CN113550303A - Pile forming method for down-the-hole impact high-pressure jet grouting composite pile - Google Patents

Pile forming method for down-the-hole impact high-pressure jet grouting composite pile Download PDF

Info

Publication number
CN113550303A
CN113550303A CN202110860097.3A CN202110860097A CN113550303A CN 113550303 A CN113550303 A CN 113550303A CN 202110860097 A CN202110860097 A CN 202110860097A CN 113550303 A CN113550303 A CN 113550303A
Authority
CN
China
Prior art keywords
pile
hole
pressure
jet grouting
forming
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110860097.3A
Other languages
Chinese (zh)
Inventor
蒋仕清
姜大伟
汤湘军
乌青松
柳东
黄俊辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cnbm Guilin Geological Engineering Investigation Institute Co ltd
Original Assignee
Cnbm Guilin Geological Engineering Investigation Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cnbm Guilin Geological Engineering Investigation Institute Co ltd filed Critical Cnbm Guilin Geological Engineering Investigation Institute Co ltd
Priority to CN202110860097.3A priority Critical patent/CN113550303A/en
Publication of CN113550303A publication Critical patent/CN113550303A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention provides a down-the-hole impact high-pressure jet grouting composite pile forming method, including S1 pile hole forming step, S2 high-pressure jet grouting pile forming step and S3 precast pile sinking step, its step lies in that the down-the-hole hammer is impacted and drilled into the pile hole under the drive of high-pressure air, at the same time, the injector nozzle of the down-the-hole impact high-pressure jet grouting drill sprays high-pressure jet grouting cement paste to cut, stir and reinforce the soil body around the pile to form uniform cement-soil mixture, then the precast pile whose diameter is smaller than the hole forming aperture of the down-the-hole hammer is driven into the hole bottom along the center of the high-pressure jet grouting pile by adopting a hammering pile machine or a static pressure pile machine, thus forming the composite pile, the pile forming method can be applied to the aspects of foundation treatment, pile foundation, foundation pit support, water-stop curtain, eliminating or reducing the dilatancy of foundation liquefaction and expansive soil, etc., it has the advantages of stable quality, convenient construction, saving the construction period, saving material and construction cost, the manufacturing cost is reduced, and the like.

