CN112460328A - Construction method of pipe-jacking tunneling machine - Google Patents

Construction method of pipe-jacking tunneling machine Download PDF

Info

Publication number
CN112460328A
CN112460328A CN202010972996.8A CN202010972996A CN112460328A CN 112460328 A CN112460328 A CN 112460328A CN 202010972996 A CN202010972996 A CN 202010972996A CN 112460328 A CN112460328 A CN 112460328A
Authority
CN
China
Prior art keywords
jacking
pipe
pipeline
well
tunneling machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202010972996.8A
Other languages
Chinese (zh)
Inventor
陈刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Glory Machinery Manufacturing Co ltd
Original Assignee
Jiangsu Glory Machinery Manufacturing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Glory Machinery Manufacturing Co ltd filed Critical Jiangsu Glory Machinery Manufacturing Co ltd
Priority to CN202010972996.8A priority Critical patent/CN112460328A/en
Publication of CN112460328A publication Critical patent/CN112460328A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • F16L1/036Laying or reclaiming pipes on land, e.g. above the ground in the ground the pipes being composed of sections of short length
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a construction method of a pipe-jacking tunneling machine in the field of pipe-jacking machines, and particularly relates to a construction method of a pipe-jacking tunneling machine. The construction method of the pipe-jacking tunneling machine comprises the steps of firstly, excavating a vertical well, excavating an initial well and a receiving well by adopting an open excavation method, and placing a pipe-jacking machine head and a cutter head into the initial well; step two, erecting a working platform around the starting well, and erecting a hoisting frame and a winch on the working platform; step three, placing a cutter head of the pipe-jacking tunneling machine into the receiving well, arranging an oil cylinder at one end of the cutter head, and calculating the thrust of the oil cylinder; step four, selecting a sliding heavy rail, jacking the first section of concrete pipeline, then placing the next section of concrete pipeline on the heavy rail, repeatedly excavating the tunnel and jacking the pipeline, and jacking all the concrete pipelines into the receiving well; and step five, recovering the cutter head and the pipeline. The invention has good universality and is suitable for different cutter heads and construction places.

Description

Construction method of pipe-jacking tunneling machine
Technical Field
The invention relates to the technical field of pipe-jacking machines, in particular to a construction method of a pipe-jacking tunneling machine.
Background
The pipe jacking technology gradually becomes a construction technology means mastered and applied by more small and medium-sized construction units, and is not a proprietary technology of some large-scale construction enterprises. The pipe-jacking construction method is gradually applied to middle and western cities from a developed coastal region, and the geological conditions of pipe-jacking construction can be applied to complicated and variable soft and hard stratums along with the continuous development of the technology. The pipe jacking construction provides an effective and convenient construction way for jacking underground box culverts under highway and railway roadbeds, and simultaneously provides a scientific and effective method for large-scale underground pipe network construction projects such as underground pipeline laying and on-line modification projects of underground pipelines.
The pipe jacking method is used for enabling the pipeline to conveniently pass through railways, highways, water ways and other obstacles, and the purpose of pipe jacking construction technology is the earliest to be applied by people. The underground crossing engineering has the advantages that the jacking length is generally small, the jacking length is dozens of meters less, the jacking length is hundreds of meters more, a working well and a receiving well in the construction process are single, trenching operation can be performed even without arranging the working well and the receiving well when the embankment section is jacked, the construction is very convenient, the construction speed is high, the construction period is short, however, the cutter head is required to have certain jacking force to realize the propulsion of the cutter head in the long-length construction process, and the inventor provides further improvement on the construction.
Disclosure of Invention
The invention aims to provide a construction method of a pipe-jacking tunneling machine, which has good universality and is adaptive to different cutterheads and construction places.
In order to achieve the purpose, the construction method of the pipe-jacking tunneling machine adopts the following technical scheme:
a construction method of a pipe-jacking tunneling machine comprises the following steps:
step one, vertical shaft excavation, namely excavating an initial well and a receiving well by adopting an open excavation method, and placing a pipe jacking machine head and a cutter head into the initial well;
step two, erecting a working platform around the starting well, and erecting a hoisting frame and a winch on the working platform;
step three, placing a cutter head of the pipe-jacking tunneling machine into the receiving well, arranging an oil cylinder at one end of the cutter head, calculating the axial allowable jacking force of the pipeline,
Figure BDA0002684780230000021
in the formula Fr-allowable pipeline stress (kN);
σc-pipe body compressive strength (kPa);
a-area of pressing by jacking force (m)2);
S-safety factor;
the dimensions between the receiving well and the originating well are calculated,
L=l1+l2+l3+S1+S2+S3
l in the formula is the length of the bottom of the working pit;
l1-length of pipe section;
l2-jack length;
l3-the back thickness;
S1-the distance the jacking pipe section is pre-set on the guide rail;
S2-unearthing in the pipe, leaving a length at the tail of the pipe;
S3the additional length during the U-turn jacking is generally larger than 0.5m, and the one-way jacking is 0;
calculating the stress of the back rest after the operation,
Figure BDA0002684780230000022
in the formula: r is the counter force of the total thrust;
alpha-coefficient (taking 1.5-2.5);
b-the width of the rear seat wall (m);
gamma-volume weight of soil (kN/m)3);
H-height of rear seat wall (m),;
KP-passive earth pressure system
Figure BDA0002684780230000031
Figure BDA0002684780230000032
Taking 8;
c-soil cohesion (kPa);
h is the height from the ground to the soil mass at the top of the back wall;
calculate the combination of the thrust of the cylinder being greater than the allowable jacking force and the stress on the back
Step four, selecting a sliding heavy rail, jacking the first section of concrete pipeline, then placing the next section of concrete pipeline on the heavy rail, repeatedly excavating the tunnel and jacking the pipeline, and jacking all the concrete pipelines into the receiving well;
and step five, recovering the cutter head and the pipeline.
The construction method of the pipe-jacking tunneling machine is further improved in the fourth step, the jacking direction of the concrete pipeline is measured in time during jacking, and each jacking time of the first section of the concrete pipeline is 20-50 cm/time; when the jack is normally pushed, pushing for 1 m/time; and if the measured rear direction deviation is more than 10mm, performing pipe jacking deviation rectifying correction.
The construction method of the pipe-jacking tunneling machine is further improved in that the construction method further comprises an air supply device which is arranged in the working well and supplies air to the designed pipeline, and the air volume of the air supply device is not less than 25 liters per second.
Compared with the prior art, the invention has the beneficial effects that: good universality, and is adaptive to different cutter heads and construction places
Detailed Description
The present invention is further illustrated by the following detailed description, which is to be construed as merely illustrative and not limitative of the remainder of the disclosure, and modifications and variations such as those ordinarily skilled in the art can be made without departing from the scope of the present invention are intended to be limited only by the appended claims.
In the description of the present invention, it should also be noted that, unless otherwise explicitly specified or limited, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly and may, for example, be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. Specific meanings of the above terms in the present invention can be specifically understood by those of ordinary skill in the art.
A construction method of a pipe-jacking tunneling machine comprises the following steps:
step one, vertical shaft excavation, namely excavating an initial well and a receiving well by adopting an open excavation method, and placing a pipe jacking machine head and a cutter head into the initial well;
step two, erecting a working platform around the starting well, and erecting a hoisting frame and a winch on the working platform;
step three, placing a cutter head of the pipe-jacking tunneling machine into the receiving well, arranging an oil cylinder at one end of the cutter head, calculating the axial allowable jacking force of the pipeline,
Figure BDA0002684780230000041
in the formula Fr-allowable pipeline stress (kN);
σc-pipe body compressive strength (kPa);
a-area of pressing by jacking force (m)2);
S-safety factor;
the dimensions between the receiving well and the originating well are calculated,
L=1l+2l+3l+S1+S2+S3
l in the formula is the length of the bottom of the working pit;
l1-length of pipe section;
l2-jack length;
l3-the back thickness;
S1-the distance the jacking pipe section is pre-set on the guide rail;
S2-unearthing in the pipe, leaving a length at the tail of the pipe;
S3the additional length during the U-turn jacking is generally larger than 0.5m, and the one-way jacking is 0;
calculating the stress of the back rest after the operation,
Figure BDA0002684780230000051
in the formula: r is the counter force of the total thrust;
alpha-coefficient (taking 1.5-2.5);
b-the width of the rear seat wall (m);
gamma-volume weight of soil (kN/m)3);
H-height of rear seat wall (m),;
KP-passive earth pressure system
Figure BDA0002684780230000052
Figure BDA0002684780230000053
Taking 8;
c-soil cohesion (kPa);
h is the height from the ground to the soil mass at the top of the back wall;
calculate the combination of the thrust of the cylinder being greater than the allowable jacking force and the stress on the back
Step four, selecting a sliding heavy rail, jacking the first section of concrete pipeline, then placing the next section of concrete pipeline on the heavy rail, repeatedly excavating the tunnel and jacking the pipeline, and jacking all the concrete pipelines into the receiving well;
and step five, recovering the cutter head and the pipeline.
The construction method of the pipe-jacking tunneling machine is further improved in the fourth step, the jacking direction of the concrete pipeline is measured in time during jacking, and each jacking time of the first section of the concrete pipeline is 20-50 cm/time; when the jack is normally pushed, pushing for 1 m/time; and if the measured rear direction deviation is more than 10mm, performing pipe jacking deviation rectifying correction.
The construction method of the pipe-jacking tunneling machine is further improved in that the construction method further comprises an air supply device which is arranged in the working well and supplies air to the designed pipeline, and the air volume of the air supply device is not less than 25 liters per second.

Claims (3)

1. A construction method of a pipe-jacking tunneling machine is characterized by comprising the following steps:
step one, vertical shaft excavation, namely excavating an initial well and a receiving well by adopting an open excavation method, and placing a pipe jacking machine head and a cutter head into the initial well;
step two, erecting a working platform around the starting well, and erecting a hoisting frame and a winch on the working platform;
step three, placing a cutter head of the pipe-jacking tunneling machine into the receiving well, arranging an oil cylinder at one end of the cutter head, calculating the axial allowable jacking force of the pipeline,
Figure FDA0002684780220000011
in the formula Fr-allowable pipeline stress (kN);
σc-pipe body compressive strength (kPa);
a-area of pressing by jacking force (m)2);
S-safety factor;
the dimensions between the receiving well and the originating well are calculated,
L=1l+2l+3l+S1+S2+S3
l in the formula is the length of the bottom of the working pit;
l1-length of pipe section; l2-jack length;
l3-the back thickness;
S1-the distance the jacking pipe section is pre-set on the guide rail;
S2-unearthing in the pipe, leaving a length at the tail of the pipe;
S3-additional length when turning around and jacking;
calculating the stress of the back rest after the operation,
Figure FDA0002684780220000013
in the formula: r is the counter force of the total thrust;
alpha-coefficient (taking 1.5-2.5);
b-the width of the rear seat wall (m);
gamma-volume weight of soil (kN/m)3);
H-height of rear seat wall (m),;
KP-passive earth pressure system
Figure FDA0002684780220000021
Figure FDA0002684780220000022
Taking 8;
c-soil cohesion (kPa);
h is the height from the ground to the soil mass at the top of the back wall;
calculate the combination of the thrust of the cylinder being greater than the allowable jacking force and the stress on the back
Step four, selecting a sliding heavy rail, jacking the first section of concrete pipeline, then placing the next section of concrete pipeline on the heavy rail, repeatedly excavating the tunnel and jacking the pipeline, and jacking all the concrete pipelines into the receiving well;
and step five, recovering the cutter head and the pipeline.
2. The pipe-jacking tunneling machine construction method according to claim 1, characterized in that: in the fourth step, the jacking direction of the concrete pipeline is measured in time when the concrete pipeline is jacked, and each jacking time is 20-50 cm/time when the first section of the concrete pipeline is jacked; when the jack is normally pushed, pushing for 1 m/time; and if the measured rear direction deviation is more than 10mm, performing pipe jacking deviation rectifying correction.
3. The pipe-jacking tunneling machine construction method according to claim 1, characterized in that: the air supply device is arranged in the working well and used for supplying air to the designed pipeline, and the air quantity of the air supply device is not less than 25 liters per second.
CN202010972996.8A 2020-09-16 2020-09-16 Construction method of pipe-jacking tunneling machine Withdrawn CN112460328A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010972996.8A CN112460328A (en) 2020-09-16 2020-09-16 Construction method of pipe-jacking tunneling machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010972996.8A CN112460328A (en) 2020-09-16 2020-09-16 Construction method of pipe-jacking tunneling machine

Publications (1)

Publication Number Publication Date
CN112460328A true CN112460328A (en) 2021-03-09

Family

ID=74833352

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010972996.8A Withdrawn CN112460328A (en) 2020-09-16 2020-09-16 Construction method of pipe-jacking tunneling machine

Country Status (1)

Country Link
CN (1) CN112460328A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113283106A (en) * 2021-06-10 2021-08-20 中铁九局集团有限公司 Method for predicting influence of pipe-jacking tunneling machine construction on safety of overlying pipeline
CN114508629A (en) * 2022-01-24 2022-05-17 中铁四局集团有限公司 Pipe jacking construction method for penetrating through mixed egg gravel layer and sandstone layer

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113283106A (en) * 2021-06-10 2021-08-20 中铁九局集团有限公司 Method for predicting influence of pipe-jacking tunneling machine construction on safety of overlying pipeline
CN113283106B (en) * 2021-06-10 2024-02-13 中铁九局集团有限公司 Method for predicting influence of pipe jacking tunneling machine construction on safety of overlying pipeline
CN114508629A (en) * 2022-01-24 2022-05-17 中铁四局集团有限公司 Pipe jacking construction method for penetrating through mixed egg gravel layer and sandstone layer

Similar Documents

Publication Publication Date Title
CN101963061B (en) Construction method for underground box culvert of existing railway line
CN106641440B (en) A kind of transverse crossing railway line underground piping jacking construction method
CN107060796B (en) It is a kind of to use Slurry Balanced Pipe Jacking Construction technique
CN111075474B (en) Rectangular pipe jacking construction method for subway station access and exit channel
CN100580220C (en) Shield construction method for three-line parallel under-passing trunk railway tunnel
CN100501124C (en) Construction method for tunnel contact passage in shield section of underground railway
CN100497841C (en) Supporting leg type underground continuous wall construction method
CN109594990B (en) Large-section jacking pipe construction method for complex stratum
CN106950070A (en) Experimental rig for rectangular top pipe jacking construction Whole Process Simulation
CN112460328A (en) Construction method of pipe-jacking tunneling machine
CN104120731A (en) Tunnel settlement protecting device and construction method thereof
CN104452754A (en) Prestress concrete pipe pile construction method
CN106979021A (en) Large-section loess tunnel is excavated and preliminary bracing quick closure looping technique
CN108362856B (en) Model experiment device for simulating long-term ground settlement of urban high-density area
CN105804048A (en) Strengthening method for soft foundation drain boards
CN111075457A (en) In-hole repairing method for shield deformation of tail shield of shield tunneling machine under complex geological condition
CN114108664A (en) Landslide treatment method by vertical small-diameter guide hole high-pressure jet grouting
CN113847042A (en) Construction method for side-penetrating high-voltage electric tower of subway shield tunnel
CN111677521B (en) High-pressure gas pipe settlement control method for subway interval tunnel construction
CN204040021U (en) Large diameter pile construction equipment system in city underground engineering tunneling pilot tunnel
CN112538870A (en) Isolation and reinforcement structure and method for water-rich sand layer shield tunnel to pass through viaduct
CN109119943A (en) System of laying optimization method of the cable at push pipe both ends
CN203891047U (en) Equipment equipped with steel platform for foundation construction of land bridge
CN115681613A (en) Pipe jacking construction method for silt silty clay layer construction
CN115217487A (en) Earth pressure balance circular pipe jacking construction method for underpass railway roadbed stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20210309