CN113202109A - High-water-level jacking construction method for railway passenger underpass with multiple underpass railways - Google Patents

High-water-level jacking construction method for railway passenger underpass with multiple underpass railways Download PDF

Info

Publication number
CN113202109A
CN113202109A CN202110385813.7A CN202110385813A CN113202109A CN 113202109 A CN113202109 A CN 113202109A CN 202110385813 A CN202110385813 A CN 202110385813A CN 113202109 A CN113202109 A CN 113202109A
Authority
CN
China
Prior art keywords
construction
layer
underpass
earthwork
frame structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110385813.7A
Other languages
Chinese (zh)
Other versions
CN113202109B (en
Inventor
刘晓欢
张志恒
王富强
王燕昇
霍俊清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Sixth Group Co Ltd
Taiyuan Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
Taiyuan Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, Taiyuan Railway Construction Co Ltd of China Railway Sixth Group Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN202110385813.7A priority Critical patent/CN113202109B/en
Publication of CN113202109A publication Critical patent/CN113202109A/en
Application granted granted Critical
Publication of CN113202109B publication Critical patent/CN113202109B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention relates to a jacking construction method, in particular to a high-water-level jacking construction method for a passenger underpass multi-lane railway, aiming at solving the technical problems of large jacking stroke, large direction and height control difficulty in foundation pit jacking construction at the outer side of the existing line. The method specifically comprises the following steps: s1, a ballast supporting block of an inter-track is prepared for construction of supporting piles among lines; s2, reinforcing a railway section above the tunnel by adopting a D beam; s3, excavating a foundation pit below the outgoing line: s4, prefabricating a positive wire frame structure; s5, jacking a positive wire frame structure; s6, constructing a waterproof layer of the positive wire frame structure; s7, casting a hair line frame structure in situ; s8, constructing a construction joint and a settlement joint; and S9, backfilling the transition section.