Description

Pile forming method for down-the-hole impact high-pressure jet grouting composite pile
Technical Field
The invention belongs to the field of geotechnical engineering, and particularly relates to a pile forming method of a down-the-hole impact high-pressure jet grouting composite pile.
Background
In the geotechnical engineering field, the bored concrete pile that punches is applicable to and has the multilayer solution cavity in the underground, but the hole is little and the thin geological conditions of upper portion roof, and this kind of pile can punch through upper solution cavity roof, reaches lower floor solution cavity roof, but when the underground has big solution cavity, and the pouring concrete can cause concrete loss and be difficult to control. The cast-in-situ bored pile can be embedded into rock, has high bearing capacity, can drill through underground boulders and interlayers, but easily generates the phenomena of drill burying, drill dropping, inclined piles and the like in bedrock with a plurality of cracks, seriously prolongs the construction period and has low economic benefit when being used for treating the problems; the prestressed pipe pile has the advantages of high pile body bearing capacity and short construction period, is suitable for geological conditions such as silt, soil cavern, quicksand, underground river communication and the like, but sometimes has overlong piles due to large rock surface fluctuation and high inclined pile and broken pile rate. In summary, a single pile type is difficult to meet the requirements of feasible technology, reliable quality, economy, reasonability and the like. Therefore, a better pile type is urgently expected to be found in engineering practice, the advantages of the respective single pile types can be integrated, the good matching of the pile body strength and the bearing capacity of the surrounding rock soil of the pile is realized, and the problem that the over-irrigation amount of concrete is uncontrollable is solved.
Disclosure of Invention
In order to overcome the defects of the prior art, the invention aims to provide a method for forming a down-the-hole impact high-pressure jet grouting composite pile, which aims to solve the problems in the background technology.
The technical scheme of the invention provides a pile forming method of a down-the-hole impact high-pressure jet grouting composite pile, which comprises the following steps:
s1 pile hole forming step: the hammer of the down-the-hole impact high-pressure jet drilling machine provides high-pressure air, and the down-the-hole hammer is driven by the high-pressure air to impact and drill to form a pile hole;
s2 high-pressure jet grouting pile forming step: jetting high-pressure cement slurry to surrounding soil bodies by a jet nozzle of a down-the-hole impact high-pressure jet drilling machine to perform high-pressure jet grouting to form a high-pressure jet grouting pile;
s3 precast pile sinking step: the pile hammering machine or the static pressure pile machine drives the precast pile with the diameter smaller than the hole forming aperture of the down-the-hole hammer into the bottom of the hole of the pile hole along the center of the high-pressure jet grouting pile to form the composite pile.
Further, in the step of forming the hole by the S1 pile hole, the air pressure of high-pressure air is not lower than 20 Mpa.
Further, the step of forming the hole by the S1 pile hole further comprises the step of spraying high-pressure cement slurry by nozzles on the periphery of the upper part of the impactor to cut, soften, vibrate, densify and impact and crush the surrounding soil body, wherein the pressure of the high-pressure cement slurry is not lower than 5 Mpa.
Further, the step of forming the S2 high-pressure jet grouting pile further comprises the step of jetting high-pressure air at the bottom of the down-the-hole hammer to extrude the high-pressure cement paste to the periphery, and stirring and mixing the high-pressure cement paste with the surrounding soil body to form a uniform cement-soil mixture.
Further, in the step of forming the S2 high-pressure jet grouting pile, the jet pressure of the high-pressure cement paste is 20-25 Mpa.
Further, in the step of sinking the precast pile S3, the precast pile may include any one of a tubular pile, a hollow square pile, a bamboo joint pile, and a screw pile.
Further, the down-the-hole hammer is of a high frequency vibratory type.
Further, in the step of forming the hole by the S1 pile hole, the diameter of the pile hole is 500-1200 mm.
Further, the down-the-hole impact high-pressure jet grouting composite pile is formed by a pile forming method of the down-the-hole impact high-pressure jet grouting composite pile, is of a concentric annular sandwich structure and comprises a flexible outer pile, a flexible precast pile in wrapping connection with the flexible outer pile and a flexible pile core in wrapping connection with the flexible precast pile.
Compared with the prior art, the invention has the technical characteristics that: (1) the soil around the pile is improved, and the side friction resistance is improved; (2) the construction is similar to dry operation, and the environmental pollution is small; (3) a down-the-hole hammer is used for forming holes, high-pressure jet grouting is followed with jet, a non-borrowing construction process is adopted, and pile-forming waste soil is reduced; (4) the pipe pile adopts hammering soil squeezing construction to squeeze soil around the pile, so that the side frictional resistance of the soil around the pile is improved again; (5) the bearing capacity of a single pile is higher than that of a immersed tube cast-in-place pile or a drilling cast-in-place pile with the same diameter; (6) the construction progress is fast, the construction quality is easy to guarantee, the pile breaking accidents are few, and the hidden danger of concrete segregation is avoided; (7) after the high-pressure rotary spraying guniting cementing solidification, the sediment at the bottom of the pile is very little; (8) the rock-socketed depth is easy to guarantee, and the problem that the pile foundation of the hard rock layer is difficult to enter the rock is effectively solved; (9) under the same single pile bearing capacity requirement, the down-the-hole impact high-pressure jet grouting composite pile is low in manufacturing cost, and particularly has more obvious manufacturing cost advantage in a hard rock stratum.
