CN111878115A - Cavity assembly type tunnel inverted arch and construction method - Google Patents

Cavity assembly type tunnel inverted arch and construction method Download PDF

Info

Publication number
CN111878115A
CN111878115A CN202010693229.3A CN202010693229A CN111878115A CN 111878115 A CN111878115 A CN 111878115A CN 202010693229 A CN202010693229 A CN 202010693229A CN 111878115 A CN111878115 A CN 111878115A
Authority
CN
China
Prior art keywords
tunnel
inverted arch
block
precast
blocks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010693229.3A
Other languages
Chinese (zh)
Other versions
CN111878115B (en
Inventor
王保群
陈成勇
董旭
髙昇
葛颜慧
孙超群
樊建房
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qilu Transportation Development Group Co ltd
Shandong Jiaotong University
Original Assignee
Qilu Transportation Development Group Co ltd
Shandong Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qilu Transportation Development Group Co ltd, Shandong Jiaotong University filed Critical Qilu Transportation Development Group Co ltd
Priority to CN202010693229.3A priority Critical patent/CN111878115B/en
Publication of CN111878115A publication Critical patent/CN111878115A/en
Application granted granted Critical
Publication of CN111878115B publication Critical patent/CN111878115B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/083Methods or devices for joining adjacent concrete segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention provides a cavity assembly type tunnel inverted arch and a construction method, relating to the field of tunnel construction and comprising a plurality of inverted arch blocks which are sequentially laid on the bottom surface of a tunnel along the longitudinal direction of the tunnel, wherein the center position of each inverted arch block is provided with a channel which is longitudinally distributed along the tunnel, the channels are symmetrically distributed relative to the vertical symmetrical plane of the tunnel, the bottom of the channel is a plane, the top of the channel is an arch far away from the bottom surface, the channels corresponding to all the inverted arch blocks are sequentially communicated in a butt joint way and are used for accommodating personnel to pass through, and through a prefabricated assembly structure, a channel structure for people to escape is arranged in the prefabricated inverted arch structure, after the inverted arch structure is continuously arranged, a rescue channel is formed in the tunnel construction period, wherein a safety area outside the tunnel is communicated to a construction point, the traditional construction method for arranging a trestle and a cast-in-place inverted arch is replaced, the construction efficiency is improved, and meanwhile, the safety in the tunnel construction process is ensured.