Description

High-water-level jacking construction method for railway passenger underpass with multiple underpass railways
Technical Field
The invention relates to a jacking construction method, in particular to a high-water-level jacking construction method for a passenger tunnel of a multi-track railway passing through downwards.
Background
The horizontal distance between the existing platform and the newly-built platform of a certain railway is about 100 meters, and the middle part of the railway has 14 railway business lines which are 4 main lines and 10 arrival lines respectively. In order to meet the requirement of passengers for entering and exiting, the existing passenger tunnels for entering and exiting need to be lengthened, the lengthened part of the passenger tunnels is 75m long, the clear width is 6.5m, the clear height is 4.0m, the lengthened part is butted with the existing tunnels, and the heights of the top plate bottom and the bottom plate top of the newly-built passenger tunnels are consistent with the existing heights. The existing design scheme is that an L-shaped prefabricated foundation pit is arranged on the outer side of a line, and then jacking construction is carried out between relays. The method has the problems of large jacking stroke and large difficulty in controlling the direction and height. If dig the foundation ditch under the circuit, foundation ditch inner space is limited, and the main equipment can't get into, can't adopt traditional fender pile + guan liang + mode of steel shotcrete to carry out foundation ditch support, has technical obstacle.
Disclosure of Invention
The invention aims to solve the technical problems of large jacking stroke and large control difficulty of direction and height of foundation pit jacking construction dug outside the existing line.
The technical scheme adopted by the invention for solving the technical problems is as follows:
the construction method for high water level jacking of passenger underpass multi-track railway comprises the following steps in sequence:
s1, line-to-line ballast retaining is prepared for line-to-line support pile construction;
s2, reinforcing a railway section above the tunnel by adopting a D beam;
s3, excavating a foundation pit:
1) excavating a first section of earthwork of a first layer, releasing slopes on the side slopes on two sides of the earthwork according to the ratio of 1:0.5, releasing slopes on the face according to the ratio of 1:1, and performing soil nailing wall construction and net hanging and anchor spraying construction on the formed slopes;
2) processing a first section of earthwork side wall of a second layer by adopting a high-pressure jet grouting pile, keeping a distance between the construction position of the high-pressure jet grouting pile and a slope toe of the first layer of earthwork to form an operation platform, vertically driving a steel sheet pile for reinforcement before the second layer of earthwork side wall is completely solidified, penetrating the steel sheet pile through the second layer of earthwork side wall and inserting the steel sheet pile into the lower earthwork, and sequentially performing soil nailing wall construction and net hanging and anchor spraying construction on the formed second layer of earthwork side wall;
3) repeating the steps 1) and 2) for sectional construction;
4) after the length of the foundation pit is reached, excavating a second layer of earthwork from the face to the outside and from the middle part to two sides, putting the face on a slope according to the ratio of 1:1, and sequentially carrying out soil nailing wall construction and net hanging and anchor spraying construction on the face, so that the foundation pit supporting is completed;
s4, prefabricating a positive wire frame structure;
s5, jacking a positive wire frame structure;
s6, constructing a waterproof layer of the positive wire frame structure;
s7, casting a hair line frame structure in situ;
s8, constructing a construction joint and a settlement joint;
and S9, backfilling the transition section.
The invention has the beneficial effects that:
1) according to the construction method for high water level jacking of the passenger underpass multi-track railway underpass, provided by the invention, the foundation pit under the starting line is used as the prefabricated working pit of the main line frame structure, so that the jacking range of the frame structure is reduced, and the deviation risk is reduced for jacking the frame structure under poor geology;
2) according to the construction method for high water level jacking of the passenger underpass multi-track railway, the side slope of the working pit below the departure line is protected and stopped by adopting the occlusion mode of the soil nailing wall, the net hanging spray anchor, the high-pressure jet grouting pile and the steel sheet pile, so that the influence of high water level underground water on the foundation pit is effectively reduced, the safety of the working pit is ensured, and the construction cost is saved;
3) the high-water-level jacking construction method for the underpass multi-track railway passenger underpass, provided by the invention, has the advantages of strong pertinence, simplicity in operation and easiness for operators to master.
Drawings
In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present application, and other drawings can be obtained by those skilled in the art without creative efforts.
Fig. 1 is a schematic view of the foundation pit structure of the present invention.
In the figure:
1 ┄ D beam; 2 ┄ side slopes; 3 ┄ high-pressure jet grouting pile; 4 ┄ work platform.
Detailed Description
In order to make the objects, technical solutions and advantages of the present application more apparent, the present application is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the present application and are not intended to limit the present application.
A specific scenario is given below, and the construction method of the present invention is explained with reference to a specific embodiment of the scenario:
situation: the newly-built Taijiao railway is located in the north side of the existing promotion middle station, the horizontal distance between the existing platform and the newly-built platform is about 100 meters, the middle part has 14 railway business lines which are respectively 4 positive lines and 10 arrival lines. In order to meet the requirement that passengers on a Taijiao line enter and exit a promotion middle station, an existing promotion middle station entrance and exit passenger tunnel needs to be lengthened, the length of a lengthened part of the passenger tunnel is 75m, the net width is 6.5m, the net height is 4.0m, the lengthened part is in butt joint with the existing tunnel, and the heights of the top plate bottom and the bottom plate top of the newly-built passenger tunnel are consistent with the existing heights.
Referring to fig. 1, the construction method for high water level jacking of the underpass multi-lane railway passenger underpass adopted by aiming at the situation sequentially comprises the following construction steps:
s1, line-to-line ballast retaining is prepared for line-to-line support pile construction; some of the support piles are arranged outside the line, some of the support piles are arranged among lines, if railway ballasts are not supported, the railway ballasts can easily enter pile holes of the support piles among the lines, construction is affected, and therefore railway ballast supporting and blocking among the lines are needed. The method specifically comprises the following steps: 1) two rows of steel pipes are driven into two sides of the inter-line support pile along the line direction, a gap of 0.2m is reserved between each row of steel pipes and the corresponding sleeper, 8 steel pipes are arranged in each row, the diameter of each steel pipe is 50mm, the length of each steel pipe is 1.5m, the buried depth of each steel pipe is 1.0m, and the spacing is 1 m; 2) a wood board adjacent to the steel pipe is driven into the gap, the thickness of the wood board is 4cm, and the upper edge of the wood board is flush with the top of the sleeper; 3) the steel bars are adopted to oppositely pull and lock the steel pipes on the two sides of the line, the steel bars are sleeved with the PVC pipes and then penetrate through the rail bottom, and the PVC pipes cannot abut against the rail bottom, so that the stability of the ballast bed and the disconnection of a track circuit are ensured.
S2, reinforcing the railway section above the ground by adopting the D beam 1: the D beam 1 is reinforced into a mature structure in the field, support piles are firstly processed at two ends of the D beam 1, then the D beam 1 is supported on the support piles, and finally a longitudinal beam vertically penetrating through the lower portion of the track is fixedly connected with the D beam 1.
S3, excavating a foundation pit below the outgoing line: 1) excavating a first section of earthwork of a first layer, releasing slopes on the slopes 2 on two sides of the earthwork according to the ratio of 1:0.5, releasing slopes on the face according to the ratio of 1:1, and performing soil nailing wall construction and net hanging and anchor spraying construction on the formed slopes 2; 2) processing a first section of earthwork side wall of a second layer by adopting a high-pressure jet grouting pile 3, keeping a distance between the construction position of the high-pressure jet grouting pile 3) and a slope toe of the first layer of earthwork to form an operation platform 4, vertically driving a steel sheet pile for reinforcement before the second layer of earthwork side wall is completely solidified, penetrating the steel sheet pile through the second layer of earthwork side wall and inserting the steel sheet pile into the lower earthwork, and sequentially performing soil nailing wall construction and net hanging and anchor spraying construction on the formed second layer of earthwork side wall; 3) repeating the steps 1) and 2), and constructing in sections; 4) and after the length of the foundation pit is reached, excavating a second layer of earthwork from the face to the outside and from the middle part to two sides, putting the face on a slope according to the ratio of 1:1, and sequentially performing soil nailing wall construction and net hanging and anchor spraying construction on the face to complete foundation pit supporting. Specifically, the soil nailing wall construction and the net hanging and anchor spraying construction comprise the following steps: 1) weaving a reinforcing mesh; 2) manufacturing a soil nail, wherein the soil nail adopts an anchor tubular structure; 3) drilling holes on the side slope 2 or the tunnel face, and inserting soil nails; 4) grouting into the soil nail; 5) hanging the woven reinforcing mesh on soil nails; 6) and spraying a concrete surface layer. Specifically, the construction of the high-pressure jet grouting pile 3 comprises the following steps: 1) positioning a drilling machine; 2) preparing slurry; 3) drilling; 4) injecting and grouting; 5) flushing and cleaning equipment; 6) moving the drilling machine to the next hole position; 7) and repeating the operations of the steps 1) to 6) until the construction is finished.
