CN109119943A - System of laying optimization method of the cable at push pipe both ends - Google Patents

System of laying optimization method of the cable at push pipe both ends Download PDF

Info

Publication number
CN109119943A
CN109119943A CN201811053237.0A CN201811053237A CN109119943A CN 109119943 A CN109119943 A CN 109119943A CN 201811053237 A CN201811053237 A CN 201811053237A CN 109119943 A CN109119943 A CN 109119943A
Authority
CN
China
Prior art keywords
pipe
cable
push pipe
laying
cable protection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811053237.0A
Other languages
Chinese (zh)
Inventor
任树清
王凤凯
乐坤
王勃
罗开信
凌天涵
杨宇全
郝泽琪
刘玉珩
孙福锋
任建利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201811053237.0A priority Critical patent/CN109119943A/en
Publication of CN109119943A publication Critical patent/CN109119943A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • H02G1/08Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

A kind of system of laying optimization method the invention discloses cable at push pipe both ends comprising following steps: 1) with pipe jacking construction technique one section push pipe is built;2) weldable, the cable protection pipe with certain flexibility are added inside push pipe, and cable protection pipe is fixed using plain concrete every 5-10 meters inside push pipe;3) two ends of push pipe are blocked with concrete;4) cable protection pipe that laying has armored concrete protection is tilted upward in push pipe two sides, laying is located to 1-2 meter from the ground, and construction cable observation well here, and wherein cable is observed well and totally two and split in push pipe two sides oblique upper;5) cabling in the cable protection pipe laid.

Description

System of laying optimization method of the cable at push pipe both ends
Technical field
The present invention relates to power cable pipe jacking construction technique field, system of laying of especially a kind of cable at push pipe both ends Optimization method.
Background technique
With the process of modernization of the country, urban construction step is getting faster, various municipal pipelines underground it is criss-cross, Stacking is gathered, and the civic building on ground is also more and more, and excavation construction becomes road quality when cable laying in power engineering Difference, welding, while carrying out inconvenience to people's lives, work belt, construction cost is higher and higher.Boring more some iron When the important means of transportation such as road, highway, river, do not allow to break off a friendship brokenly road construction, trenchless technology brill can only be taken to get over, generally Push pipe can be used or trombone slide bores the technology of getting over.
1. pipe jacking construction technique: jacking construction is a kind of underground pipeline construction side for growing up after the shield-tunneling construction Method, it does not need to excavate surface layer, and being capable of Zuan Yue highway, railway and various underground utilities etc..Jacking construction is by means of master The thrust for pushing up oil cylinder and pipeline enclosure, relay well etc. passes through tool pipe or development machine out of active well soil layer and shifts reception onto always It is sling in well.At the same time, also just the piping laying after tool pipe or development machine is followed closely between Liang Jing, to realize non-open Dig the construction method of laying underground piping.
Jacking is that support is first arranged in active well and installs main jack, and the pipeline of required laying is immediately work After having pipe, tool pipe is tunneled into soil layer under the action of main jack thrust, and the soil excavated is by soil pump or screw conveyor Discharge is discharged by slush pump through pipeline in the form of mud, and after promoting a length of tubing, main jack is retracted, another in lifting Length of tubing continues jacking.And so on, until pipeline laying finishes.After pipeline has been laid with, tool pipe is hung to ground from received well Face.
2. power cable engineering traditional system of laying in push pipe: push pipe, which bores, to be got in construction, need to be arranged at push pipe both ends Size is arranged by depth in active well, active well, and 5-10 meters of upper pipe working well is 8 × 5 × h, and reception active well is 6 × 5 × h, It can borrow institute's construction working well that cable shaft is set under normal circumstances, then cable, which gets over the common laying scheme of push pipe in cable drill, is Cable shaft is respectively set at push pipe both ends, cable is applied along cable installations such as cable ditch, comb, tunnels again after climbing up from cable shaft If as shown in Fig. 1, in figure 1 ' be cable, 2 ' be push pipe, 3 ' be cable shaft.
3. power cable engineering defect existing for traditional system of laying in push pipe: such scheme can in cable shaft shape At two approximate right angle sections, cable laying difficulty is increased, while the cost of cable shaft is higher, increases construction budget;By It is deeper in push pipe and cable shaft, it is larger to cable laying difficulty of construction, and to late maintenance cost also can relative increase, it is right In the relatively high position in coastal area or level of ground water, easy ponding in vertical shaft also can to later period cable construction and maintenance difficulties It further increases.
Summary of the invention
There is provided that a kind of short construction period, overall cost be low, safety it is an object of the invention to solve above-mentioned technical problem System of laying optimization method of the good cable of performance at push pipe both ends.
In order to solve the above-mentioned technical problem, the present invention adopts the following technical scheme:
A kind of system of laying optimization method of cable at push pipe both ends, comprising the following steps:
1) one section of push pipe is built with pipe jacking construction technique;
2) weldable, the cable protection pipe with certain flexibility are added inside push pipe, and every 5-10 inside push pipe Rice fixes cable protection pipe using plain concrete;
3) two ends of push pipe are blocked with concrete;
4) cable protection pipe that laying has armored concrete protection is tilted upward in push pipe two sides, laid to from the ground At 1-2 meters, and construction cable observes well here, and wherein cable observation well two and is split in push pipe two sides oblique upper totally;
5) cabling in the cable protection pipe laid.
Further, the detailed process of cable protection pipe of the laying with armored concrete protection includes: in step 4) It is tilted upward respectively at push pipe both ends first and excavates out a channel, reinforced concrete foundation is then done in channel, and use plank With the fixed cable protection tube model out of reinforcing bar, it is put into cable protection pipe later, is finally tamped with concrete.
Further, the angle of cable protection pipe and horizontal plane that push pipe two sides tilt upward setting of being laid in is 20-30 Degree.
Further, the cable protection pipe is made of PE material.
The beneficial effects of the present invention are:
1, it avoids creating cable shaft in push pipe mouth, need to only climb in cable protection pipe to one electricity of increase at liftoff two meters Cable observes well, reduces project cost.
2, it is avoided in cable laying instead of cable shaft with cable observation well and quarter bend occurs, meeting cable While the requirement of turning radius, tractive force of the cable in laying is reduced, the difficulty of cable laying is reduced.
It is 3, this to be convenient for later operation and maintenance with the method that push pipe part is connected with direct-burried section cable in a manner of climbing, Reduce failure odds.
4, this kind of method short construction period, overall cost is low, has a safety feature.
Detailed description of the invention
Fig. 1 is to optimize preceding cable in traditional system of laying schematic diagram at push pipe both ends;
Fig. 2 is using cable after method optimization of the invention in the system of laying schematic diagram at push pipe both ends;
Fig. 3 is the cross-section diagram in the present invention inside push pipe.
Specific embodiment
The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments:
System of laying schematic diagram Fig. 2 shows cable after optimization at push pipe both ends;1 is cable in figure, and 2 be push pipe, and 3 are Cable observes well, and 4 be cable protection pipe.
Fig. 3 shows the cross-section diagram in the present invention inside push pipe;2 be push pipe in figure, and 4 be cable protection pipe, wherein basis The requirement of the quantity and size of cable, cable protection pipe are equipped with different-diameter there are many more and designs.
The present invention adds the weldables such as PE, with certain flexibility on the basis of original pipe-jacking project inside push pipe 2 Cable protection pipe 4 is fixed cable protection pipe 4 using plain concrete, inside push pipe 2 every 5-10 meters inside push pipe 2 Cross-section diagram is as shown in Figure 3.
After the completion of cable protection pipe 4 is constructed, 2 end of push pipe is blocked using concrete, then utilizes the soft of its tubing Toughness is laid to two upper sides, wait lay at away from ground 1-2 meters be connected to newly set cable observation well 3 terminate, cable 1 cable guarantor It is laid in pillar 4, as shown in Figure 2.
Cable of the invention push pipe both ends system of laying optimization method, specifically includes the following steps:
1) one section of push pipe 2 is built with pipe jacking construction technique;
2) on the basis of original pipe-jacking project, weldable, the cable protection with certain flexibility are added inside push pipe 2 Pipe 4, and cable protection pipe 4 is fixed using plain concrete every 5-10 meters inside push pipe 2;Wherein cable protection pipe 4 More are laid with, and multi-cable protection pipe 4 constitutes cable duct bank;
3) two ends of push pipe 2 are blocked with concrete;
4) cable protection pipe that laying has armored concrete protection is tilted upward in 2 two sides of push pipe, laid to liftoff At face 1-2 meters, and construction cable observes well 3 here, and wherein cable observation well 3 two and is split on 2 liang of skew backs of push pipe totally Side;It includes: to incline respectively at 2 both ends of push pipe first that wherein laying, which has the detailed process of the cable protection pipe of armored concrete protection, A channel is excavated out obliquely, reinforced concrete foundation is then done in channel, and fix out cable protection with plank and reinforcing bar Tube model is put into multi-cable protection pipe (cable duct bank) later, is finally tamped with concrete.
5) cabling 1 in the multi-cable protection pipe (cable duct bank) laid.
Further, 2 two sides of push pipe that are laid in tilt upward the cable protection pipe 4 of setting and the angle of horizontal plane is 20- 30 degree.
Further, the cable protection pipe 4 is made of PE material.
Previous jacking pipe construction process is optimized in the present invention, and the cable with certain flexibility is added inside push pipe Protection pipe, cable protection pipe is extended and climbed using its flexibility to away from ground by push pipe both ends is suitble to the height such as cable ditch, comb, tunnel Afterwards, then cable observation well is set, provides construction site for later period cable laying.This kind of method can effectively reduce cable and push up Laying difficulty in the vertical shaft of nozzle, while also can reduce later period operation and maintenance difficulty.
In conclusion the contents of the present invention are not limited in the above embodiments, those skilled in the art can be It is proposed other embodiments within technological guidance's thought of the invention, but these embodiments be included in the scope of the present invention it It is interior.

Claims (4)

1. a kind of cable is in the system of laying optimization method at push pipe both ends, which comprises the following steps:
1) one section of push pipe is built with pipe jacking construction technique;
2) weldable, the cable protection pipe with certain flexibility are added inside push pipe, and right every 5-10 meters inside push pipe Cable protection pipe is fixed using plain concrete;
3) two ends of push pipe are blocked with concrete;
4) cable protection pipe that laying has armored concrete protection, laying to 1-2 from the ground are tilted upward in push pipe two sides Rice place, and construction cable observes well here, wherein cable is observed well and totally two and is split in push pipe two sides oblique upper;
5) cabling in the cable protection pipe laid.
2. cable described in accordance with the claim 1 is in the system of laying optimization method at push pipe both ends, which is characterized in that in step 4) It includes: to tilt upward respectively at push pipe both ends first that middle laying, which has the detailed process of the cable protection pipe of armored concrete protection, A channel is excavated out, reinforced concrete foundation is then done in channel, and fix out cable protection tube model with plank and reinforcing bar, It is put into cable protection pipe later, is finally tamped with concrete.
3. cable described in accordance with the claim 1 is in the system of laying optimization method at push pipe both ends, which is characterized in that be laid in top The angle of cable protection pipe and horizontal plane that pipe two sides tilt upward setting is 20-30 degree.
4. cable described in accordance with the claim 1 is in the system of laying optimization method at push pipe both ends, which is characterized in that the cable Protection pipe is made of PE material.
CN201811053237.0A 2018-09-10 2018-09-10 System of laying optimization method of the cable at push pipe both ends Pending CN109119943A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811053237.0A CN109119943A (en) 2018-09-10 2018-09-10 System of laying optimization method of the cable at push pipe both ends

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811053237.0A CN109119943A (en) 2018-09-10 2018-09-10 System of laying optimization method of the cable at push pipe both ends

Publications (1)

Publication Number Publication Date
CN109119943A true CN109119943A (en) 2019-01-01

Family

ID=64858252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811053237.0A Pending CN109119943A (en) 2018-09-10 2018-09-10 System of laying optimization method of the cable at push pipe both ends

Country Status (1)

Country Link
CN (1) CN109119943A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112972940A (en) * 2021-03-18 2021-06-18 国网安徽省电力有限公司电力科学研究院 Quick filler plugging device of cable pit conflagration
CN113241682A (en) * 2021-06-17 2021-08-10 广东威恒输变电工程有限公司 Cable laying construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006121800A (en) * 2004-10-20 2006-05-11 Aron Kasei Co Ltd Method of laying cable using land-buried pipe, and the land-buried pipe
CN203239355U (en) * 2013-04-26 2013-10-16 苏州二建建筑集团有限公司 Jacking type cable sleeve channel structure
CN103711492A (en) * 2013-04-26 2014-04-09 苏州二建建筑集团有限公司 Pipe-jacking type cable sleeve passage construction method
CN103791159A (en) * 2012-11-02 2014-05-14 成张佳宁 Pipe-jacking construction method for small-diameter pipes
CN205231678U (en) * 2015-12-11 2016-05-11 福州万山电力咨询有限公司 Non - excavation trombone slide of power cable
CN105604555A (en) * 2016-03-11 2016-05-25 广州电力设计院 Pipe-jacking tunnel and construction method of pipe-jacking tunnel
CN106329401A (en) * 2015-06-19 2017-01-11 国网天津市电力公司 Laying method for jacking pipe

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006121800A (en) * 2004-10-20 2006-05-11 Aron Kasei Co Ltd Method of laying cable using land-buried pipe, and the land-buried pipe
CN103791159A (en) * 2012-11-02 2014-05-14 成张佳宁 Pipe-jacking construction method for small-diameter pipes
CN203239355U (en) * 2013-04-26 2013-10-16 苏州二建建筑集团有限公司 Jacking type cable sleeve channel structure
CN103711492A (en) * 2013-04-26 2014-04-09 苏州二建建筑集团有限公司 Pipe-jacking type cable sleeve passage construction method
CN106329401A (en) * 2015-06-19 2017-01-11 国网天津市电力公司 Laying method for jacking pipe
CN205231678U (en) * 2015-12-11 2016-05-11 福州万山电力咨询有限公司 Non - excavation trombone slide of power cable
CN105604555A (en) * 2016-03-11 2016-05-25 广州电力设计院 Pipe-jacking tunnel and construction method of pipe-jacking tunnel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112972940A (en) * 2021-03-18 2021-06-18 国网安徽省电力有限公司电力科学研究院 Quick filler plugging device of cable pit conflagration
CN113241682A (en) * 2021-06-17 2021-08-10 广东威恒输变电工程有限公司 Cable laying construction method

Similar Documents

Publication Publication Date Title
CN106369223B (en) A kind of silt stratum pipe jacking construction method
Chen et al. Long rectangular box jacking project: a case study
CN106641440B (en) A kind of transverse crossing railway line underground piping jacking construction method
CN106402490B (en) Silt stratum push pipe jacking construction method based on steel bushing head tool pipe
CN102606167B (en) Settlement control construction method for transverse grouting guide pipe of shallow underground excavation tunnel
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN103874803A (en) Method for building structures, particularly passages under operating railways or the like.
CN101343868B (en) Underground continuous wall construction method of city-across pipeline
CN103711492B (en) A kind of jacking-type cable sleeve channel construction method
CN112502734B (en) Construction method for water-rich sand layer shield zone connecting channel
CN104612696B (en) Overpass column hole method construction method is passed through in big cross section tunneling subway station in fine sand layer
CN102635119A (en) Supporting method for construction of swirl well
CN105822311A (en) In-situ extension construction structure and method for extra-large-section tunnel with opening formed inside to enlarge working face
CN206175812U (en) Powder sandy soil stratum push pipe construction structures based on steel bushing head instrument pipe
CN111379573B (en) Connecting system for connecting shield tunnel in middle of oil and gas pipeline
CN109119943A (en) System of laying optimization method of the cable at push pipe both ends
CN112502732B (en) Construction method of shield tunnel in water-rich sand layer
CN208058113U (en) A kind of amendment construction system of construction push pipe
Qiu et al. First application of mechanized method using earth pressure balance TBM with large horseshoe-shaped cross section to loess mountain tunnel: A case study of Baicheng tunnel
CN110761795B (en) Construction method of shallow tunnel in loess gully
CN101141054A (en) Compaction grouting method for preventing land subsidence after non-digging horizontal drilling
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN115653499A (en) Non-excavation horizontal directional drilling construction method for drainage pipeline at bottom of tunnel inverted arch
CN215256188U (en) Overlapping shield tunnel foundation treatment structure for next-to-old house
CN112502717B (en) Construction method for excavating connecting channels between shield sections of water-rich sand layer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190101