embedded in the concrete, the upper part of the foundation bolt penetrates through the bottom plate, the elevation of the bottom plate is finely adjusted through the leveling nut and the fastening nut, and then the shaft is hung on the bottom plate;
S3: installing a truss structure;
two ends of a truss structure are fixed on an angle steel truss column, the angle steel truss column is fixed at the root of a vertical rib of a wall body, the truss structure is integrally assembled on site, fine-tooth lead screws or inclined washers are adopted between the truss structure and the embedded penetrating pieces for fine adjustment, and welding fixation is carried out after adjustment is completed;
S4: measuring a penetrating piece;
and measuring the central position and the elevation of the penetration piece one by one, and adjusting the central position and the elevation one by one.
Further, in the step S3The truss structure comprises a middle-layer angle steel frame and a top-layer angle steel frame, and the truss structure is installed from bottom to top in a layered mode.
Further, in the step S1In the above, the total station is adopted for the measurement of the penetration piece.
Further, the assembly clearance between the detection cover plate and the wellhead is smaller than-0.5 mm.
Furthermore, the detection cover plate comprises a circular base plate, support plates, screw caps and handles, the four support plates are uniformly connected to the lower surface of the circular base plate along the circumferential direction, the screw caps are connected to the center of the circular base plate, and the two handles are connected to the upper surface of the circular base plate.
Furthermore, the positioning steel plate is manufactured and processed by a numerical control plasma cutting machine, and the flatness of the positioning steel plate is less than or equal to 3mm per square meter.
Furthermore, the length of the positioning steel plate is less than or equal to 7320mm, the width of the positioning steel plate is less than or equal to 5340mm, and the thickness of the positioning steel plate is greater than or equal to 6 mm.
Compared with the prior art, the invention has obvious advantages and beneficial effects, and is embodied in the following aspects:
the invention ensures the installation precision of the lower shaft by controlling the flatness of the bottom plate and the installation precision of the upper penetrating piece. The upper opening of the lower shaft is embedded into the upper penetrating piece, the upper penetrating piece is embedded into the floor slab, a scaffold is erected at the lower opening of the lower shaft, after the foundation construction of the storage well is completed, the upper embedded penetrating piece is installed firstly, the floor slab is poured by concrete, and the lower shaft is installed after the scaffold at the bottom is dismantled. The process flow method is simple and easy to understand and easy to operate, the first-time qualified rate of the installation of the penetration piece is greatly improved, and the construction efficiency is improved; powerful support is provided for penetrating member installation quality and construction progress.
Drawings
FIG. 1 is a schematic flow chart of a construction method of an embedded part installation method of a nuclear chemical storage well in an embodiment of the invention;
FIG. 2 is an overall structural schematic diagram of installation of embedded parts of a nuclear chemical storage well in the embodiment of the invention;
FIG. 3 is a schematic diagram of a through part bottom plate installation node in the installation method of the embedded part of the nuclear chemical storage well in the embodiment of the invention;
FIG. 4 is a schematic view of a mounting node between the bottom of the penetration assembly and the positioning steel plate according to the embodiment of the present invention;
FIG. 5 is a schematic block diagram of a positioning steel plate according to an embodiment of the present invention;
FIG. 6 is a schematic structural diagram of the angle iron support truss fixing in the embodiment of the invention;
fig. 7 is a schematic structural diagram of a detection cover plate in the embodiment of the present invention.
Detailed Description
In order to make the aforementioned objects, features and advantages of the present invention comprehensible, embodiments accompanied with figures are described in detail below.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as being fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; the two elements may be directly connected or indirectly connected through an intermediate medium, or may be communicated with each other inside the two elements, or may be wirelessly connected or wired connected. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Furthermore, the terms front, back, upper and lower in the description and the drawings are defined by the parts in the figures and the positions of the parts relative to each other, and are used for the sake of clarity and convenience in the technical solution. It is to be understood that the use of the directional terms described should not be taken to limit the scope of the claims.
Referring to fig. 1 to 7, an embodiment of the invention provides an embedded part installation method for a nuclear chemical industry storage well, the embedded part used in the installation method comprises a bottom plate, penetrating pieces, positioning steel plates, truss structures and a detection cover plate, the bottom plate is connected to the bottoms of the penetrating pieces, the truss structures are erected among the penetrating pieces,
