CN112502715A - Temporary plugging and reinforcing method for end of shield tunnel - Google Patents

Temporary plugging and reinforcing method for end of shield tunnel Download PDF

Info

Publication number
CN112502715A
CN112502715A CN202011235152.1A CN202011235152A CN112502715A CN 112502715 A CN112502715 A CN 112502715A CN 202011235152 A CN202011235152 A CN 202011235152A CN 112502715 A CN112502715 A CN 112502715A
Authority
CN
China
Prior art keywords
freezing
steel
wall
pipe
shield tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202011235152.1A
Other languages
Chinese (zh)
Inventor
陈鸿
曹伟飚
李胜杰
王书磊
管攀峰
张晓菲
王天翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tunnel Engineering and Rail Transit Design and Research Institute
Original Assignee
Shanghai Tunnel Engineering and Rail Transit Design and Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Tunnel Engineering and Rail Transit Design and Research Institute filed Critical Shanghai Tunnel Engineering and Rail Transit Design and Research Institute
Priority to CN202011235152.1A priority Critical patent/CN112502715A/en
Publication of CN112502715A publication Critical patent/CN112502715A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Soil Sciences (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a shield method tunnel end temporary plugging and reinforcing method, which comprises the following steps: horizontally arranging a plurality of steel freezing pipes along a newly-built shield tunnel line to be excavated and freezing to form an annular freezing reinforcement body; chiseling off the underground continuous wall and excavating soil body in layers to form a barrier clearing channel, and before excavating the last underground continuous wall, driving a steel freezing pipe into the soil body at the end part to perform secondary supplementary freezing to form a frozen wall at the end part; pulling out the steel freezing pipe in the freezing wall at the end part and replacing the steel freezing pipe with a hard PVC pipe to maintain freezing; backfilling the obstacle clearing channel layer by layer; stopping freezing the frozen wall at the end part after the layered backfilling is finished; and the shield machine cuts and advances in the backfilled obstacle clearing channel along the newly built shield tunnel line. The invention has the advantages that: before the shield machine advances to cut, the steel freezing pipe in the end freezing wall is replaced by a hard PVC pipe which can be cut, and the freezing effect of the tunnel end freezing wall is powerfully guaranteed under the condition that the normal cutting advance of the shield machine is not influenced.

Description

Temporary plugging and reinforcing method for end of shield tunnel
Technical Field
The invention belongs to the technical field of freezing of shield tunnels, and particularly relates to a shield method tunnel end temporary plugging and reinforcing method.
Background
The artificial stratum freezing technology is widely applied to the construction of a shield tunnel, a low-carbon seamless steel pipe is adopted as a freezing pipe in the conventional freezing process, low-temperature saline water is circulated, and the steel freezing pipe is pulled out after the freezing wall is formed and before a shield is pushed; because the periphery of the freezing pipe is wrapped by frozen soil, hot brine circulation is carried out before the freezing pipe is pulled out, and the frozen soil on the surface of the freezing pipe is melted; after the freezing pipe is pulled out, because continuous cold energy supply is not provided, the formed freezing wall is gradually heated under the influence of external conditions (terrestrial heat, heat dissipation and the like), the strength is weakened, the risk of collapse is caused, and certain potential safety hazards exist.
Disclosure of Invention
The invention aims to provide a temporary plugging and reinforcing method for a tunnel end by a shield method according to the defects of the prior art, the method is characterized in that before the shield machine is cut and pushed, a steel freezing pipe in an end freezing wall is thawed and pulled out, then a hard PVC pipe which can be free from pulling is replaced to maintain the end freezing wall frozen, safe operation time is created for backfilling an excavated obstacle clearing channel, after backfilling is completed, the shield machine is pushed to the position of the end freezing wall on a newly-built shield tunnel line, and the end freezing wall and the hard PVC pipe in the end freezing wall are directly cut by a cutter head of the shield machine.
The purpose of the invention is realized by the following technical scheme:
a shield method tunnel end temporary plugging and reinforcing method is characterized by comprising the following steps: horizontally arranging a plurality of steel freezing pipes along a newly-built shield tunnel line to be excavated and freezing to form an annular freezing reinforcement body; chiseling underground continuous walls in the annular freezing reinforcement body, excavating soil bodies in layers to form a barrier clearing channel, and driving steel freezing pipes into the soil bodies at the end parts to perform secondary supplementary freezing to form end part freezing walls before excavating the last underground continuous wall at the end parts of the barrier clearing channel; pulling out the steel freezing pipe in the end freezing wall and replacing the steel freezing pipe with a hard PVC pipe, and maintaining the freezing of the end freezing wall by using the hard PVC pipe; backfilling the obstacle clearing channel layer by layer; stopping freezing the frozen wall at the end part after the barrier clearing channel is backfilled in a layered manner; and the shield machine carries out cutting propulsion in the backfilled obstacle clearing channel along the newly-built shield tunnel line.
The newly-built shield tunnel line is located below an existing subway station, a plurality of underground continuous walls are distributed below the existing subway station, the annular freezing reinforcement bodies on the newly-built shield tunnel line penetrate through the underground continuous walls, the initial end parts of the annular freezing reinforcement bodies are barrier clearing working wells, a plurality of steel freezing pipes are horizontally arranged in the barrier clearing working wells along the extending direction of the newly-built shield tunnel line, and the soil body is frozen by circulating low-temperature saline water in the steel freezing pipes, so that the annular freezing reinforcement bodies are formed.
A cross-shaped freezing reinforcement wall is provided in the ring-shaped freezing reinforcement body to divide an inner space of the ring-shaped freezing reinforcement body into an upper space and a lower space, each of which is divided into a left unit and a right unit.
The thickness of the frozen wall at the end part in the line direction of the newly-built shield tunnel is not less than 4m, and the average temperature is not more than-10 ℃.
The method for pulling out the steel freezing pipe in the end freezing wall and replacing the steel freezing pipe with the hard PVC pipe comprises the following steps: and performing hot brine circulation in the steel freezing pipe to defrost and pull out the steel freezing pipe, then plugging the hard PVC pipe into the freezing hole where the steel freezing pipe is pulled out, and recovering the low-temperature brine circulation in the hard PVC pipe to maintain the freezing of the frozen wall at the end part.
The temperature of the hot brine is controlled to be 50-80 ℃, and the drawing force when the steel freezing pipe is drawn out is not more than 0.5 ton.
Temperature measuring holes are arranged in the freezing wall at the end part.
The invention has the advantages that: according to the shield tunnel end temporary plugging and reinforcing method, the steel freezing pipe is replaced by the pulling-free pipe, so that the freezing effect of the freezing reinforcing body is powerfully guaranteed, the frozen soil curtain is basically not weakened, the safe operation time is created for backfilling of the excavated channel, and the engineering risk is reduced; when the shield is pushed to the end of the tunnel, the frozen wall and the hard PVC pipe are directly cut by the cutter head of the shield machine, and the normal operation of the shield machine is not influenced.
Drawings
FIG. 1 is a schematic diagram of the primary freezing of the shield tunnel end temporary plugging and reinforcing method of the present invention;
FIG. 2 is a cross-sectional view taken along line A-A of FIG. 1 in accordance with the present invention;
FIG. 3 is a schematic diagram of secondary freezing of the shield tunnel end temporary plugging and reinforcing method of the present invention;
FIG. 4 is a cross-sectional view B-B of FIG. 3 according to the present invention;
FIG. 5 is a schematic view of a construction step a of temporarily blocking and reinforcing the end of the shield tunnel in the present invention;
FIG. 6 is a schematic diagram of a construction step b of temporarily blocking and reinforcing the end of the shield tunnel in the invention;
FIG. 7 is a schematic view of a construction step c of temporarily blocking and reinforcing the end of the shield tunnel according to the present invention;
FIG. 8 is a schematic view of a construction step d of temporarily plugging and reinforcing the end of the shield tunnel according to the present invention;
FIG. 9 is a schematic view of a construction step e for temporarily blocking and reinforcing the end of the shield tunnel in the present invention;
fig. 10 is a schematic view of a construction step f of temporarily blocking and reinforcing the end of the shield tunnel in the present invention.
Detailed Description
The features of the present invention and other related features are described in further detail below by way of example in conjunction with the following drawings to facilitate understanding by those skilled in the art:
referring to fig. 1-10, the symbols in the figures are: the system comprises an existing subway station 1, an annular freezing reinforcement body 2, a cross freezing reinforcement wall 3, a barrier clearing working well 4, a newly-built shield tunnel line 5, an underground continuous wall 6a, an underground continuous wall 6b, an underground continuous wall 6c, an underground continuous wall 6d, an end freezing wall 7, a protective door 8, a profile steel support 9 and foam concrete 10.
Example (b): as shown in fig. 1-10, the present embodiment specifically relates to a temporary plugging and reinforcing method for a shield tunnel end, which mainly works on the principle that before the shield machine is cut and advanced, a steel freezing pipe in an end freezing wall 7 is defrosted and pulled out, and then a cuttable rigid PVC pipe is replaced to maintain the end freezing wall 7 frozen, so as to create a safe operation time for backfilling an excavated obstacle clearing channel, after the backfilling is completed, the shield machine is cut and advanced to the position of the end freezing wall 7 on a newly-built shield tunnel line 5, the end freezing wall 7 and the rigid PVC pipe therein are directly cut by a cutter head of the shield machine, the rigid PVC pipe is easy to cut, and the normal operation of the shield machine is not affected.
As shown in fig. 1 to 10, the method for temporarily blocking and reinforcing the end of the shield tunnel in this embodiment includes the following steps:
(1) the newly-built shield tunnel line 5 is positioned below the existing subway station 1 and is intersected with the existing subway station 1, wherein one newly-built shield tunnel line 5 is vertically intersected with the existing subway station 1 in the direction, and the other newly-built shield tunnel line 5 is obliquely intersected with the existing subway station 1 in the direction; the newly-built shield tunnel line 5 passes through four underground continuous walls 6 below the existing subway station 1, namely an underground continuous wall 6a, an underground continuous wall 6b, an underground continuous wall 6c and an underground continuous wall 6 d;
arranging an obstacle clearing working well 4 at one side of an existing subway station 1, horizontally driving a circle of a plurality of steel freezing pipes (low-carbon seamless steel pipes) into a soil body along a newly-built shield tunnel line 5 in the obstacle clearing working well 4, and circulating by introducing low-temperature saline water into each steel freezing pipe to form an annular freezing reinforcement body 2 shown in figures 1 and 2; meanwhile, a cross-shaped freezing reinforcing wall 3 is further arranged in the annular freezing reinforcing body 2 to further improve the stability of freezing reinforcement, the cross-shaped freezing reinforcing wall 3 divides the internal space of the annular freezing reinforcing body 2 into an upper layer space and a lower layer space, and each layer of space is divided into a left unit and a right unit.
(2) Adopting segmented step excavation for the shield crossing area, as shown in fig. 5, installing a protective door 8, chiseling the upper part of the underground continuous wall 6a, excavating the soil body in the upper space, and installing a section steel bracket 9 while excavating; then installing a protective door 8, chiseling the lower part of the underground continuous wall 6a, and excavating soil in the lower-layer space; referring to fig. 6, 7 and 8, the underground continuous wall 6b, the underground continuous wall 6c and the underground continuous wall 6d are sequentially chiseled off by the method, upper and lower soil bodies are respectively excavated, and the section steel support 9 is installed while excavating to form a barrier removal channel.
(3) It should be noted that, as shown in fig. 8, before the underground continuous wall 6d is chiseled off, a plurality of steel freezing pipes (∅ 108 × 8 low-carbon seamless steel pipes) are horizontally driven into the soil body on the underground continuous wall 6d to a depth of not less than 4m from the end of the barrier removal channel, the steel freezing pipes are uniformly distributed on the whole section of the end, then low-temperature saline water is circulated in each steel freezing pipe, the temperature of the saline water is minus 28 ℃ to minus 32 ℃, secondary freezing is carried out, and therefore an end freezing wall 7 is formed, the average temperature is less than or equal to minus 10 ℃, as shown in fig. 3, 4 and 9. In addition, it should be noted that an additional temperature measuring hole is drilled at the weak point of the end frost wall 7 so as to measure the temperature.
(4) After the last underground continuous wall 6d is removed, introducing high-temperature saline water into the steel freezing pipes in the end freezing wall 7 for circularly thawing, performing thawing in groups, plugging the steel freezing pipes into holes by prefabricated phi 100 hard PVC pipes immediately after the steel freezing pipes are pulled out, and recovering low-temperature saline water freezing; then the next group of steel freezing pipes is defrosted and pulled out, and the frozen wall 7 at the end part is protected to the maximum extent. After the hard PVC pipe is replaced, the shield propulsion area is only provided with the hard PVC pipe and the high-pressure rubber pipe of the connecting pipeline, after the light concrete is filled in the tunnel, the high-pressure rubber pipe is poured in the concrete and fixed by the concrete, and the cutter head of the shield machine can be easily cut off.
(5) And after the hard PVC pipe is replaced, removing the section steel support 9 and each protective door 8 in the barrier clearing channel, backfilling foam concrete 10 layer by layer, and stopping freezing the frozen wall 7 at the end part. Then, the shield machine carries out propulsion cutting in the backfilled obstacle clearing channel along a newly-built shield tunnel line 5, the frozen wall 7 at the end part and the hard PVC pipe in the frozen wall can be directly cut by a cutter head of the shield machine, the hard PVC pipe is easy to cut, and the normal operation of the shield machine is not influenced; and after the shield tunneling machine passes through the end part freezing wall 7 and the annular freezing reinforcing body 2, performing melt-sinking grouting by using the reserved grouting holes of the pipe pieces.
The beneficial effect of this embodiment lies in: after the steel freezing pipe which is difficult to cut is subjected to secondary freezing of the frozen wall at the end part, the steel freezing pipe is quickly thawed and is replaced by a hard PVC pipe, and then freezing is continuously maintained, so that safe operation time is created for backfilling of an excavated channel; when the shield is pushed to the reinforced area of the end of the tunnel, the frozen wall and the hard PVC frozen pipe are directly cut by the cutter head of the shield machine, the hard PVC pipe is easy to cut, and the normal operation of the shield machine is not influenced. The freezing effect of the tunnel end freezing reinforcing body is powerfully guaranteed by freezing the hard PVC pipes, the frozen walls at the ends are basically not weakened, and the engineering risk is greatly reduced.

Claims (7)

1. A shield method tunnel end temporary plugging and reinforcing method is characterized by comprising the following steps: horizontally arranging a plurality of steel freezing pipes along a newly-built shield tunnel line to be excavated and freezing to form an annular freezing reinforcement body; chiseling underground continuous walls in the annular freezing reinforcement body, excavating soil bodies in layers to form a barrier clearing channel, and driving steel freezing pipes into the soil bodies at the end parts to perform secondary supplementary freezing to form end part freezing walls before excavating the last underground continuous wall at the end parts of the barrier clearing channel; pulling out the steel freezing pipe in the end freezing wall and replacing the steel freezing pipe with a hard PVC pipe, and maintaining the freezing of the end freezing wall by using the hard PVC pipe; backfilling the obstacle clearing channel layer by layer; stopping freezing the frozen wall at the end part after the barrier clearing channel is backfilled in a layered manner; and the shield machine carries out cutting propulsion in the backfilled obstacle clearing channel along the newly-built shield tunnel line.
2. The method of claim 1, wherein the newly-built shield tunnel line is located below an existing subway station, a plurality of underground continuous walls are distributed below the existing subway station, the annular freezing reinforcement body on the newly-built shield tunnel line passes through each underground continuous wall, the initial end part of the annular freezing reinforcement body is an obstacle clearing working well, a plurality of steel freezing pipes are horizontally arranged in the obstacle clearing working well along the extending direction of the newly-built shield tunnel line, and a soil body is frozen by circulating low-temperature saline water in the steel freezing pipes to form the annular freezing reinforcement body.
3. The method as claimed in claim 2, wherein cross-shaped freezing reinforcing walls are provided in the freezing annular reinforcing bodies to divide the inner space of the freezing annular reinforcing bodies into an upper space and a lower space, and each space is divided into a left unit and a right unit.
4. The method of claim 1, wherein the thickness of the frozen wall at the end part in the line direction of the newly-built shield tunnel is not less than 4m, and the average temperature is less than or equal to-10 ℃.
5. The method for temporarily plugging and reinforcing the end of the shield tunnel according to claim 1, wherein the method for pulling out the steel freezing pipe in the end freezing wall and replacing the steel freezing pipe with the hard PVC pipe comprises the following steps: and performing hot brine circulation in the steel freezing pipe to defrost and pull out the steel freezing pipe, then plugging the hard PVC pipe into the freezing hole where the steel freezing pipe is pulled out, and recovering the low-temperature brine circulation in the hard PVC pipe to maintain the freezing of the frozen wall at the end part.
6. The method for temporarily plugging and reinforcing the end of the shield tunnel according to claim 5, wherein the temperature of the hot brine is controlled to be 50-80 ℃, and the drawing force when the steel freezing pipe is drawn out is not more than 0.5 ton.
7. The shield tunnel end temporary plugging and reinforcing method according to claim 1, wherein temperature measuring holes are arranged in the frozen wall at the end part.
CN202011235152.1A 2020-11-08 2020-11-08 Temporary plugging and reinforcing method for end of shield tunnel Withdrawn CN112502715A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011235152.1A CN112502715A (en) 2020-11-08 2020-11-08 Temporary plugging and reinforcing method for end of shield tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011235152.1A CN112502715A (en) 2020-11-08 2020-11-08 Temporary plugging and reinforcing method for end of shield tunnel

Publications (1)

Publication Number Publication Date
CN112502715A true CN112502715A (en) 2021-03-16

Family

ID=74955530

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011235152.1A Withdrawn CN112502715A (en) 2020-11-08 2020-11-08 Temporary plugging and reinforcing method for end of shield tunnel

Country Status (1)

Country Link
CN (1) CN112502715A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113775342A (en) * 2021-09-23 2021-12-10 海南大学 Shield butt-joint freezing and reinforcing method and device

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201460904U (en) * 2009-06-29 2010-05-12 上海市基础工程公司 Ultra-long horizontal freezing consolidation structure for shield entry
CN103924980A (en) * 2014-04-24 2014-07-16 上海隧道工程股份有限公司 Obstacle removing construction method
CN104790961A (en) * 2015-04-27 2015-07-22 海南大学 Vertical cup type freezing reinforcement structure and method at shield tunnel end
CN105952458A (en) * 2016-03-29 2016-09-21 中铁时代建筑设计院有限公司 Shield tunnel end semispherical freezing wall reinforcement structure and construction method thereof
CN108005663A (en) * 2017-12-18 2018-05-08 上海市基础工程集团有限公司 Export & import exempts from tube drawing consolidation by freezing construction method
CN111058850A (en) * 2019-11-13 2020-04-24 上海隧道工程有限公司 Underground obstacle freezing, detecting and clearing method
CN111119900A (en) * 2019-12-10 2020-05-08 中铁十四局集团隧道工程有限公司 Earth pressure balance shield liquid nitrogen vertical freezing and underwater receiving comprehensive construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201460904U (en) * 2009-06-29 2010-05-12 上海市基础工程公司 Ultra-long horizontal freezing consolidation structure for shield entry
CN103924980A (en) * 2014-04-24 2014-07-16 上海隧道工程股份有限公司 Obstacle removing construction method
CN104790961A (en) * 2015-04-27 2015-07-22 海南大学 Vertical cup type freezing reinforcement structure and method at shield tunnel end
CN105952458A (en) * 2016-03-29 2016-09-21 中铁时代建筑设计院有限公司 Shield tunnel end semispherical freezing wall reinforcement structure and construction method thereof
CN108005663A (en) * 2017-12-18 2018-05-08 上海市基础工程集团有限公司 Export & import exempts from tube drawing consolidation by freezing construction method
CN111058850A (en) * 2019-11-13 2020-04-24 上海隧道工程有限公司 Underground obstacle freezing, detecting and clearing method
CN111119900A (en) * 2019-12-10 2020-05-08 中铁十四局集团隧道工程有限公司 Earth pressure balance shield liquid nitrogen vertical freezing and underwater receiving comprehensive construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113775342A (en) * 2021-09-23 2021-12-10 海南大学 Shield butt-joint freezing and reinforcing method and device

Similar Documents

Publication Publication Date Title
JP4803428B2 (en) Tunnel construction method
CN108194102B (en) The dismounting of limit section and safe stress check calculation construction method are invaded in Tunnel deformation
CN102787846B (en) Upper-blocking and lower-draining construction method for undersea tunnel fault fracture zone
US4516878A (en) Tunnel constructing
JP6594003B2 (en) Freezing method and freezing device for shield tunnel construction
JP4793655B2 (en) Tunnel construction method
JP4958035B2 (en) Shield roof construction method
KR100847352B1 (en) Supporting tube assembly for tunnel supporting method with grouted steel pipe in the borehole and supporting method of using thereof
CN101144384B (en) Tunnel engineering non-blasting weak disturbance excavating method
CN112502723B (en) Single-shield TBM blocking machine escaping construction method
CN111335902B (en) Construction method for shield tunneling ground connection wall underpass operation subway station
CN110159274B (en) Sea area high water pressure shield method tunnel emergency tool changing structure and construction method
CN105863646A (en) Freezing construction method in steel pipe curtain of large-section subsurface tunnel
CN104314585A (en) Pre-reinforcement method and pre-reinforcement structure for full section of tunnel
CN112647956B (en) Construction method for short-distance underpass subway station of water-rich composite stratum shield
CN108825247B (en) External inclination side wall horizontal bottom-making basin-shaped freezing water stop construction method for 8 pilot tunnel PBA construction method
CN105937397A (en) Segmented excavation freezing method reinforcing construction method for deep tunnel
CN113803074A (en) Construction method of tunnel structure for artificial and mechanical combined obstacle removal of water-rich sand layer
CN112502715A (en) Temporary plugging and reinforcing method for end of shield tunnel
CN207033463U (en) Mine shield handing-over tunnel folded type joint design in the middle part of marine site
RU2739880C1 (en) Method of inclined tunnels construction in weak water-saturated soils
CN116398165A (en) New tunnel penetrating through existing station at zero distance and construction method thereof
CN108643926B (en) Freezing water stop construction method for pilot tunnel of section tunnel
CN107269283B (en) A kind of big cross section tunneling subway station and running tunnel penetrate through construction method
CN112302669B (en) Subway shield arrival auxiliary construction method and structure under complex environment condition

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20210316