Description

Cavity assembly type tunnel inverted arch and construction method
Technical Field
The disclosure relates to the field of tunnel construction, in particular to a cavity assembly type tunnel inverted arch and a construction method.
Background
The statements in this section merely provide background information related to the present disclosure and may not necessarily constitute prior art.
With the development of urbanization, the construction mode change is mainly related to the construction aspect of traffic infrastructure, and the assembly type building advocated vigorously has the advantages of saving energy resources, reducing construction pollution, improving labor production efficiency, ensuring quality safety and the like, and is widely used in the fields of building construction, bridges, tunnels and the like.
The inventor finds that the traditional construction of the tunnel inverted arch at present comprises the processes of inverted arch excavation, substrate cleaning, reinforcing steel bar binding, template installation, concrete pouring and maintenance and the like, and the defects of multiple construction procedures, great influence caused by climatic conditions, high cost of artificial machinery, difficulty in guaranteeing the construction quality and the like exist, so that the defects of tunnel bottom deformation, slurry pumping, primary support cracking and the like easily occur in the later-stage operation of the tunnel, and the engineering adaptability of the tunnel inverted arch is weaker than that of an assembled prefabricated inverted arch. Secondly, during tunnel excavation and primary support construction, accidents such as cave entrance collapse, vault collapse and tunnel face collapse are often accompanied under unfavorable geological conditions, and constructors are trapped in the tunnel; after an accident occurs, the traditional escape mode is to adopt an ultrahigh molecular escape pipeline and a steel escape pipeline which are preset in advance, the placement positions of the pipelines are only limited to the upper space of an inverted arch, but when the traditional rescue channel is blocked, the consequences of slow rescue speed, increased casualties, serious engineering damage and the like can be caused, and the requirement of quick rescue can not be met; thirdly, by arranging necessary transverse embedded pipelines, the inverted arch cavity can be used as a place for laying facilities for traffic monitoring, operation ventilation, illumination and the like in an operation period.
Disclosure of Invention
The disclosed aim is to provide a cavity assembly type tunnel inverted arch and a construction method aiming at the defects in the prior art, wherein a channel structure for people to escape is arranged in the prefabricated inverted arch structure through a prefabricated assembly structure, and after the inverted arch structure is continuously arranged, a rescue channel communicated to a construction point is formed in a safety region outside a tunnel during tunnel construction; meanwhile, after the tunnel is built, the cavity can be used for laying traffic monitoring, ventilation, illumination and other line facilities, and the construction arrangement in the tunnel clearance is optimized.
The first purpose of this disclosure is to provide a cavity assembled tunnel invert, adopts following technical scheme:
including being used for along the tunnel vertically lay a plurality of arch pieces of facing upward in proper order in the tunnel bottom surface, every central point that faces upward the arch piece puts and is equipped with along the passageway of tunnel longitudinal distribution, and the passageway is for the vertical plane of symmetry symmetric distribution in tunnel, and the passageway bottom is the plane, and the arch of bottom surface is kept away from to the top, and the passageway that all inverted arch pieces correspond docks the intercommunication in proper order for hold personnel and pass through.
Furthermore, each inverted arch block comprises a first prefabricated block, a second prefabricated block and a third prefabricated block which are sequentially arranged along the transverse direction of the tunnel, the channel is arranged on the second prefabricated block, the first prefabricated block and the third prefabricated block are identical in structure and are symmetrically arranged on two sides of the second prefabricated block.
Furthermore, cavities which are longitudinally distributed along the tunnel are formed in the first precast block and the third precast block, the cavities in the first precast block corresponding to the adjacent inverted arch blocks are communicated, and the cavities in the third precast block corresponding to the adjacent inverted arch blocks are communicated.
Furthermore, the cavities are distributed along the centers of the corresponding precast blocks, and the tops of the cavities are of arch structures; the prefabricated section is matched with a waterproof structure.
Furthermore, a groove is arranged on one side end face of the precast block corresponding to the same inverted arch block, the groove is positioned at the joint part of the adjacent precast blocks and the joint part of the precast blocks and the inverted arch cushion layer, and the groove is matched with a connecting piece.
Furthermore, bolt grooves are formed in the top surfaces of the prefabricated blocks, and adjacent prefabricated blocks are connected through the bolt grooves and the connecting pieces in a matched mode;
and joints are reserved at the positions, corresponding to the tunnel secondary linings, of the top surfaces of the precast blocks and used for butting the secondary linings.
Furthermore, all be equipped with the gutter in first prefabricated section and the third prefabricated section, the gutter is through horizontal drainage blind pipe intercommunication tunnel vertical drainage blind pipe, and the slope of gutter is unanimous with the whole slope of tunnel.
A second object of the present disclosure is to provide a method for constructing an inverted arch of a cavity-assembled tunnel, using the inverted arch of the cavity-assembled tunnel as described above, comprising the steps of:
preprocessing an inverted arch block, preprocessing a tunnel, and arranging an inverted arch cushion layer;
hoisting each inverted arch block in sequence, and installing the inverted arch blocks in sequence along the longitudinal extension direction of the tunnel;
aligning channels in the inverted arch blocks, and sequentially connecting adjacent inverted arch blocks;
and (4) constructing a tunnel leveling layer on the top surface of the inverted arch block, and laying other accessory facilities.