The invention has the following beneficial effects:
the composite pile is characterized by that it integrates the advantages of prefabricated pile and jet grouting pile, and can utilize the conditions of different geological conditions, upper structure requirements and reinforcement goal to pertinently and flexibly regulate pile diameter, pile length, ash-mixing quantity and strength of various piles so as to make the composite pile fully give out side friction resistance of soft soil around the pile, at the same time it can effectively solve the problem of that the construction difficulty of embedding prefabricated pile into hard rock is large, ensure rock-socketing depth and raise single pile bearing capacity, and can obviously raise the strength of soil body between piles and participation degree to bearing so as to meet different design requirements.
Drawings
The present invention will be described in detail with reference to the accompanying drawings.
FIG. 1 is a schematic flow chart of a method according to an embodiment of the present invention;
fig. 2 is a schematic cross-sectional view of a composite pile according to an embodiment of the invention;
FIG. 3 is a schematic longitudinal section of a composite pile according to an embodiment of the invention;
fig. 4 is a schematic diagram of composite pile hammering construction according to the embodiment of the present invention.
The method comprises the following steps of 1, 2, 3 and 4, namely a down-the-hole impact high-pressure jet grouting composite pile, an external pile and a pile core.
Detailed Description
Embodiments according to the present invention will now be described in detail with reference to the accompanying drawings.
Referring to fig. 1 to 4, the invention relates to a pile forming method of a down-the-hole impact high-pressure jet grouting composite pile, which comprises an S1 pile hole forming step, an S2 high-pressure jet grouting pile forming step and an S3 precast pile sinking step.
Example 1
High-quality R42.5# ordinary silica cement is selected, and the maximum water level line is calibrated according to the size of the stirring barrel, the water-cement ratio and the mud proportion. Adding cement according to the water cement ratio of 1:1, fully stirring, and determining whether the specific gravity of the slurry reaches the trial specific gravity of 1.47 or not, if not, continuing to add the cement until the trial specific gravity of the cement slurry is reached. The stirring time can not exceed the initial setting time of the cement paste, and the cement paste is filtered by two filter screens to prevent the nozzle from being blocked.
S1 pile hole forming step: after the down-the-hole impact high-pressure rotary jet drilling machine is in place, the verticality deviation is not more than +/-0.5% after correction, the down-the-hole hammer is driven to drill under the drive of 20Mpa high-pressure air provided by an impactor at the bottom of a drill rod until the depth reaches 10m, the diameter of a pile hole is 800mm, and meanwhile, 5Mpa high-pressure cement slurry is sprayed on a soil body for the first time through nozzles on the periphery of the upper part of the impactor, so that the effects of cutting, softening, vibrating compaction and impact crushing are achieved through rotary jet. The combined action of the high-frequency vibration impact of the down-the-hole hammer and the high-pressure air can also generate a 'micro air explosion' effect in the space at the bottom of the hammer, further enhance the impact damage capability to cohesive soil, silt and sandy soil, adjust the positions of the stones through vibration and air explosion on pebble and stone strata, open a channel and facilitate the follow-up cement paste to enter a reinforced area.
S2 high-pressure jet grouting pile forming step: after the hole is formed, lifting the drill rod to start high-pressure rotary spraying, and performing 20Mpa high-pressure jet grouting from a nozzle on the side wall of the ejector to the surrounding soil body from bottom to top; at the moment, the soil body in the flow plastic or liquefied state is fully stirred and mixed by the high-pressure cement slurry sprayed around the sprayer, meanwhile, the stirring and mixing force can be increased by the high-pressure gas sprayed at the bottom of the hammer, the slurry is extruded around, and the reinforced soil body is injected along the pores and channels opened by gas explosion, so that a uniform cement-soil mixture is formed. When the re-spraying is carried out within the range of 1m below the pile head, the drill is slowly lifted and ascended, and the re-spraying is carried out once, so that the compactness of the pile body is increased. Because the range of 1m below the pile top can bear larger load, the mass of the pile body at the position is strengthened to play a key role in exerting the bearing capacity of the pile body.
S3 precast pile sinking step: within 4h after the construction of the high-pressure jet grouting pile is completed, a hammering pile machine or a static pressure pile machine is adopted to drive the precast pile 2 with the diameter smaller than the hole forming aperture of the down-the-hole hammer into the bottom of the hole along the center of the high-pressure jet grouting pile, so that the composite pile is formed.
In the embodiment, the precast pile adopts a tubular pile which is a hollow cylindrical elongated concrete precast member manufactured by a prestress process and a centrifugal forming method, the type of the hollow cylindrical elongated concrete precast member is PHC-600-AB-125-C80, the diameter of the pile is 600mm, and the wall thickness is 125 mm.
According to general construction experience, main technical and economic parameters of a cast-in-situ bored pile and a down-the-hole impact high-pressure jet grouting composite pile (1) in the Guangxi karst region are compared, the cast-in-situ bored pile is a common reinforced concrete pile with the diameter of phi 800, the process pile of the down-the-hole impact high-pressure jet grouting composite pile method adopts a down-the-hole hammer to impact the hole with the diameter of phi 800, and the PHC-600-AB-125-C80 prefabricated pipe pile is implanted after jet grouting. The technical and economic parameters are compared as shown in the following table:
Figure BDA0003185506720000031
Figure BDA0003185506720000041
under the same condition, the characteristic value of the bearing capacity of a single pile of the process pile applied to the down-the-hole impact high-pressure jet grouting composite pile method in the karst area in Guangxi is improved by about 12-14% compared with a cast-in-situ bored pile, the manufacturing cost of the single pile is reduced by about 6-25% compared with the cast-in-situ bored pile, and the unit bearing capacity manufacturing cost is reduced by about 24-34% compared with the cast-in-situ bored pile.
Example 2
High-quality R42.5# ordinary silica cement is selected, and the maximum water level line is calibrated according to the size of the stirring barrel, the water-cement ratio and the mud proportion. Adding cement according to the water cement ratio of 1:1, fully stirring, and determining whether the specific gravity of the slurry reaches the trial specific gravity of 1.47 or not, if not, continuing to add the cement until the trial specific gravity of the cement slurry is reached. The stirring time can not exceed the initial setting time of the cement paste, and the cement paste is filtered by two filter screens to prevent the nozzle from being blocked.
S1 pile hole forming step: after the down-the-hole impact high-pressure rotary jet drilling machine is in place, the verticality deviation is not more than +/-0.5% after correction, the down-the-hole hammer is driven to drill under the drive of 20Mpa high-pressure air provided by an impactor at the bottom of a drill rod until the depth reaches 10m of the design depth, the diameter of a pile hole is 1000mm, meanwhile, 10Mpa high-pressure cement slurry is sprayed on a soil body for the first time through nozzles on the periphery of the upper part of the impactor, and the rotary jet drilling machine plays roles in cutting, softening, vibrating compaction and impact crushing. The combined action of the high-frequency vibration impact of the down-the-hole hammer and the high-pressure air can also generate a 'micro air explosion' effect in the space at the bottom of the hammer, further enhance the impact damage capability to cohesive soil, silt and sandy soil, adjust the positions of the stones through vibration and air explosion on pebble and stone strata, open a channel and facilitate the follow-up cement paste to enter a reinforced area.
S2 high-pressure jet grouting pile forming step: lifting the drill rod to start high-pressure rotary spraying after hole forming is finished, and performing 25Mpa high-pressure jet grouting from a nozzle on the side wall of the ejector to the surrounding soil body from bottom to top; at the moment, the soil body in the flow plastic or liquefied state is fully stirred and mixed by the high-pressure cement slurry sprayed around the sprayer, meanwhile, the stirring and mixing force can be increased by the high-pressure gas sprayed at the bottom of the hammer, the slurry is extruded around, and the reinforced soil body is injected along the pores and channels opened by gas explosion, so that a uniform cement-soil mixture is formed. When the re-spraying is carried out within the range of 1m below the pile head, the drill is slowly lifted and ascended, and the re-spraying is carried out once, so that the compactness of the pile body is increased. Because the range of 1m below the pile top can bear larger load, the mass of the pile body at the position is strengthened to play a key role in exerting the bearing capacity of the pile body.
S3 precast pile sinking step: within 4h after the construction of the high-pressure jet grouting pile is completed, a hammering pile machine or a static pressure pile machine is adopted to drive the precast pile 2 with the diameter smaller than the hole forming aperture of the down-the-hole hammer into the bottom of the hole along the center of the high-pressure jet grouting pile, so that the composite pile is formed.
In the embodiment, the precast pile adopts a tubular pile which is a hollow cylindrical elongated concrete precast member manufactured by a prestress process and a centrifugal forming method, the type of the hollow cylindrical elongated concrete precast member is PHC-600-AB-125-C80, the diameter of the pile is 600mm, and the wall thickness is 125 mm.
According to general construction experience, main technical and economic parameters of a cast-in-situ bored pile and a down-the-hole impact high-pressure jet grouting composite pile (1) in the Guangxi karst region are compared, the cast-in-situ bored pile is a common reinforced concrete pile with the diameter of phi 1000, a down-the-hole impact high-pressure jet grouting composite pile method process pile adopts a down-the-hole hammer to impact the hole with the diameter of phi 1000, and a PHC-600-AB-125-C80 prefabricated pipe pile is implanted after jet grouting. The technical and economic parameters are compared as shown in the following table:
Figure BDA0003185506720000051
under the same condition, the characteristic value of the bearing capacity of a single pile of the process pile applied to the down-the-hole impact high-pressure jet grouting composite pile method in the karst area in Guangxi is improved by about 11-12% compared with a cast-in-situ bored pile, the manufacturing cost of the single pile is reduced by about 8-15% compared with the cast-in-situ bored pile, and the unit bearing capacity manufacturing cost is reduced by about 17-24% compared with the cast-in-situ bored pile.
Example 3
High-quality R42.5# ordinary silica cement is selected, and the maximum water level line is calibrated according to the size of the stirring barrel, the water-cement ratio and the mud proportion. Adding cement according to the water cement ratio of 1:1, fully stirring, and determining whether the specific gravity of the slurry reaches the trial specific gravity of 1.47 or not, if not, continuing to add the cement until the trial specific gravity of the cement slurry is reached. The stirring time can not exceed the initial setting time of the cement paste, and the cement paste is filtered by two filter screens to prevent the nozzle from being blocked.
S1 pile hole forming step: after the down-the-hole impact high-pressure rotary jet drilling machine is in place, the verticality deviation is not more than +/-0.5% after correction, a down-the-hole hammer is driven to drill under the driving of 25Mpa high-pressure air provided by an impactor at the bottom of a drill rod until the depth reaches 10m of the design depth, the diameter of a pile hole is 1200mm, meanwhile, 10Mpa high-pressure cement slurry is sprayed to a soil body for the first time through nozzles on the periphery of the upper portion of the impactor, and the rotary jet drilling machine plays roles in cutting, softening, vibrating and compacting and impacting and crushing. The combined action of the high-frequency vibration impact of the down-the-hole hammer and the high-pressure air can also generate a 'micro air explosion' effect in the space at the bottom of the hammer, further enhance the impact damage capability to cohesive soil, silt and sandy soil, adjust the positions of the stones through vibration and air explosion on pebble and stone strata, open a channel and facilitate the follow-up cement paste to enter a reinforced area.
S2 high-pressure jet grouting pile forming step: lifting the drill rod to start high-pressure rotary spraying after hole forming is finished, and performing 25Mpa high-pressure jet grouting from a nozzle on the side wall of the ejector to the surrounding soil body from bottom to top; at the moment, the soil body in the flow plastic or liquefied state is fully stirred and mixed by the high-pressure cement slurry sprayed around the sprayer, meanwhile, the stirring and mixing force can be increased by the high-pressure gas sprayed at the bottom of the hammer, the slurry is extruded around, and the reinforced soil body is injected along the pores and channels opened by gas explosion, so that a uniform cement-soil mixture is formed. When the re-spraying is carried out within the range of 1m below the pile head, the drill is slowly lifted and ascended, and the re-spraying is carried out once, so that the compactness of the pile body is increased. Because the range of 1m below the pile top can bear larger load, the mass of the pile body at the position is strengthened to play a key role in exerting the bearing capacity of the pile body.
S3 precast pile sinking step: within 4h after the construction of the high-pressure jet grouting pile is completed, a hammering pile machine or a static pressure pile machine is adopted to drive the precast pile 2 with the diameter smaller than the hole forming aperture of the down-the-hole hammer into the bottom of the hole along the center of the high-pressure jet grouting pile, so that the composite pile is formed.
In the embodiment, the precast pile adopts a tubular pile which is a hollow cylindrical elongated concrete precast member manufactured by a prestress process and a centrifugal forming method, the type of the hollow cylindrical elongated concrete precast member is PHC-600-AB-125-C80, the diameter of the pile is 600mm, and the wall thickness is 125 mm.
According to general construction experience, main technical and economic parameters of a cast-in-situ bored pile and a down-the-hole impact high-pressure jet grouting composite pile (1) in the Guangxi karst region are compared, the cast-in-situ bored pile is a relatively common reinforced concrete pile with the diameter of phi 1200, a down-the-hole impact high-pressure jet grouting composite pile method process pile adopts a down-the-hole hammer to impact the hole with the diameter of phi 1200, and a PHC-600-AB-125-C80 prefabricated pipe pile is implanted after jet grouting. The technical and economic parameters are compared as shown in the following table:
Figure BDA0003185506720000061
under the same condition, the characteristic value of the bearing capacity of a single pile of the process pile applied to the down-the-hole impact high-pressure jet grouting composite pile method in the karst area in Guangxi is improved by about 10-11% compared with a cast-in-situ bored pile, the manufacturing cost of the single pile is reduced by about 4-8% compared with the cast-in-situ bored pile, and the unit bearing capacity manufacturing cost is reduced by about 12-17% compared with the cast-in-situ bored pile.
While there have been shown and described what are at present considered the fundamental principles and essential features of the invention and its advantages, it will be apparent to those skilled in the art that the invention is not limited to the details of the foregoing exemplary embodiments, but is capable of other specific forms without departing from the spirit or essential characteristics thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (9)

1. A pile forming method for a down-the-hole impact high-pressure jet grouting composite pile is characterized by comprising the following steps: the method comprises the following steps:
s1 pile hole forming step: the hammer of the down-the-hole impact high-pressure jet drilling machine provides high-pressure air, and the down-the-hole hammer is driven by the high-pressure air to impact and drill to form a pile hole;
s2 high-pressure jet grouting pile forming step: jetting high-pressure cement slurry to surrounding soil bodies by a jet nozzle of a down-the-hole impact high-pressure jet drilling machine to perform high-pressure jet grouting to form a high-pressure jet grouting pile;
s3 precast pile sinking step: the pile hammering machine or the static pressure pile machine drives the precast pile with the diameter smaller than the hole forming aperture of the down-the-hole hammer into the bottom of the hole of the pile hole along the center of the high-pressure jet grouting pile to form the composite pile.
2. The method for forming the down-the-hole impact high-pressure jet grouting composite pile according to claim 1, characterized by comprising the following steps: and in the step of forming the hole in the S1 pile hole, the air pressure of high-pressure air is not lower than 20 Mpa.
3. The method for forming the down-the-hole impact high-pressure jet grouting composite pile according to claim 1, characterized by comprising the following steps: and the step of forming the hole by the S1 pile hole further comprises the step of spraying high-pressure cement slurry by nozzles on the periphery of the upper part of the impactor to cut, soften, vibrate, densify and impact and crush the surrounding soil body, wherein the pressure of the high-pressure cement slurry is not lower than 5 Mpa.
4. The method for forming the down-the-hole impact high-pressure jet grouting composite pile according to claim 1, characterized by comprising the following steps: and the S2 high-pressure jet grouting pile forming step also comprises the step of jetting high-pressure air at the bottom of the down-the-hole hammer to extrude the high-pressure cement paste to the periphery, and stirring and mixing the high-pressure cement paste with the surrounding soil body to form a uniform cement-soil mixture.
5. The method for forming the down-the-hole impact high-pressure jet grouting composite pile according to claim 1, characterized by comprising the following steps: and in the S2 high-pressure jet grouting pile forming step, the high-pressure cement paste jet pressure is 20-25 Mpa.
6. The method for forming the down-the-hole impact high-pressure jet grouting composite pile according to claim 1, characterized by comprising the following steps: and S3 precast pile sinking step, wherein the precast pile comprises any one of a tubular pile, a hollow square pile, a bamboo joint pile and a threaded pile.
7. The method for forming the down-the-hole impact high-pressure jet grouting composite pile according to claim 1, characterized by comprising the following steps: the down-the-hole hammer is in a high-frequency vibration mode.
8. The method for forming the down-the-hole impact high-pressure jet grouting composite pile according to claim 1, characterized by comprising the following steps: and in the step of forming the hole by the S1 pile hole, the diameter of the pile hole is 500-1200 mm.
9. A down-the-hole impact high-pressure rotary jet composite pile (1), which is formed by the pile-forming method of the down-the-hole impact high-pressure rotary jet composite pile (1) according to any one of claims 1 to 8, wherein the down-the-hole impact high-pressure rotary jet composite pile (1) is a concentric annular sandwich structure and comprises an outer pile (3), a precast pile (2) connected with the outer pile (3) in a wrapping manner and a pile core (4) connected with the precast pile (2) in a wrapping manner.
CN202110860097.3A 2021-07-28 2021-07-28 Pile forming method for down-the-hole impact high-pressure jet grouting composite pile Pending CN113550303A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110860097.3A CN113550303A (en) 2021-07-28 2021-07-28 Pile forming method for down-the-hole impact high-pressure jet grouting composite pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110860097.3A CN113550303A (en) 2021-07-28 2021-07-28 Pile forming method for down-the-hole impact high-pressure jet grouting composite pile

Publications (1)

Publication Number Publication Date
CN113550303A true CN113550303A (en) 2021-10-26

Family

ID=78133142

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110860097.3A Pending CN113550303A (en) 2021-07-28 2021-07-28 Pile forming method for down-the-hole impact high-pressure jet grouting composite pile

Country Status (1)

Country Link
CN (1) CN113550303A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114703847A (en) * 2022-04-13 2022-07-05 珠海市三湘建筑基础工程有限公司 Construction process method of pulse hydraulic static pile machine

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005113573A (en) * 2003-10-09 2005-04-28 Fudo Constr Co Ltd Composite pile and its execution method
RU2004105094A (en) * 2004-02-20 2005-07-20 Анатолий Иванович Полищук (RU) METHOD FOR CONSTRUCTION OF INJECTION PILES (OPTIONS)
CN101255696A (en) * 2008-04-14 2008-09-03 河南国基建设集团有限公司 PHC pipe-pile pile-anchor combined support water stop construction method
CN105964678A (en) * 2016-06-23 2016-09-28 北京建工环境修复股份有限公司 Soil and groundwater in-situ remediation system and method through in-situ infusion and high-pressure jet grouting injection
CN107023002A (en) * 2016-08-30 2017-08-08 北京荣创岩土工程股份有限公司 Down-the-hole impacts churning composite pile pile making method
CN206956714U (en) * 2016-08-25 2018-02-02 北京荣创岩土工程股份有限公司 Down-the-hole impacts rotating spraying mixture pile construction equipment
CN207904903U (en) * 2017-12-04 2018-09-25 汤湘军 Down-hole hammer grouting behind shaft or drift lining prefabricating composite pile
DE202018106282U1 (en) * 2018-11-05 2018-11-28 Stump Spezialtiefbau Gmbh API drill pipe
CN109518676A (en) * 2018-11-06 2019-03-26 北京荣创岩土工程股份有限公司 A kind of method of micro- gas explosion injecting treatment macrovoid, loose foundation soil
CN109577307A (en) * 2019-01-10 2019-04-05 上海市市政规划设计研究院有限公司 Combination of rigidity and flexibility stake and its construction method

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005113573A (en) * 2003-10-09 2005-04-28 Fudo Constr Co Ltd Composite pile and its execution method
RU2004105094A (en) * 2004-02-20 2005-07-20 Анатолий Иванович Полищук (RU) METHOD FOR CONSTRUCTION OF INJECTION PILES (OPTIONS)
CN101255696A (en) * 2008-04-14 2008-09-03 河南国基建设集团有限公司 PHC pipe-pile pile-anchor combined support water stop construction method
CN105964678A (en) * 2016-06-23 2016-09-28 北京建工环境修复股份有限公司 Soil and groundwater in-situ remediation system and method through in-situ infusion and high-pressure jet grouting injection
CN206956714U (en) * 2016-08-25 2018-02-02 北京荣创岩土工程股份有限公司 Down-the-hole impacts rotating spraying mixture pile construction equipment
CN107023002A (en) * 2016-08-30 2017-08-08 北京荣创岩土工程股份有限公司 Down-the-hole impacts churning composite pile pile making method
CN207904903U (en) * 2017-12-04 2018-09-25 汤湘军 Down-hole hammer grouting behind shaft or drift lining prefabricating composite pile
DE202018106282U1 (en) * 2018-11-05 2018-11-28 Stump Spezialtiefbau Gmbh API drill pipe
CN109518676A (en) * 2018-11-06 2019-03-26 北京荣创岩土工程股份有限公司 A kind of method of micro- gas explosion injecting treatment macrovoid, loose foundation soil
CN109577307A (en) * 2019-01-10 2019-04-05 上海市市政规划设计研究院有限公司 Combination of rigidity and flexibility stake and its construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
任连伟等: "组合桩研究与技术发展探讨", 《水利与建筑工程学报》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114703847A (en) * 2022-04-13 2022-07-05 珠海市三湘建筑基础工程有限公司 Construction process method of pulse hydraulic static pile machine

Similar Documents

Publication Publication Date Title
AU2020103672A4 (en) Construction method of rotary drilling hole-forming and jet mixing cement-soil occlusion curtain piles
US7326004B2 (en) Apparatus for providing a rammed aggregate pier
WO2018210019A1 (en) Pile formation method for down-the-hole impact rotary jet composite piles
CN106223331B (en) A kind of construction method for creeping into the construction equipment and foundation that spray stirring of vibrating
US8043028B2 (en) Apparatus for providing a support column
CN107417182B (en) Expansion type high polymer cement slurry, grouting reinforcement device and grouting reinforcement method
CN108729440B (en) Spiral high-spraying wing-expanding stirring bottom-expanding stiffness composite pile, construction method thereof and drilling machine
CN106996105A (en) Down-the-hole impacts jet mixing pile constructing process and equipment
US9243379B2 (en) Method of providing a support column
CN206784372U (en) Injection forming club-footed pile
CN111809611A (en) Construction method of jet grouting prefabricated composite pile
CN111485547A (en) Prefabricated horizontal bearing type high-toughness concrete permeable pile and preparation method thereof
CN214656943U (en) Core pile and slurry-fixed rigid-flexible combined pile
CN113550303A (en) Pile forming method for down-the-hole impact high-pressure jet grouting composite pile
CN114352189B (en) Construction method of jet grouting pile
CN217974332U (en) Concrete precast pile structure
CN217352573U (en) Fixed quicksand layer combined pile foundation structure
CN112252312B (en) Construction method for enhancing integral stress performance of PHC pipe pile
CN102619223A (en) Binding-enhanced type rigid and soft combined pile and construction method
CN212248222U (en) Construction equipment for grouting thin-wall tubular pile
CN111636419A (en) Construction equipment and construction method for grouting thin-wall tubular pile
CN115492088B (en) Pile forming method for pile bottom enlarged grouting CFG pile in karst region
CN102619218B (en) Rear slotting reinforcing cage CFG and piling method thereof
CN112323836A (en) Construction method of combined assembly type deep foundation pile
CN214738005U (en) Long spiral jet enlarged footing pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211026

RJ01 Rejection of invention patent application after publication