CN113153306B - Major diameter shaft excavation supporting construction method - Google Patents

Major diameter shaft excavation supporting construction method Download PDF

Info

Publication number
CN113153306B
CN113153306B CN202110500310.XA CN202110500310A CN113153306B CN 113153306 B CN113153306 B CN 113153306B CN 202110500310 A CN202110500310 A CN 202110500310A CN 113153306 B CN113153306 B CN 113153306B
Authority
CN
China
Prior art keywords
layer
blasting
supporting construction
excavation
excavating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110500310.XA
Other languages
Chinese (zh)
Other versions
CN113153306A (en
Inventor
何金星
叶明�
杨伟刚
戚敬师
王贵燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 6 Co Ltd
Original Assignee
Sinohydro Bureau 6 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 6 Co Ltd filed Critical Sinohydro Bureau 6 Co Ltd
Priority to CN202110500310.XA priority Critical patent/CN113153306B/en
Publication of CN113153306A publication Critical patent/CN113153306A/en
Application granted granted Critical
Publication of CN113153306B publication Critical patent/CN113153306B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Earth Drilling (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention is applicable to the technical field of shaft construction, and provides a large-diameter shaft excavation supporting construction method, which comprises the following steps: s1, constructing a top layer, firstly excavating a groove, and then excavating the rest parts divided into 6 areas according to the sequence; s2, conducting well construction, namely conducting 4-meter well guidance excavation while conducting support construction, and excavating the 4-meter well guidance into 9-meter well guidance after the 4-meter well guidance is communicated; s3, constructing a plurality of middle layers, slotting before each layer is excavated, and then sequentially excavating in a circumferential sequence; s4, constructing a bottom layer, namely, filling slag to the top of a rock column in the annular guide hole of the bottom layer by using the caving rock slag when the last middle layer is communicated with the annular guide hole of the bottom layer, and then carrying out layered excavation treatment according to the sequence to divide the rock column into 3 rock column regions; s5, constructing the annular pilot tunnel, and excavating the annular pilot tunnel by adopting a full section once. The invention can improve the dimensional accuracy and strength of each layer structure and can also improve the construction efficiency of each layer.