Furthermore, each inverted arch block comprises a first prefabricated block, a second prefabricated block and a third prefabricated block which are transversely distributed along the tunnel, and when the inverted arch blocks are hoisted, the second prefabricated block is firstly positioned and hoisted, and then the first prefabricated block and the third prefabricated block are respectively hoisted.
Further, the adjacent prefabricated blocks are connected through connecting pieces.
Compared with the prior art, the utility model has the advantages and positive effects that:
(1) the inverted arch is prefabricated and assembled, components are manufactured in a prefabricated field, the quality strength is reliable, the traditional cast-in-place mode of arranging a trestle on the inverted arch is replaced, the cost of manual machinery in the traditional inverted arch construction is reduced, and the overall construction progress of the tunnel is accelerated;
(2) the assembled inverted arch channel structure adopts a channel structure with flat bottom and arched top, the arched top structure can ensure that the whole structure is well stressed, materials are saved, the assembled inverted arch channel structure can also be used as a rescue channel during construction, the arched top structure can ensure that the channel has better supporting strength, good protection capability for internally passing personnel is ensured when a tunnel dangerous situation occurs, the flat bottom of the tunnel can improve the passing speed of rescue personnel and instruments, and the assembled inverted arch channel structure has positive significance in accelerating the rescue speed, reducing casualties and reducing engineering loss;
(3) the assembled inverted arch adopts a bolt connection mode, so that the longitudinal and transverse connection of the prefabricated blocks can be enhanced in a short time, the concept of early looping of the tunnel is realized, and the tunnel structure and construction safety are ensured;
(4) through the drainage side ditch reserved in the first precast block and the third precast block and the pre-buried transverse drainage pipe in advance, the drainage pipes of the tunnel are communicated, so that the 'prevention, blockage, interception and drainage combination' of the tunnel is effectively realized, and the 'comprehensive treatment' water prevention and drainage principle is realized according to local conditions.
Drawings
The accompanying drawings, which are included to provide a further understanding of the disclosure, illustrate embodiments of the disclosure and together with the description serve to explain the disclosure and are not to limit the disclosure.
Fig. 1 is a schematic cross-sectional view of an inverted arch and a tunnel front in embodiments 1 and 2 of the present disclosure;
fig. 2 is a schematic perspective view of a completed inverted arch construction in one section in embodiments 1 and 2 of the present disclosure;
fig. 3 is a schematic end-face structure diagram of a precast block in embodiments 1 and 2 of the present disclosure;
fig. 4 is a schematic view of a connection structure of adjacent prefabricated sections in embodiments 1 and 2 of the present disclosure;
fig. 5 is a schematic top view of a connection structure of adjacent prefabricated sections in embodiments 1 and 2 of the present disclosure;
fig. 6 is a schematic top view of a groove with a reserved arc surface in an inverted arch cushion layer according to embodiments 1 and 2 of the present disclosure;
fig. 7 is a schematic structural diagram of a junction between an inverted arch and a tunnel secondary lining in embodiments 1 and 2 of the present disclosure.
In the figure, 1, primary support, 2, secondary lining, 3, a first precast block, 4, a second precast block, 5, a third precast block, 6, a leveling layer, 7, a waist iron, 8, an inverted arch cushion layer, 81, a longitudinal drainage blind pipe, 9, a tunnel ditch and a cable trough, 10, a water stopping groove, 11, a hoisting hole, 12, a transverse drainage blind pipe, 13, a longitudinal drainage side ditch, 14, a bolt through hole, 15, a steel bar joint, 111, a transverse groove, 112, an arc groove, 113 and a bolt groove.
Detailed Description
It should be noted that the following detailed description is exemplary and is intended to provide further explanation of the disclosure. Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this disclosure belongs.
It is noted that the terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of example embodiments according to the present disclosure. As used herein, the singular forms "a", "an", and/or "the" are intended to include the plural forms as well, and it should be understood that when the terms "comprises" and/or "comprising" are used in this specification, they specify the presence of stated features, steps, operations, devices, components, and/or combinations thereof;
for convenience of description, the words "up", "down", "left" and "right" in this disclosure, if any, merely indicate that the directions of movement are consistent with those of the figures themselves, and are not limiting in structure, but merely facilitate the description of the invention and simplify the description, rather than indicate or imply that the referenced device or element must have a particular orientation, be constructed and operated in a particular orientation, and thus should not be construed as limiting the present disclosure.
As introduced in the background art, in the construction process of tunnel excavation and primary support in the prior art, risks such as tunnel face collapse and water burst are associated, and after a traditional rescue channel is blocked, consequences such as slow rescue speed, increased casualties, serious damage to engineering and the like can be caused; in order to solve the problems, the disclosure provides a cavity assembly type tunnel inverted arch and a construction method.
Example 1
In an exemplary embodiment of the present disclosure, as shown in fig. 1 to 7, a cavity-mounted tunnel invert is proposed.
The assembled tunnel inverted arch mainly comprises inverted arch blocks which are sequentially arranged along the extending direction of the tunnel, wherein each inverted arch block is composed of a plurality of prefabricated blocks, so that a plurality of rows of prefabricated blocks which are sequentially arranged along the extending direction of the tunnel are formed;
the inverted arch adopts prefabricated assembly formula, and the component is at the preparation of prefabricated field, and quality intensity is reliable, has replaced traditional inverted arch to establish the cast-in-place mode of landing stage, has reduced the artifical mechanical cost in the construction of traditional inverted arch for the holistic construction progress of tunnel.
The inverted arch block comprises a first prefabricated block, a second prefabricated block and a third prefabricated block which are sequentially arranged along the transverse direction of the tunnel, and the first prefabricated block, the second prefabricated block and the third prefabricated block are spliced through a through seam, and the first prefabricated block and the third prefabricated block are identical in structural form;
the center of each inverted arch block is provided with a channel which is distributed along the longitudinal direction of the tunnel, the channels are symmetrically distributed relative to the vertical symmetrical plane of the tunnel, the bottom of each channel is a plane, the top of each channel is an arch far away from the bottom, and the channels corresponding to all inverted arch blocks are sequentially communicated in a butt joint mode and used for accommodating personnel to pass through;
in the embodiment, the channel is arranged at the geometric center of the second precast block, and the combining center of the first precast block and the third precast block is provided with a cavity which penetrates through the tunnel longitudinally;
for the channel, the upper part of the channel is of an arch structure, the upper part of the cavity is of an arch structure, the positions of the second precast block corresponding to the two sides of the channel have enough structural thickness, and the positions of the first precast block and the third precast block corresponding to the two sides of the cavity also have enough structural thickness;
in this embodiment, the precast blocks are all concrete precast blocks, and the corresponding precast block structures on both sides of the channel and both sides of the cavity have sufficient concrete thickness.
The sectional area of the channel structure of the second precast block is larger than that of the cavity, so that people can pass through the channel structure, and the sequentially communicated channels can form a lifesaving channel for the survival of people and instruments;
the assembled inverted arch channel structure adopts a channel structure with a flat bottom and an arched top, the left side and the right side have enough concrete thickness, and the arched top structure can ensure that the whole structure is well stressed and saves materials;
the channels are symmetrically distributed relative to the vertical symmetrical plane of the tunnel, so that the tunnel can be arranged at the position with the largest vertical thickness of the second prefabricated block, and the thickness of concrete around the channels can be ensured to be the largest while enough large sections are obtained, so that the strength of the channels can be ensured to be optimal;
the tunnel can be used as a rescue channel during construction, the arched structure at the top can enable the channel to have better supporting strength, good protection capability for internal traffic personnel is guaranteed when a tunnel dangerous situation occurs, the bottom of the tunnel is smooth, the passing speed of rescue personnel and equipment can be improved, and the tunnel has positive significance in the aspects of accelerating rescue speed, reducing casualties and reducing engineering loss.
In addition, in order to be matched with the channel to serve as a rescue escape channel, the cross section of the rescue escape channel can at least accommodate an adult to pass through, when a dangerous case occurs, working personnel on the working face can reach a working pit reserved at the tunnel portal from the working face through the channel of the second precast block, the working pit is designed to be 2m wide, the length of the working pit is consistent with the span of the tunnel, a ladder stand is arranged on the left side in the pit, and a steel plate is laid on the pit for normal construction of the tunnel.
For the connection of the corresponding prefabricated blocks of the same inverted arch block, a groove is arranged on the end surface of one side of the inverted arch block, the groove is positioned at the joint part of the adjacent prefabricated blocks and the joint part of the prefabricated blocks and the inverted arch cushion layer, and the groove is matched with a connecting piece;
specifically, the same transverse grooves 111 and arc-surface grooves 112 which are only formed in the front surfaces of the precast blocks are reserved at the joint parts of the first precast block 3, the second precast block 4 and the third precast block 5 and the joint parts of the precast blocks and the inverted arch cushion layer 8 for placing the lumbar irons 7, and the lumbar irons 7 are cuboid solid iron blocks, so that the transverse relation among the precast blocks and the vertical relation between the precast blocks and the inverted arch cushion layer 8 can be enhanced, the inverted arch rigidity of the whole is increased, and the using amount of bolts is reduced;
the top surfaces of the prefabricated blocks are provided with bolt grooves, and the adjacent prefabricated blocks are connected through the bolt grooves and the connecting pieces in a matching mode; a joint is reserved at the position, corresponding to the tunnel secondary lining, of the top surface of the precast block and used for butting the secondary lining;
specifically, the top surfaces of the three prefabricated blocks are all provided with the same bolt grooves 113, and the front surface, the back surface and the end surfaces of the prefabricated blocks are all provided with bolt through holes 14;
in the embodiment, 6 bolt grooves 113 are reserved on the top surfaces of the first prefabricated block 3 and the third prefabricated block 5, wherein the number of the bolt grooves 113 responsible for transverse connection of the prefabricated blocks is 2, and the number of the bolt grooves 113 responsible for longitudinal connection of the prefabricated blocks is 4;
the top surface of second prefabricated section 4 is reserved has 6 bolt recess 113, and the bolt recess 113 of being responsible for prefabricated section transverse connection totally 4, and the bolt recess 113 of being responsible for the prefabricated section longitudinal tie totally 2, and all prefabricated sections all use elastic seal ring, gasket, nut and curved bolt to connect, and when assembling, will bend the bolt and wear to the opposite side by one side bolt recess 113, lay elastic seal ring, gasket and nut in proper order again, accomplish the fastening.
The bolt connection mode that assembled inverted arch adopted can strengthen the vertical and horizontal relation of prefabricated section in the short time, realizes the tunnel "early looping" theory, has guaranteed tunnel structure and construction safety.
For the drainage structure, drainage side ditches are arranged in the first precast block 3 and the third precast block 5 and are communicated with a tunnel pre-embedded longitudinal drainage blind pipe 81 through a transverse drainage blind pipe 12, and the gradient of the drainage side ditches is consistent with the gradient of the whole tunnel;
it should be noted that, in this embodiment, the longitudinal width of the precast block is considered to be 2m, and each 10m is an assembly cycle, wherein the first precast block 3 and the third precast block 5 of the fifth ring are embedded with the horizontal drainage blind pipes 12, and the horizontal drainage blind pipes 12 of all the inverted arch precast blocks of the tunnel are arranged according to this principle;
the horizontal drainage blind pipe 12 is sleeved and installed once in every five rings, and the horizontal drainage blind pipe 12 is connected with the tunnel longitudinal drainage blind pipe 81 through a tee joint;
of course, it can be understood that the assembly cycle can be adjusted according to actual construction requirements in different tunnels, for example, the longitudinal width of the precast blocks is set to be 2.5m, each 10m is an assembly cycle, and the transverse drainage blind pipes are embedded in the first precast block and the third precast block of the corresponding fourth ring.
And a longitudinally-through drainage side ditch 13 is reserved in each of the first precast block 3 and the third precast block 5, and the gradient of the drainage side ditch 13 is equal to the integral gradient of the tunnel for convenient drainage.
Through the drainage side ditch reserved in the first precast block and the third precast block and the pre-buried transverse drainage blind pipe in advance, the annular drainage blind pipe and the longitudinal drainage blind pipe of the tunnel are communicated, and the waterproof and drainage principle that the tunnel is 'prevented, blocked, cut and drained combined, comprehensively treated' according to local conditions is effectively realized.
Hoisting holes 11 are reserved on the top surfaces of the precast blocks, and hoisting operation of the precast blocks can be facilitated.
For the joint structure, 8 steel bar joints 15 are reserved at the combined positions of the first precast block 3, the third precast block 5 and the tunnel secondary lining 2, and in order to enhance the lining strength of the joint position, a proper amount of stirrups can be bound at the steel bar joints 15 during the actual construction of the secondary lining 2.
In addition, water stopping grooves 10 which are sleeved with ethylene propylene diene monomer water stopping rubber strips are reserved on the back surfaces of the first precast block 3, the second precast block 4 and the third precast block 5 and the left and right end surfaces of the second precast block 4, the contour of each groove is basically consistent with that of each precast block, circumferential waterproof cork liners are only adhered to the back surfaces of the precast blocks, and longitudinal waterproof butyronitrile cork rubber plates are only adhered to the left and right end surfaces of the second precast block 4;
the assembled inverted arch has the advantages that the waterproof performance of the tunnel inverted arch is enhanced by combining the ethylene propylene diene monomer rubber strips and the waterproof material of the annular longitudinal seams, and a third waterproof system except the waterproof plate and the inverted arch base cushion layer is constructed for the waterproof of the tunnel inverted arch.
Example 2
In another exemplary embodiment of the present disclosure, as shown in fig. 1 to 7, a method for constructing an inverted arch of a cavity-mounted tunnel using the inverted arch of the cavity-mounted tunnel described in example 1 is provided.
The method comprises the following steps:
preprocessing an inverted arch block, preprocessing a tunnel, and arranging an inverted arch cushion layer;
hoisting each inverted arch block in sequence, and installing the inverted arch blocks in sequence along the longitudinal extension direction of the tunnel;
aligning channels in the inverted arch blocks, and sequentially connecting adjacent inverted arch blocks;
and (4) constructing a tunnel leveling layer on the top surface of the inverted arch block, and laying other accessory facilities.
Specifically, the construction process is described in detail with reference to the respective structures in embodiment 1:
pretreating a first prefabricated block, a second prefabricated block and a third prefabricated block on a construction site, wherein the first prefabricated block, the second prefabricated block and the third prefabricated block comprise sleeved and pasted ethylene propylene diene monomer rubber strips, pasted cork liners for circumferential waterproofing of the prefabricated blocks and butyronitrile cork rubber plates for longitudinal waterproofing of the prefabricated blocks;
the tunnel primary support 1 is constructed, the tunnel is completely waterproof by adopting a waterproof board, and a longitudinal drainage blind pipe 81 of an inverted arch cushion layer 8 is embedded along the longitudinal central line of the bottom of the tunnel;
three rows of arc-shaped grooves 112 are formed in the inverted arch cushion layer 8 of the whole road, one row of arc-shaped grooves 112 are formed every 2m, and the shape of the grooves is required to be matched with the shape of the reserved arc-shaped grooves on the precast block;
when the inverted arch cushion layer 8 is constructed, the arc surface is required to be smooth, after maintenance and the strength meeting the design requirement, the waist iron 7 is placed in the arc surface groove 112 of the inverted arch cushion layer 8 and is fixed by the anchoring agent;
hoisting a second precast block 4 for initial positioning, then hoisting a first precast block 3 and a third precast block 5 respectively, and fixing a waist rail 7 by using an anchoring agent;
firstly installing and fastening the precast block bolt, wherein the bolt installation principle follows the principle of 'longitudinal and horizontal firstly', and then placing the lumbar iron 7 in the transverse groove 111 of the joint surface of the precast block and fixing the lumbar iron by using an anchoring agent;
after all the installed precast block bolts are repeatedly tightened for multiple times, the bolt grooves 113 are filled and leveled with cement mortar;
and after the cement mortar in the bolt groove 113 reaches the strength required by the design, constructing an inverted arch leveling layer 6 of the tunnel, and constructing a tunnel ditch, a cable groove 9 and other accessory facilities on the leveling layer 6.
The above description is only a preferred embodiment of the present disclosure and is not intended to limit the present disclosure, and various modifications and changes may be made to the present disclosure by those skilled in the art. Any modification, equivalent replacement, improvement and the like made within the spirit and principle of the present disclosure should be included in the protection scope of the present disclosure.

Claims (10)

1. The utility model provides a cavity assembled tunnel invert, its characterized in that, is including being used for vertically laying a plurality of arch pieces of facing upward in the tunnel bottom surface in proper order along the tunnel, and every central point that faces upward the arch piece puts and is equipped with the passageway along the longitudinal distribution of tunnel, and the passageway is for the vertical plane of symmetry symmetric distribution in tunnel, and the passageway bottom is the plane, and the top is the arch of keeping away from the bottom surface, and the passageway that all invert pieces correspond docks the intercommunication in proper order for hold personnel and pass through.
2. The cavity-mounted tunnel invert of claim 1, wherein each invert block comprises a first precast block, a second precast block and a third precast block sequentially arranged in a transverse direction of the tunnel, the passages are arranged in the second precast block, and the first precast block and the third precast block are identical and symmetrically arranged at both sides of the second precast block.
3. The cavity-assembled tunnel invert of claim 2, wherein the first precast block and the third precast block are provided with cavities distributed along the longitudinal direction of the tunnel, the cavities of the first precast block corresponding to the adjacent invert blocks are communicated, and the cavities of the third precast block corresponding to the adjacent invert blocks are communicated.
4. The cavity-assembled tunnel invert of claim 3, wherein the cavities are distributed along the center of the corresponding precast block and have an arch-shaped top; the prefabricated section is matched with a waterproof structure.
5. The inverted arch of cavity-assembled tunnel according to claim 2, wherein the same inverted arch block is provided with a groove on one side end surface of the corresponding precast block, the groove is located at the joint portion of the adjacent precast blocks and the joint portion of the precast blocks and the inverted arch cushion layer, and the groove is fitted with a connecting member.
6. The cavity-assembled tunnel invert of claim 5, wherein the top surfaces of the precast blocks are provided with bolt grooves, and the adjacent precast blocks are connected by bolt groove-fit connectors;
and joints are reserved at the positions, corresponding to the tunnel secondary linings, of the top surfaces of the precast blocks and used for butting the secondary linings.
7. The cavity-assembled tunnel invert of claim 2, wherein each of the first precast block and the third precast block is provided with a drainage gutter which is communicated with a longitudinal drainage blind pipe of the tunnel through a transverse drainage blind pipe, and the gradient of the drainage gutter is consistent with the gradient of the whole tunnel.
8. A cavity assembly type tunnel invert construction method, wherein the cavity assembly type tunnel invert of any claim 1 to 7 is used, comprising the steps of:
preprocessing an inverted arch block, preprocessing a tunnel, and arranging an inverted arch cushion layer;
hoisting each inverted arch block in sequence, and installing the inverted arch blocks in sequence along the longitudinal extension direction of the tunnel;
aligning channels in the inverted arch blocks, and sequentially connecting adjacent inverted arch blocks;
and (4) constructing a tunnel leveling layer on the top surface of the inverted arch block, and laying other accessory facilities.
9. The inverted arch construction method of the cavity assembly type tunnel according to claim 8, wherein each inverted arch block comprises a first prefabricated block, a second prefabricated block and a third prefabricated block which are distributed along the transverse direction of the tunnel, and when the inverted arch blocks are hoisted, the second prefabricated block is hoisted in a positioning mode, and then the first prefabricated block and the third prefabricated block are hoisted respectively.
10. The inverted arch construction method of a cavity-assembled tunnel according to claim 9, wherein adjacent prefabricated sections are connected by a connecting member.
CN202010693229.3A 2020-07-17 2020-07-17 Cavity assembly type tunnel inverted arch and construction method Active CN111878115B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010693229.3A CN111878115B (en) 2020-07-17 2020-07-17 Cavity assembly type tunnel inverted arch and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010693229.3A CN111878115B (en) 2020-07-17 2020-07-17 Cavity assembly type tunnel inverted arch and construction method

Publications (2)

Publication Number Publication Date
CN111878115A true CN111878115A (en) 2020-11-03
CN111878115B CN111878115B (en) 2022-06-07

Family

ID=73156041

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010693229.3A Active CN111878115B (en) 2020-07-17 2020-07-17 Cavity assembly type tunnel inverted arch and construction method

Country Status (1)

Country Link
CN (1) CN111878115B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112458834A (en) * 2020-11-13 2021-03-09 中国铁建股份有限公司 Hopper device for tunnel inverted arch cushion layer laying and construction method
CN112593975A (en) * 2020-12-11 2021-04-02 中铁二十局集团有限公司 Inverted arch structure, construction method thereof and tunnel supporting structure
CN112627853A (en) * 2020-11-27 2021-04-09 中铁第一勘察设计院集团有限公司 Tunnel inverted arch structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107387119A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 Prefabricated assembled tunnel inverted arch, tunnel structure and its construction method
CN207499880U (en) * 2017-09-27 2018-06-15 贵州省公路工程集团有限公司 A kind of assembled inverted arch
CN108843380A (en) * 2018-05-07 2018-11-20 中铁工程设计咨询集团有限公司 Precast construction under a kind of Railway Tunnel three-piece type rail
CN208236441U (en) * 2018-05-28 2018-12-14 四川省交通运输厅公路规划勘察设计研究院 Tunnel inverted arch backfill construction
CN109252874A (en) * 2018-11-15 2019-01-22 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of Tunnel Base and its construction
CN109267435A (en) * 2018-11-15 2019-01-25 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of Tunnel Base and its construction
CN210599005U (en) * 2019-08-21 2020-05-22 中交第二公路勘察设计研究院有限公司 TBM tunnel is faced upward and is encircleed piece lining structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107387119A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 Prefabricated assembled tunnel inverted arch, tunnel structure and its construction method
CN207499880U (en) * 2017-09-27 2018-06-15 贵州省公路工程集团有限公司 A kind of assembled inverted arch
CN108843380A (en) * 2018-05-07 2018-11-20 中铁工程设计咨询集团有限公司 Precast construction under a kind of Railway Tunnel three-piece type rail
CN208236441U (en) * 2018-05-28 2018-12-14 四川省交通运输厅公路规划勘察设计研究院 Tunnel inverted arch backfill construction
CN109252874A (en) * 2018-11-15 2019-01-22 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of Tunnel Base and its construction
CN109267435A (en) * 2018-11-15 2019-01-25 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of Tunnel Base and its construction
CN210599005U (en) * 2019-08-21 2020-05-22 中交第二公路勘察设计研究院有限公司 TBM tunnel is faced upward and is encircleed piece lining structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112458834A (en) * 2020-11-13 2021-03-09 中国铁建股份有限公司 Hopper device for tunnel inverted arch cushion layer laying and construction method
CN112458834B (en) * 2020-11-13 2022-02-08 中国铁建股份有限公司 Hopper device for tunnel inverted arch cushion layer laying and construction method
CN112627853A (en) * 2020-11-27 2021-04-09 中铁第一勘察设计院集团有限公司 Tunnel inverted arch structure
CN112593975A (en) * 2020-12-11 2021-04-02 中铁二十局集团有限公司 Inverted arch structure, construction method thereof and tunnel supporting structure

Also Published As

Publication number Publication date
CN111878115B (en) 2022-06-07

Similar Documents

Publication Publication Date Title
CN111878115B (en) Cavity assembly type tunnel inverted arch and construction method
CN107387117B (en) Prefabricated tunnel structure with tunnel bottom and construction method thereof
US20180274197A1 (en) Final Joint of Immersed Tunnel as well as Prefabrication Method and Installation Method
CN110318776B (en) Tunnel construction method based on inverted arch and inverted arch filling layer replacing steel-concrete composite structure
CN108677922B (en) Manufacturing and mounting method of reinforcement cage
CN111676819A (en) Jacking construction method for combined type temporary beam continuous reinforced line large-span frame structure bridge
CN111271087B (en) Construction method for arch prefabricated lining structure with post-cast strip connection
CN112502186A (en) Building space structure integrated assembly type subway station structure
CN113006822A (en) Special-shaped shield segment structure penetrating through yellow land cracks and construction method thereof
CN111305869A (en) Prefabricated lining structure of arch wall and construction method
CN109252874A (en) A kind of Tunnel Base and its construction
CN109667376B (en) Novel superposed floor system suitable for H-shaped steel beam of steel structure and construction method thereof
CN110055952B (en) Underground diaphragm wall joint structure and construction method thereof
CN108951642B (en) Reinforced structure capable of preventing foundation pit from rising and crossing existing tunnel and construction method
CN114352289A (en) Air shaft duct and method for breaking shield tunnel segment in mine construction section
CN212898516U (en) Cavity assembled tunnel invert
CN110344442B (en) Prefabricated assembly type open cut tunnel for railway and construction method thereof
CN111472813A (en) Super-large-span anchor-shotcrete support rock tunnel water-proof and drainage system and construction method
CN109555902B (en) Method for installing pipeline
CN112922641B (en) Circular prestress bracket system for subway communication channel construction and assembling method
CN210599100U (en) There is tiny fragments of stone, coal, etc. tunnel center ditch manhole
CN210317326U (en) Tunnel inverted arch and inverted arch filling layer replacing steel-concrete composite structure
CN209875166U (en) Hollow assembled tunnel inverted arch structure
CN114215548A (en) Method for treating lining defect of tunnel of operation railway in assembled type
CN209853542U (en) Lifting appliance for lifting pipe gallery

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 250023 No. 5 Jiao Tong Road, Tianqiao District, Shandong, Ji'nan

Applicant after: Shandong Jiaotong University

Applicant after: QILU TRANSPORTATION DEVELOPMENT GROUP Co.,Ltd.

Address before: No. 5001, Haitang Road, Science Park, Changqing University, Jinan City, Shandong Province, 250300

Applicant before: Shandong Jiaotong University

Applicant before: QILU TRANSPORTATION DEVELOPMENT GROUP Co.,Ltd.

GR01 Patent grant
GR01 Patent grant