CN113445436A - 一种桥梁不停车情况下的桥墩临时加固结构 - Google Patents

一种桥梁不停车情况下的桥墩临时加固结构 Download PDF

Info

Publication number
CN113445436A
CN113445436A CN202110761958.2A CN202110761958A CN113445436A CN 113445436 A CN113445436 A CN 113445436A CN 202110761958 A CN202110761958 A CN 202110761958A CN 113445436 A CN113445436 A CN 113445436A
Authority
CN
China
Prior art keywords
bridge
fixedly connected
jacking
reinforcing structure
steel support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110761958.2A
Other languages
English (en)
Inventor
李奇志
黄�俊
张洪庆
陈之
徐达
张鹏
郭淯晟
漆佳欣
宋永良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202110761958.2A priority Critical patent/CN113445436A/zh
Publication of CN113445436A publication Critical patent/CN113445436A/zh
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明所述的一种桥梁不停车情况下的桥墩临时加固结构,实现了在对桥墩进行养护加固同时对桥梁进行临时支撑,桥梁路面能正常使用,不阻碍交通,本发明结构稳定,承重支撑能力强,能稳定支撑桥梁,防止发生安全事故。包括由上到下依次设置的油压千斤顶、顶升纵梁、柱顶承重梁和多个支撑架,所述顶升纵梁与柱顶承重梁之间设置有多个贝雷梁,所述支撑架包括两个钢支撑立柱和设置在两个钢支撑立柱之间的多个剪刀撑,剪刀撑的两端分别与两个钢支撑立柱固定连接,每个剪刀撑的上部和下部均固定连接有一个联系梁,联系梁的两端分别与两个钢支撑立柱固定连接,所述两个钢支撑立柱的底部固定安装在地基上。

Description

一种桥梁不停车情况下的桥墩临时加固结构
技术领域
本发明涉及桥梁施工技术领域,尤其涉及一种桥梁不停车情况下的桥墩临时加固结构。
背景技术
目前,在对桥墩进行养护加固时,需要桥梁上停止通过车辆。然而在路况复杂、流动人员及车辆繁多的桥梁上停车、停止交通是一件非常困难的事情。并且在对桥墩进行养护加固的过程中,桥梁结构易发生失稳,从而造成安全事故。
发明内容
为了克服上述技术的不足,本发明的目的是提供一种桥梁不停车情况下的桥墩临时加固结构。
本发明所采用的技术方案是:一种桥梁不停车情况下的桥墩临时加固结构,包括由上到下依次设置的油压千斤顶、顶升纵梁、柱顶承重梁和多个支撑架,所述顶升纵梁与柱顶承重梁之间设置有多个贝雷梁,所述支撑架包括两个钢支撑立柱和设置在两个钢支撑立柱之间的多个剪刀撑,剪刀撑的两端分别与两个钢支撑立柱固定连接,每个剪刀撑的上部和下部均固定连接有一个联系梁,联系梁的两端分别与两个钢支撑立柱固定连接,所述两个钢支撑立柱的底部固定安装在地基上,两个钢支撑立柱的顶部与柱顶承重梁的底部固定连接,柱顶承重梁的顶部与贝雷梁的底部固定连接,贝雷梁的顶部与顶升纵梁的底部固定连接,顶升纵梁的顶部与油压千斤顶的缸体固定连接,油压千斤顶的伸缩杆顶在桥梁,所述桥梁与顶升纵梁之间设置有支座,支座的顶部抵在桥梁上,支座的底部与顶升纵梁固定连接,所述多个贝雷梁共有三个,三个贝雷梁沿顶升纵梁长度方向依次间隔设置,相邻两个贝雷梁之间均设置有一个横向斜撑架,横向斜撑架的两端分别和两个相邻的两个贝雷梁固定连接。
进一步的,所述顶升纵梁与柱顶承重梁呈平行设置。
进一步的,所述钢支撑立柱与柱顶承重梁呈垂直设置。
与现有技术相比,本发明具有以下有益效果:本发明所述的一种桥梁不停车情况下的桥墩临时加固结构,实现了在对桥墩进行养护加固同时对桥梁进行临时支撑,桥梁路面能正常使用,不阻碍交通,本发明结构稳定,承重支撑能力强,能稳定支撑桥梁,防止发生安全事故。
附图说明
图1是本发明的结构示意图。
具体实施方式
下面结合附图和具体实施例对本发明作详细说明。
如图1所示,一种桥梁不停车情况下的桥墩临时加固结构,包括由上到下依次设置的油压千斤顶1、顶升纵梁2、柱顶承重梁4和多个支撑架,所述顶升纵梁2与柱顶承重梁4之间设置有多个贝雷梁3,所述支撑架包括两个钢支撑立柱5和设置在两个钢支撑立柱5之间的多个剪刀撑6,剪刀撑6的两端分别与两个钢支撑立柱5固定连接,每个剪刀撑6的上部和下部均固定连接有一个联系梁7,联系梁7的两端分别与两个钢支撑立柱5固定连接,所述两个钢支撑立柱5的底部固定安装在地基8上,两个钢支撑立柱5的顶部与柱顶承重梁4的底部固定连接,柱顶承重梁4的顶部与贝雷梁3的底部固定连接,贝雷梁3的顶部与顶升纵梁2的底部固定连接,顶升纵梁2的顶部与油压千斤顶1的缸体固定连接,油压千斤顶1的伸缩杆顶在桥梁9。
所述桥梁9与顶升纵梁2之间设置有支座10,支座10的顶部抵在桥梁9上,支座10的底部与顶升纵梁2固定连接。
所述多个贝雷梁3共有三个,三个贝雷梁3沿顶升纵梁2长度方向依次间隔设置,相邻两个贝雷梁3之间均设置有一个横向斜撑架11,横向斜撑架11的两端分别和两个相邻的两个贝雷梁3固定连接。
所述顶升纵梁2与柱顶承重梁4呈平行设置。
所述钢支撑立柱5与柱顶承重梁4呈垂直设置。
上述实施例以本发明技术方案为前提,给出了详细的实施方式和具体的操作过程,但本发明的保护范围不限于上述的实施例。

Claims (3)

1.一种桥梁不停车情况下的桥墩临时加固结构,其特征在于:包括由上到下依次设置的油压千斤顶(1)、顶升纵梁(2)、柱顶承重梁(4)和多个支撑架,所述顶升纵梁(2)与柱顶承重梁(4)之间设置有多个贝雷梁(3),所述支撑架包括两个钢支撑立柱(5)和设置在两个钢支撑立柱(5)之间的多个剪刀撑(6),剪刀撑(6)的两端分别与两个钢支撑立柱(5)固定连接,每个剪刀撑(6)的上部和下部均固定连接有一个联系梁(7),联系梁(7)的两端分别与两个钢支撑立柱(5)固定连接,所述两个钢支撑立柱(5)的底部固定安装在地基(8)上,两个钢支撑立柱(5)的顶部与柱顶承重梁(4)的底部固定连接,柱顶承重梁(4)的顶部与贝雷梁(3)的底部固定连接,贝雷梁(3)的顶部与顶升纵梁(2)的底部固定连接,顶升纵梁(2)的顶部与油压千斤顶(1)的缸体固定连接,油压千斤顶(1)的伸缩杆顶在桥梁(9),所述桥梁(9)与顶升纵梁(2)之间设置有支座(10),支座(10)的顶部抵在桥梁(9)上,支座(10)的底部与顶升纵梁(2)固定连接,所述多个贝雷梁(3)共有三个,三个贝雷梁(3)沿顶升纵梁(2)长度方向依次间隔设置,相邻两个贝雷梁(3)之间均设置有一个横向斜撑架(11),横向斜撑架(11)的两端分别和两个相邻的两个贝雷梁(3)固定连接。
2.如权利要求1所述的一种桥梁不停车情况下的桥墩临时加固结构,其特征在于:所述顶升纵梁(2)与柱顶承重梁(4)呈平行设置。
3.如权利要求1所述的一种桥梁不停车情况下的桥墩临时加固结构,其特征在于:所述钢支撑立柱(5)与柱顶承重梁(4)呈垂直设置。
CN202110761958.2A 2021-07-06 2021-07-06 一种桥梁不停车情况下的桥墩临时加固结构 Pending CN113445436A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110761958.2A CN113445436A (zh) 2021-07-06 2021-07-06 一种桥梁不停车情况下的桥墩临时加固结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110761958.2A CN113445436A (zh) 2021-07-06 2021-07-06 一种桥梁不停车情况下的桥墩临时加固结构

Publications (1)

Publication Number Publication Date
CN113445436A true CN113445436A (zh) 2021-09-28

Family

ID=77815156

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110761958.2A Pending CN113445436A (zh) 2021-07-06 2021-07-06 一种桥梁不停车情况下的桥墩临时加固结构

Country Status (1)

Country Link
CN (1) CN113445436A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114395976A (zh) * 2022-03-11 2022-04-26 广西航务建设工程有限公司 一种无级调节的贝雷片支撑施工方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103981816A (zh) * 2014-04-15 2014-08-13 河南省公路工程局集团有限公司 立交桥框架墩柱托换施工方法
CN203947428U (zh) * 2014-07-21 2014-11-19 沈阳铁道勘察设计院有限公司 桥梁可调高支撑顶伸加固结构
CN205024600U (zh) * 2015-10-06 2016-02-10 中交第四公路工程局有限公司 一种用于桥梁水中桩基施工的作业平台
CN205474844U (zh) * 2015-12-30 2016-08-17 中交第二航务工程局有限公司 一种跨式贝雷梁支架
CN107254847A (zh) * 2017-06-15 2017-10-17 上海颖川路桥科技有限公司 一种城市环形立交同步顶升钢支撑结构
CN107761573A (zh) * 2017-11-29 2018-03-06 中铁二十四局集团安徽工程有限公司 跨河桥梁底部贝雷梁临时支架顶升浮运拆除方法
CN208917702U (zh) * 2018-09-29 2019-05-31 中铁二十四局集团安徽工程有限公司 鱼腹式混凝土箱梁现浇施工模板支撑架
CN210049116U (zh) * 2019-05-27 2020-02-11 贾垂朋 一种桥梁施工支架

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103981816A (zh) * 2014-04-15 2014-08-13 河南省公路工程局集团有限公司 立交桥框架墩柱托换施工方法
CN203947428U (zh) * 2014-07-21 2014-11-19 沈阳铁道勘察设计院有限公司 桥梁可调高支撑顶伸加固结构
CN205024600U (zh) * 2015-10-06 2016-02-10 中交第四公路工程局有限公司 一种用于桥梁水中桩基施工的作业平台
CN205474844U (zh) * 2015-12-30 2016-08-17 中交第二航务工程局有限公司 一种跨式贝雷梁支架
CN107254847A (zh) * 2017-06-15 2017-10-17 上海颖川路桥科技有限公司 一种城市环形立交同步顶升钢支撑结构
CN107761573A (zh) * 2017-11-29 2018-03-06 中铁二十四局集团安徽工程有限公司 跨河桥梁底部贝雷梁临时支架顶升浮运拆除方法
CN208917702U (zh) * 2018-09-29 2019-05-31 中铁二十四局集团安徽工程有限公司 鱼腹式混凝土箱梁现浇施工模板支撑架
CN210049116U (zh) * 2019-05-27 2020-02-11 贾垂朋 一种桥梁施工支架

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114395976A (zh) * 2022-03-11 2022-04-26 广西航务建设工程有限公司 一种无级调节的贝雷片支撑施工方法
CN114395976B (zh) * 2022-03-11 2023-12-01 广西航务建设工程有限公司 一种无级调节的贝雷片支撑施工方法

Similar Documents

Publication Publication Date Title
CN105155414A (zh) 大跨度索塔下横梁落地式斜腿钢桁支架
CN113445436A (zh) 一种桥梁不停车情况下的桥墩临时加固结构
CN214362953U (zh) 一种提高桥梁抗倾覆能力的独柱墩加固结构
CN112267390A (zh) 一种提高桥梁抗倾覆能力的独柱墩加固结构
CN215405658U (zh) 一种桥梁不停车情况下的桥墩临时加固结构
CN214301300U (zh) 钢箱梁安装可调节式支架体系
CN112921841B (zh) 跨线下承式拱桥上部结构快速拆除方法
CN213476666U (zh) 一种主桥钢箱梁整体顶升时主墩的限位装置
CN112664235A (zh) 一种行走式管廊模板支撑装置
CN211973136U (zh) 一种大跨度现浇桥梁模板支撑架
CN218147879U (zh) 一种用于桥墩及承台拆除落低重建的钢支架体系结构
CN111395204A (zh) 一种大悬臂盖梁的预应力悬臂支架结构及施工方法
CN215718762U (zh) 一种车站与盾构同步施工的支架结构
CN221421702U (zh) 一种同时满足大悬臂墩顶梁段现浇及架桥机架梁的钢结构支架
CN216238152U (zh) 一种变宽桥预制梁架设临时支墩平台
CN205382428U (zh) 一种整孔现浇梁倒三角模板支撑架
CN215947912U (zh) 山区地形现浇箱梁反拉反压支架
CN214116296U (zh) 一种贝雷现浇支架拆除装置
CN215210553U (zh) 一种卸载大悬臂预应力盖梁荷载的桥面支架
CN220645356U (zh) 一种桁架高空架散装辅助支撑装置
CN213061657U (zh) 一种大跨度斜拉式钢栈桥结构
CN215052204U (zh) 一种圆柱墩0#块支撑架结构
CN117418474A (zh) 一种空腹式连续刚构桥下弦钢斜撑0号块安装定位支架
CN216892039U (zh) 一种用于上跨铁路预制梁架设的盖梁外延操作平台
CN215669015U (zh) 框架桥施工用模架装置以及双跨桥整体浇筑***

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210928

RJ01 Rejection of invention patent application after publication