Description

Major diameter shaft excavation supporting construction method
Technical Field
The invention relates to the technical field of shaft construction, in particular to a large-diameter shaft excavation supporting construction method.
Background
The vertical shaft is a well-shaped pipeline with an upright hole wall, and is mainly used for connecting the bottom of a water pool with a traffic support hole to be used as a slag discharging channel.
The existing shaft construction is directly carried out by blasting excavation from top to bottom, each layer is not subjected to targeted construction, collapse is easily caused by the construction mode of directly carrying out the direct blasting excavation from top to bottom, the size of the shaft is inconsistent with the design size, and the construction efficiency is low.
Disclosure of Invention
The invention provides a large-diameter shaft excavation supporting construction method, which aims to solve the problems that collapse is easy to cause because no targeted construction is carried out on each layer in the conventional shaft construction, the size of the shaft is inconsistent with the design size, and the construction efficiency is low.
The invention provides a construction method for excavating and supporting a large-diameter vertical shaft, which comprises the following steps:
s1, constructing a top layer, firstly excavating a groove along the direction of an exit of a hall, paving inclined ramps at two ends of the groove after the groove is excavated, and then excavating the rest parts divided into 6 areas according to the sequence;
s2, conducting well construction, namely conducting 4-meter conducting well excavation while conducting supporting construction on the top layer after the top layer excavation is completed, and conducting 9-meter conducting well excavation after the 4-meter conducting well is communicated;
s3, constructing a plurality of middle layers, and excavating the layers from top to bottom; slotting before each layer of excavation, and then sequentially excavating in a circumferential sequence;
s4, constructing a bottom layer, namely, filling slag to the top of a rock column in the annular guide hole of the bottom layer by using the caving rock slag when the last middle layer is communicated with the annular guide hole of the bottom layer, and then carrying out layered excavation treatment according to the sequence to divide the rock column into 3 rock column regions;
s5, constructing the annular pilot tunnel, and excavating the annular pilot tunnel by adopting a full section once after the bottom layer is excavated.
Furthermore, the 6 areas of the top layer are symmetrically arranged on two sides of the groove, and the excavation sequence is sequentially two areas with symmetrical middle parts, two areas with opposite angles and the other two areas with opposite angles.
Furthermore, the grooves are drilled by a hydraulic drilling machine, the hollow surface of the middle pair Tao Xingcheng is formed by partitioned and segmented bench blasting; drilling holes on the rest part of the top layer by adopting a hydraulic drilling machine, and blasting the micro-differential bench; the explosive amount for blasting the groove is smaller than or equal to a first preset explosive amount, and the explosive amount for blasting the rest part of the top layer is smaller than or equal to a second preset explosive amount.
Furthermore, the 4-meter guide well is blasted from bottom to top, and PVC plastic pipes are respectively inserted into four blastholes at intervals before the 4-meter guide well is blasted, wherein the manufacturing steps of the blastpipe for the 4-meter guide well blasting are that 30 cm to 50 cm of the bottom of the pipe body is plugged, then emulsion explosive is filled, and the top of the pipe body is plugged after 30 cm to 50 cm of the emulsion explosive is filled.
Further, the blasting method and the blasting tube used for the 9-meter guide well are the same as those for the 4-meter guide well.
Furthermore, the middle layer adopts a hydraulic drilling machine rotary hole, the main explosion area adopts differential bench explosion, and the peripheral holes adopt vertical smooth blasting.
Furthermore, the annular guide hole adopts a hand wind drill to rotate holes, the middle wedge is cut and blasted, the caving holes adopt a slight difference millisecond blasting, and the peripheral holes adopt a smooth blasting.
Furthermore, the support construction steps of the top layer sequentially comprise concrete spraying, anchor cable installation and reinforced concrete lining.
Further, the middle layer construction comprises support construction, and the support construction steps of the middle layer comprise installation of a mortar anchor rod, concrete spraying, installation of an anchor rope and reinforced concrete lining in sequence.
Furthermore, the bottom layer construction comprises supporting construction, and the supporting construction steps of the bottom layer sequentially comprise mounting mortar anchor rods, spraying concrete, anchor bar piles, bottom plate cushion layer concrete, reinforced concrete lining and side wall reinforced concrete lining.
According to the invention, the top layer, the guide well, the plurality of middle layers, the bottom layer and the reversing guide hole are subjected to targeted construction, so that the dimensional accuracy and the strength of each layer of structure can be improved, the construction efficiency of each layer can be improved, and the problems that collapse is easy to occur during construction, the size of a vertical shaft is inconsistent with the design size, and the construction efficiency is low are solved.
Drawings
Fig. 1 is a schematic flow chart of a large-diameter shaft excavation supporting construction method provided by an embodiment of the invention.
Fig. 2 is a schematic structural diagram of layering and blocking in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 3 is a schematic block diagram of partition of layer 1 in the construction method for excavating and supporting a large-diameter vertical shaft according to the embodiment of the invention.
Fig. 4 is a schematic block diagram of a 4m pilot shaft and a 9 m pilot shaft in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 5 is a schematic view of circumferential zoning from layer 2 to layer 7 in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 6 is a schematic diagram of an annular pilot tunnel and an expanded excavation section in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 7 is a schematic diagram of blasting arrangement of a layer 1 groove in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 8 is a schematic diagram of blasting arrangement of a layer 1 region A, B in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 9 is a schematic diagram of a blasting cross-section of a region A, B of layer 1 in a large-diameter shaft excavation supporting construction method.
Fig. 10 is a schematic diagram of blasting arrangement of a layer 1 region C, D, E, F in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 11 is a schematic diagram of a blasting cross-section of a layer 1 region C, D, E, F in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 12 is a schematic diagram of blasting arrangement of a 4m pilot shaft in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 13 is a schematic structural diagram of a blasting tube of a 4m pilot shaft in the construction method for excavating and supporting a large-diameter vertical shaft according to the embodiment of the invention.
Fig. 14 is a schematic diagram of blasting arrangement of a 9 m pilot shaft in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 15 is a schematic diagram of blasting arrangement of a grooving area from layer 2 to layer 7 in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 16 is a schematic diagram of blasting cross-sections of layers 2 to 7 in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 17 is a schematic diagram of blasting arrangement of annular excavation regions from layer 2 to layer 7 in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 18 is a schematic cross-sectional view of a circumferential pilot tunnel and a rock pillar region in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 19 is a schematic diagram of blasting arrangement of a circumferential pilot tunnel and a rock pillar region in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 20 is a schematic diagram of a blasting cross-section of a circumferential pilot tunnel and a rock pillar area in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 21 is a schematic diagram of blasting arrangement of an annular pilot tunnel in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Fig. 22 is a schematic diagram of a blasting section of an annular pilot tunnel in a large-diameter shaft excavation supporting construction method according to an embodiment of the present invention.
Detailed Description
The present invention will be described in further detail with reference to the drawings and examples, in order to make the objects, technical solutions and advantages of the present invention more apparent. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the scope of the invention.
The embodiment of the invention provides a large-diameter shaft excavation supporting construction method, which is shown in the accompanying drawings from 1 to 22 and comprises the following steps of.
S1, constructing a top layer, firstly excavating a groove along the direction of a hall outlet, paving inclined ramps at two ends of the groove after the groove is excavated, and then excavating the rest parts divided into 6 areas according to the sequence.
In this embodiment, the construction height of the top layer is 5 meters, which is layer 1.
Specifically, the 6 areas of the top layer are symmetrically arranged on two sides of the groove, and the excavation sequence is sequentially two areas with symmetrical middle parts, two areas with opposite angles and the other two areas with opposite angles. In this embodiment, the 6 areas are A, B, C, D, E, F, and the excavation sequence is A-B-C-D-E-F.
Specifically, the grooves are drilled by a hydraulic drilling machine, the hollow surface of the middle pair Tao Xingcheng is formed by blasting in a partitioned and block-separated bench; drilling holes on the rest part of the top layer by adopting a hydraulic drilling machine, and blasting the micro-differential bench; the explosive amount for blasting the groove is smaller than or equal to a first preset explosive amount, and the explosive amount for blasting the rest part of the top layer is smaller than or equal to a second preset explosive amount. The first preset medicine amount and the second preset medicine amount are set according to actual requirements.
S2, conducting well construction, namely conducting 4 meters of conducting well excavation while supporting the top layer after the top layer excavation is completed, conducting 9 meters of conducting well excavation after the 4 meters of conducting well is penetrated, so that the conducting well is penetrated with the bottom layer annular guide hole, and a slag discharging channel of the whole vertical shaft is formed.
Specifically, the 4-meter guide well is blasted from bottom to top, and PVC plastic pipes are respectively inserted into four blastholes at intervals before the 4-meter guide well is blasted, wherein the manufacturing steps of the blastpipe for the 4-meter guide well blasting are that 30 cm to 50 cm of the bottom of the pipe body is plugged, then emulsion explosive is filled, and the top of the pipe body is plugged after 30 cm to 50 cm of the emulsion explosive is filled.
The method comprises the steps of plugging the bottom of a pipe body, namely, threading a steel wire from a drilling hole to the bottom, fixing gunny bags, cloth and the like on the steel wire to serve as plugging materials, filling quick setting cement from the upper part of the drilling hole to enable the bottom to be plugged to a designed length, and then, reloading the emulsion explosive after the cement strength reaches the design requirement. The sealing step of the top of the pipe body is to seal the top after binding plastic bagged cement with the length of 50 cm and the diameter of 10 cm.
The blasting parameters are determined through a blasting test during blasting of the 4-meter guide well, the flatness of the guide well is ensured, the influence on slag sliding is reduced, a non-electric millisecond plastic detonating tube is adopted for blasting in series to form a blasting network to realize differential blasting, and an electric detonator is used for detonating, so that the detonating tube is adopted for leading to an upper wellhead.
Specifically, the blasting method and the blasting tube used for the 9-meter guide well are the same as those of the 4-meter guide well.
S3, constructing a plurality of middle layers, and excavating the layers from top to bottom; each layer is firstly grooved before excavation, and then sequentially excavated in a circumferential order.
In this embodiment, the number of middle layers is 6, and is 2 to 7 layers respectively, and each layer is divided into a slotting region 1 and 2 to 17 annular excavation regions. Wherein, the slotting area 1 to the excavation area 17 are divided into 6 large areas (without a guide well), the excavation height of the 2 nd layer to the 6 th layer is 5 meters, and the excavation height of the 7 th layer is 6.7 meters.
Specifically, the middle layer adopts a hydraulic drilling machine rotary hole, the main explosion area adopts a slight difference bench for blasting, the peripheral holes adopt a vertical smooth blasting, the contour line adopts a smooth blasting, and slag is slipped out from the guide well by adopting a back hoe.
S4, constructing a bottom layer, namely, using the last rock slag which is caving when the middle layer is communicated with the bottom layer annular guide hole to pad slag to the top of a rock column in the bottom layer annular guide hole, and then dividing the rock column into rock column regions of 3 regions according to sequential layered excavation treatment.
In this embodiment, the bottom layer is an 8 th layer, and is divided into 6 large areas, the excavation height of the large areas is 9.2 meters, and the rock pillar area is divided into 1 to 3 areas, wherein the area 1 corresponds to the annular guide hole, and the excavation sequence is 1-2-3.
S5, constructing the annular pilot tunnel, and excavating the annular pilot tunnel by adopting a full section once after the bottom layer is excavated.
Specifically, the annular pilot tunnel bottom plate and the traffic branch tunnel bottom plate are Cheng Yizhi in height, the pilot tunnel is 6 m wide and 7 m high, and the pilot tunnel bottom plate and the pool bottom plate are reserved with 1.2 m protection layers for later excavation treatment.
Specifically, the annular guide hole adopts a hand wind drill to rotate holes, the middle wedge adopts cut blasting, the caving holes adopt slight difference millisecond blasting, and the peripheral holes adopt smooth blasting.
Wherein, the blasting technical parameters of the layer 1 groove are shown as follows:
the blast parameter design table for the layer 1 trench is as follows:
the blasting-technical parameters of the zone of layer 1A, B are shown below:
the blast parameter design table for zone 1, layer A, B, is as follows:
the blasting-technical parameters of the zone of layer 1C, D, E, F are shown below:
the blast parameter design table for zone 1, layer C, D, E, F, is as follows:
the blasting-technical parameters of the 4m pilot well are shown below:
the blasting parameter design table of the 4m pilot well is as follows:
9 blasting-technical parameters of the pilot shaft are shown below:
9 the blasting parameter design table of the guide well is as follows:
blasting-technical parameters of the 2 nd to 7 th layer grooving regions are shown below:
the blast parameter design table for the 2 nd to 7 th layer slotting region is as follows:
another blasting-technical parameter table for the slotted zone of layers 2 to 7 is as follows:
another blast parameter design table for the 2 nd to 7 th floor slotted zone is as follows:
the blasting-technical parameters of the 8 th layer of the rock pillar area are shown as follows:
the blasting parameter design table for the 8 th layer of rock pillar area is as follows:
another blasting-technical parameter table for the zone of layer 8 rock string is as follows:
another blast parameter design table for the zone of layer 8 rock string is as follows:
/>
in the method, a partition block diagram of a layer 1 is shown in fig. 3, a layer 1 groove blasting arrangement diagram is shown in fig. 7, a blasting arrangement diagram of a layer 1 region A, B is shown in fig. 8, a blasting arrangement diagram of a layer 1 region C, D, E, F is shown in fig. 10, a partition block diagram of a 4m pilot well and a 9 m pilot well is shown in fig. 4, a blasting arrangement diagram of a 4m pilot well is shown in fig. 12, a structural diagram of a blasting tube of a 4m pilot well is shown in fig. 13, a blasting arrangement diagram of a 9 m pilot well is shown in fig. 14, a circumferential partition diagram of a layer 2 to a layer 7 is shown in fig. 5, a blasting arrangement diagram of a slotted region of a layer 2 to a layer 7 is shown in fig. 15, a blasting section diagram of a layer 2 to a layer 7 is shown in fig. 16, a section diagram of a ring-shaped excavation region of a layer 2 to a layer 7 is shown in fig. 17, a section diagram of a ring-shaped pilot hole and a hole-expanded section of a ring-shaped pilot hole is shown in fig. 6, a section diagram of a ring-shaped pilot hole and a hole region is shown in fig. 18, a section of a ring-shaped pilot hole and a ring-shaped pilot hole is shown in fig. 19 is shown in fig. 20, a section of a ring-shaped pilot hole is shown in fig. 21 is shown in fig. 20, a section of a ring-shaped section is shown in fig. 21.
It should be noted that, in this document, the term "comprises," "comprising," or any other variation thereof is intended to cover a non-exclusive inclusion, such that a process, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, article, or apparatus. Without further limitation, an element defined by the phrase "comprising" does not exclude the presence of other like elements in a process or apparatus that includes such element.
The foregoing description of the preferred embodiments of the invention is not intended to be limiting, but rather is intended to cover all modifications, equivalents, and alternatives falling within the spirit and principles of the invention.

Claims (8)

1. The construction method for excavating and supporting the large-diameter vertical shaft is characterized by comprising the following steps:
s1, constructing a top layer, firstly excavating a groove along the direction of an exit of a hall, paving inclined ramps at two ends of the groove after the groove is excavated, and then excavating the rest parts divided into 6 areas according to the sequence; the 6 areas of the top layer are symmetrically arranged on two sides of the groove, and the excavation sequence is sequentially two areas with symmetrical middle parts, two opposite angles and the other two opposite angles; the grooves are drilled by a hydraulic drilling machine, the middle part is opposite to the Tao Xingcheng temporary surface, and the grooves are formed by partitioned and segmented bench blasting; drilling holes on the rest part of the top layer by adopting a hydraulic drilling machine, and blasting the micro-differential bench; the explosive amount for blasting the groove is smaller than or equal to a first preset explosive amount, and the explosive amount for blasting the rest part of the top layer is smaller than or equal to a second preset explosive amount;
s2, conducting well construction, namely conducting 4-meter conducting well excavation while conducting supporting construction on the top layer after the top layer excavation is completed, and conducting 9-meter conducting well excavation after the 4-meter conducting well is communicated;
s3, constructing a plurality of middle layers, and excavating the layers from top to bottom; slotting before each layer of excavation, and then sequentially excavating in a circumferential sequence;
s4, constructing a bottom layer, namely, filling slag to the top of a rock column in the annular guide hole of the bottom layer by using the caving rock slag when the last middle layer is communicated with the annular guide hole of the bottom layer, and then carrying out layered excavation treatment according to the sequence to divide the rock column into 3 rock column regions;
s5, constructing the annular pilot tunnel, and excavating the annular pilot tunnel by adopting a full section once after the bottom layer is excavated.
2. The large-diameter shaft excavation supporting construction method as claimed in claim 1, wherein the 4-meter guide well is blasted from bottom to top, and PVC plastic pipes are respectively inserted into four blastholes at intervals before the 4-meter guide well is blasted, wherein the blasting pipes for the 4-meter guide well are manufactured by plugging 30 cm to 50 cm at the bottom of a pipe body, then installing emulsion explosive, and plugging the top of the pipe body by 30 cm to 50 cm after the emulsion explosive is installed.
3. The large diameter shaft excavation supporting construction method of claim 1, wherein the blasting method and the blasting tube used for the 9 m pilot shaft are the same as those for the 4m pilot shaft.
4. The large-diameter shaft excavation supporting construction method as claimed in claim 1, wherein the middle layer adopts a hydraulic drilling machine rotary hole, the main explosion area adopts differential bench explosion, and the peripheral holes adopt vertical smooth blasting.
5. The large-diameter shaft excavation supporting construction method as claimed in claim 1, wherein the annular guide hole adopts a hand wind drill turning hole, the middle wedge adopts cut blasting, the caving hole adopts a slight difference millisecond blasting, and the peripheral hole adopts a smooth blasting.
6. The large-diameter shaft excavation supporting construction method as claimed in claim 1, wherein the supporting construction step of the top layer is sequentially spraying concrete, installing anchor ropes and lining with reinforced concrete.
7. The large diameter shaft excavation supporting construction method of claim 1, wherein the middle layer construction comprises supporting construction, and the supporting construction steps of the middle layer are installing a mortar anchor rod, spraying concrete, installing an anchor rope, and lining with reinforced concrete in sequence.
8. The large diameter shaft excavation supporting construction method of claim 1, wherein the bottom layer construction comprises supporting construction, and the supporting construction steps of the bottom layer are installing mortar anchor rods, spraying concrete, anchor bar piles, floor bedding concrete and reinforced concrete lining, and side wall reinforced concrete lining in sequence.
CN202110500310.XA 2021-05-08 2021-05-08 Major diameter shaft excavation supporting construction method Active CN113153306B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110500310.XA CN113153306B (en) 2021-05-08 2021-05-08 Major diameter shaft excavation supporting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110500310.XA CN113153306B (en) 2021-05-08 2021-05-08 Major diameter shaft excavation supporting construction method

Publications (2)

Publication Number Publication Date
CN113153306A CN113153306A (en) 2021-07-23
CN113153306B true CN113153306B (en) 2023-11-14

Family

ID=76873845

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110500310.XA Active CN113153306B (en) 2021-05-08 2021-05-08 Major diameter shaft excavation supporting construction method

Country Status (1)

Country Link
CN (1) CN113153306B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114320303A (en) * 2021-12-09 2022-04-12 中国铁建大桥工程局集团有限公司 Method for excavating vertical shaft flood discharge tunnel body support
CN114320304A (en) * 2022-02-11 2022-04-12 中国水利水电第五工程局有限公司 Excavation method of large-aperture slag chute open type surge shaft and hoisting construction platform
CN115262500B (en) * 2022-08-10 2024-05-28 武汉理工大学 Cave type dam abutment groove spiral excavation structure and method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10140968A (en) * 1996-11-08 1998-05-26 Tone Chika Gijutsu Kk Construction method and apparatus of extremely large diameter and extremely deep shaft
JP2001207774A (en) * 2000-01-26 2001-08-03 Mitsui Constr Co Ltd Shaft excavating method
CN101349064A (en) * 2008-08-26 2009-01-21 中国水利水电第五工程局 Construction method of hydroelectric power station surge chamber vertical shaft under soft rock geological condition
CN104819670A (en) * 2015-05-19 2015-08-05 重庆交通建设(集团)有限责任公司 Pre-drilling mesopore shaft excavation blasting method
CN106677786A (en) * 2017-01-14 2017-05-17 中铁隧道集团有限公司 Ultra-deep large-section vertical shaft one-time blasting forming method based on electronic detonators
CN107255433A (en) * 2017-07-07 2017-10-17 中国电建集团华东勘测设计研究院有限公司 The long drilling depth guide well photoface exploision excavating load of a kind of soft rock, dead-soft petrographic province major diameter surge shaft
CN111594174A (en) * 2020-05-08 2020-08-28 中电建十一局工程有限公司 Full-section one-time pore-forming segmented blasting vertical shaft excavation method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10140968A (en) * 1996-11-08 1998-05-26 Tone Chika Gijutsu Kk Construction method and apparatus of extremely large diameter and extremely deep shaft
JP2001207774A (en) * 2000-01-26 2001-08-03 Mitsui Constr Co Ltd Shaft excavating method
CN101349064A (en) * 2008-08-26 2009-01-21 中国水利水电第五工程局 Construction method of hydroelectric power station surge chamber vertical shaft under soft rock geological condition
CN104819670A (en) * 2015-05-19 2015-08-05 重庆交通建设(集团)有限责任公司 Pre-drilling mesopore shaft excavation blasting method
CN106677786A (en) * 2017-01-14 2017-05-17 中铁隧道集团有限公司 Ultra-deep large-section vertical shaft one-time blasting forming method based on electronic detonators
CN107255433A (en) * 2017-07-07 2017-10-17 中国电建集团华东勘测设计研究院有限公司 The long drilling depth guide well photoface exploision excavating load of a kind of soft rock, dead-soft petrographic province major diameter surge shaft
CN111594174A (en) * 2020-05-08 2020-08-28 中电建十一局工程有限公司 Full-section one-time pore-forming segmented blasting vertical shaft excavation method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
中国水利水电第十一工程局有限公司.《地下工程施工技术与实例》.北京:中国铁道出版社,2014,(第1版),第281-289页. *
张荣君.《水利水电工程建造师便携手册》.沈阳:辽宁科学技术出版社,2009,(第1版),第65-70页. *
白鹤滩水电站调压室竖井开挖施工技术研究;杨继承 等;《水利水电技术》;第48卷(第2017年增刊2期);第54-58页 *

