CN113668613A - Application of GRP sewage well in ultra-deep sewage pipeline system - Google Patents

Application of GRP sewage well in ultra-deep sewage pipeline system Download PDF

Info

Publication number
CN113668613A
CN113668613A CN202110993077.3A CN202110993077A CN113668613A CN 113668613 A CN113668613 A CN 113668613A CN 202110993077 A CN202110993077 A CN 202110993077A CN 113668613 A CN113668613 A CN 113668613A
Authority
CN
China
Prior art keywords
pipeline
test
grp
approved
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110993077.3A
Other languages
Chinese (zh)
Inventor
陈正益
钱程
谌世荣
朱政稳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Jiangsu International Economic And Technical Cooperation Group Ltd
Original Assignee
China Jiangsu International Economic And Technical Cooperation Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Jiangsu International Economic And Technical Cooperation Group Ltd filed Critical China Jiangsu International Economic And Technical Cooperation Group Ltd
Priority to CN202110993077.3A priority Critical patent/CN113668613A/en
Publication of CN113668613A publication Critical patent/CN113668613A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Sewage (AREA)

Abstract

The invention discloses an application of a GRP sewage well in an ultra-deep sewage pipeline system, which comprises the steps of work preparation, pipeline installation, GRP well installation, a water closing test, a deflection ball passing test and the like. The invention reduces the secondary coating of GRP anticorrosive coating on the outer side of the concrete well, is prefabricated in a factory, saves the construction period, is convenient to install, can ensure the quality, and reduces the leakage of a sewage system through technical and technological innovation.

Description

Application of GRP sewage well in ultra-deep sewage pipeline system
Technical Field
The invention relates to an application of a GRP sewage well in an ultra-deep sewage pipeline system.
Background
In ultra-deep sewer line systems. How to reduce the problem that the concrete well is secondarily coated with a GRP anticorrosive coating on the outer side and reduce the leakage of a sewage system is a problem which needs to be solved for a long time in the field, and the problems can not be effectively solved by the existing construction technology. .
Disclosure of Invention
The invention aims to provide the application of the GRP sewage well in the ultra-deep sewage pipeline system, which saves the construction period, is convenient to install and reduces the leakage of a sewage system.
The technical solution of the invention is as follows:
the application of the GRP sewage well in the ultra-deep sewage pipeline system is characterized in that: comprises the following steps:
preparing for work:
the method comprises the following steps: preparing a pipeline; couplers and fittings to be installed on defective items, inspected by engineers, and then installed on trenches and replacement items, ensuring that the associated recipe statements are approved; submitting the RFI for pipeline laying; ensuring that traffic management is in place as required; submitting and approving a construction drawing of a specific project; confirmation of ILS of pipe/MHS; from prior to approved construction drawings/detailed design, the pipeline is installed with the pre-excavation precipitation system in place;
ensuring that the pipes and fittings are tested at the factory in compliance with ADSSC specifications and approved material submissions; ensure that the pipes and fittings are safe and reliable during transport, provide adequate support along their length and should be covered during transport; ensuring that the pipe and fittings are lifted using nylon or large diameter rope slings, the slings should be placed in the center and two per quarter of the pipe length from each side; the storage area must be covered with a sun cloth; the pipeline and the fittings are covered under the opaque sunshade cloth, and the sunshade cloth is not directly irradiated by sunlight at any time and keeps the air around the pipeline to freely flow; the rubber joint ring is stored in a well ventilated place and is not irradiated by sunlight; ensuring that each submitted QA/QC report is attached, and ensuring that the material is inspected and approved by a consultant, ensuring that the height of the stacked pipes does not exceed 2 m;
(II) pipeline installation
During transport from storage to construction, ensuring that the pipe and fittings are lifted using nylon or large diameter rope slings, one quarter of the pipe length should be placed from each side for lifting; the pipeline cutting uses special tools, and the installation, laying and connection of pipelines and fittings along a planned ditch bed and to lines and elevations are carried out by a machine; the laying of the pipeline is carried out from downstream to upstream; the ends of the pipes should be protected from any foreign material; before laying the pipeline, arranging geotextile in the groove, covering the pipeline with broken stone to cover the thickness of not less than 300mm, and once the pipeline is laid from the manhole to the manhole, checking whether the pipeline is aligned and elevated by an engineer; after approval, the bottom bed and top mat are compacted prior to backfilling, and after backfilling the trench, the layers should be layered with the selected materials and compacted as specified. Concrete is required to be wrapped and protected for the pipelines which are not deeply buried or pass through the pipelines, and the required concrete periphery is poured according to the size shown in a standard drawing, namely the specified outer diameter thickness; after concrete pouring, immediately covering and curing the surface for at least one day by using a polyethylene sheet;
the pipes should be tested as follows: a water closing test and a deflection ball test; quality assurance/quality control checks should ensure compliance with quality assurance/quality control procedures and specifications, and the mesh/warning tape should be used for safe and correct working procedures;
continuing excavating to a stratum elevation according to the approved construction drawing, and performing pipe well construction; the construction site will be kept clean all the time and continuously supervised; setting a safety barrier for foundation pit excavation according to a safety manual, rules and approved safety plans; after the foundation pit excavation reaches the stratum report, slowly excavating to a pipe bottom report according to an approved construction drawing; protecting the excavation side to avoid collapse; the formation level should be manually leveled and compacted with a compactor, as approved by engineers, to ensure a sufficiently firm formation;
if precipitation is required according to standard and approved protocols, formation compaction tests should be performed and the required compaction must be passed with an MDD of at least 95%; before pouring concrete, submitting WIR in advance, and checking elevation and coordination;
GRP well installation
(1) Concrete for foundation mat
The excavated foundation pit is leveled and compacted to a designed elevation; placing 1000G polyethylene plates before pouring so as to pour C20-grade concrete with the specified thickness of 100 mm; curing is carried out according to the regulations; if the excavation exceeds the elevation required by the design, filling the concrete with C20 grade concrete; the size of the template is required to be used for manufacturing a manhole base installation larger than 150mm according to an approved construction drawing; the waterproofing membrane should be installed according to the materials and methods of use approved by approved suppliers; leveling concrete is adopted for waterproof protection; the WIR acceptance needs to be submitted in advance before the manhole base is installed; filling the concrete in the base with C40;
(2) installing GRP manhole well
Checking and accepting the GRP well, closing the pouring hole, moving the GRP manhole out of the warehouse area by using a mobile crane, fixing chain slings on 4 lifting hooks, and loading a truck; the GRP well is the MH main well and will be installed at the final confirmation location according to the approved construction drawings; before the manhole is installed, please put forward inspection requirements to engineers in advance; after the MH main well is installed, the bobbin is lifted, and the centering direction is checked; repairing the background and pouring concrete around the background; filling the manhole layer by layer according to standard requirements, wherein the layering does not exceed 250mm, and each layer is tested for FDT 95%; the tests required for GRP (hydrostatic and deflection) should be performed as per standard requirements and approved by engineers for separate method statements; after the GRP manhole is installed, an engineer checks and measures the elevation, and then the upstream port and the downstream port of the manhole are connected; the pipe between the two manholes is tested and inspected according to an approved protocol, before laying the underlayment and the surround, and inspected by an engineer; before the manhole is installed, WIR inspection elevation and positioning are required to be submitted;
(IV) Water shut-off test
After the supervision approval is obtained, performing a water-closing test; water shut-off tests and pipeline cleaning with potable water, using appropriately designed fittings to temporarily close the opening in the pipeline for testing; sufficiently supported using a fitting to withstand a specified pressure; ensuring that the arrangement of the test pipes includes provisions for purging air from the pipes prior to the water test; in the case of multiple pipelines, either common or trench-laid, testing only one pipeline at any one time ensures availability and operational status of all test equipment; pressure gauges for testing pipes, the accuracy of which should be checked in a separate laboratory, providing engineers with detailed accuracy certificates, precipitation should be stopped at least 3 days before testing, all points must be checked before testing to avoid failures and to ensure that the trench keeps the dry line to be slowly and uniformly filled with drinking water, from lowest end point to highest point; installing a vent to release the entrapped air, leaving the test portion for stable observation after filling the pipeline with water; the filling rate of the waterline should be controlled to ensure proper and flow rate kept below the allowable limit for testing all non-pressurized pipes, after concrete or granular wrapping is completed, until the sewage system of the pipe is completed, cleaning the objects around the pipe joints, allowing visual inspection of leakage using a water head test for any depth inversion plus 1.0m or 5.0m, whichever is greater; the end socket at the lower end of the measuring pipeline keeps a water head for 30 minutes, and water is added from the measuring container every 10 minutes if necessary; recording the water addition of the measuring container, which is evaluated to pass the formula of the test; if any leaks or damage is found during the inspection, the pipe or joint must not be accepted; the length of the test pipe between manholes or the shorter length precipitation that an engineer may allow will stop 3 days before the test; saving all test records and providing for inspection; the process should be repeated until the specification requirements are met;
(V) deflection ball test
After a UPVC pipeline is installed, a water closing test and groove backfilling are carried out, but before precipitation is removed, a ball is pulled through the pipeline as soon as possible, so that the size of the ball cannot pass through any point in the pipeline, and the point is allowed to be larger than the point allowed after the initial installation; immediately before issuing the provisional acceptance certificate, passing the ball through the conduit so that it does not pass through any point in the conduit which is deflected to a greater extent than is permitted for a longer period of time, the conduit being replaced if any of these tests indicate that the deflection may exceed the permitted value;
detaching any pipeline which cannot be subjected to deflection inspection from the site, wherein all replaced pipelines are deflected; carrying out deflection test on 20m adjacent pipelines at two sides of the removed pipeline; the positive and negative deflections on the pipe must not exceed the following values: a 3m, 5% long term diameter reduction after initial installation should be considered as negative deflection.
In the middle of the work progress, some local change or deviation often can appear, especially in the well height, as long as it is more convenient to repair at certain increase height within range, utilizes finished product GRP pipe, directly with GRP glass steel glue butt joint increase, if the part that the superelevation appears also can directly cut off.
The invention reduces the secondary coating of GRP anticorrosive coating on the outer side of the concrete well, is prefabricated in a factory, saves the construction period, is convenient to install, can ensure the quality, and reduces the leakage of a sewage system through technical and technological innovation. Is particularly suitable for middle east.
The present invention will be further described with reference to the following examples.
Detailed Description
Use of a GRP bilge well in an ultra-deep bilge pipeline system, comprising the steps of:
preparing for work:
the method comprises the following steps: preparing a pipeline; couplers and fittings to be installed on defective items, inspected by engineers, and then installed on trenches and replacement items, ensuring that the associated recipe statements are approved; submitting the RFI for pipeline laying; ensuring that traffic management is in place as required; submitting and approving a construction drawing of a specific project; confirmation of ILS of pipe/MHS; from prior to approved construction drawings/detailed design, the pipeline is installed with the pre-excavation precipitation system in place;
ensuring that the pipes and fittings are tested at the factory in compliance with ADSSC specifications and approved material submissions; ensure that the pipes and fittings are safe and reliable during transport, provide adequate support along their length and should be covered during transport; ensuring that the pipe and fittings are lifted using nylon or large diameter rope slings, the slings should be placed in the center and two per quarter of the pipe length from each side; the storage area must be covered with a sun cloth; the pipeline and the fittings are covered under the opaque sunshade cloth, and the sunshade cloth is not directly irradiated by sunlight at any time and keeps the air around the pipeline to freely flow; the rubber joint ring is stored in a well ventilated place and is not irradiated by sunlight; ensuring that each submitted QA/QC report is attached, and ensuring that the material is inspected and approved by a consultant, ensuring that the height of the stacked pipes does not exceed 2 m;
(II) pipeline installation
During transport from storage to construction, ensuring that the pipe and fittings are lifted using nylon or large diameter rope slings, one quarter of the pipe length should be placed from each side for lifting; the pipeline cutting uses special tools, and the installation, laying and connection of pipelines and fittings along a planned ditch bed and to lines and elevations are carried out by a machine; the laying of the pipeline is carried out from downstream to upstream; the ends of the pipes should be protected from any foreign material; before laying the pipeline, arranging geotextile in the groove, covering the pipeline with broken stone to cover the thickness of not less than 300mm, and once the pipeline is laid from the manhole to the manhole, checking whether the pipeline is aligned and elevated by an engineer; after approval, the bottom bed and top mat are compacted prior to backfilling, and after backfilling the trench, the layers should be layered with the selected materials and compacted as specified. Concrete is required to be wrapped and protected for the pipelines which are not deeply buried or pass through the pipelines, and the required concrete periphery is poured according to the size shown in a standard drawing, namely the specified outer diameter thickness; after concrete pouring, immediately covering and curing the surface for at least one day by using a polyethylene sheet;
the pipes should be tested as follows: a water closing test and a deflection ball test; quality assurance/quality control checks should ensure compliance with quality assurance/quality control procedures and specifications, and the mesh/warning tape should be used for safe and correct working procedures;
continuing excavating to a stratum elevation according to the approved construction drawing, and performing pipe well construction; the construction site will be kept clean all the time and continuously supervised; setting a safety barrier for foundation pit excavation according to a safety manual, rules and approved safety plans; after the foundation pit excavation reaches the stratum report, slowly excavating to a pipe bottom report according to an approved construction drawing; protecting the excavation side to avoid collapse; the formation level should be manually leveled and compacted with a compactor, as approved by engineers, to ensure a sufficiently firm formation;
if precipitation is required according to standard and approved protocols, formation compaction tests should be performed and the required compaction must be passed with an MDD of at least 95%; before pouring concrete, submitting WIR in advance, and checking elevation and coordination;
GRP well installation
(1) Concrete for foundation mat
The excavated foundation pit is leveled and compacted to a designed elevation; placing 1000G polyethylene plates before pouring so as to pour C20-grade concrete with the specified thickness of 100 mm; curing is carried out according to the regulations; if the excavation exceeds the elevation required by the design, filling the concrete with C20 grade concrete; the size of the template is required to be used for manufacturing a manhole base installation larger than 150mm according to an approved construction drawing; the waterproofing membrane should be installed according to the materials and methods of use approved by approved suppliers; leveling concrete is adopted for waterproof protection; the WIR acceptance needs to be submitted in advance before the manhole base is installed; filling the concrete in the base with C40;
(2) installing GRP manhole well
Checking and accepting the GRP well, closing the pouring hole, moving the GRP manhole out of the warehouse area by using a mobile crane, fixing chain slings on 4 lifting hooks, and loading a truck; the GRP well is the MH main well and will be installed at the final confirmation location according to the approved construction drawings; before the manhole is installed, please put forward inspection requirements to engineers in advance; after the MH main well is installed, the bobbin is lifted, and the centering direction is checked; repairing the background and pouring concrete around the background; filling the manhole layer by layer according to standard requirements, wherein the layering does not exceed 250mm, and each layer is tested for FDT 95%; the tests required for GRP (hydrostatic and deflection) should be performed as per standard requirements and approved by engineers for separate method statements; after the GRP manhole is installed, an engineer checks and measures the elevation, and then the upstream port and the downstream port of the manhole are connected; the pipe between the two manholes is tested and inspected according to an approved protocol, before laying the underlayment and the surround, and inspected by an engineer; before the manhole is installed, WIR inspection elevation and positioning are required to be submitted;
(IV) Water shut-off test
After the supervision approval is obtained, performing a water-closing test; water shut-off tests and pipeline cleaning with potable water, using appropriately designed fittings to temporarily close the opening in the pipeline for testing; sufficiently supported using a fitting to withstand a specified pressure; ensuring that the arrangement of the test pipes includes provisions for purging air from the pipes prior to the water test; in the case of multiple pipelines, either common or trench-laid, testing only one pipeline at any one time ensures availability and operational status of all test equipment; pressure gauges for testing pipes, the accuracy of which should be checked in a separate laboratory, providing engineers with detailed accuracy certificates, precipitation should be stopped at least 3 days before testing, all points must be checked before testing to avoid failures and to ensure that the trench keeps the dry line to be slowly and uniformly filled with drinking water, from lowest end point to highest point; installing a vent to release the entrapped air, leaving the test portion for stable observation after filling the pipeline with water; the filling rate of the waterline should be controlled to ensure proper and flow rate kept below the allowable limit for testing all non-pressurized pipes, after concrete or granular wrapping is completed, until the sewage system of the pipe is completed, cleaning the objects around the pipe joints, allowing visual inspection of leakage using a water head test for any depth inversion plus 1.0m or 5.0m, whichever is greater; the end socket at the lower end of the measuring pipeline keeps a water head for 30 minutes, and water is added from the measuring container every 10 minutes if necessary; recording the water addition of the measuring container, which is evaluated to pass the formula of the test; if any leaks or damage is found during the inspection, the pipe or joint must not be accepted; the length of the test pipe between manholes or the shorter length precipitation that an engineer may allow will stop 3 days before the test; saving all test records and providing for inspection; the process should be repeated until the specification requirements are met;
(V) deflection ball test
After a UPVC pipeline is installed, a water closing test and groove backfilling are carried out, but before precipitation is removed, a ball is pulled through the pipeline as soon as possible, so that the size of the ball cannot pass through any point in the pipeline, and the point is allowed to be larger than the point allowed after the initial installation; immediately before issuing the provisional acceptance certificate, passing the ball through the conduit so that it does not pass through any point in the conduit which is deflected to a greater extent than is permitted for a longer period of time, the conduit being replaced if any of these tests indicate that the deflection may exceed the permitted value;
detaching any pipeline which cannot be subjected to deflection inspection from the site, wherein all replaced pipelines are deflected; carrying out deflection test on 20m adjacent pipelines at two sides of the removed pipeline; the positive and negative deflections on the pipe must not exceed the following values: a 3m, 5% long term diameter reduction after initial installation should be considered as negative deflection.
In the middle of the work progress, some local change or deviation often can appear, especially in the well height, as long as it is more convenient to repair at certain increase height within range, utilizes finished product GRP pipe, directly with GRP glass steel glue butt joint increase, if the part that the superelevation appears also can directly cut off.

Claims (2)

1. The application of the GRP sewage well in the ultra-deep sewage pipeline system is characterized in that: comprises the following steps:
preparing for work:
the method comprises the following steps: preparing a pipeline; couplers and fittings to be installed on defective items, inspected by engineers, and then installed on trenches and replacement items, ensuring that the associated recipe statements are approved; submitting the RFI for pipeline laying; ensuring that traffic management is in place as required; submitting and approving a construction drawing of a specific project; confirmation of ILS of pipe/MHS; from prior to approved construction drawings/detailed design, the pipeline is installed with the pre-excavation precipitation system in place;
ensuring that the pipes and fittings are tested at the factory in compliance with ADSSC specifications and approved material submissions; ensure that the pipes and fittings are safe and reliable during transport, provide adequate support along their length and should be covered during transport; ensuring that the pipe and fittings are lifted using nylon or large diameter rope slings, the slings should be placed in the center and two per quarter of the pipe length from each side; the storage area must be covered with a sun cloth; the pipeline and the fittings are covered under the opaque sunshade cloth, and the sunshade cloth is not directly irradiated by sunlight at any time and keeps the air around the pipeline to freely flow; the rubber joint ring is stored in a well ventilated place and is not irradiated by sunlight; ensuring that each submitted QA/QC report is attached, and ensuring that the material is inspected and approved by a consultant, ensuring that the height of the stacked pipes does not exceed 2 m;
(II) pipeline installation
During transport from storage to construction, ensuring that the pipe and fittings are lifted using nylon or large diameter rope slings, one quarter of the pipe length should be placed from each side for lifting; the pipeline cutting uses special tools, and the installation, laying and connection of pipelines and fittings along a planned ditch bed and to lines and elevations are carried out by a machine; the laying of the pipeline is carried out from downstream to upstream; the ends of the pipes should be protected from any foreign material; before laying the pipeline, arranging geotextile in the groove, covering the pipeline with broken stone to cover the thickness of not less than 300mm, and once the pipeline is laid from the manhole to the manhole, checking whether the pipeline is aligned and elevated by an engineer; after approval, the bottom bed and top mat are compacted prior to backfilling, and after backfilling the trench, the layers should be layered with the selected materials and compacted as specified. Concrete is required to be wrapped and protected for the pipelines which are not deeply buried or pass through the pipelines, and the required concrete periphery is poured according to the size shown in a standard drawing, namely the specified outer diameter thickness; after concrete pouring, immediately covering and curing the surface for at least one day by using a polyethylene sheet;
the pipes should be tested as follows: a water closing test and a deflection ball test; quality assurance/quality control checks should ensure compliance with quality assurance/quality control procedures and specifications, and the mesh/warning tape should be used for safe and correct working procedures;
continuing excavating to a stratum elevation according to the approved construction drawing, and performing pipe well construction; the construction site will be kept clean all the time and continuously supervised; setting a safety barrier for foundation pit excavation according to a safety manual, rules and approved safety plans; after the foundation pit excavation reaches the stratum report, slowly excavating to a pipe bottom report according to an approved construction drawing; protecting the excavation side to avoid collapse; the formation level should be manually leveled and compacted with a compactor, as approved by engineers, to ensure a sufficiently firm formation;
if precipitation is required according to standard and approved protocols, formation compaction tests should be performed and the required compaction must be passed with an MDD of at least 95%; before pouring concrete, submitting WIR in advance, and checking elevation and coordination;
GRP well installation
(1) Concrete for foundation mat
The excavated foundation pit is leveled and compacted to a designed elevation; placing 1000G polyethylene plates before pouring so as to pour C20-grade concrete with the specified thickness of 100 mm; curing is carried out according to the regulations; if the excavation exceeds the elevation required by the design, filling the concrete with C20 grade concrete; the size of the template is required to be used for manufacturing a manhole base installation larger than 150mm according to an approved construction drawing; the waterproofing membrane should be installed according to the materials and methods of use approved by approved suppliers; leveling concrete is adopted for waterproof protection; the WIR acceptance needs to be submitted in advance before the manhole base is installed; filling the concrete in the base with C40;
(2) installing GRP manhole well
Checking and accepting the GRP well, closing the pouring hole, moving the GRP manhole out of the warehouse area by using a mobile crane, fixing chain slings on 4 lifting hooks, and loading a truck; the GRP well is the MH main well and will be installed at the final confirmation location according to the approved construction drawings; before the manhole is installed, please put forward inspection requirements to engineers in advance; after the MH main well is installed, the bobbin is lifted, and the centering direction is checked; repairing the background and pouring concrete around the background; filling the manhole layer by layer according to standard requirements, wherein the layering does not exceed 250mm, and each layer is tested for FDT 95%; the testing of the GRP requirements should be performed as per the standard requirements and the individual method statements approved by the engineer; after the GRP manhole is installed, an engineer checks and measures the elevation, and then the upstream port and the downstream port of the manhole are connected; the pipe between the two manholes is tested and inspected according to an approved protocol, before laying the underlayment and the surround, and inspected by an engineer; before the manhole is installed, WIR inspection elevation and positioning are required to be submitted;
(IV) Water shut-off test
After the supervision approval is obtained, performing a water-closing test; water shut-off tests and pipeline cleaning with potable water, using appropriately designed fittings to temporarily close the opening in the pipeline for testing; sufficiently supported using a fitting to withstand a specified pressure; ensuring that the arrangement of the test pipes includes provisions for purging air from the pipes prior to the water test; in the case of multiple pipelines, either common or trench-laid, testing only one pipeline at any one time ensures availability and operational status of all test equipment; pressure gauges for testing pipes, the accuracy of which should be checked in a separate laboratory, providing engineers with detailed accuracy certificates, precipitation should be stopped at least 3 days before testing, all points must be checked before testing to avoid failures and to ensure that the trench keeps the dry line to be slowly and uniformly filled with drinking water, from lowest end point to highest point; installing a vent to release the entrapped air, leaving the test portion for stable observation after filling the pipeline with water; the filling rate of the waterline should be controlled to ensure proper and flow rate kept below the allowable limit for testing all non-pressurized pipes, after concrete or granular wrapping is completed, until the sewage system of the pipe is completed, cleaning the objects around the pipe joints, allowing visual inspection of leakage using a water head test for any depth inversion plus 1.0m or 5.0m, whichever is greater; the end socket at the lower end of the measuring pipeline keeps a water head for 30 minutes, and water is added from the measuring container every 10 minutes if necessary; recording the water addition of the measuring container, which is evaluated to pass the formula of the test; if any leaks or damage is found during the inspection, the pipe or joint must not be accepted; the length of the test pipe between manholes or the shorter length precipitation that an engineer may allow will stop 3 days before the test; saving all test records and providing for inspection; the process should be repeated until the specification requirements are met;
(V) deflection ball test
After a UPVC pipeline is installed, a water closing test and groove backfilling are carried out, but before precipitation is removed, a ball is pulled through the pipeline as soon as possible, so that the size of the ball cannot pass through any point in the pipeline, and the point is allowed to be larger than the point allowed after the initial installation; immediately before issuing the provisional acceptance certificate, passing the ball through the conduit so that it does not pass through any point in the conduit which is deflected to a greater extent than is permitted for a longer period of time, the conduit being replaced if any of these tests indicate that the deflection may exceed the permitted value;
detaching any pipeline which cannot be subjected to deflection inspection from the site, wherein all replaced pipelines are deflected; carrying out deflection test on 20m adjacent pipelines at two sides of the removed pipeline; the positive and negative deflections on the pipe must not exceed the following values: a 3m, 5% long term diameter reduction after initial installation should be considered as negative deflection.
2. The use of a GRP bilge well in an ultra-deep bilge pipeline system according to claim 1, wherein: in the middle of the work progress, some local change or deviation often can appear, especially in the well height, as long as it is more convenient to repair at certain increase height within range, utilizes finished product GRP pipe, directly with GRP glass steel glue butt joint increase, if the part that the superelevation appears also can directly cut off.
CN202110993077.3A 2021-08-27 2021-08-27 Application of GRP sewage well in ultra-deep sewage pipeline system Pending CN113668613A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110993077.3A CN113668613A (en) 2021-08-27 2021-08-27 Application of GRP sewage well in ultra-deep sewage pipeline system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110993077.3A CN113668613A (en) 2021-08-27 2021-08-27 Application of GRP sewage well in ultra-deep sewage pipeline system

Publications (1)

Publication Number Publication Date
CN113668613A true CN113668613A (en) 2021-11-19

Family

ID=78546738

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110993077.3A Pending CN113668613A (en) 2021-08-27 2021-08-27 Application of GRP sewage well in ultra-deep sewage pipeline system

Country Status (1)

Country Link
CN (1) CN113668613A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5553975A (en) * 1995-05-15 1996-09-10 Elkins; Michael L. Method of installing underground pipes for sewer lines
CN106978843A (en) * 2017-04-25 2017-07-25 杭州之江市政建设有限公司 Municipal drainage pipeline construction technology
CN107761911A (en) * 2016-08-17 2018-03-06 彭建明 A kind of construction method for the blowdown pipe network for improving installation quality
CN108589885A (en) * 2018-04-24 2018-09-28 青岛新华友建工集团股份有限公司 Finished product sewage network construction under complex geological condition
JP2019099994A (en) * 2017-11-28 2019-06-24 アロン化成株式会社 Drain piping structure and drain piping method
CN110306616A (en) * 2019-08-02 2019-10-08 中交上海航道局有限公司 A kind of construction method of sewage conduct
CN110926727A (en) * 2019-12-09 2020-03-27 中交上海航道局有限公司 Water closing test method for plastic drainage pipeline in rural domestic sewage collection project
CN112145792A (en) * 2020-09-25 2020-12-29 中建六局水利水电建设集团有限公司 PCCP pipeline construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5553975A (en) * 1995-05-15 1996-09-10 Elkins; Michael L. Method of installing underground pipes for sewer lines
CN107761911A (en) * 2016-08-17 2018-03-06 彭建明 A kind of construction method for the blowdown pipe network for improving installation quality
CN106978843A (en) * 2017-04-25 2017-07-25 杭州之江市政建设有限公司 Municipal drainage pipeline construction technology
JP2019099994A (en) * 2017-11-28 2019-06-24 アロン化成株式会社 Drain piping structure and drain piping method
CN108589885A (en) * 2018-04-24 2018-09-28 青岛新华友建工集团股份有限公司 Finished product sewage network construction under complex geological condition
CN110306616A (en) * 2019-08-02 2019-10-08 中交上海航道局有限公司 A kind of construction method of sewage conduct
CN110926727A (en) * 2019-12-09 2020-03-27 中交上海航道局有限公司 Water closing test method for plastic drainage pipeline in rural domestic sewage collection project
CN112145792A (en) * 2020-09-25 2020-12-29 中建六局水利水电建设集团有限公司 PCCP pipeline construction method

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
中国市政工程协会: "《中国市政工程海绵城市建设 实用技术手册》", 30 June 2017, 中国建材工业出版社 *
本书编委会: "《园林工程监理一本通》", 31 August 2007, 地震出版社 *
杨云芳等: "《城市道路工程施工监理要点》", 29 February 2004, 人民交通出版社 *
段琪: "钢筋混凝土排水管道施工质量控制分析", 《石家庄铁道大学学报(自然科学版)》 *
王旭: "《管道施工简明手册(第三版)》", 31 January 2008, 上海科学技术出版社 *

Similar Documents

Publication Publication Date Title
CN101565964A (en) Construction method for mounting outdoor embedded high-density polyethylene double-wall corrugated drain pipe
CN108612910B (en) Construction method for installing T-shaped nodular cast iron pipe
CN111059353B (en) Construction method of water supply pipeline
CN101858161B (en) Construction method of low-temperature double-wall storage tanks
CN104776268B (en) Mechanical construction method for mounting large-caliber reinforced concrete drainage pipe
CN115262730A (en) Construction method of rain sewage pipeline
CN107035918A (en) One kind feedwater pipe fitting engineering construction method
CN113668613A (en) Application of GRP sewage well in ultra-deep sewage pipeline system
CN207327592U (en) A kind of Pneumatic turnover equipment for pipeline rehabilitation
Kou et al. Application progress of oil and gas pipeline rehabilitation technology
CN113338983B (en) Large-pipe-diameter mud-water balance jacking pipe construction method suitable for high-water-level rock geology
CN113374055A (en) Construction method of buried reinforced HDPE (high-density polyethylene) spiral corrugated pipe
CN114855822A (en) Construction method for deep foundation pit of rain sewage pipeline on highway
CN110906058B (en) Construction method of thermosetting resin pipeline in desert soil
CN112112248A (en) Method for repairing defect of channel box
Tanks Installation Instructions
CN117107882A (en) Connection sealing method for lining type prestress steel cylinder concrete pipe joint
CN117781028A (en) Large-diameter long-distance pipeline hoisting construction process
CN111075992B (en) Water supply pipeline construction method
CN117432044A (en) Building water supply and drainage installation process
GARDINER et al. NORTHSHORE UTILITY DISTRICT
American Concrete Pipe Association Concrete pipe and box culvert installation
CN118065413A (en) Steel sleeve box-open caisson construction method for water-rich geological integrated pump station
CN115560128A (en) Construction and acceptance inspection process for large-diameter bamboo-wound composite pipeline
Berry et al. Grouting around Trenchless Repairs: The Forgotten Technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211119

RJ01 Rejection of invention patent application after publication