CN111851504A - Method for installing water stopping steel hanging box of tie beam between piles in water - Google Patents
Method for installing water stopping steel hanging box of tie beam between piles in water Download PDFInfo
- Publication number
- CN111851504A CN111851504A CN202010568834.8A CN202010568834A CN111851504A CN 111851504 A CN111851504 A CN 111851504A CN 202010568834 A CN202010568834 A CN 202010568834A CN 111851504 A CN111851504 A CN 111851504A
- Authority
- CN
- China
- Prior art keywords
- steel
- die
- lock catch
- water
- casing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/06—Placing concrete under water
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Architecture (AREA)
- Revetment (AREA)
Abstract
The invention discloses a method for installing a water stop steel hanging box of a tie beam between piles in water, which comprises the steps of welding a surrounding purlin and a lock catch steel pipe in advance at the position of a pile tie beam when a steel pile casing is manufactured; pre-manufacturing a bottom die, a side die, an inner support and a suspension system, and then integrally assembling and forming; carrying out steel casing pile foundation construction; integrally hoisting the assembled bottom die and side die to a pier position by a floating crane, and lowering the T-shaped plates at the two ends of the side die to insert into the lock catch steel pipe; forming a bottom sealing concrete area among the steel casing, the bottom die and the side die and pouring underwater bottom sealing concrete; cement mortar is injected into the lock catch steel pipe through the grouting pipe; and pumping water in the steel casing and between the side mold and the steel casing to form an inter-pile beam tying dry operation environment, and pouring beam tying concrete to perform inter-pile beam tying construction. The invention has the advantages of good economy, convenient construction and safety.
Description
Technical Field
The invention belongs to a construction method of an underwater structure of a bridge, and particularly relates to an installation method of a beam-tying water-stopping steel suspension box between underwater piles.
Background
At present, in the construction of bridge underwater structures, a method of a sleeve box or a cofferdam is mainly adopted to create a dry-under-water working environment and then cast-in-place construction is carried out on the underwater structures, wherein the main installation mode of the sleeve box is that the sleeve box is integrally lowered, and the method is suitable for the construction of large-volume underwater structures. However, for the structure of the tie beam between the underwater piles, the integrally-wrapped steel hanging box water stop structure is adopted, so that the operation is complex, the number of auxiliary processes is large, the construction period is long, the construction cost investment is large, the unsafe factors are large, the construction risk is large, and the structure is obviously not suitable in terms of social and economic benefits.
Disclosure of Invention
The invention aims to provide a method for installing a beam tie water stop steel hanging box between underwater piles, which has the advantages of good economy, convenient construction and higher safety.
The technical scheme adopted for realizing the purpose of the invention is as follows:
the invention provides a method for installing a water stop steel hanging box of a tie beam between underwater piles, which comprises the following steps:
1. when the steel casing is manufactured, welding a surrounding purlin and a lock catch steel pipe in advance at the position of a pile tie beam, wherein the lock catch steel pipe is vertically arranged at the tie beam side of the steel casing;
2. pre-manufacturing a bottom die, a front side die and a rear side die which are arranged between the steel casing, an inner support arranged between the front side die and the rear side die and a suspension system connected with the bottom die, and then integrally assembling and molding; temporarily fixing a bottom die water stop movable plate on a bottom die panel, wherein an inner support is positioned at the top of a tie beam; the side mold consists of a standard template 4 and T-shaped plates arranged at two side ends of the standard template 4, the T-shaped plates are formed by two angle iron resistance welding, and the inner support is arranged between the front standard template and the rear standard template;
3. carrying out steel casing pile foundation construction, and cutting an opening seam of the lock catch steel pipe underwater before the bottom die and the side die are integrally lowered after the strength of pile foundation concrete in the steel casing reaches a certain degree;
4. integrally hoisting the assembled bottom die and side die to a pier position by using a floating crane, aligning the T-shaped plates at the two ends of the side die with the opening seams of the lock catch steel pipe, and lowering and inserting the T-shaped plates into the lock catch steel pipe;
5. After the bottom die and the side die are installed in place, a bottom sealing concrete area is formed among the steel casing, the bottom die and the side die, and underwater bottom sealing concrete is poured in the bottom sealing concrete area;
6. after the underwater bottom sealing concrete is finished, cement mortar is injected into the lock catch steel pipe through the grouting pipe;
7. after the cement mortar in the lock catch steel pipe is strengthened, water in the steel pile casing and between the side mold and the steel pile casing is drained to form a beam tying dry operation environment between piles, and beam tying concrete is poured to perform construction of beam tying between piles.
In the step 1, the enclosing purlin on the outer side of the steel casing is determined by calculation according to the construction working condition after water pumping, the enclosing purlin and the steel casing are discontinuously welded, the lock catch steel pipe is in full-length welding with the steel casing by foot sticking, and meanwhile, the small-sized set square is reinforced and connected, so that the part is prevented from being torn and is prevented from leaking water.
In the step 3, the verticality and the plane position of the steel casing are ensured to be accurate in the process of lowering the steel casing, and the position of the center of the lock catch steel pipe is controlled not to be larger than 5cm, so that the control of later-period errors is facilitated; because pile foundation construction allows the off normal that exists within 5cm, its vertical degree of control during the gap cutting, consequently need adjust the width of side form T template according to the measuring result of actual hasp steel pipe position, be convenient for steel hanging box die block and side form whole transfer smoothly target in place.
In the step 4, the T-shaped plate is slowly lowered and inserted into the lock catch steel pipe, and after the T-shaped plate enters a certain position, the T-shaped plate is converted into a jack for fine adjustment, and finally the jack reaches a preset position
In the step 5, the shear nails are welded in the bottom sealing concrete area outside the steel casing, meanwhile, the gap between the bottom die and the steel casing is sealed underwater, and then the underwater bottom sealing concrete is poured in the bottom sealing concrete area.
In the step 6, a gap between the lock catch steel pipe and the side die T-shaped plate is filled and blocked, then a grouting pipe is inserted into the lock catch steel pipe to the bottom, after the prepared cement mortar is fully stirred, the cement mortar is injected into the lock catch steel pipe through the grouting pipe, in order to ensure the grouting concentration, the grouting pipe is pulled out after thick slurry is discharged from a top opening of the lock catch steel pipe, and the water-stopping grouting operation in the lock catch pipe is completed; meanwhile, after the bottom die and the side die of the steel hanging box are put down in place, the T-shaped plate and the lock catch pipe are welded and fixed as necessary; the cement mortar refers to the ratio of the prestressed pipeline grouting material, and grouting is stopped only when thick slurry is discharged from the upper opening of the lock catch pipe during grouting.
The bottom die comprises a bottom die framework and a bottom die panel positioned on the bottom die framework, and the bottom die water stop movable plate is arranged on the bottom die panel.
The method of the invention also comprises the step 8: after the construction of the beam tying among the piles is finished, the side die is disassembled underwater, and the construction of the next beam tying of the pile can be recycled.
Advantageous effects
The method of the invention is characterized in that: the steel hanging box adopts the overall design, utilizes the steel to protect a section of thick bamboo as the partly of stagnant water structure, follow-up with die block and side form whole insertion, and the steel that has accomplished pile foundation construction protects a section of thick bamboo and is connected into a closed stake straining construction stagnant water structure, can regard as the template of structure to use simultaneously, the construction of straining between the stake of being convenient for. The manufacturing scale of the steel hanging box is greatly reduced, the manufacturing and installation of the structural template are omitted, the whole construction process is convenient and rapid, the construction period is greatly shortened, and the investment of considerable construction cost is reduced.
The technical scheme of the invention is further explained by combining the attached drawings.
Drawings
Fig. 1 is a schematic structural view of a steel suspension box used in the present invention.
Fig. 2 is a schematic structural view of the steel casing.
Fig. 3 is a schematic structural diagram of the assembly of the bottom die, the front side die and the rear side die and the suspension system.
Fig. 4 is a schematic diagram of a side mold configuration.
Fig. 5 is a schematic view of the connection of the end of the side die with the locking steel tube.
Fig. 6 is a schematic view of the bottom mold structure.
Fig. 7 is a schematic view of water stopping construction of the side walls of the bottom die and the steel casing.
FIG. 8 is a schematic view of the pouring of tie-beam concrete between piles in the steel suspension box.
In the figure: 1-a steel casing; 2-enclosing purlin; 3, locking the steel pipe; 4-standard template; 5-T type board; 6-bottom die framework; 7-bottom die panel; 8-bottom die water stop movable plate; 9-cement cloth bag sausage; 10-hanging shoulder pole beam; 11-a jack; 12-an anchor plate; 13-a nut; 14-a boom; 15-suspension fulcrum stiffener; 16-inner support.
Detailed Description
Referring to fig. 1-7, the steel hanging box for stopping water by tying a beam between piles in water, which is adopted by the invention, comprises a steel casing 1, a bottom mould, a front side mould and a rear side mould which are arranged between the steel casing 1, an inner support arranged between the front side mould and the rear side mould and a suspension system connected with the bottom mould; the outer wall of the steel casing 1 is provided with a circumferential enclosing purlin 2 and a vertical lock catch steel pipe 3 with a sealed bottom; the side mold consists of a standard template 4 and T-shaped plates 5 arranged at two side ends of the standard template 4, and the T-shaped plates 5 are formed by welding two angle steels; the bottom die sequentially comprises a bottom die framework 6, a bottom die panel 7 and a bottom die water stop movable plate 8 from bottom to top; the inner support 16 is arranged between the front standard template 4 and the rear standard template 4; the suspension system mainly comprises a suspension shoulder pole beam 10, an anchor plate 12, a nut 13, a suspender 14 and a suspension fulcrum reinforcing plate 15 on the top of the steel casing 1, wherein the suspender 14 is connected with the template framework 6; the lock catch steel pipe 3 is provided with an opening seam, and the side die and the lock catch steel pipe 3 are connected in a matched mode through the T-shaped plate 5 and the opening seam of the lock catch steel pipe 3.
The integral installation method of the underwater steel suspension box provided by the invention adopts the steel suspension box, the construction scheme is shown as the following steps in figure 1, figure 2, figure 3 and figure 4:
1. when the steel casing 1 is manufactured, the enclosing purlin 2 and the lock catch steel pipe 3 are welded in advance at the position of a pile tie beam, wherein the lock catch steel pipe 3 is vertically arranged at the tie beam side of the steel casing 1, a bottom opening of the lock catch steel pipe 3 is welded with a plugging plate, the steel casing 1 and the lock catch steel pipe 3 are welded by one-side full welding, and the steel casing 1 and the outer enclosing purlin 2 are welded discontinuously;
3. the construction of the pile foundation of the steel casing 1 is carried out, the verticality and the plane position of the steel casing are accurate in the lowering process of the steel casing 1, the position of the center of the lock catch steel pipe 3 is controlled not to be larger than 5cm, the control of later-stage errors is facilitated, after the strength of the pile foundation concrete in the steel casing 1 reaches a certain degree, the opening seam of the lock catch steel pipe 3 is cut underwater before the bottom die and the side die are integrally lowered, the width of the seam is about 3cm, the verticality of the steel pipe is controlled during cutting, and meanwhile, the width of the T-shaped plate 5 of the side die is adjusted according to the position of the lock catch steel pipe 3 which is repeatedly measured;
4. Integrally hoisting the assembled bottom die and side die to a pier position by a floating crane, aligning the T-shaped plates 5 at the two ends of the side die with the opening seams of the lock catch steel tubes 3, slowly lowering the T-shaped plates 5 to be inserted into the lock catch steel tubes 3, converting the T-shaped plates into jacks to perform fine adjustment after entering a certain position, and finally reaching a preset position;
5. after the bottom die and the side die are installed in place, a bottom sealing concrete area is formed among the steel casing 1, the bottom die and the side die, a shear nail is welded in the bottom sealing concrete area outside the steel casing 1, so that the friction effect between the bottom sealing concrete and the steel casing is enhanced, the floating force after water pumping is convenient to resist, meanwhile, a gap between the bottom die and the steel casing 1 is plugged under water, a movable water stop plate 8 of the bottom die is adjusted under water to tightly push against the steel casing 1, the gap is plugged by adopting a cement cloth bag sausage 9 and the like, and then the underwater bottom sealing concrete is poured in the bottom sealing concrete area;
6. after the underwater bottom sealing concrete is finished, filling and plugging a gap between the lock catch steel pipe 3 and the side die T-shaped plate 5, then inserting a grouting pipe into the lock catch steel pipe 3 to the bottom, after the prepared cement mortar is fully stirred, injecting the cement mortar into the lock catch steel pipe 3 through the grouting pipe, in order to ensure the grouting concentration, pulling out the grouting pipe after thick slurry is discharged from a top opening of the lock catch steel pipe 3, and finishing the water stopping grouting operation in the lock catch pipe 3; because the last water stopping of the method is concentrated in the lock catch pipe, the T-shaped plate is inserted into the lock catch pipe, and the length of the water seepage path is increased; meanwhile, after the bottom die and the side die of the steel hanging box are put down in place, the T-shaped plate and the lock catch pipe are welded and fixed as necessary; the cement mortar is matched with the prestressed pipeline grouting material;
7. After cement mortar in the lock catch steel pipe 3 is strengthened, water in the steel pile casing and between the side mold and the steel pile casing is drained to form a beam tying dry operation environment between piles, and beam tying concrete is poured to carry out construction of beam tying between piles;
8. after the construction of the beam tying among the piles is finished, the side die is disassembled underwater, and the construction of the next beam tying of the pile can be recycled.
Claims (8)
1. A method for installing a water stop steel hanging box of a tie beam between piles in water is characterized by comprising the following steps:
step 1, welding a surrounding purlin and a lock catch steel pipe in advance at the position of a pile tie beam when the steel pile casing is manufactured, wherein the lock catch steel pipe is vertically arranged at the tie beam side of the steel casing;
step 2, pre-manufacturing a bottom die, a front side die and a rear side die which are arranged between the steel casing, an inner support arranged between the front side die and the rear side die and a suspension system connected with the bottom die, and then integrally assembling and forming; temporarily fixing a bottom die water stop movable plate on a bottom die panel, wherein an inner support is positioned at the top of a tie beam; the side mold consists of a standard template 4 and T-shaped plates arranged at two side ends of the standard template 4, the T-shaped plates are formed by two angle iron resistance welding, and the inner support is arranged between the front standard template and the rear standard template;
step 3, constructing a pile foundation of the steel casing, and cutting an opening seam of the lock catch steel pipe under water before the bottom die and the side die are integrally lowered after the strength of pile foundation concrete in the steel casing reaches a certain degree;
Step 4, integrally hoisting the assembled bottom die and side die to a pier position by using a floating crane, aligning the T-shaped plates at the two ends of the side die with the opening seams of the lock catch steel tubes, and lowering the T-shaped plates to insert the T-shaped plates into the lock catch steel tubes;
step 5, after the bottom die and the side die are installed in place, a bottom sealing concrete area is formed among the steel casing, the bottom die and the side die, and underwater bottom sealing concrete is poured in the bottom sealing concrete area;
step 6, after the underwater bottom sealing concrete is finished, injecting cement mortar into the lock catch steel pipe through the grouting pipe;
and 7, after cement mortar in the lock catch steel pipe is strengthened, pumping water in the steel pile casing and between the side mold and the steel pile casing to form a dry operation environment of the beam tie between the piles, and pouring beam tie concrete to carry out construction of the beam tie between the piles.
2. The method for installing the water-stop steel hanging box of the tie beam between the underwater piles according to claim 1, wherein in the step 1, the purlin surrounding the outer side of the steel casing is determined by calculation according to the construction working condition after water pumping, the purlin surrounding the steel casing is intermittently welded with the steel casing, the lock catch steel pipe is fully welded with the steel casing by foot attachment, and meanwhile, the small-sized triangular plate is reinforced and connected to ensure that the position is not torn and does not leak water.
3. The method for installing the water stopping steel hanging box of the tie beam between the underwater piles according to claim 1, wherein in the step 3, the steel casing is placed downwards, so that the verticality and the plane position of the steel casing are not only ensured to be accurate, but also the position of the center of the lock catch steel pipe is controlled not to be larger than 5cm, and the control of later-stage errors is facilitated; because pile foundation construction allows the off normal that exists within 5cm, its vertical degree of control during the gap cutting, consequently need adjust the width of side form T template according to the measuring result of actual hasp steel pipe position, be convenient for steel hanging box die block and side form whole transfer smoothly target in place.
4. The method for installing the water-stop steel hanging box of the tie beam between the underwater piles according to claim 1, wherein in the step 4, the T-shaped plate is slowly lowered and inserted into the lock catch steel pipe, and after the T-shaped plate enters a certain position, the T-shaped plate is converted into a jack to be finely adjusted, and finally the jack reaches a preset position.
5. The method for installing the water-stop steel hanging box of the inter-underwater-pile beam tie beam according to claim 1, wherein in the step 5, shear nails are welded in the bottom-sealing concrete area outside the steel casing, a gap between the bottom die and the steel casing is sealed underwater, and then underwater bottom-sealing concrete is poured in the bottom-sealing concrete area.
6. The method for installing the water-stop steel hanging box of the underwater inter-pile tie beam according to claim 1, wherein in the step 6, a gap between the lock catch steel pipe and the side die T-shaped plate is filled and blocked, then a grouting pipe is inserted into the lock catch steel pipe to the bottom, after the prepared cement mortar is fully stirred, the cement mortar is injected into the lock catch steel pipe through the grouting pipe, in order to ensure the grouting concentration, the grouting pipe is pulled out after thick slurry is discharged from a top opening of the lock catch steel pipe, and the water-stop grouting operation in the lock catch pipe is completed; meanwhile, after the bottom die and the side die of the steel hanging box are put down in place, the T-shaped plate and the lock catch pipe are welded and fixed as necessary; the cement mortar refers to the ratio of the prestressed pipeline grouting material, and grouting is stopped only when thick slurry is discharged from the upper opening of the lock catch pipe during grouting.
7. The method for installing the water stop steel hanging box of the underwater inter-pile tie beam according to claim 1, which is characterized by further comprising the step 8: after the construction of the beam tying among the piles is finished, the side die is disassembled underwater, and the construction of the next beam tying of the pile can be recycled.
8. The method for installing the water stopping steel hanging box of the tie beam between the underwater piles according to claim 1, wherein the bottom die comprises a bottom die framework and a bottom die panel positioned on the bottom die framework, and the bottom die water stopping movable plate is arranged on the bottom die panel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010568834.8A CN111851504A (en) | 2020-06-19 | 2020-06-19 | Method for installing water stopping steel hanging box of tie beam between piles in water |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010568834.8A CN111851504A (en) | 2020-06-19 | 2020-06-19 | Method for installing water stopping steel hanging box of tie beam between piles in water |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111851504A true CN111851504A (en) | 2020-10-30 |
Family
ID=72987788
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010568834.8A Pending CN111851504A (en) | 2020-06-19 | 2020-06-19 | Method for installing water stopping steel hanging box of tie beam between piles in water |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111851504A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114000525A (en) * | 2021-11-23 | 2022-02-01 | 中国二十二冶集团有限公司 | Construction method of tie beam in water |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201850559U (en) * | 2010-11-06 | 2011-06-01 | 中铁十七局集团第五工程有限公司 | H-shaped light slip jacket slip jacket for constructing tie beam in water |
CN203066095U (en) * | 2013-01-24 | 2013-07-17 | 中交第三航务工程局有限公司南京分公司 | Assembled single-wall steel hanging box |
CN103215962A (en) * | 2013-03-22 | 2013-07-24 | 中铁大桥局集团第五工程有限公司 | Pier stud type pile foundation tie beam steel hanging box cofferdam |
CN105442622A (en) * | 2015-12-15 | 2016-03-30 | 中交一公局桥隧工程有限公司 | Water-retaining construction technology for locked steel pipe piles |
CN109295982A (en) * | 2018-11-15 | 2019-02-01 | 中国二十二冶集团有限公司 | The construction method of binder steel jacket box in water |
CN109594478A (en) * | 2018-12-21 | 2019-04-09 | 中交二航局第二工程有限公司 | Applied to the high-rise pile cap steel lifted trunk bottom sealing method under long-period wave surge condition |
CN209620061U (en) * | 2019-01-07 | 2019-11-12 | 中交第二航务工程局有限公司 | Latch steel-pipe pile and I-shaped sheet pile combined cofferdam structure |
-
2020
- 2020-06-19 CN CN202010568834.8A patent/CN111851504A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201850559U (en) * | 2010-11-06 | 2011-06-01 | 中铁十七局集团第五工程有限公司 | H-shaped light slip jacket slip jacket for constructing tie beam in water |
CN203066095U (en) * | 2013-01-24 | 2013-07-17 | 中交第三航务工程局有限公司南京分公司 | Assembled single-wall steel hanging box |
CN103215962A (en) * | 2013-03-22 | 2013-07-24 | 中铁大桥局集团第五工程有限公司 | Pier stud type pile foundation tie beam steel hanging box cofferdam |
CN105442622A (en) * | 2015-12-15 | 2016-03-30 | 中交一公局桥隧工程有限公司 | Water-retaining construction technology for locked steel pipe piles |
CN109295982A (en) * | 2018-11-15 | 2019-02-01 | 中国二十二冶集团有限公司 | The construction method of binder steel jacket box in water |
CN109594478A (en) * | 2018-12-21 | 2019-04-09 | 中交二航局第二工程有限公司 | Applied to the high-rise pile cap steel lifted trunk bottom sealing method under long-period wave surge condition |
CN209620061U (en) * | 2019-01-07 | 2019-11-12 | 中交第二航务工程局有限公司 | Latch steel-pipe pile and I-shaped sheet pile combined cofferdam structure |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114000525A (en) * | 2021-11-23 | 2022-02-01 | 中国二十二冶集团有限公司 | Construction method of tie beam in water |
CN114000525B (en) * | 2021-11-23 | 2023-08-22 | 中国二十二冶集团有限公司 | Construction method of underwater tie beam |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205742213U (en) | Foundation pit supporting construction | |
CN107338801B (en) | Prestressing force assembled Complex retaining wall structure and construction method | |
CN113550317B (en) | Permanent-temporary combined supporting structure and construction method for open excavation reverse construction foundation pit of large shield starting well | |
CN107119917A (en) | Increase the construction method of basement structure behind strip footing house | |
CN112211319A (en) | Same-layer grouting method for mounting prefabricated shear wall of fabricated building | |
CN109914644A (en) | A kind of assembled heat insulation masonry wall and preparation method thereof | |
CN110924313B (en) | Construction method of bridge foundation cofferdam | |
CN106677162B (en) | A kind of stiffness composite precast slab stake building enclosure | |
CN114215090B (en) | Construction method of raft and pile pressing in closed space | |
CN213448537U (en) | Steel hanging box for sealing water of tie beam between piles in water | |
CN111851504A (en) | Method for installing water stopping steel hanging box of tie beam between piles in water | |
CN104594389A (en) | Post-cast strip external wall plugging structure with elastic water stoppers | |
CN202644531U (en) | Pressure-preloading pile sealing device for static pressure pile of anchor rod | |
CN107326924A (en) | Outer wall of underground structure HCMW engineering methods overlap wall and its construction method | |
CN105113513A (en) | Anti-seepage foundation pit supporting structure and construction method | |
CN213625699U (en) | Basement outer wall waterproof construction structure for reverse construction | |
CN206090534U (en) | Foundation ditch and side slope envelope of prestressing force assembled dysmorphism stake wall | |
CN212452765U (en) | Two-in-one underground pipe gallery structure | |
CN204919582U (en) | Collar tie beam is assembled to portable steel sheet case of special prefabricated filling of air film building | |
CN112177041B (en) | Underground space prefabricated and assembled integral structure and construction method thereof | |
CN210152660U (en) | Hole reinforcing and supporting structure entering underground excavation pipe gallery tunnel from slope | |
CN111851576A (en) | Template support system for tunnel construction | |
CN110512866A (en) | A kind of constructing structure being used to support beam and construction method | |
CN110424408A (en) | A kind of assembled PC plate stake of foundation pit enclosure structure | |
CN218622339U (en) | Prefabricated part for plugging post-cast strip of basement outer wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20201030 |
|
WD01 | Invention patent application deemed withdrawn after publication |