Also Published As

Publication number Publication date
CN113153306A (en) 2021-07-23

Similar Documents

Publication Publication Date Title
CN113153306B (en) Major diameter shaft excavation supporting construction method
CN112431599B (en) Tunnel excavation method for upper soft and lower hard stratum
CN111912307B (en) Blasting excavation method for V-level surrounding rock large-section granite tunnel
CN109723443B (en) Tunnel construction method
AU2020257049B2 (en) Construction method for forming water-proof grouting curtain in water-rich porous rock stratum by blasting
CN105401946A (en) Reverse blasting excavation method of shaft and pilot shaft
CN105649012A (en) Construction method for bored pile of subway station enclosure structure of upper-soft lower-hard ground
CN110230495B (en) Core soil excavation method for double-side-wall pilot tunnel construction of subway station
KR20180105100A (en) Vibration-free rapid excavation method using pilot tunnel in large-scale tunnel
CN112252973A (en) Non-excavation directional drilling construction method for pipeline buried channel
CN111365002A (en) Ground pre-grouting method for small-section high wellbore in complex stratum
CN114483109B (en) Curtain grouting advanced large pipe shed through construction method for crossing tunnel fault fracture zone
CN110863832B (en) Large-section tunnel stability control construction method for penetrating through earth-rock boundary stratum
CN104314076A (en) Recycled type prestressed anchor cable structure for soft soil foundation and construction method
KR20160149177A (en) Construction method of internal pre-support tunnel for complete blocking water of all directions of the tunnel
CN107091094A (en) Short inclined shaft pilot shaft excavation method in one kind
CA2456303C (en) Continuous method of realization of underground tunnels including peripheral perforations
CN105019431A (en) Large-diameter super-long bored pile construction method for steep dip stratified rock mass with alternative smashed parts and integral parts
CN110735641B (en) Construction method of transfer passage of underpass pipeline
KR102609304B1 (en) A grouting method using a direction-controlled borehole and a grouting system for the soft ground and void area
KR102325623B1 (en) Construction method of retaining wall
CN110144903B (en) Construction method for foundation pit support in air defense cavity
CN111220036B (en) Blasting method for pilot tunnel at lower section of vertical shaft water curtain roadway
CN110644439B (en) Method for quickly forming barrier body impervious wall
EP0911449A1 (en) A cast-in-place pile and the process for manufacturing of the same

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant