CN112417564B - Segment beam prefabrication construction monitoring method based on three-dimensional laser scanning and BIM technology - Google Patents

Segment beam prefabrication construction monitoring method based on three-dimensional laser scanning and BIM technology Download PDF

Info

Publication number
CN112417564B
CN112417564B CN202011319373.7A CN202011319373A CN112417564B CN 112417564 B CN112417564 B CN 112417564B CN 202011319373 A CN202011319373 A CN 202011319373A CN 112417564 B CN112417564 B CN 112417564B
Authority
CN
China
Prior art keywords
construction
bim
segment
segmental
dimensional laser
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011319373.7A
Other languages
Chinese (zh)
Other versions
CN112417564A (en
Inventor
薛东焱
陆培
莫鲁晟
肖峥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu University of Science and Technology
Original Assignee
Jiangsu University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu University of Science and Technology filed Critical Jiangsu University of Science and Technology
Priority to CN202011319373.7A priority Critical patent/CN112417564B/en
Publication of CN112417564A publication Critical patent/CN112417564A/en
Application granted granted Critical
Publication of CN112417564B publication Critical patent/CN112417564B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T2200/00Indexing scheme for image data processing or generation, in general
    • G06T2200/08Indexing scheme for image data processing or generation, in general involving all processing steps from image acquisition to 3D model generation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T2210/00Indexing scheme for image generation or computer graphics
    • G06T2210/04Architectural design, interior design

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Architecture (AREA)
  • General Engineering & Computer Science (AREA)
  • Evolutionary Computation (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Computer Graphics (AREA)
  • Software Systems (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Length Measuring Devices By Optical Means (AREA)

Abstract

The invention discloses a segment beam prefabrication construction monitoring method based on three-dimensional laser scanning and BIM technology, which comprises the following specific steps: and establishing a point cloud data model through three-dimensional laser scanning, establishing a Building Information (BIM) model, comparing the point cloud data model with the BIM model, verifying construction precision, and adjusting the manufacturing size of the next adjacent section beam according to the construction precision. The invention applies the three-dimensional laser scanning and BIM drawing technology to the construction monitoring of the segmental beam by a short line method, and performs fine detection and monitoring on the segmental beam construction. The monitoring method can realize the detection of the precision of the construction dimensions of all details of the external structure, the internal structure, the steering block, the anchoring block, the shear key tooth block and the diaphragm plate of the segmental beam, and adjust the manufacturing dimension of the next adjacent segmental beam according to the detection result, so that the accumulation of construction errors is avoided, and the precision of the prefabrication processing of the segmental beam is ensured.