the installation method comprises the following steps:
S1: through-penetration installation
Wherein the penetration mount comprises:
S21: manufacturing and installing a positioning steel plate;
as shown in fig. 5, in the present embodiment, after being transported to the site, the positioning steel plates are directly laid on the primary and secondary keels, and the peripheries of the positioning steel plates are welded and fixed at the bottoms of the vertical ribs of the wall body by using flat carbon steel;
controlling a gap between the positioning steel plate and a lower flange of the penetrating piece, wherein the mounting gap is controlled to be 1-1.5 mm;
S22: installing a penetrating piece;
S1: installing a bottom shaft;
as shown in fig. 3, in the present embodiment, an anchor bolt is embedded in concrete, the upper portion of the anchor bolt passes through a bottom plate, the elevation of the bottom plate is finely adjusted by a leveling nut and a fastening nut, and then a shaft is hung on the bottom plate;
S3: installing a truss structure;
as shown in fig. 6, in this embodiment, two ends of the truss structure are fixed on the angle steel truss columns, the angle steel truss columns are fixed at the roots of the vertical ribs of the wall body, the truss structure is integrally assembled on site, fine screws or inclined washers are used for fine adjustment between the truss structure and the embedded penetration pieces, and the truss structure and the embedded penetration pieces are welded and fixed after the adjustment is completed;
S4: measuring a penetrating piece;
and measuring the central position and the elevation of the penetration piece one by one, and adjusting the central position and the elevation one by one.
Further, as shown in FIG. 6, in the placeThe step S3The truss structure comprises a middle-layer angle steel frame and a top-layer angle steel frame, and the truss structure is installed from bottom to top in a layered mode.
Two ends of the truss structure are fixed on the angle steel truss columns, and the angle steel truss columns are fixed at the roots of vertical ribs of the wall body to form a stable truss structure. The truss structure is integrally assembled on site, fine screw rods or inclined iron pads are adopted between the truss structure and the embedded penetrating pieces for fine adjustment, and welding fixation is carried out after adjustment is completed.
Because the whole angle steel frame is of a truss structure, the truss structure is divided into a middle layer angle steel frame and a top layer angle steel frame due to binding and cross construction with civil engineering steel bars, and therefore the angle steel frames are installed from bottom to top in a layered mode.
Specifically, in the step S1In the above, the total station is adopted for the measurement of the penetration piece.
Therefore, after the installation of the angle iron bracket at the top layer is completed, the central position and the elevation of the penetrating piece are measured one by one through the total station and are adjusted one by one.
Specifically, the assembly clearance between the detection cover plate and the wellhead is smaller than-0.5 mm.
Preferably, in the embodiment, through the self-made cover plate, after machining, the assembly error between the cover plate and the wellhead is-0.5 mm.
Specifically, detect apron includes circular bottom plate, backup pad, nut and handle, four the backup pad is evenly connected along the circumferencial direction in the lower surface of circular bottom plate, the nut is connected the center of circular bottom plate, two the handle is connected the upper surface of circular bottom plate.
Specifically, the positioning steel plate is manufactured and processed by a numerical control plasma cutting machine, and the flatness of the positioning steel plate is less than or equal to 3mm per square meter.
Specifically, the length of the positioning steel plate is less than or equal to 7320mm, the width of the positioning steel plate is less than or equal to 5340mm, and the thickness of the positioning steel plate is greater than or equal to 6 mm.
The invention ensures the installation precision of the lower shaft by controlling the flatness of the bottom plate and the installation precision of the upper penetrating piece. The upper opening of the lower shaft is embedded into the upper penetrating piece, the upper penetrating piece is embedded into the floor slab, a scaffold is erected at the lower opening of the lower shaft, after the foundation construction of the storage well is completed, the upper embedded penetrating piece is installed firstly, the floor slab is poured by concrete, and the lower shaft is installed after the scaffold at the bottom is dismantled. The process flow method is simple and easy to understand and operate, the primary qualified rate of the penetration piece installation is greatly improved, and the construction efficiency is improved; powerful support is provided for penetrating member installation quality and construction progress.
Although the present disclosure has been described above, the scope of the present disclosure is not limited thereto. Various changes and modifications may be effected therein by one of ordinary skill in the pertinent art without departing from the spirit and scope of the present disclosure, and these changes and modifications are intended to be within the scope of the present disclosure.

Claims (7)

1. The method for installing the embedded parts of the nuclear chemical storage well is characterized in that the embedded parts used in the installation method comprise bottom plates, penetrating parts, positioning steel plates, truss structures and detection cover plates, the bottom plates are connected to the bottoms of the penetrating parts, the truss structures are erected among the penetrating parts,
the installation method comprises the following steps:
S1: installing a penetrating piece;
wherein the penetration mount comprises:
S11: manufacturing and installing a positioning steel plate;
after the positioning steel plates are transported to the site, the positioning steel plates are directly laid on the primary and secondary keels, and the peripheries of the positioning steel plates are welded and fixed at the bottoms of the vertical ribs of the wall body by adopting carbon steel flat irons;
controlling a gap between the positioning steel plate and a lower flange of the penetrating piece, wherein the installation gap is controlled to be 1-1.5 mm;
S12: the upper penetrating piece is installed;
S2: installing a bottom shaft;
the foundation bolt is embedded in the concrete, the upper part of the foundation bolt penetrates through the bottom plate, the elevation of the bottom plate is finely adjusted through the leveling nut and the fastening nut, and then the shaft is hung on the bottom plate;
S3: mounting an angle steel bracket;
two ends of a truss structure are fixed on an angle steel truss column, the angle steel truss column is fixed at the root of a vertical rib of a wall body, the truss structure is integrally assembled on site, fine-tooth lead screws or inclined washers are adopted between the truss structure and the embedded penetrating pieces for fine adjustment, and welding fixation is carried out after adjustment is completed;
S4: measuring a penetrating piece;
and measuring the central position and the elevation of the penetration piece one by one, and adjusting the central position and the elevation one by one.
2. The method for installing the embedded part of the nuclear chemical storage well as claimed in claim 1, wherein the step S3The truss structure comprises a middle-layer angle steel frame and a top-layer angle steel frame, and the truss structure is installed from bottom to top in a layered mode.
3. The nuclear chemical storage well embedded part installation method according to claim 1 or 2, wherein the step S1In the above, the total station is adopted for the measurement of the penetration piece.
4. The method for installing the embedded part of the nuclear chemical storage well, according to claim 1, wherein the assembly clearance between the detection cover plate and the well head is less than-0.5 mm.
5. The method for installing the embedded part of the nuclear chemical industry storage well according to claim 4, wherein the detection cover plate comprises a circular bottom plate, support plates, screw caps and handles, four support plates are uniformly connected to the lower surface of the circular bottom plate along the circumferential direction, the screw caps are connected to the center of the circular bottom plate, and two handles are connected to the upper surface of the circular bottom plate.
6. The method for installing the embedded part of the nuclear chemical storage well according to claim 1, wherein the positioning steel plate is manufactured and processed by a numerical control plasma cutting machine, and the flatness of the positioning steel plate is less than or equal to 3mm per square meter.
7. The method for installing the embedded part of the nuclear chemical industry storage well, according to claim 1, wherein the length of the positioning steel plate is less than or equal to 7320mm, the width of the positioning steel plate is less than or equal to 5340mm, and the thickness of the positioning steel plate is greater than or equal to 6 mm.
CN202210013341.7A 2022-01-06 2022-01-06 Installation method of embedded part of nuclear chemical storage well Active CN114482562B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210013341.7A CN114482562B (en) 2022-01-06 2022-01-06 Installation method of embedded part of nuclear chemical storage well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210013341.7A CN114482562B (en) 2022-01-06 2022-01-06 Installation method of embedded part of nuclear chemical storage well

Publications (2)

Publication Number Publication Date
CN114482562A true CN114482562A (en) 2022-05-13
CN114482562B CN114482562B (en) 2023-04-18

Family

ID=81509399

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210013341.7A Active CN114482562B (en) 2022-01-06 2022-01-06 Installation method of embedded part of nuclear chemical storage well

Country Status (1)

Country Link
CN (1) CN114482562B (en)

Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09113667A (en) * 1995-10-18 1997-05-02 Hitachi Ltd Method for constructing upper drywell in reactor containment and module used in this method
CN1448556A (en) * 2002-03-30 2003-10-15 特鲁菲舍尔股份有限公司及两合公司 Apparatus for separating transporting air in fibrous material transportation
CN101967886A (en) * 2010-11-16 2011-02-09 中国核工业第五建设有限公司 Assembly and installation methods of steel containment vessel of nuclear power station
CN102465715A (en) * 2010-11-16 2012-05-23 韩国地质资源研究院 Integration management system for carbon dioxide geologic injection
CN102605803A (en) * 2012-04-17 2012-07-25 哈尔滨金阳光管业有限责任公司 Inspection well
US20120210669A1 (en) * 2011-02-18 2012-08-23 Senvex Co., Ltd. Method of constructing prefabricated steel reinforced concrete (psrc) column using angle steels and psrc column using angle steels
CN103174302A (en) * 2013-03-27 2013-06-26 江苏省江建集团有限公司 Construction method for large-diameter barrel cabin top
CN103526954A (en) * 2013-10-24 2014-01-22 中国建筑第二工程局有限公司 Support for overweight precision embedded part and construction method thereof
CN104775545A (en) * 2015-03-09 2015-07-15 沈阳建筑大学 Novel disassembling component for assembling type concrete frame and shear wall structure and connecting method
CN105715061A (en) * 2014-12-02 2016-06-29 中国核工业二四建设有限公司 Safe isolation platform for vertical shaft
CN107806264A (en) * 2017-09-29 2018-03-16 中铁科建有限公司 A kind of engineering method and jiffy stand of assembled jiffy stand
US20180119982A1 (en) * 2016-10-28 2018-05-03 Louis A. Waters, Jr. Security for grate covering underground air vents
CN108643572A (en) * 2018-05-31 2018-10-12 山东省建设建工(集团)有限责任公司 Concrete crossbeam support, shellfish thunder platform construction and steel strand wires combined installation method
CN109036613A (en) * 2018-07-11 2018-12-18 中国核电工程有限公司 A kind of concrete liner steel linear water tank and its construction method
CN109175802A (en) * 2018-09-28 2019-01-11 中国核工业二三建设有限公司 A kind of welding anti-deformation supporting device
CN110107094A (en) * 2019-04-01 2019-08-09 南京市第九建筑安装工程有限公司 The quick location and installation construction method of fabricated construction concrete vertical member
CN110847289A (en) * 2019-12-19 2020-02-28 中铁五局集团第二工程有限责任公司 Ultra-deep large-span circular water intake pump house roof support and construction method thereof
CN112411714A (en) * 2020-11-17 2021-02-26 海澄环保科技(上海)有限公司 Prevent deposiing prefabricated sewage interception well and installation device thereof
US10968594B1 (en) * 2018-11-20 2021-04-06 Predl Systems North America Inc. Manhole rehabilitation system

Patent Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09113667A (en) * 1995-10-18 1997-05-02 Hitachi Ltd Method for constructing upper drywell in reactor containment and module used in this method
CN1448556A (en) * 2002-03-30 2003-10-15 特鲁菲舍尔股份有限公司及两合公司 Apparatus for separating transporting air in fibrous material transportation
CN101967886A (en) * 2010-11-16 2011-02-09 中国核工业第五建设有限公司 Assembly and installation methods of steel containment vessel of nuclear power station
CN102465715A (en) * 2010-11-16 2012-05-23 韩国地质资源研究院 Integration management system for carbon dioxide geologic injection
US20120210669A1 (en) * 2011-02-18 2012-08-23 Senvex Co., Ltd. Method of constructing prefabricated steel reinforced concrete (psrc) column using angle steels and psrc column using angle steels
CN102605803A (en) * 2012-04-17 2012-07-25 哈尔滨金阳光管业有限责任公司 Inspection well
CN103174302A (en) * 2013-03-27 2013-06-26 江苏省江建集团有限公司 Construction method for large-diameter barrel cabin top
CN103526954A (en) * 2013-10-24 2014-01-22 中国建筑第二工程局有限公司 Support for overweight precision embedded part and construction method thereof
CN105715061A (en) * 2014-12-02 2016-06-29 中国核工业二四建设有限公司 Safe isolation platform for vertical shaft
CN104775545A (en) * 2015-03-09 2015-07-15 沈阳建筑大学 Novel disassembling component for assembling type concrete frame and shear wall structure and connecting method
US20180119982A1 (en) * 2016-10-28 2018-05-03 Louis A. Waters, Jr. Security for grate covering underground air vents
CN107806264A (en) * 2017-09-29 2018-03-16 中铁科建有限公司 A kind of engineering method and jiffy stand of assembled jiffy stand
CN108643572A (en) * 2018-05-31 2018-10-12 山东省建设建工(集团)有限责任公司 Concrete crossbeam support, shellfish thunder platform construction and steel strand wires combined installation method
CN109036613A (en) * 2018-07-11 2018-12-18 中国核电工程有限公司 A kind of concrete liner steel linear water tank and its construction method
CN109175802A (en) * 2018-09-28 2019-01-11 中国核工业二三建设有限公司 A kind of welding anti-deformation supporting device
US10968594B1 (en) * 2018-11-20 2021-04-06 Predl Systems North America Inc. Manhole rehabilitation system
CN110107094A (en) * 2019-04-01 2019-08-09 南京市第九建筑安装工程有限公司 The quick location and installation construction method of fabricated construction concrete vertical member
CN110847289A (en) * 2019-12-19 2020-02-28 中铁五局集团第二工程有限责任公司 Ultra-deep large-span circular water intake pump house roof support and construction method thereof
CN112411714A (en) * 2020-11-17 2021-02-26 海澄环保科技(上海)有限公司 Prevent deposiing prefabricated sewage interception well and installation device thereof

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
刁春娜;田新军;时良辰;赵其文;弓泽业;: "某地铀矿原地浸出采铀工艺对环境的影响" *
谭韶;: "用于城市地下管井测量的摄影测量仪研制与试验" *
陈海峰;: "核电站电气贯穿件安装后电气性能试验方法研究" *
马新朝;: "核电工程建造阶段的雨水防漏问题的处理" *

Also Published As

Publication number Publication date
CN114482562B (en) 2023-04-18

Similar Documents

Publication Publication Date Title
CN101871265B (en) Flat shim plate-adjustable grouting installation method
CN102061746B (en) Steel structure assembled embedded part and construction method thereof
CN112049146A (en) Steel structure foundation embedded part and technological process thereof
CN109322323B (en) Installation method of large-angle inclined equipment bottom plate
CN112127637A (en) Construction method for pre-buried vertical component steel bars of foundation layer of fabricated building
CN114482562B (en) Installation method of embedded part of nuclear chemical storage well
CN110629782B (en) Adjusting method of anchor bolt offline assembly device
CN210887278U (en) Fixing device for cup mouth type concrete foundation pit stand column
CN202706582U (en) Installation elevation adjusting device for base steel column of cup rabbet
CN109518942B (en) Tool-based bracket system for controlling precision of two-dimensional component and application method thereof
CN114658027B (en) Construction method of standard frame, pouring template and foundation of chemical factory building equipment
CN213358957U (en) Foundation embedded part structure
CN202787999U (en) Movable type support bridge for efficient large area concrete terrace construction
CN209760786U (en) instrumentization support system for controlling precision of two-dimensional component
CN213806583U (en) Large-section inclined column template construction structure for constructional engineering
CN102042461A (en) Evenness adjusting methods for industrial factory building T-shaped groove and platform thereof
CN211395731U (en) Foundation bolt off-line assembly device
CN211080288U (en) Adjusting device for mounting anchor bolt cage of wind driven generator
CN216105626U (en) Channel steel installation adjusting device of equipment foundation
CN203282081U (en) Tool for installing electric mechanism of switch blade
CN220978043U (en) Novel steel corbel suitable for deep basal pit supports
CN212375895U (en) Height-adjustable raft plate flatness control track
CN114575371B (en) Cup-mouth foundation H-shaped steel column positioning method
CN217000959U (en) Positioning auxiliary tool for circular reactor foundation embedded part
CN215107062U (en) Terrace pouring construction device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant