CN111851296A - Steel beam hoisting method - Google Patents

Steel beam hoisting method Download PDF

Info

Publication number
CN111851296A
CN111851296A CN202010573969.3A CN202010573969A CN111851296A CN 111851296 A CN111851296 A CN 111851296A CN 202010573969 A CN202010573969 A CN 202010573969A CN 111851296 A CN111851296 A CN 111851296A
Authority
CN
China
Prior art keywords
steel beam
crane
hoisting
steel
hoisting method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010573969.3A
Other languages
Chinese (zh)
Inventor
杜宪武
杨玉平
周建军
李邓
任晓光
王晶
焦朋乐
王磊冈
陈学彬
莒海彤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Beijing Engineering Group Co Ltd
Tianjin Engineering Co Ltd of China Railway Beijing Engineering Group Co Ltd
Original Assignee
China Railway Beijing Engineering Group Co Ltd
Tianjin Engineering Co Ltd of China Railway Beijing Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Beijing Engineering Group Co Ltd, Tianjin Engineering Co Ltd of China Railway Beijing Engineering Group Co Ltd filed Critical China Railway Beijing Engineering Group Co Ltd
Priority to CN202010573969.3A priority Critical patent/CN111851296A/en
Publication of CN111851296A publication Critical patent/CN111851296A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/36Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/60Derricks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a steel beam hoisting method, which comprises the following steps: s100, paving a crane operation area with steel plates to provide a stable supporting platform; step S200, extending out a suspension arm of the crane and simultaneously descending a lifting hook; step S300, trial hoisting is carried out on the steel beam; s400, binding steel beam components and firmly sleeving ropes at the same time; s500, adopting a pull rope to control stability, and lifting the steel beam component upwards; s600, rotating and moving the crane to a position point, and transporting the steel beam component; step S700, descending a steel beam component; and step S800, untying the rope to finish the hoisting of the steel beam. The invention belongs to the technical field of building construction, and aims to solve the problems of large volume and difficult installation of a steel beam in the prior art. The technical effects achieved are as follows: the steel beam hoisting method is simple and rapid in construction method, effectively achieves hoisting of the steel beam, remarkably improves safety in the construction process, reduces construction period and improves construction quality.

Description

Steel beam hoisting method
Technical Field
The invention relates to the technical field of building construction, in particular to a steel beam hoisting method.
Background
In the existing bridge construction, a cantilever splicing method is usually adopted for construction, and by adopting the method, the rear end of a steel beam needs to be pressed or anchored, so that the temporary engineering quantity is huge. When the method is adopted to construct the large-span steel beam, the front end of the cantilever deforms greatly, and the pier construction at the front end of the cantilever is difficult and dangerous.
In addition, the engineering steel beam has complicated structural body, compact construction period, multiple construction operation surfaces and large transportation difficulty, the engineering steel beams are all ultra-long and ultra-wide, and the whole transportation is difficult to realize; the complexity of the construction environment also puts high demands on the aspects of construction quality, construction period progress, safe production, civilized construction, safety around the site, material equipment entering and leaving the field and the like.
Disclosure of Invention
Therefore, the invention provides a steel beam hoisting method, which aims to solve the problems of large size and difficult installation of a steel beam in the prior art.
In order to achieve the above purpose, the invention provides the following technical scheme:
according to a first aspect of the invention, a steel beam hoisting method comprises the following steps:
s100, paving a crane operation area with steel plates to provide a stable supporting platform;
step S200, extending out a suspension arm of the crane and simultaneously descending a lifting hook;
Step S300, trial hoisting is carried out on the steel beam;
s400, binding steel beam components and firmly sleeving ropes at the same time;
s500, adopting a pull rope to control stability, and lifting the steel beam component upwards;
s600, rotating and moving the crane to a position point, and transporting the steel beam component;
step S700, descending a steel beam component;
and step S800, untying the rope to finish the hoisting of the steel beam.
Further, the thickness of the steel plate used in step S100 is 20 cm.
Further, step S100 specifically includes: removing surface soil, sundries and sludge in the range of a crane before the crane is in place, then adopting coarse gravel or other water seepage materials to tamp in layers, paving a stone powder cushion layer with the thickness of 10cm on the crane, then repeatedly compacting by using a road roller, then paving two layers of lime soil with the thickness of 20cm, and adopting a level gauge to control the flatness of the installation of a foundation formwork when paving concrete.
Further, step 100 specifically includes: after the operation ground is processed, carrying out bearing capacity inspection, and detecting the ground by adopting a static load test or a static sounding test to ensure that the bearing capacity of the foundation meets the operation requirement of the 400-ton crawler crane.
Further, step S300 specifically includes: and (5) hanging to a height of 5 cm-10 cm in a test, and carrying out hovering inspection.
Further, step S400 specifically includes: the steel beam should be firmly bound, the binding points and the gravity centers of the steel beam components should be symmetrical to each other, and the centers of the binding points are aligned with the gravity centers of the objects and are higher than the gravity centers of the components.
Further, step S500 specifically includes: the uniform movement is kept in the hoisting process, and the collision of the peripheral steel beams is avoided.
Further, the step S700 specifically includes that when the crane hoists the steel beam arm rod to rotate, the cable wind rope is tied to the diagonal of the steel beam, the crane arm rod and the steel beam are kept to rotate in parallel, when the crane descends to 1.5m height during loading of the steel beam, manual steering is adopted, and after steering and aligning, the rope is descended to be unhooked.
Further, step S100 specifically includes: four supporting base plates are correspondingly added under the four supporting legs of the crane.
Further, the support base plate is made of Q235B steel plate and 36B hot rolled steel channels.
The invention has the following advantages: the steel beam hoisting method is simple and rapid in construction method, effectively achieves hoisting of the steel beam, remarkably improves safety in the construction process, reduces construction period and improves construction quality.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below. It should be apparent that the drawings in the following description are merely exemplary, and that other embodiments can be derived from the drawings provided by those of ordinary skill in the art without inventive effort.
The structures, ratios, sizes, and the like shown in the present specification are only used for matching with the contents disclosed in the specification, so as to be understood and read by those skilled in the art, and are not used to limit the conditions that the present invention can be implemented, so that the present invention has no technical significance, and any structural modifications, changes in the ratio relationship, or adjustments of the sizes, without affecting the effects and the achievable by the present invention, should still fall within the range that the technical contents disclosed in the present invention can cover.
Fig. 1 is a flowchart of a steel beam hoisting method according to some embodiments of the present invention.
Fig. 2 is a crane structure diagram of a method for hoisting a steel beam according to some embodiments of the present invention.
Detailed Description
The present invention is described in terms of particular embodiments, other advantages and features of the invention will become apparent to those skilled in the art from the following disclosure, and it is to be understood that the described embodiments are merely exemplary of the invention and that it is not intended to limit the invention to the particular embodiments disclosed. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example 1
As shown in fig. 1, the steel beam hoisting method in this embodiment includes the following steps:
s100, paving a crane operation area with steel plates to provide a stable supporting platform;
step S200, extending out a suspension arm of the crane and simultaneously descending a lifting hook;
step S300, trial hoisting is carried out on the steel beam;
s400, binding steel beam components and firmly sleeving ropes at the same time;
s500, adopting a pull rope to control stability, and lifting the steel beam component upwards;
s600, rotating and moving the crane to a position point, and transporting the steel beam component;
step S700, descending a steel beam component;
and step S800, untying the rope to finish the hoisting of the steel beam.
The technical effect that this embodiment reaches does: according to the steel beam hoisting method, the construction method is simple and rapid, the steel beam is effectively hoisted, the safety in the construction process is obviously improved, the construction period is shortened, and the construction quality is improved.
Example 2
As shown in fig. 1 and 2, the steel beam hoisting method in this embodiment includes all the technical features of embodiment 1, and in addition, the steel plate used in step S100 has a thickness of 20cm to protect the road surface from being damaged, so as to prevent the hoisting weight of the crane from being too concentrated to damage the road surface.
Specifically, the steel beam transported to the site is subjected to secondary splicing work, assembled into a hoisting section, the elevation of the pad stone of the main line bridge is retested, and the steel beam support is installed after the elevation is compared with a design value without errors. After the support is installed, re-measuring the elevation of the support; arranging a temporary support; and hoisting the steel beams at different positions in sequence, and unloading and dismantling the temporary support after welding the steel box beam and screwing the high bolt.
In some optional embodiments, step S100 specifically further includes: removing surface soil, sundries and sludge in the range of a crane before the crane is in place, then adopting coarse gravel or other water seepage materials to tamp in layers, paving a stone powder cushion layer with the thickness of 10cm on the crane, then repeatedly compacting by using a road roller, then paving two layers of lime soil with the thickness of 20cm, and adopting a level gauge to control the flatness of the installation of a foundation template when paving concrete; the foundation is ensured to be basically horizontal after pouring, so that the safe construction of a crane is facilitated; if the original surface soil is too wet, the original ground wet soil is turned loose and aired to the optimum water content range for leveling, lime is doped for improvement when the soil quality is poor, then a heavy road roller is adopted for rolling compaction, and the bearing capacity of the foundation is guaranteed to be not less than 241 KPa.
In some optional embodiments, step 100 specifically further includes: after the operation ground is processed, carrying out bearing capacity inspection, and detecting the ground by adopting a static load test or a static sounding test to ensure that the bearing capacity of the foundation meets the operation requirement of the 400-ton crawler crane.
In the implementation process, a crane driver checks whether the operation conditions meet the requirements after boarding, and a specially certified installation mechanic and an electrician check barrier factors influencing the crane operation, check the state of the counterweight and determine the states of all working devices of the crane; checking whether the multiplying power of the lifting hook and the steel wire rope is matched with the hung object; the technical state of the crane is checked, in particular the state of a worktable of the safety protection device is checked, and the functions of the safety protection device are checked by being provided with an electronic moment limit or a safety load indicator. The starting can be carried out only after confirming that each operating lever is at the neutral position (or the clutch is released), and for the crane provided with the energy accumulator and needing to check whether the pressure meets the specified requirement, the crane driver provided with the clutch needs to check whether the function of the clutch can work normally by using the clutch operating handle. At the same time, the clutch must be locked after the clutch is pushed in. The lifting hook is loosened, the arm support is lifted up, the working mechanisms are operated at low speed, the lifting, amplitude variation, stretching and rotation of the working mechanisms and the brake pedal are stably operated, and whether the instruments and the indicator lamps of all parts are normal or not is observed, so that the working can be normally operated when all parts are normal in function.
The beneficial effects in this embodiment are: this embodiment has guaranteed the stability of construction, the safety goes on.
Example 3
As shown in fig. 1 and fig. 2, the steel beam hoisting method in this embodiment includes all the technical features of embodiment 2, and in addition, the step S300 further includes: and when the steel beam is lifted to a height of 5cm to 10cm in an attempt, hovering for checking whether potential safety hazards exist or not, continuing to lift off after the potential safety hazards are confirmed, arranging a lifting point on the steel beam, and connecting the lifting point with a steel wire rope by using a clamping ring during lifting.
In some optional embodiments, step S400 further specifically includes: the steel beam should be firmly bound, the binding points and the gravity centers of the steel beam components should be symmetrical, and the centers of the binding points are aligned with the gravity centers of the objects and are higher than the gravity centers of the components, so that the components are stable after being lifted, and accidents caused by overturning are avoided.
In some optional embodiments, step S500 further specifically includes: the uniform movement is kept in the hoisting process, and the collision of the peripheral steel beams is avoided.
Arranging a cable wind rope: the system is characterized in that 2 cable wind ropes are adopted and bound on steel wire ropes on the side faces of steel beams, when a crane lifts the steel beams, a lifting master commands to closely observe whether the starting points of the steel beams move with lifting waves or not, the interphone commands the rope pulling direction of cable wind ropes pulled by each side to be responsible for people, the steel beams are guaranteed to rotate in the air according to the preset track direction, the steel beams are not touched with un-lifted steel beams, obstacles, crane arms and transport vehicles, and the cable wind ropes can be taken out after the steel beams fall to a lifting person and can hold the steel beams.
The beneficial effects in this embodiment are: the safety of subsequent construction is ensured through trial hoisting; through setting up the guy rope, realized the construction in strong wind weather, guaranteed the security.
Example 4
As shown in fig. 1 and 2, the steel beam hoisting method in this embodiment includes all the technical features of embodiment 3, and in addition, step S700 specifically includes that when the crane rotates the steel beam hoisting arm, the cable wind rope is tied to the diagonal of the steel beam, the crane arm and the steel beam are kept rotating in parallel, when the crane is rope-lowered to 1.5m height when the steel beam is loaded, the crane is manually steered, and after the crane is rope-lowered and aligned, the rope-lowered is unhooked.
The beneficial effects in this embodiment are: through the steps of the embodiment, the construction stability is ensured.
Example 5
As shown in fig. 1 and fig. 2, the steel beam hoisting method in this embodiment includes all the technical features of embodiment 4, and in addition, the step S100 further includes: four supporting base plates are correspondingly added below the four support legs of the crane; the support backing plate is made of Q235B steel plate and 36B hot rolled steel channel.
The beneficial effects in this embodiment are: four 2.5m multiplied by 0.3m support base plates (road base plates) are additionally arranged under four supporting legs of the crane and are used for increasing the stress area and reducing the specific grounding pressure of each supporting leg to the ground.
Although the invention has been described in detail above with reference to a general description and specific examples, it will be apparent to one skilled in the art that modifications or improvements may be made thereto based on the invention. Accordingly, such modifications and improvements are intended to be within the scope of the invention as claimed.
In the present specification, the terms "upper", "lower", "left", "right", "middle", and the like are used for clarity of description, and are not intended to limit the scope of the present invention, and changes or modifications in the relative relationship may be made without substantial changes in the technical content.

Claims (10)

1. A steel beam hoisting method is characterized by comprising the following steps:
s100, paving a crane operation area with steel plates to provide a stable supporting platform;
step S200, extending out a suspension arm of the crane and simultaneously descending a lifting hook;
step S300, trial hoisting is carried out on the steel beam;
s400, binding steel beam components and firmly sleeving ropes at the same time;
s500, adopting a pull rope to control stability, and lifting the steel beam component upwards;
s600, rotating and moving the crane to a position point, and transporting the steel beam component;
Step S700, descending a steel beam component;
and step S800, untying the rope to finish the hoisting of the steel beam.
2. The steel beam hoisting method according to claim 1, wherein the steel plate used in step S100 has a thickness of 20 cm.
3. The steel beam hoisting method according to claim 2, wherein the step S100 further comprises: removing surface soil, sundries and sludge in the range of a crane before the crane is in place, then adopting coarse gravel or other water seepage materials to tamp in layers, paving a stone powder cushion layer with the thickness of 10cm on the crane, then repeatedly compacting by using a road roller, then paving two layers of lime soil with the thickness of 20cm, and adopting a level gauge to control the flatness of the installation of a foundation formwork when paving concrete.
4. The steel beam hoisting method according to claim 3, wherein the step 100 further comprises: after the operation ground is processed, carrying out bearing capacity inspection, and detecting the ground by adopting a static load test or a static sounding test to ensure that the bearing capacity of the foundation meets the operation requirement of the 400-ton crawler crane.
5. The steel beam hoisting method according to claim 1, wherein the step S300 further comprises: and (5) hanging to a height of 5 cm-10 cm in a test, and carrying out hovering inspection.
6. The steel beam hoisting method according to claim 1, wherein the step S400 further comprises: the steel beam should be firmly bound, the binding points and the gravity centers of the steel beam components should be symmetrical to each other, and the centers of the binding points are aligned with the gravity centers of the objects and are higher than the gravity centers of the components.
7. The steel beam hoisting method according to claim 1, wherein the step S500 further comprises: the uniform movement is kept in the hoisting process, and the collision of the peripheral steel beams is avoided.
8. The steel beam hoisting method according to claim 1, wherein the step S700 further comprises the steps of tying a guy rope to the diagonal of the steel beam when the hoisting steel beam arm of the crane rotates, keeping the crane arm and the steel beam rotating in parallel, turning by manual hand when the crane descends to 1.5m height when the steel beam is loaded, and unhooking the rope after the turning is aligned.
9. The steel beam hoisting method according to claim 1, wherein the step S100 further comprises: four supporting base plates are correspondingly added under the four supporting legs of the crane.
10. The method of hoisting a steel beam as claimed in claim 9, wherein the support mat is made of Q235B steel sheet and 36B hot rolled steel.
CN202010573969.3A 2020-06-22 2020-06-22 Steel beam hoisting method Pending CN111851296A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010573969.3A CN111851296A (en) 2020-06-22 2020-06-22 Steel beam hoisting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010573969.3A CN111851296A (en) 2020-06-22 2020-06-22 Steel beam hoisting method

Publications (1)

Publication Number Publication Date
CN111851296A true CN111851296A (en) 2020-10-30

Family

ID=72987303

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010573969.3A Pending CN111851296A (en) 2020-06-22 2020-06-22 Steel beam hoisting method

Country Status (1)

Country Link
CN (1) CN111851296A (en)

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07138914A (en) * 1993-11-11 1995-05-30 Taisei Corp Method for constructing pier
JP2004115179A (en) * 2002-09-25 2004-04-15 Mitsubishi Heavy Ind Ltd Mobile unit crane, and bridge erection method
JP2006009421A (en) * 2004-06-25 2006-01-12 Sumitomo Mitsui Construction Co Ltd Construction method for building by use of tower crane
CN101591887A (en) * 2008-05-30 2009-12-02 上海宝冶建设有限公司 Method for hoisting elevated railway prefabricated U-shaped beam
CN101712436A (en) * 2009-12-22 2010-05-26 中煤建筑安装工程公司第七十三工程处 Steel truss hoisting tool and steel truss hoisting process thereof
CN101845848A (en) * 2010-06-22 2010-09-29 中国建筑第二工程局有限公司 Large-span steel connecting bridge and integral hoisting method thereof
CN102888991A (en) * 2012-10-25 2013-01-23 南通纺织职业技术学院 Large-scale profile steel beam and concrete combined house roof constructing method
CN105645278A (en) * 2016-03-31 2016-06-08 中冶建工集团有限公司 Method for mounting crawler cranes in side slope sites
CN109555106A (en) * 2017-09-25 2019-04-02 中石化重型起重运输工程有限责任公司 The method for processing foundation of mud large scale equipment lifting
CN109720976A (en) * 2018-12-28 2019-05-07 上海二十冶建设有限公司 The installation method of overall skid-mounted formula ice chest in Large Air Separation Devices engineering
CN110027987A (en) * 2019-04-30 2019-07-19 中国十七冶集团有限公司 A kind of arc cantilever steel girder construction method for hanging
CN110258339A (en) * 2019-06-05 2019-09-20 中建八局第三建设有限公司 A kind of overbridge roof beam structure bridge construction method
CN110528390A (en) * 2019-08-14 2019-12-03 中铁六局集团太原铁路建设有限公司 It closes on both wired narrow spaces and sets up T beam construction method
CN110904846A (en) * 2019-12-03 2020-03-24 中铁北京工程局集团有限公司 Continuous beam stub matching prefabricated cantilever splicing linear control method

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07138914A (en) * 1993-11-11 1995-05-30 Taisei Corp Method for constructing pier
JP2004115179A (en) * 2002-09-25 2004-04-15 Mitsubishi Heavy Ind Ltd Mobile unit crane, and bridge erection method
JP2006009421A (en) * 2004-06-25 2006-01-12 Sumitomo Mitsui Construction Co Ltd Construction method for building by use of tower crane
CN101591887A (en) * 2008-05-30 2009-12-02 上海宝冶建设有限公司 Method for hoisting elevated railway prefabricated U-shaped beam
CN101712436A (en) * 2009-12-22 2010-05-26 中煤建筑安装工程公司第七十三工程处 Steel truss hoisting tool and steel truss hoisting process thereof
CN101845848A (en) * 2010-06-22 2010-09-29 中国建筑第二工程局有限公司 Large-span steel connecting bridge and integral hoisting method thereof
CN102888991A (en) * 2012-10-25 2013-01-23 南通纺织职业技术学院 Large-scale profile steel beam and concrete combined house roof constructing method
CN105645278A (en) * 2016-03-31 2016-06-08 中冶建工集团有限公司 Method for mounting crawler cranes in side slope sites
CN109555106A (en) * 2017-09-25 2019-04-02 中石化重型起重运输工程有限责任公司 The method for processing foundation of mud large scale equipment lifting
CN109720976A (en) * 2018-12-28 2019-05-07 上海二十冶建设有限公司 The installation method of overall skid-mounted formula ice chest in Large Air Separation Devices engineering
CN110027987A (en) * 2019-04-30 2019-07-19 中国十七冶集团有限公司 A kind of arc cantilever steel girder construction method for hanging
CN110258339A (en) * 2019-06-05 2019-09-20 中建八局第三建设有限公司 A kind of overbridge roof beam structure bridge construction method
CN110528390A (en) * 2019-08-14 2019-12-03 中铁六局集团太原铁路建设有限公司 It closes on both wired narrow spaces and sets up T beam construction method
CN110904846A (en) * 2019-12-03 2020-03-24 中铁北京工程局集团有限公司 Continuous beam stub matching prefabricated cantilever splicing linear control method

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
劳动和社会保障部中国就业培训技术指导中心: "《起重工(初级、中级)》", 31 March 2004 *
季豪等: "《建筑工程创优使用新技术及应用》", 30 November 2016 *
贾璐等: "《南昌地区复合地层盾构施工技术探索与创新》", 30 November 2017 *
顾满林等: "《石油化工厂设备检修手册 第十一分册 吊装工程》", 30 June 1998 *

Similar Documents

Publication Publication Date Title
US3974618A (en) Method of and means for multi-story building construction
CN201228206Y (en) Self-made small-sized hoisting machine
CN103086279B (en) Vertical transportation construction method for building construction
CA2593286A1 (en) Clamp for a construction apparatus
CN109296374B (en) TBM hoisting and translation method for deep well enclosed space
CN206538126U (en) The large-scale overweight equipment handling constructing device of Super High
CN102530721A (en) Anti-typhoon method for portal crane and special equipment thereof
CN114835016A (en) Lifting equipment for transferring large-scale equipment in basement and mounting construction method thereof
CN111851296A (en) Steel beam hoisting method
CN212175879U (en) Movable foundation pile static load testing device
CN218893051U (en) Step stone traction track device
CN111157211A (en) Large-scale hydraulic pile hammer test bench
CN215291562U (en) Device for high-rise building construction by adopting cantilever crane
CN211001334U (en) Retraction device for rail vehicle or equipment
CN114396057A (en) Static force cutting construction method for high-span foundation pit inner support under trestle bridge
CN210260884U (en) Port crane gust-preventing capability detection device
CN210597062U (en) Old bridge T-shaped beam dismantling and transporting system
CN206917297U (en) A kind of large-span steel girder upper air installing system in place
CN108059088B (en) Method and device for deflection turning and transposition of carrying pole Liang Kongzhong of slot erecting machine
JPS5811221A (en) Method and apparatus for moving mobile crane
CN220642411U (en) ALC panel installation auxiliary device
CN212269274U (en) Tower crane supporting system for reconstruction of existing building
CN114295483B (en) Loading device and loading method for structure performance test of prefabricated laminated slab
CN103255937A (en) Movable lifting communication base station and construction method thereof
CN214939311U (en) Prefabricated bridge pier and beam integrated bridge girder erection machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201030

RJ01 Rejection of invention patent application after publication