Description

Segment beam prefabrication construction monitoring method based on three-dimensional laser scanning and BIM technology
Technical Field
The invention belongs to the technical field of bridge engineering, and particularly relates to a monitoring method for segmental beam stub method prefabrication construction.
Background
For the prefabricated bridge, the precision control of the prefabricated construction of the segmental beams is an important point and a difficult problem of construction quality, and the construction precision of each segmental beam is an important guarantee for guaranteeing the integral assembly precision of the main beam.
The traditional method for controlling the prefabrication construction precision of the segmental beam by using the short line method mainly uses measuring equipment such as a total station, a level gauge, a steel tape and the like to measure and control individual control points of the prefabrication segmental beam. The monitoring method can only roughly monitor the top surface, the end surface and the height of the section beam, and cannot quickly and accurately measure and control each structure and each detail size of the section beam, which is incomplete and imperfect for controlling the precision of the section beam.
Therefore, it is necessary to develop a method capable of performing fine construction monitoring on the segment beam, rapidly, comprehensively and accurately detecting the prefabrication construction precision of the segment beam by a stub method, and providing a precision control scheme according to the detection result.
Disclosure of Invention
The invention aims to avoid the defects of the existing construction monitoring technology and provides a segment beam prefabrication construction monitoring method based on three-dimensional laser scanning and BIM technology.
The invention establishes the segment beam prefabrication construction monitoring method by using the three-dimensional laser scanning and BIM technology, detects and monitors the segment beam prefabrication construction, can greatly improve the density, efficiency and precision of detection, and ensures that the construction monitoring measures are more comprehensive and accurate.
In order to achieve the above purpose, the technical scheme adopted by the invention is as follows:
A segment beam prefabrication construction monitoring method based on three-dimensional laser scanning and BIM technology comprises the following steps:
a. scanning the prefabricated first segment beam by using a three-dimensional laser scanner and automatically photographing to obtain first segment Liang Dianyun data, and establishing a first segment Liang Dianyun data model;
b. Building a Building Information (BIM) model of the first segmental beam;
c. Comparing the point cloud data model of the first segmental beam with the BIM model of the first segmental beam, and verifying construction accuracy;
d. taking a first segment beam as a matched beam section to serve as an end template, prefabricating a next adjacent segment beam, and directly prefabricating the next adjacent segment beam if the construction deviation of the segment beam meets the requirement; if the construction deviation of the section beam is larger, the manufacturing size of the next adjacent section beam is adjusted and then prefabricated so that the bridge line shape meets the design requirement;
e. building a BIM model of the adjacent section beam according to the adjusted size of the adjacent section beam;
f. And (3) detecting construction precision of the prefabricated adjacent sections, and repeating the steps until all the section beams are manufactured, wherein the next adjacent section beam is prefabricated.
Further preferably, in the step a, the point cloud data includes point cloud data of all construction details of an external structure, an internal structure, a steering block, an anchoring block, a shear key tooth block and a diaphragm of the segmental beam; the photographing is automatically completed for the three-dimensional laser scanner, and aims to render a scanning result and realize live-action restoration; the point cloud data model is formed by post-processing means of noise reduction, registration, splicing and rendering of the point cloud data.
Further preferably, in step b, the modeling method for Building Information (BIM) models of the first segment beams is to use Revit software to build parameterized families of all members of the first segment beams, and then build the BIM models of the first segment beams through the family of members.
Further preferably, in step c, the comparison of the two models is realized by feature point matching; the construction precision comprises the precision of the geometric dimensions of the external structure and the internal structure of the segmental beam, and the precision of the structural dimensions of all details of the segmental beam steering block, the anchoring block, the shear key tooth block and the diaphragm plate.
Further preferably, in the step d, the adjustment of the manufacturing dimension includes the external structural dimension and the internal structural dimension of the segmental beam, and the dimensions of all constructional details of the steering block, the anchoring block, the shear key tooth block and the diaphragm; the linear design requirements of the bridge comprise geometric dimensions of the top surface along the bridge direction and the transverse bridge direction, the levelness of the top surface, the verticality of the end surface and the height of the beam.
Further preferably, in step e, the specific content and method of building the BIM model of the adjacent section beam need to be adjusted correspondingly according to the actual measurement result of the previous section beam and the adjustment of the section beam size; the adjustment is realized by changing the parameters of the component family.
Compared with the prior art, the invention has the following advantages and beneficial effects:
1. The invention provides a method for detecting the geometric dimension of a segment beam, which uses a three-dimensional laser scanner to scan a prefabricated segment beam, and can realize the rapid, comprehensive and accurate omnibearing detection of the geometric dimension of the external structure and the internal structure of the highway segment of the segment beam, and all constructional details of a steering block, an anchoring block, a shear key tooth block and a diaphragm plate.
2. The invention provides a method for monitoring the prefabrication precision of a segment beam by using a three-dimensional laser scanning and BIM technology, which is used for comparing a point cloud data model scanned by a three-dimensional laser scanner with a segment beam BIM model, so that the construction precision of each detail can be clearly known, and further, whether the next adjacent segment beam needs to be adjusted and the size and the method of the adjustment can be determined, thereby realizing the monitoring of the prefabrication construction precision of the segment beam by a stub method.
3. The invention provides a method for adjusting the prefabrication size of a segment beam by using a three-dimensional laser scanning and BIM technology, which adjusts the positions and the geometric dimensions of all constructional details of the external structure, the internal structure, a steering block, an anchoring block, a shear key tooth block and a diaphragm plate of the next adjacent segment beam according to the comparison result of a point cloud data model and a segment beam BIM model, and realizes the omnibearing monitoring of the prefabrication of the segment beam.
Drawings
Fig. 1 is a schematic view of the present invention for monitoring the construction of a segmented beam.
In the figure, 1 is a segmented beam; 2 adjacent segment beams; 3 is the joint surface of two adjacent sections of beams; 4. 5, 6 and 7 are control points; 8. is a segment Liang Duanmian; 9 is the top surface of the segmental beam.
Detailed Description
The present application is further illustrated in the accompanying drawings and detailed description which are to be understood as being merely illustrative of the application and not limiting of its scope, and various modifications of the application, which are equivalent to those skilled in the art upon reading the application, will fall within the scope of the application as defined in the appended claims.
Examples:
As shown in the attached figure 1, the invention discloses a segment beam prefabrication construction monitoring method based on three-dimensional laser scanning and BIM technology, which comprises the following steps:
a. and scanning the prefabricated segment beam 1by using a three-dimensional laser scanner and automatically photographing to obtain the point cloud data of all construction details of the external structure and the internal structure of the segment beam 1, and the steering block, the anchoring block, the shear key tooth block and the diaphragm plate. Post-processing point cloud data by using point cloud data software, deleting noise points, registering and splicing scanning results of different measuring stations, importing a shot photo into the point cloud data for rendering to form a live-action graph, and establishing a segment beam 1 point cloud data model;
b. Establishing parameterization families of all members of the segmental beam 1, such as an external structure, an internal structure, a steering block, an anchoring block, a shear key tooth block and a diaphragm by using Revit software, and establishing a segmental beam 1 Building Information (BIM) model by setting the sizes of the member families according to a design drawing;
c. And selecting control points 4,5, 6 and 7 on the segmental beam 1 as characteristic points, matching and comparing the point cloud data model of the segmental beam 1 with the BIM model, and verifying the precision of all the detail structural dimensions of the external structure, the internal structure, the steering block, the anchoring block, the shear key tooth block and the diaphragm of the segmental beam 1.
D. The next adjacent segment beam 2 is prefabricated with the segment beam 1 as a matching beam segment serving as an end form. If the construction deviation of the section beam 1 meets the requirement, directly prefabricating the next adjacent section beam 2; if the construction deviation of the section beam 1 is larger, the positions and the geometric dimensions of all construction details of the external structure, the internal structure, the steering block, the anchoring block, the shear key tooth block and the diaphragm of the next adjacent section beam 2 are adjusted and prefabricated, so that the bridge line shape accords with the design requirements of the geometric dimensions of the top surface 9 of the section beam along the bridge direction and the transverse bridge direction, the levelness of the top surface 9 of the section beam, the verticality of the end surface 8, the height of the section beam and the joint surface 3 of the adjacent two section beams;
e. according to the position and the geometric dimension of the external structure, the internal structure, the steering block, the anchoring block, the shear key tooth block and the diaphragm plate of the next adjacent section beam 2 after all the detailed structures are adjusted, a BIM model of the next adjacent section beam 2 is established by changing the parameters of the component family;
f. Prefabricating the next adjacent section beam 2, comparing the prefabricated next adjacent section beam 2 with a BIM model of the next adjacent section beam 2, detecting construction precision, and repeating the steps until all section beams are manufactured.
While the invention has been described with reference to preferred embodiments, it is not intended to be limiting. Those skilled in the art will appreciate that various modifications and adaptations can be made without departing from the spirit and scope of the present invention. Accordingly, the scope of the invention is defined by the appended claims.

Claims (6)

1. A segment beam prefabrication construction monitoring method based on three-dimensional laser scanning and BIM technology is characterized by comprising the following steps:
a. scanning the prefabricated first segment beam by using a three-dimensional laser scanner and automatically photographing to obtain first segment Liang Dianyun data, and establishing a first segment Liang Dianyun data model;
b. Building a Building Information (BIM) model of the first segmental beam;
c. Comparing the point cloud data model of the first segmental beam with the BIM model of the first segmental beam, and verifying construction accuracy;
d. taking a first segment beam as a matched beam section to serve as an end template, prefabricating a next adjacent segment beam, and directly prefabricating the next adjacent segment beam if the construction deviation of the segment beam meets the requirement; if the construction deviation of the section beam is larger, the manufacturing size of the next adjacent section beam is adjusted and then prefabricated so that the bridge line shape meets the design requirement;
e. building a BIM model of the adjacent section beam according to the adjusted size of the adjacent section beam;
f. And (3) detecting construction precision of the prefabricated adjacent sections, and repeating the steps until all the section beams are manufactured, wherein the next adjacent section beam is prefabricated.
2. The method for monitoring the prefabricated construction of the segmental beam based on the three-dimensional laser scanning and BIM technology, which is disclosed by claim 1, is characterized in that: in the step a, the point cloud data comprises the point cloud data of all construction details of an external structure, an internal structure, a steering block, an anchoring block, a shear key tooth block and a diaphragm plate of the segmental beam; the photographing is automatically completed for the three-dimensional laser scanner, and aims to render a scanning result and realize live-action restoration; the point cloud data model is formed by post-processing means of noise reduction, registration, splicing and rendering of the point cloud data.
3. The method for monitoring the prefabricated construction of the segmental beam based on the three-dimensional laser scanning and BIM technology, which is disclosed by claim 1, is characterized in that: in the step b, the modeling method for Building Information (BIM) model of the first segment beam is to build parameterized families of all members of the first segment beam by adopting Revit software, and build the BIM model of the first segment beam through the member families.
4. The method for monitoring the prefabricated construction of the segmental beam based on the three-dimensional laser scanning and BIM technology, which is disclosed by claim 1, is characterized in that: in the step c, the comparison of the two models is realized through characteristic point matching; the construction precision comprises the precision of the geometric dimensions of the external structure and the internal structure of the segmental beam, and the precision of the structural dimensions of all details of the segmental beam steering block, the anchoring block, the shear key tooth block and the diaphragm plate.
5. The method for monitoring the prefabricated construction of the segmental beam based on the three-dimensional laser scanning and BIM technology, which is disclosed by claim 1, is characterized in that: in the step d, the adjustment of the manufacturing size comprises the external structure size, the internal structure size of the segmental beam and the sizes of all construction details of the steering block, the anchoring block, the shear key tooth block and the diaphragm; the linear design requirements of the bridge comprise geometric dimensions of the top surface along the bridge direction and the transverse bridge direction, the levelness of the top surface, the verticality of the end surface and the height of the beam.
6. The method for monitoring the prefabricated construction of the segmental beam based on the three-dimensional laser scanning and BIM technology, which is disclosed by claim 1, is characterized in that: in step e, specific content and method of building BIM model of adjacent section beam need to be adjusted according to actual measurement result of the last section beam and adjustment of section beam size; the adjustment is realized by changing the parameters of the component family.
CN202011319373.7A 2020-11-23 2020-11-23 Segment beam prefabrication construction monitoring method based on three-dimensional laser scanning and BIM technology Active CN112417564B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011319373.7A CN112417564B (en) 2020-11-23 2020-11-23 Segment beam prefabrication construction monitoring method based on three-dimensional laser scanning and BIM technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011319373.7A CN112417564B (en) 2020-11-23 2020-11-23 Segment beam prefabrication construction monitoring method based on three-dimensional laser scanning and BIM technology

Publications (2)

Publication Number Publication Date
CN112417564A CN112417564A (en) 2021-02-26
CN112417564B true CN112417564B (en) 2024-04-23

Family

ID=74777274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011319373.7A Active CN112417564B (en) 2020-11-23 2020-11-23 Segment beam prefabrication construction monitoring method based on three-dimensional laser scanning and BIM technology

Country Status (1)

Country Link
CN (1) CN112417564B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7412864B2 (en) 2021-04-20 2024-01-15 日本高圧コンクリート株式会社 Construction method of concrete structure using precast segments
CN113239429A (en) * 2021-04-26 2021-08-10 河南省交通规划设计研究院股份有限公司 Method for manufacturing precast assembled bridge of concrete segments
CN113628177A (en) * 2021-07-29 2021-11-09 北京好运达智创科技有限公司 Double-layer beam storage detection system for beam body
CN114086467A (en) * 2021-11-24 2022-02-25 中铁四局集团第五工程有限公司 Prefabricated installation construction method for steel-concrete composite beam bridge deck
CN113977750A (en) * 2021-11-26 2022-01-28 中交二航局第四工程有限公司安徽混凝土装配化构件分公司 Process for quickly disassembling and assembling integrated section beam steering block template
CN114549780B (en) * 2022-01-27 2024-04-05 重庆大学 Intelligent detection method for large complex component based on point cloud data
CN114577141A (en) * 2022-01-29 2022-06-03 中国建筑第八工程局有限公司 Method for optimizing surface measurement of curved surface template based on three-dimensional laser scanning technology
CN115618472B (en) * 2022-10-27 2024-05-14 中交一公局第七工程有限公司 Engineering structure digital pre-assembly method, system and application based on BIM model
CN115659470A (en) * 2022-11-01 2023-01-31 中交一公局第七工程有限公司 Assembling method, system and application of prefabricated assembled bridge based on BIM concrete segments

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106436579A (en) * 2016-08-25 2017-02-22 中铁二十三局集团轨道交通工程有限公司 Linear control method and linear control device for sectional beam with specially-shaped cross section through short-line pedestal matching method
CN106886659A (en) * 2017-03-21 2017-06-23 湖南联智监测科技有限公司 The virtual pre-splicing and detection method of steel structure bridge based on 3 D laser scanning and cloud platform
CN110619140A (en) * 2019-07-16 2019-12-27 中铁十八局集团第四工程有限公司 Accurate and rapid adjusting method for prefabricated section beam template
CN111121733A (en) * 2019-12-30 2020-05-08 青岛国信海天中心建设有限公司 Construction quality detection method and system based on BIM and three-dimensional laser scanning
CN111660422A (en) * 2020-06-16 2020-09-15 河南省交通规划设计研究院股份有限公司 BIM-based box girder segment prefabricating method by adopting short line method
US10825243B1 (en) * 2019-08-15 2020-11-03 Autodesk, Inc. Three-dimensional (3D) model creation and incremental model refinement from laser scans

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106436579A (en) * 2016-08-25 2017-02-22 中铁二十三局集团轨道交通工程有限公司 Linear control method and linear control device for sectional beam with specially-shaped cross section through short-line pedestal matching method
CN106886659A (en) * 2017-03-21 2017-06-23 湖南联智监测科技有限公司 The virtual pre-splicing and detection method of steel structure bridge based on 3 D laser scanning and cloud platform
CN110619140A (en) * 2019-07-16 2019-12-27 中铁十八局集团第四工程有限公司 Accurate and rapid adjusting method for prefabricated section beam template
US10825243B1 (en) * 2019-08-15 2020-11-03 Autodesk, Inc. Three-dimensional (3D) model creation and incremental model refinement from laser scans
CN111121733A (en) * 2019-12-30 2020-05-08 青岛国信海天中心建设有限公司 Construction quality detection method and system based on BIM and three-dimensional laser scanning
CN111660422A (en) * 2020-06-16 2020-09-15 河南省交通规划设计研究院股份有限公司 BIM-based box girder segment prefabricating method by adopting short line method

Also Published As

Publication number Publication date
CN112417564A (en) 2021-02-26

Similar Documents

Publication Publication Date Title
CN112417564B (en) Segment beam prefabrication construction monitoring method based on three-dimensional laser scanning and BIM technology
CN111627099B (en) Steel structure non-contact actual measurement real quantity method and system based on three-dimensional scanning technology
CN109025319B (en) Quality detection and disposal method for prefabricated part butt joint interface
CN106370670A (en) 3D laser scanning based building prefabricated part quality detection system and method
CN108824816B (en) High-altitude long-span net frame sliding, positioning, installing and monitoring method
CN112489028B (en) Engineering quality acceptance method integrating information model and laser three-dimensional scanning technology
CN106767524A (en) A kind of hydraulic spoon of blade detection method and device
CN108827255A (en) A kind of steel-based on BIM mixes the cable saddle measurement method of composite structure Sarasota
CN107270814A (en) A kind of prefabricated assembled wind-tunnel high accuracy install control method
CN113239429A (en) Method for manufacturing precast assembled bridge of concrete segments
CN110940299B (en) Method for measuring three-dimensional roughness of concrete surface
CN112962462A (en) Multi-section steel box girder assembling method
CN111660422B (en) BIM-based box girder segment prefabricating method by adopting short line method
CN115130170A (en) Steel truss bridge construction monitoring method and system based on three-dimensional laser scanning and BIM
CN112304233B (en) Deformation detection method for construction process of cantilever steel structural member
CN115841484A (en) Steel structure welding quality detection system based on three-dimensional laser scanning
CN112699436A (en) Building structure reverse engineering analysis method based on three-dimensional laser scanning modeling
Ma et al. Review on automated quality inspection of precast concrete components
CN106441147B (en) A kind of method for building up for essence casting moving turbine blade three dimensional optical measuring benchmark
CN116989675B (en) Prefabricated part appearance detection system and detection method thereof
CN113865570A (en) Steel structure circular stand column verticality measuring method
CN109855611B (en) PC wall body rapid measurement and calibration method based on total station
CN114708218B (en) Road surface flatness detection method and system
CN1847780A (en) Scanning precision verifying method for laser measurement equipment
CN113267170A (en) Three-main-truss steel beam transverse height difference adjusting method based on 3D laser scanning and model calculation data comparison feedback

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant