CN113530571B - Inner support supporting system for excavating underground tunnel to station end of underground station and construction method - Google Patents

Inner support supporting system for excavating underground tunnel to station end of underground station and construction method Download PDF

Info

Publication number
CN113530571B
CN113530571B CN202110820209.2A CN202110820209A CN113530571B CN 113530571 B CN113530571 B CN 113530571B CN 202110820209 A CN202110820209 A CN 202110820209A CN 113530571 B CN113530571 B CN 113530571B
Authority
CN
China
Prior art keywords
tunnel
steel
foundation pit
support
purlin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110820209.2A
Other languages
Chinese (zh)
Other versions
CN113530571A (en
Inventor
白阳阳
王立新
高升
李储军
汪珂
崔玉龙
来凯
贾少春
王博
翁木生
郑飞
王伟
王伟龙
刘锋
张利斌
雷永生
相旭
王天明
王俊
高志宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN202110820209.2A priority Critical patent/CN113530571B/en
Publication of CN113530571A publication Critical patent/CN113530571A/en
Application granted granted Critical
Publication of CN113530571B publication Critical patent/CN113530571B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention relates to an inner support supporting system for excavating a subsurface tunnel to a station end of an underground station and a construction method, wherein the system comprises a foundation pit part and a tunnel part; the foundation pit part comprises a foundation pit support structure, and is provided with guard piles uniformly arranged on two sides and the end part of the foundation pit, wherein the inner sides of the guard piles are provided with horizontal steel purlins in the foundation pit, and inclined foundation pit steel supports are respectively arranged between the steel purlins in the foundation pit on two sides and the steel purlins in the end part of the foundation pit; the tunnel part comprises a primary support shotcrete and a tunnel secondary lining, wherein the end part of the tunnel secondary lining is provided with a horizontal steel surrounding purlin in the tunnel, the steel surrounding purlin in the tunnel is positioned outside a surrounding pile at the end part of the foundation pit, and an inclined tunnel steel support is arranged between the steel surrounding purlin in the tunnel and the tunnel secondary lining. The invention fully utilizes the construction flexibility of the steel purlin and the steel support and the reliability of the lining structure, not only has convenient construction and saves investment, but also greatly improves the construction efficiency and reduces the risk of construction period lag.

Description

Inner support supporting system for excavating underground tunnel to station end of underground station and construction method
Technical Field
The invention belongs to the technical field of underground engineering construction, and particularly relates to an inner support supporting system for excavating a subsurface tunnel to a station end of an underground station and a construction method.
Background
When urban subway construction is carried out, construction at the boundary between a station and an interval tunnel is a key problem of collecting technology and construction period, because the station is generally arranged in a traffic main channel, the environment is complex, and tunnel communication conditions cannot be provided for the tunnel in time, and the connected shallow-buried underground tunnel is conventionally excavated to the end of the station for a certain distance before construction is stopped, and when the station is constructed, the tunnel is constructed, so that the tunnel cannot be communicated in time. Therefore, higher requirements are put forward for tunnel construction procedures and construction periods at the ends of the stations. Because the procedures of the underground excavation tunnel are complex, construction stagnation and secondary starting construction can cause more conversion of the underground excavation procedures, and the construction investment and the construction progress are greatly influenced.
Disclosure of Invention
The invention aims to provide an inner support supporting system for excavating a subsurface tunnel to a station end of an underground station and a construction method, which change the construction procedure of a conventional station interval and overcome the defects of the prior construction technology.
The technical scheme adopted by the invention is as follows:
Interior support supporting system of secretly excavated tunnel excavation to underground station end, its characterized in that:
the system comprises a foundation pit part and a tunnel part;
The foundation pit part comprises a foundation pit support structure, and is provided with guard piles uniformly arranged on two sides and the end part of the foundation pit, wherein the inner sides of the guard piles are provided with horizontal steel purlins in the foundation pit, and inclined foundation pit steel supports are respectively arranged between the steel purlins in the foundation pit on two sides and the steel purlins in the end part of the foundation pit;
The tunnel part comprises a primary support shotcrete and a tunnel secondary lining, wherein the end part of the tunnel secondary lining is provided with a horizontal steel surrounding purlin in the tunnel, the steel surrounding purlin in the tunnel is positioned outside a surrounding pile at the end part of the foundation pit, and an inclined tunnel steel support is arranged between the steel surrounding purlin in the tunnel and the tunnel secondary lining.
The steel purlin and the steel purlin are located the both sides of foundation ditch tip fender post in the tunnel to set up at same height.
The end part of the primary support sprayed concrete is propped into the foundation pit support structure, and the end part of the secondary lining of the tunnel is propped into the deformation joint outside the foundation pit support structure.
The end part of the steel purlin in the tunnel goes deep into the gap between the secondary lining of the tunnel and the foundation pit support structure, and the concrete is sprayed from the top to the primary support.
The steel enclosing purlin is arranged on an angle steel bracket which is anchored into the enclosing pile through an anchor bolt.
The end part of the foundation pit steel support is welded and fixed to the inner steel purlin of the foundation pit through a long flange connecting plate outside the inner steel purlin of the foundation pit.
The steel purlin is arranged on the angle steel bracket which is anchored into the fender pile through the anchor bolt in the tunnel.
The end part of the tunnel steel support is welded and fixed to the inner steel purlin of the tunnel through a long flange connecting plate outside the inner steel purlin of the tunnel.
And an embedded connecting piece is arranged in the secondary lining of the tunnel, and the end part of the tunnel steel support is fixed on the embedded connecting piece.
The construction method of the inner support supporting system from the excavation of the underground tunnel to the station end of the underground station is characterized by comprising the following steps of:
The method comprises the following steps:
Step one: constructing a primary support structure of the excavated tunnel excavation support to the station enclosure structure, and reinforcing grouting of the primary support back, so as to ensure compaction of the primary support back;
step two: constructing a second lining of the underground excavation tunnel to the deformation joint, embedding a steel plate at a designated position of the second lining structure, and ensuring firm connection between the second lining and the steel support in the later period;
Step three: when the strength of the second lining meets the requirement, the steel purlin and the steel support are erected, the steel purlin needs to go deep into the gap between the second lining and the foundation pit support structure and be propped against the primary supporting structure of the tunnel, wherein if the deformation joint is far away from the support pile, the gap is filled, and then the steel support is erected.
The invention has the following advantages:
On the basis of a station foundation pit support structure and a hidden tunnel lining, the steel purlin and the inner support system of the steel support are arranged in the tunnel, and the number of the inner supports can be adjusted according to the size of the section of the hidden tunnel and the strength of the pressure; meanwhile, according to the characteristics of the supporting type, the connection node between the enclosing purlin and the secondary lining is optimized so as to realize good combination of the rigid support and the secondary lining structure, and the conventional supporting mode is adopted, so that the construction operation is convenient, and the engineering investment is saved; the steel support system capable of applying prestress is arranged, so that the deformation of the side wall of the enclosure structure and the subsidence of the earth surface can be effectively controlled, and the engineering risk is reduced.
After the product is molded, conventional treatment measures of boundary of the station interval are changed, and the influence of working procedures and construction periods caused by constructing the tunnel after constructing the station main body is solved. The method has wide application value in the field of urban subway tunnel construction.
Drawings
FIG. 1 is a schematic plan view of the present invention.
Fig. 2 is a schematic cross-sectional elevation view of the present invention.
In the figure, the concrete is sprayed to 1-tunnel secondary lining, 2-primary support, 3-tunnel inner steel enclosing purlin, 4-tunnel steel support, 5-foundation pit enclosure, 6-foundation pit inner steel enclosing purlin, 7-foundation pit steel support and 8-deformation joint.
Detailed Description
The present invention will be described in detail with reference to the following embodiments.
The invention relates to an inner support supporting system for excavating a subsurface tunnel to a station end of an underground station, which comprises a foundation pit part and a tunnel part; the foundation pit part comprises a foundation pit support structure 5, wherein retaining piles are uniformly arranged on two sides and the end part of the foundation pit, the inner sides of the retaining piles are provided with horizontal steel purlins 6 in the foundation pit, and inclined foundation pit steel supports 7 are respectively arranged between the steel purlins 6 in the foundation pit on two sides and the steel purlins 6 in the end part of the foundation pit; the tunnel part includes preliminary bracing shotcrete 2 and tunnel secondary lining 1, and tunnel secondary lining 1 tip is provided with horizontal tunnel inner steel purlin 3, and tunnel inner steel purlin 3 is located the fender pile outside of foundation ditch tip, is provided with slant tunnel steel support 4 between tunnel inner steel purlin 3 and the tunnel secondary lining 1.
The steel purlin 3 in the tunnel and the steel purlin 6 in the foundation ditch are located the both sides of foundation ditch tip fender post to set up at same height.
The end part of the primary support shotcrete 2 is propped into the foundation pit support structure 5, and the end part of the secondary lining of the tunnel is propped to the deformation joint 8 outside the foundation pit support structure 5. The end part of the steel purlin 3 in the tunnel goes deep into the gap between the secondary lining 1 of the tunnel and the foundation pit support structure 5, and is propped up to the primary support shotcrete 2.
The steel enclosing purlin 6 is arranged on an angle steel bracket (the bracket is anchored into an enclosing pile through an anchor bolt), and the end part of the foundation pit steel support 7 is welded and fixed on the steel enclosing purlin 6 in the foundation pit through a long flange connecting plate outside the steel enclosing purlin. The steel enclosing purlin 3 in the tunnel is arranged on an angle steel bracket (the bracket is anchored into the enclosing pile through an anchor bolt), and the end part of the tunnel steel support 4 is welded and fixed on the steel enclosing purlin 3 in the tunnel through a long flange connecting plate outside the steel enclosing purlin. An embedded connecting piece is arranged in the tunnel secondary lining 1, and the end part of the tunnel steel support 4 is fixed on the embedded connecting piece.
The construction method of the inner support supporting system from the excavation tunnel to the station end of the underground station comprises the following steps:
Step one: constructing a primary support structure of the excavated tunnel excavation support to the station enclosure structure, and reinforcing grouting of the primary support back, so as to ensure compaction of the primary support back;
step two: constructing a second lining of the underground excavation tunnel to the deformation joint, embedding a steel plate at a designated position of the second lining structure, and ensuring firm connection between the second lining and the steel support in the later period;
Step three: when the strength of the second lining meets the requirement, the steel purlin and the steel support are erected, the steel purlin needs to go deep into the gap between the second lining and the foundation pit support structure and be propped against the primary supporting structure of the tunnel, wherein if the deformation joint is far away from the support pile, the gap is filled, and then the steel support is erected.
The steel support is generally a phi 609 steel pipe internal support system commonly used in foundation pit supporting engineering, so that materials can be conveniently obtained and recycled. In the tunnel construction process, through the back slip casting of primary support, tunnel two lining, steel enclose purlin and steel support effective connection's the mutual combination, the temporary support structure of formation can satisfy the requirement of relevant function such as deformation during the station foundation ditch construction.
According to the invention, the construction procedure of processing the end head of the station conventionally is changed by arranging the steel enclosing purlin and the inner support system of the steel support in the tunnel, the arrangement quantity and the support force of the inner support can be adjusted according to the size of the section of the underground tunnel and the strength of the pressure of the enclosing structure, and meanwhile, the connection node between the enclosing purlin and the secondary lining is optimized according to the characteristics of the support type, so that the good combination of the rigid support and the secondary lining structure is realized; compared with the conventional measures, the construction operation is convenient, and the engineering investment is saved; the steel support system capable of applying prestress is arranged, so that the deformation of the side wall of the enclosure structure can be effectively controlled, and tunnel tunneling can be realized under the condition that the station end is not constructed, thereby reducing engineering risks.
The content of the invention is not limited to the examples listed, and any equivalent transformation to the technical solution of the invention that a person skilled in the art can take on by reading the description of the invention is covered by the claims of the invention.

Claims (8)

1. Interior support supporting system of secretly excavated tunnel excavation to underground station end, its characterized in that:
the system comprises a foundation pit part and a tunnel part;
The foundation pit part comprises a foundation pit support structure (5), wherein guard piles are uniformly arranged on two sides and the end part of the foundation pit, a horizontal steel purlin (6) in the foundation pit is arranged on the inner side of the guard piles, and inclined foundation pit steel supports (7) are respectively arranged between the steel purlins (6) in the foundation pit on two sides and the steel purlin (6) in the end part of the foundation pit;
The tunnel part comprises a primary support shotcrete (2) and a tunnel secondary lining (1), a horizontal tunnel inner steel enclosing purlin (3) is arranged at the end part of the tunnel secondary lining (1), the tunnel inner steel enclosing purlin (3) is positioned at the outer side of a enclosing pile at the end part of a foundation pit, and an inclined tunnel steel support (4) is arranged between the tunnel inner steel enclosing purlin (3) and the tunnel secondary lining (1);
The end part of the primary support shotcrete (2) is propped into the foundation pit support structure (5), and the end part of the secondary lining of the tunnel is propped to a deformation joint (8) outside the foundation pit support structure (5);
An embedded connecting piece is arranged in the tunnel secondary lining (1), and the end part of the tunnel steel support (4) is fixed on the embedded connecting piece.
2. The interior support system for excavated tunnels excavated to a terminal of an underground station according to claim 1, wherein:
The steel purlin (3) and the steel purlin (6) in the foundation pit are arranged on two sides of the guard pile at the end part of the foundation pit and are arranged at the same height.
3. The interior support system for excavated tunnels excavated to a terminal of an underground station according to claim 2, wherein:
The end part of the steel purlin (3) in the tunnel goes deep into the gap between the secondary lining (1) of the tunnel and the foundation pit support structure (5) and is propped against the primary support to spray concrete (2).
4. The interior support system for excavating a undercut tunnel to a terminal end of a subterranean station of claim 3 wherein:
The steel purlin (6) is arranged on the angle steel bracket which is anchored into the fender pile through the anchor bolt in the foundation pit.
5. The interior support system for excavating a undercut tunnel to a terminal of a subterranean station of claim 4 wherein:
The end part of the foundation pit steel support (7) is welded and fixed on the foundation pit inner steel purlin (6) through a long flange connecting plate outside the foundation pit inner steel purlin (6).
6. The interior support system for excavating a undercut tunnel to a terminal of a subterranean station of claim 5 wherein:
the steel purlin (3) is arranged on the angle steel bracket which is anchored into the fender pile through the anchor bolt.
7. The interior support system for excavating a undercut tunnel to a terminal end of a subterranean station of claim 6 wherein:
the end part of the tunnel steel support (4) is welded and fixed on the steel purlin (3) in the tunnel by a long flange connecting plate outside the steel purlin (3) in the tunnel.
8. The method for constructing the inner support system from the excavation of the underground tunnel to the station end of the underground station according to claim 7, which is characterized by comprising the following steps:
The method comprises the following steps:
Step one: constructing a primary support structure of the excavated tunnel excavation support to the station enclosure structure, and reinforcing grouting of the primary support back, so as to ensure compaction of the primary support back;
step two: constructing a second lining of the underground excavation tunnel to the deformation joint, embedding a steel plate at a designated position of the second lining structure, and ensuring firm connection between the second lining and the steel support in the later period;
Step three: when the strength of the second lining meets the requirement, the steel purlin and the steel support are erected, the steel purlin needs to go deep into the gap between the second lining and the foundation pit support structure and be propped against the primary supporting structure of the tunnel, wherein if the deformation joint is far away from the support pile, the gap is filled, and then the steel support is erected.
CN202110820209.2A 2021-07-20 2021-07-20 Inner support supporting system for excavating underground tunnel to station end of underground station and construction method Active CN113530571B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110820209.2A CN113530571B (en) 2021-07-20 2021-07-20 Inner support supporting system for excavating underground tunnel to station end of underground station and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110820209.2A CN113530571B (en) 2021-07-20 2021-07-20 Inner support supporting system for excavating underground tunnel to station end of underground station and construction method

Publications (2)

Publication Number Publication Date
CN113530571A CN113530571A (en) 2021-10-22
CN113530571B true CN113530571B (en) 2024-04-30

Family

ID=78129025

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110820209.2A Active CN113530571B (en) 2021-07-20 2021-07-20 Inner support supporting system for excavating underground tunnel to station end of underground station and construction method

Country Status (1)

Country Link
CN (1) CN113530571B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101775987A (en) * 2010-02-02 2010-07-14 北京交通大学 Zero spacing construction method for overlapping part of upper main tunnel and lower main tunnel of underground overpass
CN203879506U (en) * 2014-06-03 2014-10-15 中铁第一勘察设计院集团有限公司 Supporting structure system for large-section deep vertical shaft in rock stratum
CN204551487U (en) * 2015-03-30 2015-08-12 中国建筑第六工程局有限公司 A kind of steel support structure that can realize Adjacent Pit synchronous construction
CN105041349A (en) * 2015-07-26 2015-11-11 北京工业大学 Underground excavation construction method for expanded excavation of station on basis of metro regional shield tunnel
CN105839643A (en) * 2016-05-23 2016-08-10 浙江省交通规划设计研究院 Tunnel in-hole construction method adopting foundation pit support
CN211006756U (en) * 2019-05-27 2020-07-14 广东省重工建筑设计院有限公司 Interface structure of open cut station and large-span duplex arch buried tunnel
CN111677515A (en) * 2020-05-20 2020-09-18 中铁二院工程集团有限责任公司 Construction method for breaking open cut foundation pit wall into hole from pile support supporting system by adopting shallow-buried underground excavation method
RU2745310C1 (en) * 2020-08-31 2021-03-23 Открытое акционерное общество "Научно-исследовательский, проектно-изыскательский институт "Ленметрогипротранс" Method for creating upper cross-cut abutting joint of approach tunnel to existing metropolitan pilot station constructed without interruption of station operation
CN112854238A (en) * 2021-01-11 2021-05-28 上海市政工程设计研究总院(集团)有限公司 Open trench tunnel staged construction joint foundation pit supporting system and construction method thereof

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101775987A (en) * 2010-02-02 2010-07-14 北京交通大学 Zero spacing construction method for overlapping part of upper main tunnel and lower main tunnel of underground overpass
CN203879506U (en) * 2014-06-03 2014-10-15 中铁第一勘察设计院集团有限公司 Supporting structure system for large-section deep vertical shaft in rock stratum
CN204551487U (en) * 2015-03-30 2015-08-12 中国建筑第六工程局有限公司 A kind of steel support structure that can realize Adjacent Pit synchronous construction
CN105041349A (en) * 2015-07-26 2015-11-11 北京工业大学 Underground excavation construction method for expanded excavation of station on basis of metro regional shield tunnel
CN105839643A (en) * 2016-05-23 2016-08-10 浙江省交通规划设计研究院 Tunnel in-hole construction method adopting foundation pit support
CN211006756U (en) * 2019-05-27 2020-07-14 广东省重工建筑设计院有限公司 Interface structure of open cut station and large-span duplex arch buried tunnel
CN111677515A (en) * 2020-05-20 2020-09-18 中铁二院工程集团有限责任公司 Construction method for breaking open cut foundation pit wall into hole from pile support supporting system by adopting shallow-buried underground excavation method
RU2745310C1 (en) * 2020-08-31 2021-03-23 Открытое акционерное общество "Научно-исследовательский, проектно-изыскательский институт "Ленметрогипротранс" Method for creating upper cross-cut abutting joint of approach tunnel to existing metropolitan pilot station constructed without interruption of station operation
CN112854238A (en) * 2021-01-11 2021-05-28 上海市政工程设计研究总院(集团)有限公司 Open trench tunnel staged construction joint foundation pit supporting system and construction method thereof

Also Published As

Publication number Publication date
CN113530571A (en) 2021-10-22

Similar Documents

Publication Publication Date Title
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN104452809A (en) Ultra-shallow buried tunnel cover-excavation construction method
CN102979531B (en) Reinforce construction method and the structure of large-scale rock slope deep weak structural plane
CN110821503A (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN109853399B (en) Large-section inclined tunnel type arch support structure for arch bridge and construction method thereof
CN105065009A (en) Method for shield expanding construction of subway station
CN105240024A (en) Parallel shield tunneling method for extended construction of subway station
CN112031814B (en) Cave-entering construction method for crossing shallow-layer high-load highway
CN105909268A (en) Pre-stress combined well/tunnel module structure construction method and module structure
CN103114595A (en) Support method and device of support pile preformed core-soil double-buttress inclined inner-strut foundation ditch
CN111305282A (en) Subway station anti-floating system in weak water-rich stratum and construction method thereof
CN105089670A (en) Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel
CN108915702B (en) Shield receiving method in circular small-section tunnel
CN105240023A (en) Method of adopting curved pipe-jacking supporting structure for extension of shield-driven subway station
CN113530571B (en) Inner support supporting system for excavating underground tunnel to station end of underground station and construction method
CN105840209B (en) Construction method for controlling deformation of anchor pile in tunnel body section
CN217150275U (en) High water level weak foundation pit supporting device
CN116201177A (en) Novel interface for underground engineering reconstruction and expansion based on permanent-temporary combination and construction method thereof
CN214169078U (en) Prestressed advance inclined throwing support supporting structure system capable of being applied
CN211623435U (en) Construction structure of communication channel of superposed tunnel adopting' hidden receiving and hidden originating
CN113944479A (en) Unfavorable geological tunnel three-fork construction method
CN114412475A (en) Reverse tunnel exit construction method for shallow-buried broken surrounding rock
CN110318419B (en) Construction method of one-lining door opening support of underpass type pipe gallery
WO2022205075A1 (en) Jet grouting pipe curtain supporting method and system by using large-span short-distance underground excavation to under-penetrate existing underground structure
CN113605951A (en) Shallow tunnel supporting structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant