CN109252874A - A kind of Tunnel Base and its construction - Google Patents

A kind of Tunnel Base and its construction Download PDF

Info

Publication number
CN109252874A
CN109252874A CN201811357237.XA CN201811357237A CN109252874A CN 109252874 A CN109252874 A CN 109252874A CN 201811357237 A CN201811357237 A CN 201811357237A CN 109252874 A CN109252874 A CN 109252874A
Authority
CN
China
Prior art keywords
prefabricated section
inverted arch
tunnel
prefabricated
tunnel base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811357237.XA
Other languages
Chinese (zh)
Other versions
CN109252874B (en
Inventor
王志伟
马伟斌
杜晓燕
张斌
王子洪
余东洋
付兵先
马超锋
邹文浩
李尧
安哲立
郭小雄
赵鹏
常凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Academy of Railway Sciences Corp Ltd CARS
Railway Engineering Research Institute of CARS
Original Assignee
China Academy of Railway Sciences Corp Ltd CARS
Railway Engineering Research Institute of CARS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Academy of Railway Sciences Corp Ltd CARS, Railway Engineering Research Institute of CARS filed Critical China Academy of Railway Sciences Corp Ltd CARS
Priority to CN201811357237.XA priority Critical patent/CN109252874B/en
Publication of CN109252874A publication Critical patent/CN109252874A/en
Application granted granted Critical
Publication of CN109252874B publication Critical patent/CN109252874B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention provides a kind of Tunnel Base, the Tunnel Base includes: the inverted arch prefabricated section that tunnel bottom is arranged in;It is mounted on the prefabricated filled layer on inverted arch prefabricated section top, the prefabricated filled layer includes two F type prefabricated sections for connecting and be in mirror-image arrangement with the bottom of tunnel two sides arch wall respectively, and the gate prefabricated section being fixedly connected between two F type prefabricated sections;Wherein, the prefabricated filled layer is adapted to installation with the inverted arch prefabricated section, and the inverted arch prefabricated section and the prefabricated filled layer are longitudinally continuous setting along tunnel bottom and form Tunnel Base.

Description

A kind of Tunnel Base and its construction
Technical field
The present invention relates to Tunnel Engineering construction technique fields, particularly relate to a kind of Tunnel Base.The invention further relates to A kind of construction of Tunnel Base.
Background technique
In recent years, with the development of China Railway, Concerning Railway Tunnel Construction engineering is also become more and more important, investment fortune The Tunnel Engineering of battalion is also more and more.
It is formed currently, Foundation Base in Railway Tunnel generallys use concreting.In the operation phase, the common disease of Tunnel Base has Layering cracking, pucking, sink, rises soil, the diseases such as lining cracking.These are all serious to influence the safety in tunnel and normal Operation, reduces liner structure to the bearing capacity of country rock.Meanwhile shop fixtures and inverted arch are damaged, lead to surface deformation, thus seriously Jeopardize traffic safety.
Tunnel defect is very harmful, once discovery disease needs to be administered at once.It is existing in tunnel defect governance process Tunnel Base change the long construction period for filling out and changeing inverted arch, construction efficiency is low.In addition, to the serious interference of tunnel surrounding, no The bearing capacity for the Tunnel Base that only seriously affected that treated, and working security is poor, the construction of Tunnel Base and is supported It protects at high cost.
Summary of the invention
For at least some technical problems as described above, the present invention is directed to propose a kind of Tunnel Base.The Tunnel Base It being formed using prefabricated component assembly connection, prefabricated component is equipped with specific structure, and installation is easy to connect, and it is easy for construction, and effect of constructing Rate is high.The support construction of Tunnel Base can guarantee that the Tunnel Base has excellent support capability, can effectively reduce tunnel disease Evil, and the maintenance of Tunnel Base is convenient.The Tunnel Base also has good drainage performance and sealing waterproof performance.This Outside, in building course, which significantly reduces construction pollution, substantially increases construction efficiency and quality safety level, And effectively save resource, reduces construction and maintenance cost.
The present invention also provides a kind of constructions of Tunnel Base as described above.
For this purpose, according to the first aspect of the invention, providing a kind of Tunnel Base, the Tunnel Base includes: that setting exists The inverted arch prefabricated section of tunnel bottom;It is connected to the prefabricated filled layer on inverted arch prefabricated section top, the prefabricated filled layer includes Two connect with the bottom of tunnel two sides arch wall respectively and are in the F type prefabricated section of mirror-image arrangement, and are fixedly connected on two F Gate prefabricated section between type prefabricated section;Wherein, the prefabricated filled layer is adapted to installation with the inverted arch prefabricated section, and described faces upward Arch prefabricated section and the prefabricated filled layer are longitudinally continuous setting along tunnel bottom and form Tunnel Base.
In a preferred embodiment, several mounting grooves longitudinally extended are equipped in the upper end of the inverted arch prefabricated section, And two sides are equipped with vertically extending connecting lateral plate, the end of the connecting lateral plate is equipped with the protrusion that longitudinal gap opens distribution.
In a preferred embodiment, the F type prefabricated section includes body part, and vertical with the body part The first connecting plate and the second connecting plate for connecting and being separated from each other, the body part be equipped with longitudinally extend and can with it is described The groove of protrusion adaptation installation.
In a preferred embodiment, the gate prefabricated section includes entity plate and is vertically connected on the entity plate two The connecting lateral plate at end, first connecting plate, the second connecting plate and the connecting lateral plate adaptation of the F type prefabricated section are installed to In the mounting groove, so that the prefabricated filled layer is installed on the inverted arch prefabricated section.
In a preferred embodiment, the tongue-and-groove being laterally extended is equipped on the longitudinal terminal surface of the inverted arch prefabricated section, The longitudinally adjacent inverted arch prefabricated section forms connection by the tongue-and-groove.
In a preferred embodiment, the longitudinally extended along tunnel is equipped at the middle part of inverted arch prefabricated section upper end One gutter, tunnel a sidewall bottom and the second row longitudinally extended along tunnel is equipped on the F type prefabricated section Ditch.
In a preferred embodiment, the middle part of the inverted arch prefabricated section is equipped with several vertically extending drainpipes, The lower part of the inverted arch prefabricated section and longitudinal water-permeable pipe, first gutter are arranged right below in first gutter It is connected to by the drainpipe with longitudinal water-permeable pipe.
In a preferred embodiment, it is equipped in the junction of the prefabricated filled layer and the inverted arch prefabricated section anti- Shake bed course, and is equipped with the waterstop of water-swellable in the inside of the inverted arch prefabricated section.
In a preferred embodiment, inspection shaft is equipped on the gate prefabricated section for be longitudinally continuous connection, it is described Inspection shaft is along tunnel longitudinally evenly-spaced distribution.
According to the second aspect of the invention, a kind of construction of Tunnel Base as described above is provided, including following Step:
Tunnel bottom is excavated and clears up, and bottom excavation face does the flat processing of essence, and cast-in-place screed-coat;
After the concrete of the screed-coat reaches respective strengths, the inverted arch prefabricated section is placed in lifting, and assembly places three After inverted arch prefabricated section described in ring, the gap casting cement grouting material between the inverted arch prefabricated section and the screed-coat is tamped;
It is laid with the antivibration bed course on the joint face with the prefabricated filled layer of the inverted arch prefabricated section, first lifting is put The F type prefabricated section of two sides is set, then lifts and places the gate prefabricated section, so that the prefabricated filled layer adaptation is installed to On the inverted arch prefabricated section, and it is fastenedly connected;
Above steps is repeated, is longitudinally continuous construction along tunnel until Tunnel Base is laid with completion;
Place prefabricated the first gutter and the second gutter.
Detailed description of the invention
The present invention will be described below with reference to accompanying drawings.
Fig. 1 shows the schematic diagram of the transversal cross-section of Tunnel Base according to the present invention.
Fig. 2 shows the structure of inverted arch prefabricated section shown in Fig. 1.
Fig. 3 shows that inverted arch prefabricated section is longitudinally continuous the top view of mounting structure.
Fig. 4 and Fig. 5 shows the structure of the F type prefabricated section in Tunnel Base shown in Fig. 1.
Fig. 6 and Fig. 7 shows the structure of the gate prefabricated section in Tunnel Base shown in Fig. 1.
Fig. 8 shows that prefabricated filled layer is longitudinally continuous the top view of mounting structure.
In this application, all attached drawings are schematical attached drawing, are merely to illustrate the principle of the present invention, and not by real Border ratio is drawn.
Specific embodiment
Below in conjunction with the drawings and specific embodiments, the present invention will be further described.
It should be noted that be " transverse direction " by the horizontal line direction definition in the cross section of Tunnel Base in this application, And the extending direction in tunnel is defined as " longitudinal direction ", it will be " vertical " with the direction definition of horizontal plane.And by the application Used in Directional terms or the similar terms such as determiner " upper end ", " lower end " be for the attached drawing of institute's reference, it Be not used to limit the absolute position of involved components, but can change as the case may be.
Fig. 1 shows the schematic diagram of the transversal cross-section of Tunnel Base 100 according to the present invention.As shown in Figure 1, Tunnel Base 100 are mounted on the bottom in tunnel 200.According to the present invention, Tunnel Base 100 is prefabricated component.Tunnel Base 100 includes being arranged in tunnel The inverted arch prefabricated section 110 of 210 bottom of road arch wall, and the prefabricated filled layer 120 that connection is mounted on inverted arch prefabricated section 110. Prefabricated filled layer 120 includes two F type prefabricated sections 130 connecting respectively with the bottom of the tunnel arch wall 210 of tunnel two sides, with And it is fixedly connected on the gate prefabricated section 140 between two F type prefabricated sections 130.Two F type prefabricated sections 130 and gate prefabricated section 140 be fixedly connected after be adapted to and be installed on inverted arch prefabricated section 130.Prefabricated filled layer 120 is adapted to installation with inverted arch prefabricated section 110, And setting is longitudinally continuous along tunnel bottom and forms Tunnel Base 100.
In one embodiment, tunnel arch wall 210 is made of C30 armored concrete.Tunnel arch wall 210 can have Effect guarantees the support protective performance in tunnel.
Fig. 2 shows the structure of inverted arch prefabricated section 110.As shown in Fig. 2, the bottom of inverted arch prefabricated section 110 is configured to circular arc Shape.Several mounting grooves 111 longitudinally extended are equipped in the upper end of inverted arch prefabricated section 110, mounting groove 111 is horizontally according to certain Distance interval, which opens up, sets.Meanwhile vertically extending connecting lateral plate 112, connecting lateral plate are equipped in the two sides of inverted arch prefabricated section 110 112 end is equipped with the protrusion 113 that longitudinal gap opens distribution.Mounting groove 111 and protrusion 113 are used for the prefabricated filled layer of location and installation 120.In addition, being equipped with tongue-and-groove 114 on the longitudinal terminal surface of inverted arch prefabricated section 110, tongue-and-groove 114 is extended transversely.Adjacent inverted arch Prefabricated section 110 is connected with each other by tongue-and-groove 114.
Fig. 3 shows the top view of the inverted arch prefabricated section 110 after being laid with.As shown in figure 3, inverted arch prefabricated section 110 is equipped with Drainpipe 115.The middle part of inverted arch prefabricated section 110 is arranged in drainpipe 115, and vertically extending.Drainpipe 115 is equal in the longitudinal direction Even distribution spaced apart.In one embodiment, the longitudinal pitch of drainpipe 115 is set as 25m.The purposes of drainpipe 115 will be Hereafter it is introduced.
In addition, inverted arch prefabricated section 110 is additionally provided with oblique bolt hole 117, it is adjacent to connect that oblique bolt is installed in oblique bolt hole Inverted arch prefabricated section 110.In one embodiment, high-strength bolt of the oblique bolt using M24, strength grade 10.9S, and tiltedly M24 locking washer is used between bolt.Longitudinally adjacent inverted arch prefabricated section 110 connects joint bolt using tongue-and-groove as a result, The mode of connection is connected.And hole for hoist 118 used for positioning is equipped on inverted arch prefabricated section 110.In addition, in order to guarantee inverted arch Sealing waterproof performance between prefabricated section 110 is equipped with the waterstop 116 of water-swellable in the inside of inverted arch prefabricated section 110.Together When, antivibration bed course is equipped in the junction of inverted arch prefabricated section 110.Antivibration bed course can also adjust between inverted arch prefabricated section 110 Gap, so that the splicing accuracy between adjacent inverted arch prefabricated section 110 is improved, to guarantee the performance of Tunnel Base 100.
Fig. 4 and Fig. 5 shows the structure of F type prefabricated section 130.As shown in Figure 4 and Figure 5, F type prefabricated section 130 includes ontology Part 131, and first connecting plate 132 of one end of body part 131 is set and the middle part of body part 131 is set Second connecting plate 133.First connecting plate 132 and the second connecting plate 133 are vertical with body part 131, and are arranged in body part Divide on 131 end face.Longitudinal prolong is equipped on the end face of one end for being not provided with the first connecting plate 132 of body part 131 The groove 135 stretched.Groove 135 is used to be adapted to installation with the protrusion 113 on inverted arch prefabricated section 110.In the embodiment shown in fig. 5, Connecting hole 134 there are four being set on the first connecting plate 132.Meanwhile oblique bolt hole 136, oblique bolt are equipped on body part 131 Hole 136 is for installing oblique bolt to connect longitudinally adjacent F type prefabricated section 130.
Fig. 6 and Fig. 7 shows the structure of gate prefabricated section 140.As shown in Figure 6 and Figure 7, gate prefabricated section 140 includes structure The entity plate 141 of rectangular plate-like is caused, and is connected to the connecting lateral plate 142 at 141 both ends of entity plate.Connecting lateral plate 142 is arranged On an end face of entity plate 141, and it is vertical with entity plate 141.It is imported in embodiment illustrated in fig. 7 in Fig. 6, in connecting lateral plate Bolt hole 143 there are four being set on 142.Connecting hole 143 can be with the connecting hole on the first connecting plate 132 of F type prefabricated section 130 134 is corresponding, to install connection bolt, to being fixed together F type prefabricated section 130 and gate prefabricated section 140 with shape At prefabricated filled layer 120.Meanwhile oblique bolt hole 144 also is provided on entity plate 141, oblique bolt hole 144 is for installing oblique bolt To connect longitudinally adjacent gate prefabricated section 140.
In the present embodiment, in the connecting lateral plate of the first connecting plate 132 and gate prefabricated section 140 of F type prefabricated section 130 Antivibration bed course is equipped between 142.In one embodiment, antivibration bed course uses EPDM elastic packing rubber pad.Antivibration pad Layer can guarantee the sealing waterproof performance between F type prefabricated section 130 and gate prefabricated section 140, and can adjust F type prefabricated section Gap between 130 and gate prefabricated section 140 improves the splicing accuracy between F type prefabricated section 130 and gate prefabricated section 140, Further ensure the performance of Tunnel Base 100.
When lifting connects prefabricated filled layer 120 with inverted arch prefabricated section 110, F type prefabricated section 130 and gate prefabricated section 140 are logical It crosses connection bolt and is fixedly connected to form prefabricated filled layer 120.Protrusion 113 on the connecting lateral plate 112 of inverted arch prefabricated section 110 with it is recessed Slot 135 adaptation installation, and the first connecting portion 131 of F type prefabricated section 130, second connecting portion 133 and gate prefabricated section 140 The adaptation of connecting lateral plate 142 is installed in the mounting groove 111 of inverted arch prefabricated section 110.Prefabricated filled layer 120 and inverted arch are completed as a result, The installation of prefabricated section 110 connects, to form Tunnel Base 100.In one embodiment, Tunnel Base 100 passes through pre-buried steel Muscle hole is connect with the bottom of tunnel arch wall 210.This structure of Tunnel Base 100 makes it have lifting construction convenience, construction effect The advantages that rate is high, security performance is high, easy to maintain.
Fig. 8 shows that prefabricated filled layer 120 is longitudinally continuous the top view of mounting structure.As shown in figure 8, F type prefabricated section 130 Body part 131 be equipped with for lifting operation hole for hoist 137.And it also is provided on the entity plate 141 of gate prefabricated section 140 Hole for hoist 147 for lifting operation.
In one embodiment, the entity plate 141 of gate prefabricated section 140 continuously coupled in the longitudinal direction is equipped with inspection shaft 145.As shown in figure 8, the middle part of gate prefabricated section 140 is arranged in inspection shaft 145, and along tunnel longitudinally evenly-spaced setting. In one embodiment, spacing is set as 25m to inspection shaft 145 in the longitudinal direction.Inspection shaft 145 is set as rectangular opening, is used for inspection door The intracorporal situation of the chamber of type prefabricated section 140, with the situation inside inspection and maintenance Tunnel Base 100.
In one embodiment, inverted arch prefabricated section 110, F type prefabricated section 130 and gate prefabricated section 140 are all made of C40 steel Reinforced concrete material is made.As a result, inverted arch prefabricated section 110 and prefabricated filled layer 120 have good support protective performance, The support performance for effectively increasing Tunnel Base 100 improves the security performance of Tunnel Base.
According to the present invention, Tunnel Base 100 is additionally provided with the first gutter 150 and the second gutter longitudinally extended along tunnel 160.As shown in Figure 1, the middle part of 110 upper end of inverted arch prefabricated section is arranged in the first gutter 150.The setting of second gutter 160 exists The bottom of one side wall in tunnel and the upper end for being in F type prefabricated section 130.In one embodiment, the first gutter 150 and Two gutters 160 are equipped with cover board, and are prefabricated component.Preferably, the first gutter 150, the second gutter 160 and cover board Fiber glass reinforcement is all made of to be made.
In addition, being equipped with longitudinal water-permeable pipe for draining in the lower part of inverted arch prefabricated section 110.Longitudinal water-permeable pipe is in first The underface in gutter 150, and it is parallel with the first gutter 150 along tunnel longitudinally extension.In one embodiment, Zong Xiangtou Water pipe uses φ 300HDPE water-permeable pipe.Preferably, filter layer 170 is surrounded by longitudinal water-permeable pipe.As shown in Figure 1, filter layer 170 cross-sectional configuration is at trapezoidal.In one embodiment, filter layer 170 is equipped with concrete bed, and is in inverted arch prefabricated section Rubble filter layer between 110 and longitudinal water-permeable pipe.Filter layer 170 can effectively filter the impurity in tunnel rock.In this reality It applies in example, the first gutter 150 is connected to by drainpipe 115 with longitudinal water-permeable pipe.Ponding in first gutter 150 can flow Longitudinal water-permeable pipe is flowed by drainpipe 115, and passes through longitudinal water-permeable pipe discharge.Influence of the ponding to tunnel is reduced as a result, is subtracted The generation for having lacked 100 disease of Tunnel Base improves the security performance of Tunnel Base 100.
According to the present invention, the Tunnel Base 100 being connect by inverted arch prefabricated section 110 with prefabricated 120 assembled of filled layer with enclose Rock contact uses the smart stone concrete screed-coat combination grouting mode of 5-10cm.In one embodiment, cast-in-place screed-coat uses C20 concrete material is made.
The construction of brief description Tunnel Base 100 according to the present invention.
Firstly, excavating and clearing up tunnel bottom, and the excavation face of tunnel bottom does the flat processing of essence, and cast-in-place cement mortar Screed-coat.Meanwhile in the embedded longitudinal water-permeable pipe of tunnel bottom.After the concrete of screed-coat reaches respective strengths, lifting is placed After tricyclic inverted arch prefabricated section 110 is placed in assembly, the gap between inverted arch prefabricated section and screed-coat is poured for inverted arch prefabricated section 110 Cement grout material tamps.Later, the lifting for carrying out the prefabricated filled layer 120 of every ring is placed.The installation process of prefabricated filled layer 120 is such as Under, antivibration bed course is first laid on the joint face of inverted arch prefabricated section 110, then, the F type prefabricated section of tunnel two sides is placed in lifting 130, then lift and place gate prefabricated section 140, connection is mounted between the F type prefabricated section 130 of two sides, and is fastenedly connected. In this installation process of prefabricated filled layer 120, F type prefabricated section 130 passes through the pre-buried steel on corresponding inverted arch prefabricated section 110 Muscle hole and mounting groove 111 carry out positioning lifting.And before F type prefabricated section 130 and gate prefabricated section 140 lift, it is connected accordingly Connection installation antivibration bed course at position.In a longitudinal direction, between adjacent F type prefabricated section 130 and adjacent gate is prefabricated It is formed a fixed connection by connecting bolt between block 140.The prefabricated adaptation of filled layer 120 of tricyclic is installed to as a result, and has been pacified On the tricyclic inverted arch prefabricated section 110 installed, to complete the laying construction of tricyclic Tunnel Base.Later, above steps is repeated, It is that a circulation is longitudinally continuous construction until the laying of Tunnel Base 100 is completed along tunnel with tricyclic.Finally, placing prefabricated first Gutter 150 and the second gutter 160.
According to the present invention, in the lifting placement process of tricyclic Tunnel Base.To inverted arch prefabricated section 110 and prefabricated filled layer After the completion of 120 assembly, need first to check the splicing accuracy of inverted arch prefabricated section 110 Yu prefabricated 120 structure of filled layer.If meeting installation It is required that then with pneumatic impact spanner is turned round surely by all connection bolts of preset torque fastening, first screwing torque is the 50% of construction torque, to protect Card inverted arch prefabricated section 110 and tongue-and-groove are closely joined together.In one embodiment, the construction torsional moment of each nut is not small In 660Nm.When with impact wrench, twists and pull the time and continue 2s-5s.Later, tunnel is successively laid on longitudinal direction in the above manner Road substrate.
During the assembly of inverted arch prefabricated section 110 and prefabricated filled layer 120, the top surface of gate prefabricated section 140 is led with flat The vertical axis of liner structure horizontal axis distance and gate prefabricated section 140 and flat guide bush block structural vertical axial line distance are equal In error range in ± 10mm, the smooth connection between inverted arch prefabricated section 110 and prefabricated filled layer 120 ensure that.It is facing upward Encircle prefabricated section 110 and prefabricated filled layer 120 longitudinally, laterally and vertically junction is respectively provided with antivibration bed course.Inverted arch is pre- as a result, The assembled error occurred between clamp dog 110 and prefabricated filled layer 120 can adjust gap by antivibration bed course, to realize that inverted arch is pre- The control of splicing accuracy between clamp dog 110 and prefabricated filled layer 120, meanwhile, realize inverted arch prefabricated section 110 and prefabricated filled layer The fitting of 120 pairs of sweeps.In the present embodiment, when antivibration bed course is installed, it should be ensured that antivibration bed course and respective planes Angle is unanimously to prevent inverted arch prefabricated section 110 and prefabricated filled layer 120 to be uneven.
According to the present invention, in the work progress of Tunnel Base 100, in inverted arch prefabricated section 110 and prefabricated filled layer 120 Corresponding position is pre-buried for measuring the sensor of different data, to monitor 120 structure of inverted arch prefabricated section 110 and prefabricated filled layer Stabilization, meanwhile, for examining the Tunnel Base 100 under practice of construction load real works situations such as (including) transporting, lift Bottom structure bearing capacity.The situation of Tunnel Base 100 is analyzed by the data that sensor detects, and takes corresponding answer To measure, so as to which the disease of Tunnel Base is effectively reduced.
Tunnel Base 100 according to the present invention, the Tunnel Base 100 is using prefabricated component inverted arch prefabricated section 110 and prefabricated fills out It fills 120 assembly connection of layer to form, inverted arch prefabricated section 110 and prefabricated filled layer 120 have compatible connection structure, and installation connects It connects conveniently, it is easy for construction, and construction efficiency is high.It is good that the support construction of Tunnel Base 100 can guarantee that the Tunnel Base 100 has Good support performance can effectively reduce tunnel defect, and the maintenance of Tunnel Base 100 is convenient.The Tunnel Base also has There are good drainage performance and sealing waterproof performance.In addition, in work progress, Tunnel Base 100 significantly reduce construction pollution, It substantially increases construction efficiency and quality safety is horizontal, and effectively save resource, reduce construction and maintenance cost.
Finally it should be noted that the foregoing is merely the preferred embodiments of the invention, do not constitute to the present invention Any restrictions.Although referring to foregoing embodiments, invention is explained in detail, for the technology of this field It for personnel, can still modify to technical solution documented by previous embodiment, or to part of technical characteristic It is equivalently replaced.All within the spirits and principles of the present invention, any modification, equivalent replacement, improvement and so on should all wrap Containing within protection scope of the present invention.

Claims (10)

1. a kind of Tunnel Base (100), which is characterized in that the Tunnel Base includes:
The inverted arch prefabricated section (110) of tunnel bottom is set;
Be connected to the prefabricated filled layer (120) on inverted arch prefabricated section top, the prefabricated filled layer include two respectively with tunnel The bottom of road two sides arch wall connects and is in the F type prefabricated section (130) of mirror-image arrangement, and to be fixedly connected on two F types pre- Gate prefabricated section (140) between clamp dog;
Wherein, the prefabricated filled layer is adapted to installation with the inverted arch prefabricated section, and the inverted arch prefabricated section and described prefabricated fills out It fills layer and is longitudinally continuous setting along tunnel bottom and form Tunnel Base.
2. Tunnel Base according to claim 1, which is characterized in that be equipped in the upper end of the inverted arch prefabricated section several vertical It is equipped with vertically extending connecting lateral plate (112) to the mounting groove (111) of extension and two sides, the end of the connecting lateral plate is set There is longitudinal gap to open the protrusion (113) of distribution.
3. Tunnel Base according to claim 2, which is characterized in that the F type prefabricated section includes body part (131), And the first connecting plate (132) and the second connecting plate (133) for connecting and being separated from each other vertical with the body part, it is described Body part is equipped with groove (135) longitudinally extend and that installation can be adapted to the protrusion.
4. Tunnel Base according to claim 3, which is characterized in that the gate prefabricated section include entity plate (141) and It is vertically connected on the connecting lateral plate (142) of the ontology board ends, first connecting plate of the F type prefabricated section, second connect Fishplate bar and connecting lateral plate adaptation are installed in the mounting groove, so that it is pre- that the prefabricated filled layer is installed to the inverted arch On clamp dog.
5. Tunnel Base according to any one of claims 1 to 4, which is characterized in that in the vertical of the inverted arch prefabricated section The tongue-and-groove (114) being laterally extended is equipped with to end face, the longitudinally adjacent inverted arch prefabricated section forms connection by the tongue-and-groove.
6. Tunnel Base according to any one of claims 1 to 4, which is characterized in that in inverted arch prefabricated section upper end Middle part be equipped with the first gutter (150) for longitudinally extending along tunnel, tunnel a sidewall bottom and in the F type it is pre- Clamp dog is equipped with the second gutter (160) longitudinally extended along tunnel.
7. Tunnel Base according to claim 6, which is characterized in that the middle part of the inverted arch prefabricated section is equipped with several vertical The drainpipe (115) of extension, the inverted arch prefabricated section lower part and be arranged right below longitudinal direction in first gutter Water-permeable pipe, first gutter are connected to by the drainpipe with longitudinal water-permeable pipe.
8. Tunnel Base according to any one of claims 1 to 4, which is characterized in that in the prefabricated filled layer and institute The junction for stating inverted arch prefabricated section is equipped with antivibration bed course, and is equipped with the sealing of water-swellable in the inside of the inverted arch prefabricated section Band (116).
9. Tunnel Base according to any one of claims 1 to 4, which is characterized in that be longitudinally continuous described in connection Gate prefabricated section is equipped with inspection shaft (145), and the inspection shaft is along tunnel longitudinally evenly-spaced distribution.
10. one kind according to claim 1 to the construction of Tunnel Base described in any one of 9, which is characterized in that including with Lower step:
Tunnel bottom is excavated and clears up, and bottom excavation face does the flat processing of essence, and cast-in-place screed-coat;
It after the concrete of the screed-coat reaches respective strengths, lifts and places the inverted arch prefabricated section, described in assembled complete tricyclic After inverted arch prefabricated section, the gap casting cement grouting material between the inverted arch prefabricated section and the screed-coat is tamped;
It is laid with the antivibration bed course on the joint face with the prefabricated filled layer of the inverted arch prefabricated section, first lifting places two The F type prefabricated section of side, then lift and place the gate prefabricated section, to the prefabricated filled layer adaptation is installed to described On inverted arch prefabricated section, and it is fastenedly connected;
Above steps is repeated, is longitudinally continuous construction along tunnel until Tunnel Base is laid with completion;
Place prefabricated the first gutter and the second gutter.
CN201811357237.XA 2018-11-15 2018-11-15 Tunnel substrate and construction method thereof Active CN109252874B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811357237.XA CN109252874B (en) 2018-11-15 2018-11-15 Tunnel substrate and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811357237.XA CN109252874B (en) 2018-11-15 2018-11-15 Tunnel substrate and construction method thereof

Publications (2)

Publication Number Publication Date
CN109252874A true CN109252874A (en) 2019-01-22
CN109252874B CN109252874B (en) 2024-04-05

Family

ID=65043180

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811357237.XA Active CN109252874B (en) 2018-11-15 2018-11-15 Tunnel substrate and construction method thereof

Country Status (1)

Country Link
CN (1) CN109252874B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826646A (en) * 2019-03-06 2019-05-31 中铁十一局集团第五工程有限公司 One-time formed tunnel segment assembly
CN110344442A (en) * 2019-07-31 2019-10-18 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of prefabricated assembled railway open cut tunnel and its construction method
CN110821514A (en) * 2019-09-30 2020-02-21 中铁隧道局集团建设有限公司 Construction method of assembled primary support structure of tunnel in water-rich area
CN111878115A (en) * 2020-07-17 2020-11-03 山东交通学院 Cavity assembly type tunnel inverted arch and construction method
CN112627853A (en) * 2020-11-27 2021-04-09 中铁第一勘察设计院集团有限公司 Tunnel inverted arch structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002097898A (en) * 2000-09-26 2002-04-05 Ishikawajima Constr Materials Co Ltd Arch tunnel, and construction method and bottom slab block for the same
CN107178377A (en) * 2017-07-07 2017-09-19 中铁第四勘察设计院集团有限公司 Adapt to the Tunneling by mining method polycrystalline substance and its construction method of rapid construction passage
CN107387117A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 A kind of prefabricated assembled tunnel structure in tunnel bottom and its construction method
CN207177911U (en) * 2017-07-07 2018-04-03 中铁第四勘察设计院集团有限公司 Adapt to the Tunneling by mining method polycrystalline substance of rapid construction passage
CN207245719U (en) * 2017-07-07 2018-04-17 中国铁道科学研究院铁道建筑研究所 A kind of prefabricated assembled tunnel structure in tunnel bottom
JP2018109280A (en) * 2016-12-28 2018-07-12 ジオスター株式会社 Tunnel internal structure and construction method of tunnel internal structure
CN108756940A (en) * 2018-05-28 2018-11-06 四川省交通运输厅公路规划勘察设计研究院 Tunnel construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002097898A (en) * 2000-09-26 2002-04-05 Ishikawajima Constr Materials Co Ltd Arch tunnel, and construction method and bottom slab block for the same
JP2018109280A (en) * 2016-12-28 2018-07-12 ジオスター株式会社 Tunnel internal structure and construction method of tunnel internal structure
CN107178377A (en) * 2017-07-07 2017-09-19 中铁第四勘察设计院集团有限公司 Adapt to the Tunneling by mining method polycrystalline substance and its construction method of rapid construction passage
CN107387117A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 A kind of prefabricated assembled tunnel structure in tunnel bottom and its construction method
CN207177911U (en) * 2017-07-07 2018-04-03 中铁第四勘察设计院集团有限公司 Adapt to the Tunneling by mining method polycrystalline substance of rapid construction passage
CN207245719U (en) * 2017-07-07 2018-04-17 中国铁道科学研究院铁道建筑研究所 A kind of prefabricated assembled tunnel structure in tunnel bottom
CN108756940A (en) * 2018-05-28 2018-11-06 四川省交通运输厅公路规划勘察设计研究院 Tunnel construction

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826646A (en) * 2019-03-06 2019-05-31 中铁十一局集团第五工程有限公司 One-time formed tunnel segment assembly
CN110344442A (en) * 2019-07-31 2019-10-18 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of prefabricated assembled railway open cut tunnel and its construction method
CN110344442B (en) * 2019-07-31 2024-06-11 中国铁道科学研究院集团有限公司铁道建筑研究所 Prefabricated assembly type open cut tunnel for railway and construction method thereof
CN110821514A (en) * 2019-09-30 2020-02-21 中铁隧道局集团建设有限公司 Construction method of assembled primary support structure of tunnel in water-rich area
CN111878115A (en) * 2020-07-17 2020-11-03 山东交通学院 Cavity assembly type tunnel inverted arch and construction method
CN111878115B (en) * 2020-07-17 2022-06-07 山东交通学院 Cavity assembly type tunnel inverted arch and construction method
CN112627853A (en) * 2020-11-27 2021-04-09 中铁第一勘察设计院集团有限公司 Tunnel inverted arch structure

Also Published As

Publication number Publication date
CN109252874B (en) 2024-04-05

Similar Documents

Publication Publication Date Title
CN109252874A (en) A kind of Tunnel Base and its construction
CN109267435A (en) A kind of Tunnel Base and its construction
US11384501B2 (en) Method for sealing post-cast strip in foundation with no gap
CN106836479A (en) A kind of prefabricated PC concrete frame structure
CN105951612B (en) Stake head bug repairing and reinforcement structure and its construction method under active service bridge water
CN105201012A (en) Casting cable trench after assembly of L-shaped precast concrete and construction method of casting cable trench
CN110578287B (en) Assembled earthing corrugated steel plate-prestressed concrete combined arch bridge and construction method thereof
CN110258362B (en) Deformation control method for urban underground engineering to pass through existing bridge
CN106498973A (en) A kind of assembled type base for power transmission line iron tower and its installation method
CN111878115B (en) Cavity assembly type tunnel inverted arch and construction method
CN110042865A (en) Box top board structure for large span city tunnel
CN213452051U (en) Along with bridge laying gas pipeline structure
CN105244835A (en) L-shaped concrete cable trench prefabricated component and production technology
CN209443308U (en) A kind of Tunnel Base
CN205116220U (en) Pour cable pit after assembly of L type precast concrete spare
CN209339961U (en) A kind of Tunnel Base
CN102174803A (en) Assembled drainage canal of debris flows and construction method thereof
RU2369692C2 (en) Building and construction erecting method, and device for method's implementation
CN110344442A (en) A kind of prefabricated assembled railway open cut tunnel and its construction method
WO2022247015A1 (en) Retaining wall structure using corrugated plates and construction method therefor
CN110130934A (en) The construction method of city tunnel bifurcation mouth with box top board structure
CN109706970A (en) A kind of prefabricated square cable active well
CN108978713A (en) A kind of prefabrication elevator shaft foundation pit and its installation method
CN114645721A (en) Combined assembly process for highway tunnel and inverted arch structure and assembly device thereof
CN208792366U (en) A kind of prefabrication elevator shaft foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant