CN113898202A - Concrete gap repairing and anti-seepage treatment method - Google Patents

Concrete gap repairing and anti-seepage treatment method Download PDF

Info

Publication number
CN113898202A
CN113898202A CN202111195800.XA CN202111195800A CN113898202A CN 113898202 A CN113898202 A CN 113898202A CN 202111195800 A CN202111195800 A CN 202111195800A CN 113898202 A CN113898202 A CN 113898202A
Authority
CN
China
Prior art keywords
leakage
filling
pit
gap
repairing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111195800.XA
Other languages
Chinese (zh)
Inventor
刘李红
张易
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Zhitong Construction Engineering Technology Co ltd
Original Assignee
Shanghai Zhitong Construction Engineering Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Zhitong Construction Engineering Technology Co ltd filed Critical Shanghai Zhitong Construction Engineering Technology Co ltd
Priority to CN202111195800.XA priority Critical patent/CN113898202A/en
Publication of CN113898202A publication Critical patent/CN113898202A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0203Arrangements for filling cracks or cavities in building constructions
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00241Physical properties of the materials not provided for elsewhere in C04B2111/00
    • C04B2111/00293Materials impermeable to liquids

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Structural Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Ceramic Engineering (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Materials Engineering (AREA)
  • Inorganic Chemistry (AREA)
  • Organic Chemistry (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention belongs to the technical field of gap anti-leakage repair, and particularly relates to a concrete gap repair and anti-leakage treatment method, which comprises the following specific steps: s1, opening a pouring pit at one end of the gap: a filling pit is arranged between the two side buffer structures and is positioned at the upper end of a gap between the two side buffer structures, the filling pit is in a symmetrical arc shape, and a sealing flange is reserved on the inner wall of the upper side of the filling pit; s2, forming an anti-seepage groove at the upper part of the pouring pit; s3, pouring a repairing material; s4 laying anti-leakage layer. The construction is carried out in two steps by the cooperation of the filling pit and the anti-seepage groove, so that the construction effect is improved, and different raw materials are adopted in different steps, so that the anti-seepage performance of the repaired concrete can be obviously improved; through the arrangement of structures such as closed inner grooves, the leakage condition is obstructed from the physical structure.

Description

Concrete gap repairing and anti-seepage treatment method
Technical Field
The invention relates to the technical field of gap anti-leakage repair, in particular to a concrete gap repair and anti-leakage treatment method.
Background
The cement concrete is a general name of engineering composite materials formed by mixing cement, sand, stone and the like with water into a whole, and the cement concrete is as follows: the concrete is a general term for engineering composite materials formed by mixing cement, sand, stone and the like into a whole by water, and the term of concrete generally refers to that cement is used as a cementing material, and sand and stone are used as aggregates; the cement concrete, also called as common concrete, is obtained by mixing with water (with or without additive and admixture) according to a certain proportion, stirring, forming and curing, and is widely applied to civil engineering.
Concrete cracks are physical structural changes of concrete structures due to the action of internal and external factors, and cracks are a main cause of reduction in bearing capacity, durability and waterproofness of concrete structures.
The existing concrete crack construction mode is easy to leak after being repaired, causes corrosion damage from the inside and reduces the service life.
Disclosure of Invention
The invention aims to provide a concrete gap repairing and anti-leakage treatment method, which aims to solve the problems that the existing concrete gap construction mode proposed in the background art is easy to leak after repairing, causes corrosion damage from the inside and reduces the service life.
In order to achieve the purpose, the invention provides the following technical scheme: a concrete gap repairing and anti-leakage treatment method comprises the following specific steps:
s1, opening a pouring pit at one end of the gap: a filling pit is arranged between the two side buffer structures and is positioned at the upper end of a gap between the two side buffer structures, the filling pit is in a symmetrical arc shape, and a sealing flange is reserved on the inner wall of the upper side of the filling pit;
s2, forming an anti-seepage groove at the upper part of the pouring pit: an anti-seepage groove is formed in the outer surface of the buffer structure and is positioned on one side, away from the gap, of the filling pit, the anti-seepage groove and the filling pit correspond in position, and closed inner grooves are formed in the two end portions of the anti-seepage groove towards one side of the buffer structure;
s3 pouring repair materials: embedding a filling nozzle into the filling pit, inserting the filling nozzle into the gap, filling a repairing material into the filling nozzle, enabling the repairing material to permeate into the gap, filling the gap, taking out the filling nozzle, continuously filling the repairing material until the filling pit is filled with the repairing material, enabling the upper end of the repairing material to be flush with the upper end of the sealing flange, and solidifying the repairing material;
s4 filling and laying an anti-leakage layer: laying an anti-leakage layer on the solidified repairing material, filling the anti-leakage groove and the closed inner groove with the anti-leakage layer, compacting the anti-leakage layer, injecting waterproof glue into the joint between the anti-leakage layer and the anti-leakage groove, spraying water on the anti-leakage layer once every 8-10 hours, and continuously spraying for 3 days.
Preferably, the sealing flange is in a block shape protruding towards the inner part of the pouring pit, and the sealing flange intersects with one end part of a borderline of the pouring pit.
Preferably, the anti-seepage grooves are formed in the outer surface of the buffer structure in the same depth.
Preferably, the inner wall of the pouring pit is polished in advance, and the surface of the inner wall of the pouring pit is polished by a sander, so that the roughness Ra is less than or equal to 0.8 mm.
Preferably, holes are uniformly chiseled on the inner wall of the polished pouring pit.
Preferably, the aperture of the small hole is set to be 0.6-1cm, the depth of the small hole is 2-4cm, and the distance between centers of adjacent small holes is 4-10 cm.
Preferably, the small hole is in a hollow circular truncated cone shape with a large inner diameter and a small outer diameter, the maximum diameter of the small hole is 1-1.2cm, and the maximum diameter of the small hole is 0.4-0.8 cm.
Preferably, the raw materials of the repair material are 10-12 parts of glass fiber yarn, 30-40 parts of cement, 20-22 parts of pebbles, 6-10 parts of epoxy resin adhesive and 24-30 parts of water according to mass proportion.
Preferably, the raw materials of the anti-leakage layer comprise cement, cement gum, nano polyethylene powder and water, and the cement, the cement gum, the nano polyethylene powder and the water are respectively as follows according to mass proportion: 30-40 parts of cement, 10-12 parts of cement gum, 6-8 parts of nano polyethylene powder and 18-24 parts of water.
Compared with the prior art, the invention has the beneficial effects that:
1) the construction is carried out in two steps by the cooperation of the filling pit and the anti-seepage groove, so that the construction effect is improved, and different raw materials are adopted in different steps, so that the anti-seepage performance of the repaired concrete can be obviously improved;
2) through the arrangement of structures such as closed inner grooves, the leakage condition is obstructed from the physical structure.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the present invention in use;
FIG. 3 is a flow chart of the process of the present invention.
In the figure: 1 a buffer structure, 2 gaps, 3 filling pits, 4 sealing flanges, 5 anti-leakage grooves and 6 closed inner grooves.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, are merely for convenience in describing the present invention and simplifying the description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention.
The first embodiment is as follows:
referring to fig. 1-3, the present invention provides a technical solution: a concrete gap repairing and anti-leakage treatment method comprises the following specific steps:
s1 opening a pouring pit 3 at one end of the gap 2: a filling pit 3 is arranged between the two side buffer structures 1, the filling pit 3 is positioned at the upper end of a gap 2 between the two side buffer structures 1, the filling pit 3 is in a symmetrical arc shape, a sealing flange 4 is reserved on the inner wall of the upper side of the filling pit 3, the sealing flange 4 is in a block shape protruding towards the inside of the filling pit 3, and the sealing flange 4 is intersected with one end part of a sideline of the filling pit 3;
s2, arranging an anti-seepage groove 5 at the upper part of the pouring pit 3: an anti-seepage groove 5 is formed in the outer surface of the buffer structure 1, the anti-seepage groove 5 is located on one side, away from the gap 2, of the filling pit 3, the anti-seepage groove 5 corresponds to the filling pit 3 in position, and closed inner grooves 6 are formed in two end portions of the anti-seepage groove 5 towards one side of the buffer structure 1;
the anti-seepage grooves 5 are arranged on the outer surface of the buffer structure 1 in the same depth; pre-polishing the inner wall of the pouring pit 3, and polishing the surface of the inner wall of the pouring pit 3 by a sand grinder to ensure that the roughness Ra is less than or equal to 0.8 mm;
uniformly chiseling small holes on the inner wall of the polished pouring pit 3, wherein the small holes comprise the following two forms:
the first method comprises the following steps: the aperture of the small hole is set to be 0.6-1cm, the depth of the small hole is 2-4cm, and the distance between centers of adjacent small holes is 4-10 cm.
And the second method comprises the following steps: the small hole is in a hollow round table shape with a large inner diameter and a small outer diameter, the maximum diameter of the small hole is 1-1.2cm, and the maximum diameter of the small hole is 0.4-0.8 cm.
S3 pouring repair materials: embedding a filling nozzle into the filling pit 3, inserting the filling nozzle into the gap 2, filling a repairing material into the filling nozzle, enabling the repairing material to permeate into the gap 2, filling the gap 2, taking out the filling nozzle, continuously filling the repairing material until the repairing material fills the filling pit 3, enabling the upper end of the repairing material to be flush with the upper end of the sealing flange 4, and solidifying the repairing material;
the raw materials of the repair material are 10Kg of glass fiber yarn, 30Kg of cement, 20Kg of pebble, 6Kg of epoxy resin glue and 24Kg of water according to the mass proportion.
S4 filling and laying an anti-leakage layer: laying an anti-leakage layer on the solidified repairing material, filling the anti-leakage groove 5 and the closed inner groove 6 with the anti-leakage layer, compacting the anti-leakage layer, injecting waterproof glue into the joint between the anti-leakage layer and the anti-leakage groove 5, spraying water on the anti-leakage layer once every 8-10 hours, and continuously spraying for 3 days. The raw materials of the anti-leakage layer comprise cement, cement gum, nano polyethylene powder and water, wherein the cement, the cement gum, the nano polyethylene powder and the water are respectively as follows according to mass proportion: 30Kg of cement, 10Kg of cement glue, 6Kg of nano polyethylene powder and 18Kg of water.
Example two:
the concrete gap repairing and anti-seepage treatment method comprises the following specific steps:
s1 opening a pouring pit 3 at one end of the gap 2: a filling pit 3 is arranged between the two side buffer structures 1, the filling pit 3 is positioned at the upper end of a gap 2 between the two side buffer structures 1, the filling pit 3 is in a symmetrical arc shape, a sealing flange 4 is reserved on the inner wall of the upper side of the filling pit 3, the sealing flange 4 is in a block shape protruding towards the inside of the filling pit 3, and the sealing flange 4 is intersected with one end part of a sideline of the filling pit 3;
s2, arranging an anti-seepage groove 5 at the upper part of the pouring pit 3: an anti-seepage groove 5 is formed in the outer surface of the buffer structure 1, the anti-seepage groove 5 is located on one side, away from the gap 2, of the filling pit 3, the anti-seepage groove 5 corresponds to the filling pit 3 in position, and closed inner grooves 6 are formed in two end portions of the anti-seepage groove 5 towards one side of the buffer structure 1;
the anti-seepage grooves 5 are arranged on the outer surface of the buffer structure 1 in the same depth; pre-polishing the inner wall of the pouring pit 3, and polishing the surface of the inner wall of the pouring pit 3 by a sand grinder to ensure that the roughness Ra is less than or equal to 0.8 mm;
uniformly chiseling small holes on the inner wall of the polished pouring pit 3, wherein the small holes comprise the following two forms:
the first method comprises the following steps: the aperture of the small hole is set to be 0.6-1cm, the depth of the small hole is 2-4cm, and the distance between centers of adjacent small holes is 4-10 cm.
And the second method comprises the following steps: the small hole is in a hollow round table shape with a large inner diameter and a small outer diameter, the maximum diameter of the small hole is 1-1.2cm, and the maximum diameter of the small hole is 0.4-0.8 cm.
S3 pouring repair materials: embedding a filling nozzle into the filling pit 3, inserting the filling nozzle into the gap 2, filling a repairing material into the filling nozzle, enabling the repairing material to permeate into the gap 2, filling the gap 2, taking out the filling nozzle, continuously filling the repairing material until the repairing material fills the filling pit 3, enabling the upper end of the repairing material to be flush with the upper end of the sealing flange 4, and solidifying the repairing material;
the raw materials of the repair material are 11Kg of glass fiber yarn, 35Kg of cement, 21Kg of pebble, 8Kg of epoxy resin glue and 27Kg of water according to the mass proportion.
S4 filling and laying an anti-leakage layer: laying an anti-leakage layer on the solidified repairing material, filling the anti-leakage groove 5 and the closed inner groove 6 with the anti-leakage layer, compacting the anti-leakage layer, injecting waterproof glue into the joint between the anti-leakage layer and the anti-leakage groove 5, spraying water on the anti-leakage layer once every 8-10 hours, and continuously spraying for 3 days. The raw materials of the anti-leakage layer comprise cement, cement gum, nano polyethylene powder and water, wherein the cement, the cement gum, the nano polyethylene powder and the water are respectively as follows according to mass proportion: 35Kg of cement, 11Kg of cement gum, 7Kg of nano polyethylene powder and 21Kg of water.
Example three:
the concrete gap repairing and anti-seepage treatment method comprises the following specific steps:
s1 opening a pouring pit 3 at one end of the gap 2: a filling pit 3 is arranged between the two side buffer structures 1, the filling pit 3 is positioned at the upper end of a gap 2 between the two side buffer structures 1, the filling pit 3 is in a symmetrical arc shape, a sealing flange 4 is reserved on the inner wall of the upper side of the filling pit 3, the sealing flange 4 is in a block shape protruding towards the inside of the filling pit 3, and the sealing flange 4 is intersected with one end part of a sideline of the filling pit 3;
s2, arranging an anti-seepage groove 5 at the upper part of the pouring pit 3: an anti-seepage groove 5 is formed in the outer surface of the buffer structure 1, the anti-seepage groove 5 is located on one side, away from the gap 2, of the filling pit 3, the anti-seepage groove 5 corresponds to the filling pit 3 in position, and closed inner grooves 6 are formed in two end portions of the anti-seepage groove 5 towards one side of the buffer structure 1;
the anti-seepage grooves 5 are arranged on the outer surface of the buffer structure 1 in the same depth; pre-polishing the inner wall of the pouring pit 3, and polishing the surface of the inner wall of the pouring pit 3 by a sand grinder to ensure that the roughness Ra is less than or equal to 0.8 mm;
uniformly chiseling small holes on the inner wall of the polished pouring pit 3, wherein the small holes comprise the following two forms:
the first method comprises the following steps: the aperture of the small hole is set to be 0.6-1cm, the depth of the small hole is 2-4cm, and the distance between centers of adjacent small holes is 4-10 cm.
And the second method comprises the following steps: the small hole is in a hollow round table shape with a large inner diameter and a small outer diameter, the maximum diameter of the small hole is 1-1.2cm, and the maximum diameter of the small hole is 0.4-0.8 cm.
S3 pouring repair materials: embedding a filling nozzle into the filling pit 3, inserting the filling nozzle into the gap 2, filling a repairing material into the filling nozzle, enabling the repairing material to permeate into the gap 2, filling the gap 2, taking out the filling nozzle, continuously filling the repairing material until the repairing material fills the filling pit 3, enabling the upper end of the repairing material to be flush with the upper end of the sealing flange 4, and solidifying the repairing material;
the raw materials of the repair material are glass fiber yarn, cement, pebbles, epoxy resin glue and water, and the mass proportion of the repair material is 12Kg of glass fiber yarn, 40Kg of cement, 22Kg of pebbles, 10Kg of epoxy resin glue and 30Kg of water respectively.
S4 filling and laying an anti-leakage layer: laying an anti-leakage layer on the solidified repairing material, filling the anti-leakage groove 5 and the closed inner groove 6 with the anti-leakage layer, compacting the anti-leakage layer, injecting waterproof glue into the joint between the anti-leakage layer and the anti-leakage groove 5, spraying water on the anti-leakage layer once every 8-10 hours, and continuously spraying for 3 days. The raw materials of the anti-leakage layer comprise cement, cement gum, nano polyethylene powder and water, wherein the cement, the cement gum, the nano polyethylene powder and the water are respectively as follows according to mass proportion: 40Kg of cement, 12Kg of cement glue, 8Kg of nano polyethylene powder and 24Kg of water.
Detecting the leakage-proof effect of the three embodiments, specifically, cutting the buffer structure 1, the gap 2, the filling pit 3, the leakage-proof groove 5, the repair material and the leakage-proof layer of the three embodiments;
a cover body is arranged from the upper part, the cover body covers the periphery of the anti-seepage groove 5, water is injected into the cover body, and the pressure applied to the water is 0.3MPa for 12 hours.
The results are given in the following table:
repair material anti-seepage effect Anti-leakage effect of anti-leakage layer
Example one Without water seepage Without water seepage
Example two Without water seepage Without water seepage
EXAMPLE III Without water seepage Without water seepage
While there have been shown and described the fundamental principles and essential features of the invention and advantages thereof, it will be apparent to those skilled in the art that the invention is not limited to the details of the foregoing exemplary embodiments, but is capable of other specific forms without departing from the spirit or essential characteristics thereof; the present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein, and any reference signs in the claims are not intended to be construed as limiting the claim concerned.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (9)

1. A concrete gap repairing and anti-leakage treatment method is characterized by comprising the following specific steps:
s1, opening a pouring pit (3) at one end of the gap (2): a filling pit (3) is arranged between the buffer structures (1) at the two sides, the filling pit (3) is positioned at the upper end of the gap (2) between the buffer structures (1) at the two sides, the filling pit (3) is in a symmetrical arc shape, and a sealing flange (4) is reserved on the inner wall of the upper side of the filling pit (3);
s2, an anti-seepage groove (5) is arranged at the upper part of the pouring pit (3): an anti-leakage groove (5) is formed in the outer surface of the buffer structure (1), the anti-leakage groove (5) is located on one side, away from the gap (2), of the filling pit (3), the anti-leakage groove (5) and the filling pit (3) correspond in position, and closed inner grooves (6) are formed in two end portions of the anti-leakage groove (5) towards one side of the buffer structure (1);
s3 pouring repair materials: embedding a filling nozzle into the filling pit (3), inserting the filling nozzle into the gap (2), filling a repairing material into the filling nozzle, enabling the repairing material to permeate into the gap (2), filling the gap (2), taking out the filling nozzle, continuously filling the repairing material until the filling pit (3) is filled with the repairing material, enabling the upper end of the repairing material to be flush with the upper end of the sealing flange (4), and solidifying the repairing material;
s4 filling and laying an anti-leakage layer: and laying an anti-leakage layer on the solidified repairing material, filling the anti-leakage groove (5) and the closed inner groove (6) with the anti-leakage layer, compacting the anti-leakage layer, injecting waterproof glue into the joint between the anti-leakage layer and the anti-leakage groove (5), spraying water on the anti-leakage layer once every 8-10 hours, and continuously spraying for 3 days.
2. The concrete gap repairing and anti-leakage treatment method according to claim 1, characterized in that: the sealing flange (4) is in a block shape protruding towards the interior of the pouring pit (3), and the sealing flange (4) is intersected with one end part of a sideline of the pouring pit (3).
3. The concrete gap repairing and anti-leakage treatment method according to claim 1, characterized in that: the depth of the anti-leakage grooves (5) formed in the outer surface of the buffer structure (1) is the same.
4. The concrete gap repairing and anti-leakage treatment method according to claim 1, characterized in that: and (3) polishing the inner wall of the pouring pit (3) in advance, and polishing the surface of the inner wall of the pouring pit (3) by a sander to ensure that the roughness Ra is less than or equal to 0.8 mm.
5. The concrete gap repairing and leakage preventing treatment method according to claim 4, wherein the concrete gap repairing and leakage preventing treatment method comprises the following steps: and uniformly chiseling small holes on the inner wall of the polished pouring pit (3).
6. The concrete gap repairing and leakage preventing treatment method according to claim 5, wherein the concrete gap repairing and leakage preventing treatment method comprises the following steps: the aperture of the small hole is set to be 0.6-1cm, the depth of the small hole is 2-4cm, and the distance between centers of adjacent small holes is 4-10 cm.
7. The concrete gap repairing and leakage preventing treatment method according to claim 5, wherein the concrete gap repairing and leakage preventing treatment method comprises the following steps: the small hole is in a hollow round table shape with a large inner diameter and a small outer diameter, the maximum diameter of the small hole is 1-1.2cm, and the maximum diameter of the small hole is 0.4-0.8 cm.
8. The concrete gap repairing and anti-leakage treatment method according to claim 1, characterized in that: the repairing material comprises, by mass, 10-12 parts of glass fiber yarn, 30-40 parts of cement, 20-22 parts of pebble, 6-10 parts of epoxy resin glue and 24-30 parts of water.
9. The concrete gap repairing and anti-leakage treatment method according to claim 1, characterized in that: the raw materials of the anti-leakage layer comprise cement, cement gum, nano polyethylene powder and water, wherein the cement, the cement gum, the nano polyethylene powder and the water are respectively as follows according to mass proportion: 30-40 parts of cement, 10-12 parts of cement gum, 6-8 parts of nano polyethylene powder and 18-24 parts of water.
CN202111195800.XA 2021-10-14 2021-10-14 Concrete gap repairing and anti-seepage treatment method Pending CN113898202A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111195800.XA CN113898202A (en) 2021-10-14 2021-10-14 Concrete gap repairing and anti-seepage treatment method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111195800.XA CN113898202A (en) 2021-10-14 2021-10-14 Concrete gap repairing and anti-seepage treatment method

Publications (1)

Publication Number Publication Date
CN113898202A true CN113898202A (en) 2022-01-07

Family

ID=79191975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111195800.XA Pending CN113898202A (en) 2021-10-14 2021-10-14 Concrete gap repairing and anti-seepage treatment method

Country Status (1)

Country Link
CN (1) CN113898202A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005299367A (en) * 2004-03-16 2005-10-27 Yonosuke Ito Crack repairing method of structure
JP2010001686A (en) * 2008-06-23 2010-01-07 Ryozo Hirata Method of repairing linear crack occurring portion in concrete wall, or method of sealing joint at connection portion of concrete wall
JP2011080307A (en) * 2009-10-09 2011-04-21 Ryozo Hirata Repairing method of linear cracking section of concrete wall and joint sealing method in joint of concrete wall
CN111485922A (en) * 2020-05-13 2020-08-04 陕西上坤蓝箭科技有限公司 E L F railway tunnel water leakage, block falling and grout turnover disease treatment method
JP2020159137A (en) * 2019-03-27 2020-10-01 旭化成ホームズ株式会社 Joint structure and method for repairing joint
CN212742964U (en) * 2020-05-22 2021-03-19 中机工程(西安)启源咨询设计有限公司 Surface course gap processing structure on epoxy self-leveling air flotation ground
CN113027160A (en) * 2020-04-17 2021-06-25 中建二局第一建筑工程有限公司 Concrete crack repairing method
CN113323440A (en) * 2021-06-10 2021-08-31 上海凯顿百森建筑工程有限公司 Concrete gap repairing and anti-seepage treatment method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005299367A (en) * 2004-03-16 2005-10-27 Yonosuke Ito Crack repairing method of structure
JP2010001686A (en) * 2008-06-23 2010-01-07 Ryozo Hirata Method of repairing linear crack occurring portion in concrete wall, or method of sealing joint at connection portion of concrete wall
JP2011080307A (en) * 2009-10-09 2011-04-21 Ryozo Hirata Repairing method of linear cracking section of concrete wall and joint sealing method in joint of concrete wall
JP2020159137A (en) * 2019-03-27 2020-10-01 旭化成ホームズ株式会社 Joint structure and method for repairing joint
CN113027160A (en) * 2020-04-17 2021-06-25 中建二局第一建筑工程有限公司 Concrete crack repairing method
CN111485922A (en) * 2020-05-13 2020-08-04 陕西上坤蓝箭科技有限公司 E L F railway tunnel water leakage, block falling and grout turnover disease treatment method
CN212742964U (en) * 2020-05-22 2021-03-19 中机工程(西安)启源咨询设计有限公司 Surface course gap processing structure on epoxy self-leveling air flotation ground
CN113323440A (en) * 2021-06-10 2021-08-31 上海凯顿百森建筑工程有限公司 Concrete gap repairing and anti-seepage treatment method

Similar Documents

Publication Publication Date Title
CN111456196B (en) Grouting structure for repairing sewage pipeline and pipeline grouting repairing method
CN107387123B (en) The construction method of pressure grouting leak stopping is carried out for shield duct piece piece leakage phenomenon
US20200318774A1 (en) Local repair method combining internally bonded CFRP and polymer grouting for cracks in drainage pipe
CN101776187B (en) Prestressed concrete glass fiber reinforced plastic compound tubing structure and manufacture process thereof
CN111253132B (en) Special polymer epoxy resin composite mortar material for centrifugal spraying of box culvert pipeline of non-excavation well chamber
CN104018526B (en) EPR deformation joint repairs water-stopping structure and construction method thereof
CN101240662A (en) Inner binding outer cramping method architecture structural crack comprehensive processing method
CN108716410B (en) Mechanical method connecting channel high-strength elastic wall post-grouting slurry and grouting method
CN101435192A (en) New and old concrete combining construction method
CN205558920U (en) Fissured repair structure of last lining cutting of tunnel wall
CN110080550B (en) Wall surface structure
CN113898202A (en) Concrete gap repairing and anti-seepage treatment method
CN201621381U (en) Prestressed concrete and glass fiber reinforced plastic composite pipe
CN110608052A (en) Tunnel segment based on high-performance cement-based composite material and construction method thereof
CN206175889U (en) Pipeline socket joint connection structure
CN108894102A (en) A kind of high-bearing capacity shock isolating pedestal and its manufacturing method
CN112031836B (en) Waterproof structure and method for deformation joint of tunnel by using femalemeter and coagulation method
CN210179083U (en) Glass fiber reinforced polyester concrete jacking pipe
CN112727219A (en) Corrosion-resistant and waterproof protection structure and method for system of concrete structure container type structure and application
CN208884344U (en) A kind of high-bearing capacity shock isolating pedestal
CN109555165B (en) Water leakage treatment process for deformation joint of underground space structure
CN111877786A (en) Construction method for repairing crack of ultra-long concrete structure
CN111350524A (en) Hydraulic shield tunnel composite lining structure and construction method thereof
KR102161107B1 (en) Waterproofing method using acrylic backing waterproofing agent
CN218117327U (en) Polymer composite rapid repairing terrace

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20220107

RJ01 Rejection of invention patent application after publication