S4, prefabricating a positive wire frame structure: the concrete construction sequence is that the sliding plate, the lubricating isolation layer, the back construction → the bottom plate reinforcing steel bar binding → the bottom plate template installation, the bottom plate settlement joint waterproof material installation → the bottom plate concrete pouring → the support is erected, the side wall top plate template installation → the side wall binding, the top plate reinforcing steel bar, the side wall construction joint waterproof material installation, the side wall and the top plate settlement joint waterproof material installation → the side wall pouring, the top plate concrete → the side wall and the top plate waterproof plate laying.
S5, jacking a positive wire frame structure; frame jacking is a well-established technique in the art.
S6, constructing a waterproof layer of the positive line frame structure, and specifically comprising the following steps: 1) filling and compacting the lacing hole left when the positive wire frame structure is prefabricated by adopting waterproof cement; 2) paving a leveling layer with the thickness of 20mm on the top plate of the positive wire frame structure by adopting cement mortar; 3) paving waterproof coiled materials on the leveling layer of the positive wire frame structure and the outer sides of the two side walls; 4) and C40 polyacrylonitrile fiber concrete protective layers are paved on the outer sides of the waterproof rolls, and meanwhile, a transverse drainage slope is made. The waterproof coiled material preferably adopts high polymer modified asphalt.
S7, casting a hair line frame structure in situ;
s8, construction of construction joints and settlement joints: the main structure annular construction joint adopts a middle-buried steel-edged rubber water stop and a water-swelling water stop strip to strengthen waterproof treatment.
S9, backfilling a transition section: and after the waterproof and settlement joint construction of the tunnel bridge is finished, backfilling the two sides and the top of the tunnel by using C15 concrete. And symmetrically backfilling two sides layer by layer, and backfilling the top of the tunnel to the bottom of the sleeper by 0.5 m. And backfilling the platform wall to a position 2.6m below the platform surface. And after the backfilled concrete reaches a certain strength, the top of the tunnel restores the water ditch between lines and supplements ballast.
The concrete steps of the spray anchor construction aiming at the situation soil nail wall and the hanging net are given as follows:
1) weaving a reinforcing mesh: binding a bidirectional reinforcing mesh according to the design requirement, wherein the reinforcing bars are arranged in a phi 8@150 bidirectional mode, and the joints of the adjacent reinforcing bars are staggered by 150 mm.
2) The manufacturing method comprises the following steps of: 4 soil nails are arranged, the diameter of the anchor pipe is 42mm, the wall thickness is 3.5mm, the anchor pipe is arranged in a quincunx manner, and the incident angle is 15 degrees. The horizontal spacing is 1.5m, and the vertical spacing is 1.0m, 1.5m, 1.5m, and 1.5m, respectively. The lengths of the No. 1 to No. 4 soil nails meeting the requirements of stability and tensile strength are 5m, 5m, 6.5m and 6m respectively.
3) Drilling on the side slope 2 or the face, inserting the soil nail: the diameter of the drilled hole is 80 mm.
4) Grouting into the soil nail: pure cement slurry is used for grouting the anchor pipe, the water cement ratio is 0.45-0.5, and 42.5-grade ordinary portland cement is used.
5) Hanging the woven reinforcing mesh on the soil nails: the steel bar net is pressed tightly by a phi 12 screw-thread steel # -shaped frame, and the steel bar net, the soil nails and the # -shaped frame are connected by electric welding.
6) And spraying a concrete surface layer: after the earth is excavated and the slope is repaired, surface layer concrete is sprayed, and one-time spraying is finished after the reinforcing mesh weaving and welding work is finished. The particle size of the stones is 5-15 mm, the concrete is marked as C25, and the spraying thickness is 0.1 m. The sprayed concrete should be doped with an accelerating agent, the initial setting of the concrete is less than 10min, and the final setting is less than 30 min.
A specific example of construction of the high-pressure jet grouting pile 3 for the above-described situation is given below:
1) positioning a drilling machine: the drilling machine is moved to the designed hole site, the drill bit is aligned with the center of the hole site, and after the drilling machine is in place, the drilling machine needs to be horizontally aligned, so that the axis of the drill rod is vertically aligned with the center of the drill hole. The verticality of the drill rod is required to be not more than 1%.
2) And slurry preparation: the slurry of the high-pressure jet grouting pile 3 adopts PO42.5 ordinary portland cement as cement, the dosage of the cement is not less than 40 percent (weight ratio), and the dosage of the cement per linear meter is 0.110 t. The pile body unlimited compression strength value of 28 days is required to be not less than 3.0 MkPa. When the mortar is stirred, water is firstly added, then cement is added, the stirring time of each mortar is not less than 2 minutes, the cement paste is prepared one hour before the cement paste is used, and the cement paste is continuously stirred in a mortar mixer until the cement paste is sprayed. During spraying, when cement slurry is poured into the collecting hopper from the mortar mixer, the hard cement blocks are removed by the filter screen. The cement slurry is sent into a spray pipe of the rotary vibration drilling machine through a rubber pipe and finally ejected.
3) Drilling: and starting the drilling machine, rotating and drilling at the same time, and stopping drilling after reaching the designed elevation. When the spraying pipe reaches the preset depth of the soil layer, a spraying nozzle on the side face of the bottom of the pipe is used for simultaneously spraying high-pressure slurry and air to impact and cut the soil body. The high-pressure grouting pump sprays the slurry with the pressure of more than or equal to 30Mpa out of the inner spray pipe. Under the combined action of the high-pressure slurry flow and the air flow, the nozzle sprays and rotates to lift, and finally, a cylindrical solid structure is formed in the soil body. Pile position deviation is strictly controlled in the drilling process, and the position deviation of the drilled hole is not larger than 50 mm.
4) And injecting and grouting: after drilling to the designed depth, spray grouting is carried out from bottom to top strictly according to the test parameters. During construction, operators must constantly check whether parameters such as slurry initial setting time, grouting flow, pressure, rotation lifting speed and the like meet requirements and make records. When spraying, the preset spraying pressure is reached, the spraying rotation is carried out for 30 seconds, after the cement paste and the pile end soil are fully stirred, the grouting pipe is lifted by rotating at a constant speed in the reverse direction while spraying, and the lifting speed is 20 cm/min; the rotation speed is about 20r/min, and the stirring and lifting speed is slowed down until the distance between the pile top and the pile is 1 m. The pile top is guaranteed to be compact and uniform. When the middle is in fault, the lifting and the rotary spraying are stopped to prevent the pile body from being interrupted, meanwhile, the fault is immediately checked and eliminated, and the overlapping of the section of restarting spraying and grouting and the front section is not less than 1m to prevent the solidification body from disjointing. The on-site operation personnel record the parameters of start-stop time, grouting flow, force, rotary jet height, rotary lifting speed and the like in the construction process.
5) And flushing and cleaning equipment: after the injection construction is finished, the grouting pipe and other equipment are washed clean by clear water to prevent solidification and blockage. The cement slurry can not remain in the pipe and the machine, and the slurry is generally changed into clear water to be sprayed on the ground so as to completely remove the slurry in a slurry pump, a grouting pipe and a hose.
6) Moving the drilling machine to the next hole position, and inserting the steel sheet pile when the jet grouting pile paddle reaches the initial setting condition;
7) and repeating the operations of the steps 1) to 6) until the construction is finished.
The same or similar reference numerals in the drawings of the embodiments correspond to the same or similar components; in the description of the present application, it is to be understood that if there is an orientation or positional relationship indicated by the terms "upper", "lower", "left", "right", etc. based on the orientation or positional relationship shown in the drawings, it is only for convenience of description and simplification of description, but it is not intended to indicate or imply that the referred device or element must have a specific orientation, be constructed in a specific orientation, and be operated, and therefore, the terms describing the positional relationship in the drawings are only for illustrative purposes and are not to be construed as limitations of the present patent, and specific meanings of the above terms may be understood by those skilled in the art according to specific situations.
The above description is only exemplary of the present application and should not be taken as limiting the present application, as any modification, equivalent replacement, or improvement made within the spirit and principle of the present application should be included in the protection scope of the present application.

Claims (5)

1. The high water level jacking construction method for the passenger underpass multi-track railway is characterized by sequentially comprising the following construction steps:
s1, supporting the ballast among the lines, and preparing for constructing the supporting piles among the lines;
s2, reinforcing the railway section above the tunnel by using a D beam (1);
s3, excavating a foundation pit below the departure line:
1) excavating a first section of earthwork of a first layer, releasing slopes on the side slopes (2) at the two sides of the earthwork according to the ratio of 1:0.5, releasing slopes on the face surface according to the ratio of 1:1, and performing soil nailing wall construction and net hanging and anchor spraying construction on the formed slopes (2);
2) processing a first section of earthwork side wall of a second layer by adopting a high-pressure jet grouting pile (3), keeping a distance between the construction position of the high-pressure jet grouting pile (3) and a slope toe of the first layer of earthwork to form an operation platform (4), vertically driving a steel sheet pile for reinforcement before the second layer of earthwork side wall is completely solidified, penetrating the steel sheet pile through the second layer of earthwork side wall and inserting the steel sheet pile into the lower soil, and sequentially performing soil nailing wall construction and net hanging and anchor spraying construction on the formed second layer of earthwork side wall;
3) repeating the steps 1) and 2), and constructing in sections;
4) after the length of the foundation pit is reached, excavating a second layer of earthwork from the face to the outside and from the middle part to two sides, putting the face on a slope according to a ratio of 1:1, and sequentially performing soil nailing wall construction and net hanging and anchor spraying construction on the face, so that the foundation pit support is completed;
s4, prefabricating a positive wire frame structure;
s5, jacking the positive wire frame structure;
s6, constructing a positive wire frame waterproof layer;
s7, casting a hairline frame in situ;
s8, constructing a construction joint and a settlement joint;
and S9, backfilling the transition section.
2. The high water level jacking construction method for underpassing multi-track railway passenger underpass according to claim 1, characterized in that: in step S1, the method specifically includes the following steps:
1) two rows of steel pipes are driven into two sides of the inter-line support pile along the line direction, and a gap is reserved between each row of steel pipes and the corresponding sleeper;
2) a wood board adjacent to the steel pipe is driven into the gap, and the upper edge of the wood board is flush with the top of the sleeper;
3) the steel pipes on two sides of the line are locked in a counter-pulling mode by adopting the steel bars, and the steel bars are sleeved with the PVC pipes and then penetrate through the rail bottom.
3. The high water level jacking construction method for underpassing multi-track railway passenger underpass according to claim 1, characterized in that: in step S3, the earth nailing wall construction and the net hanging and anchor spraying construction include the following steps:
1) weaving a reinforcing mesh;
2) manufacturing a soil nail, wherein the soil nail adopts an anchor tubular structure;
3) drilling holes on the side slope (2) or the tunnel face, and inserting soil nails;
4) grouting into the soil nail;
5) hanging the woven reinforcing mesh on soil nails;
6) and spraying a concrete surface layer.
4. The high water level jacking construction method for underpassing multi-track railway passenger underpass according to claim 1, characterized in that: in step S3, the construction of the high-pressure jet grouting pile (3) includes the steps of:
1) positioning a drilling machine;
2) preparing slurry;
3) drilling;
4) injecting and grouting;
5) flushing and cleaning equipment;
6) moving the drilling machine to the next hole position;
7) and repeating the operations of the steps 1) to 6) until the construction is finished.
5. The high water level jacking construction method for underpassing multi-track railway passenger underpass according to claim 1, characterized in that: in step S6, the specific steps are as follows:
1) filling and compacting the lacing hole left when the positive wire frame structure is prefabricated by adopting waterproof cement;
2) paving a leveling layer on the top plate of the positive wire frame structure by adopting cement mortar;
3) paving waterproof coiled materials on the leveling layer of the positive wire frame structure and the outer sides of the two side walls;
4) and C40 polyacrylonitrile fiber concrete protective layer is laid on the outer side of the waterproof roll.
CN202110385813.7A 2021-04-11 2021-04-11 High-water-level jacking construction method for railway passenger underpass with multiple underpass railways Active CN113202109B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110385813.7A CN113202109B (en) 2021-04-11 2021-04-11 High-water-level jacking construction method for railway passenger underpass with multiple underpass railways

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110385813.7A CN113202109B (en) 2021-04-11 2021-04-11 High-water-level jacking construction method for railway passenger underpass with multiple underpass railways

Publications (2)

Publication Number Publication Date
CN113202109A true CN113202109A (en) 2021-08-03
CN113202109B CN113202109B (en) 2022-11-15

Family

ID=77026487

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110385813.7A Active CN113202109B (en) 2021-04-11 2021-04-11 High-water-level jacking construction method for railway passenger underpass with multiple underpass railways

Country Status (1)

Country Link
CN (1) CN113202109B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102808381A (en) * 2012-08-21 2012-12-05 中铁十局集团有限公司 High-water-level silty-soil underneath-pass multi-track railway frame bridge jacking and butting construction method
CN103669374A (en) * 2013-12-18 2014-03-26 安徽华力建设集团有限公司 Combined supporting construction method of steel sheet pile used in silt soil slope
US20140314494A1 (en) * 2013-04-11 2014-10-23 Henan Polytech Infrastructure Rehabilitation LTD. Polymer grouting method for constructing vertical supporting system
CN105155550A (en) * 2015-07-23 2015-12-16 甘肃第六建设集团股份有限公司 Construction method for digging deep foundation pit in large-thickness highly weathered sandstone stratum in combined supporting mode
CN111648376A (en) * 2020-06-10 2020-09-11 深圳市市政工程总公司 Construction method adopting deep foundation pit supporting and anchoring structure for supporting

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102808381A (en) * 2012-08-21 2012-12-05 中铁十局集团有限公司 High-water-level silty-soil underneath-pass multi-track railway frame bridge jacking and butting construction method
US20140314494A1 (en) * 2013-04-11 2014-10-23 Henan Polytech Infrastructure Rehabilitation LTD. Polymer grouting method for constructing vertical supporting system
CN103669374A (en) * 2013-12-18 2014-03-26 安徽华力建设集团有限公司 Combined supporting construction method of steel sheet pile used in silt soil slope
CN105155550A (en) * 2015-07-23 2015-12-16 甘肃第六建设集团股份有限公司 Construction method for digging deep foundation pit in large-thickness highly weathered sandstone stratum in combined supporting mode
CN111648376A (en) * 2020-06-10 2020-09-11 深圳市市政工程总公司 Construction method adopting deep foundation pit supporting and anchoring structure for supporting

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
彭涛: "下穿10 股既有铁路的大型框架结构顶进设计", 《铁道建筑技术》 *
王文海: "浅谈既有线站内地道接长施工过程方案优化和质量控制", 《中小企业管理与科技》 *

Also Published As

Publication number Publication date
CN113202109B (en) 2022-11-15

Similar Documents

Publication Publication Date Title
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN103306289B (en) Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN108677924B (en) Double-row miniature steel pipe pile grouting wall-forming partition structure and method
CN108797598A (en) The construction technology of pre-loaded support struts in a kind of deep basal pit
CN109371905B (en) Dam and construction method
CN110159294B (en) Construction method for lengthening open cut tunnel at tunnel junction section of high and steep terrain bridge
CN211144503U (en) High steep topography bridge tunnel meets section open cut tunnel and connects long structure
CN113266392B (en) Pipe jacking construction method for penetrating through existing anchor cable group
CN111119128B (en) Danger-removing, reinforcing and seepage-proofing method for natural rock-fill dam of barrier lake
WO2023077552A1 (en) Construction method for foundation pit enclosure and earth excavation
CN105464685A (en) Cave-pile method bored tunnel waterproof curtain and construction method thereof
US11959243B2 (en) Method for constructing large-span station with two-wing open type half-cover excavation and half-reverse construction
CN111322087A (en) Construction method for soft soil highway tunnel entrance semi-open semi-hidden tunnel in mountainous area
CN111455977A (en) Underground continuous wall construction method
CN113803074A (en) Construction method of tunnel structure for artificial and mechanical combined obstacle removal of water-rich sand layer
CN109736156A (en) A kind of highway barrier and sound barrier share integrated steel anchor tube foundation structure and construction method
CN212272234U (en) High-strength combined template for open groove section of large-section inclined shaft
CN110486062B (en) Method for mechanically underground excavating multi-layer multi-span underground engineering in soft soil
CN113202109B (en) High-water-level jacking construction method for railway passenger underpass with multiple underpass railways
CN111270665A (en) Construction method of triaxial mixing pile
CN113266362B (en) Top pipe cover excavation construction method for penetrating through existing dense anchor cable area
CN116398165A (en) New tunnel penetrating through existing station at zero distance and construction method thereof
CN113202110A (en) Construction method for supporting and protecting finite space railway bridge and culvert prefabricated foundation pit
CN110820756A (en) Shield well and vertical shaft deep foundation pit excavation safety construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant