CN111779887A - Underground pipeline maintenance method - Google Patents

Underground pipeline maintenance method Download PDF

Info

Publication number
CN111779887A
CN111779887A CN202010673778.4A CN202010673778A CN111779887A CN 111779887 A CN111779887 A CN 111779887A CN 202010673778 A CN202010673778 A CN 202010673778A CN 111779887 A CN111779887 A CN 111779887A
Authority
CN
China
Prior art keywords
hole
pipeline
excavating
tunneling
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010673778.4A
Other languages
Chinese (zh)
Inventor
王黎明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Haoyang Construction Co ltd
Original Assignee
Zhejiang Haoyang Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Haoyang Construction Co ltd filed Critical Zhejiang Haoyang Construction Co ltd
Priority to CN202010673778.4A priority Critical patent/CN111779887A/en
Publication of CN111779887A publication Critical patent/CN111779887A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The application discloses an underground pipeline maintenance method, which comprises the following steps of: excavating around the pipeline in the inspection well, excavating an excavating hole at the periphery of the pipeline, wherein the pipeline is positioned in the excavating hole, the excavating hole is vertical to the inspection well, and the excavating hole is parallel to the pipeline; a supporting step: arranging a plurality of supporting plates in the excavation hole, enclosing supporting rings between the supporting plates, and tightly attaching the outer walls of the supporting rings to the wall of the excavation hole; tunneling: and continuously tunneling along the pipeline, so that the length of the tunneling hole is further increased, a support plate is arranged in the tunneling hole while tunneling, and a support ring surrounded by the support plate is always tightly attached to the hole wall of the tunneling hole. The invention has the following beneficial effects: by adopting the maintenance method of excavating the inlet hole at the inspection well, the road surface does not need to be excavated, collapse does not occur in the excavation process, and the backfilling is carried out after the excavation is finished, so that the probability of subsequent collapse and the probability of pipeline bursting can be greatly reduced.

Description

Underground pipeline maintenance method
Technical Field
The invention relates to the technical field of urban construction, in particular to a maintenance method for underground pipelines.
Background
At present, the city construction process all can bury the pipeline underground, then set up an inspection shaft at every certain distance, the space on the ground has been practiced thrift to the mode of burying the pipeline underground, but bury the pipeline underground and have a problem, must carry out the ground excavation maintenance after the pipeline is damaged (common such as after city water supply pipe damage, all can dig the ground road earlier then maintain), and carry out the ground excavation maintenance and then influence the ground traffic huge, the follow-up reconstruction of ground road after the second excavation is very time-consuming.
The inspection well is arranged in the pipeline at intervals, and the valve and the detection instrument on the pipeline are both positioned in the inspection well, so that the pipeline is convenient to control by maintenance personnel.
Disclosure of Invention
The invention provides a method for maintaining underground pipelines, which aims at solving the problems.
The technical scheme adopted by the invention is as follows:
a method for repairing underground pipelines is characterized by comprising the following steps,
s1 (pre-excavation step): excavating around the pipeline in the inspection well, excavating an excavating hole at the periphery of the pipeline, wherein the pipeline is positioned in the excavating hole, the excavating hole is vertical to the inspection well, and the excavating hole is parallel to the pipeline;
firstly, tunneling along a pipeline in an inspection well, and excavating soil near the pipeline to gradually expose the outer wall of the pipeline;
s2 (supporting step): arranging a plurality of supporting plates in the excavation hole, enclosing supporting rings between the supporting plates, and tightly attaching the outer walls of the supporting rings to the wall of the excavation hole;
because the distance required to be excavated is relatively long in the excavation process, if the excavated part is not effectively supported, collapse can occur after excavation, the supporting plates are arranged, and the supporting plates are used for enclosing a supporting ring to support the excavation hole, so that the excavation hole is ensured not to collapse;
s3 (tunneling step): continuing tunneling along the pipeline to further lengthen the length of the tunneling hole, and arranging a support plate in the tunneling hole while tunneling, wherein a support ring surrounded by the support plate is always tightly attached to the hole wall of the tunneling hole;
the supporting plate is arranged every time a distance is excavated, so that the supporting ring is continuously lengthened in the process that the excavation hole is continuously lengthened, so that the excavation and the supporting can be carried out at the same time, the collapse is effectively avoided, and the excavation speed is greatly improved;
s4 (repair step): repairing or replacing the damaged part of the pipeline;
s5 (backfill step): and backfilling the gap between the pipeline and the support ring.
Because the maintenance and the change of the pipeline are completed, a larger gap exists between the pipeline and the support ring, the existence of the gap easily causes the road surface to collapse, and the existence of the gap easily causes the pipeline to burst due to expansion with heat and contraction with cold, so that the gap between the pipeline and the support ring is backfilled after the maintenance is completed, the collapse can be avoided due to the absence of a cavity, and the probability of burst due to expansion with heat and contraction with cold of the pipeline can be reduced. And the existence of the support ring is equivalent to forming a pressure-bearing protection ring for the pipeline, so that the compressive strength of the ground is higher, and the pipeline is not easy to be fractured by a heavy truck.
In conclusion, by adopting the maintenance method for excavating the excavation inlet hole at the inspection well, the road surface does not need to be excavated, collapse does not occur in the excavation process, and the backfilling is carried out after the excavation is finished, so that the probability of collapse and the probability of pipeline burst can be greatly reduced, and the pipeline is not easy to fracture.
Optionally, the digging hole is a circular digging hole, and the support ring is a circular support ring.
The round tunneling hole is not easy to collapse, and the supporting function of the supporting ring is achieved, so that the probability of collapse in the tunneling process can be effectively reduced.
Optionally, the support plate is a semicircular support plate.
Optionally, a nut is arranged on the outer wall of each support plate, the two support plates on the same circular cross section are fixed through bolts, and a gap between every two adjacent support plates is sealed through cement.
The two supporting plates are fixed together to prevent the supporting plates from sliding in the tunneling hole, and the two adjacent supporting plates are sealed by cement, so that sand and soil are prevented from falling into the supporting ring, and underground water is prevented from seeping into the supporting ring.
Optionally, the diameter of the support ring is 2 times of the diameter of the tunneling hole.
The diameter of the support ring is twice the diameter of the excavation hole, which is convenient for workers to move in the support ring during excavation and is convenient for transporting away soil generated during excavation.
Optionally, the gap between the pipeline and the support ring is backfilled by using a mixture of yellow sand and plain soil.
The backfilling effect by utilizing the mixture of the yellow sand and the plain soil is as follows, because the yellow sand has a good heat insulation effect, the influence of the change of the environmental temperature on the pipeline can be reduced, and simultaneously, after the yellow sand and the plain soil are mixed, the whole mixture has better viscosity relative to the yellow sand, large-scale water and soil loss caused by the seepage of underground water can not be easily caused after filling, and the probability of collapse is reduced.
Optionally, the axis of the pipeline coincides with the axis of the support ring.
Optionally, the support plate is a steel support plate.
The invention has the beneficial effects that: by adopting the maintenance method of excavating the inlet hole at the inspection well, the road surface does not need to be excavated, collapse does not occur in the excavation process, and the backfilling is carried out after the excavation is finished, so that the probability of subsequent collapse and the probability of pipeline bursting can be greatly reduced.
Description of the drawings:
FIG. 1 is a schematic block diagram of the structure of a support plate;
fig. 2 is a schematic view of the excavation process.
The figures are numbered: 1. support plate, 101, nut, 2, pipeline, 3, inspection shaft.
The specific implementation mode is as follows:
the present invention is described in detail below.
The present invention will be further described in detail with reference to fig. 1 and 2, taking the tap water supply pipe of DN400 as an example;
referring to fig. 1, the support plate 1 is a semicircular support plate with an inner radius of 400mm, the support plate is provided with a nut 101, the support plate has a length of 300mm, and is made of steel;
referring to fig. 2, the pipe 2 is perpendicular to the manhole 3;
s1: excavating around the pipeline in the inspection well, excavating an excavating hole at the periphery of the pipeline, wherein the pipeline is positioned in the excavating hole, the excavating hole is vertical to the inspection well, and the excavating hole is parallel to the pipeline;
s2: arranging support plates in a driving hole, enclosing a support ring between the support plates, wherein the outer wall of the support ring is tightly attached to the hole wall of the driving hole, the upper support plate and the lower support plate on the same circular section are fixedly connected by bolts, a gap between every two adjacent support plates is sealed by cement, the support plates enclose the support ring, the outer wall of the support ring is tightly attached to the hole wall of the driving hole, and the axial lead of the support ring is superposed with the axial lead of a pipeline;
s3: continuing tunneling along the pipeline to further lengthen the length of the tunneling hole, arranging support plates in the tunneling hole while tunneling, arranging one support plate at intervals of 30cm, and enabling a support ring surrounded by the support plates to be always attached to the wall of the tunneling hole until a damaged part of the pipeline is excavated;
s4: replacing and maintaining the damaged pipeline;
s5: and mixing the yellow sand and the plain soil, and backfilling a gap between the pipeline and the support ring.
According to the method, the maintenance method of excavating the inlet hole at the inspection well is adopted, the road surface does not need to be excavated, collapse does not occur in the excavating process, and the backfilling is carried out after the excavation is finished, so that the probability of collapse and the probability of pipeline burst can be greatly reduced. And the pipe is less susceptible to fracturing.
The above description is only a preferred embodiment of the present invention, and not intended to limit the scope of the present invention, which is defined by the claims and their equivalents, and can be directly or indirectly applied to other related fields of technology.

Claims (8)

1. A method for repairing underground pipelines is characterized by comprising the following steps,
pre-excavating: excavating around the pipeline in the inspection well, excavating an excavating hole at the periphery of the pipeline, wherein the pipeline is positioned in the excavating hole, the excavating hole is vertical to the inspection well, and the excavating hole is parallel to the pipeline;
a supporting step: arranging a plurality of supporting plates in the excavation hole, enclosing supporting rings between the supporting plates, and tightly attaching the outer walls of the supporting rings to the wall of the excavation hole;
tunneling: continuing tunneling along the pipeline to further lengthen the length of the tunneling hole, and arranging a support plate in the tunneling hole while tunneling, wherein a support ring surrounded by the support plate is always tightly attached to the hole wall of the tunneling hole;
repairing: repairing or replacing the damaged part of the pipeline;
backfilling: and backfilling the gap between the pipeline and the support ring.
2. A method of servicing an underground pipe as claimed in claim 1 wherein the excavation is a circular excavation and the support collars are circular support collars.
3. A method of servicing an underground pipe as claimed in claim 2, wherein the support plate is a semicircular support plate.
4. A method for repairing an underground pipe as claimed in claim 3, wherein nuts are provided on the outer walls of the supporting plates, two supporting plates on the same circular cross-section are fixed by bolts, and the gap between adjacent supporting plates is sealed by cement.
5. A method of servicing underground pipes according to claim 2 wherein the diameter of the support rings is 2 times the diameter of the tunnelling bore.
6. A method of servicing an underground pipeline according to claim 2, in which the gap between the pipeline and the support ring is backfilled with a mixture of yellow sand and plain soil.
7. A method of servicing an underground pipe as claimed in claim 2, in which the axis of the pipe coincides with the axis of the support ring.
8. A method of servicing underground piping according to claim 2, wherein the support plate is a steel support plate.
CN202010673778.4A 2020-07-14 2020-07-14 Underground pipeline maintenance method Pending CN111779887A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010673778.4A CN111779887A (en) 2020-07-14 2020-07-14 Underground pipeline maintenance method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010673778.4A CN111779887A (en) 2020-07-14 2020-07-14 Underground pipeline maintenance method

Publications (1)

Publication Number Publication Date
CN111779887A true CN111779887A (en) 2020-10-16

Family

ID=72767112

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010673778.4A Pending CN111779887A (en) 2020-07-14 2020-07-14 Underground pipeline maintenance method

Country Status (1)

Country Link
CN (1) CN111779887A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509589A (en) * 2009-03-31 2009-08-19 崔同悦 Non-digging pipe repairing method
CN103979880A (en) * 2014-05-30 2014-08-13 济南城建集团有限公司 Pipeline engineering trench backfill material cement all-in-one mixture and preparation method thereof
CN205277460U (en) * 2015-12-29 2016-06-01 中国水电建设集团十五工程局有限公司 Interim strutting arrangement of tunnel excavation
CN108590527A (en) * 2018-04-25 2018-09-28 邳州中燃城市燃气发展有限公司 A kind of method of high-pressure gas pipeline no-dig technique Pipeline Crossing by Horizontal Directional Drilling construction
CN109930608A (en) * 2019-03-05 2019-06-25 云南建投第十二建设有限公司 A kind of pit earthwork excavation method of peat matter weak soil
CN111335898A (en) * 2020-02-24 2020-06-26 中铁工程装备集团有限公司 Trenchless pipeline updating construction system and construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509589A (en) * 2009-03-31 2009-08-19 崔同悦 Non-digging pipe repairing method
CN103979880A (en) * 2014-05-30 2014-08-13 济南城建集团有限公司 Pipeline engineering trench backfill material cement all-in-one mixture and preparation method thereof
CN205277460U (en) * 2015-12-29 2016-06-01 中国水电建设集团十五工程局有限公司 Interim strutting arrangement of tunnel excavation
CN108590527A (en) * 2018-04-25 2018-09-28 邳州中燃城市燃气发展有限公司 A kind of method of high-pressure gas pipeline no-dig technique Pipeline Crossing by Horizontal Directional Drilling construction
CN109930608A (en) * 2019-03-05 2019-06-25 云南建投第十二建设有限公司 A kind of pit earthwork excavation method of peat matter weak soil
CN111335898A (en) * 2020-02-24 2020-06-26 中铁工程装备集团有限公司 Trenchless pipeline updating construction system and construction method

Similar Documents

Publication Publication Date Title
KR20210130725A (en) Reinforcement device and method for local freezing reinforcement in deep pits in gravel strata containing large amounts of water
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
WO2012155727A1 (en) Water conveyance tunnel with prestressed composite lining for shield tunnel
CN110878697A (en) Shield underwater receiving method next to urban main road in high-water-rich sandy gravel stratum
CN106351312A (en) Pipeline and construction method thereof
CN109779653B (en) Construction method for crossing of soft rock large-section tunnel
CN111810200A (en) Shield tunnel expanding and excavating system and method based on middle upright posts and inverted arches
CN112459785B (en) Method for reinforcing existing pipeline penetrating under ultra-shallow buried and undercut tunnel by utilizing municipal well
CN206157860U (en) Drainage pipeline
CN105065774B (en) A kind of underground piping branch connects construction method
CN112727484A (en) Shield-pipe-jacking up-down parallel overlapping tunnel structure and construction method thereof
CN111779887A (en) Underground pipeline maintenance method
CN105804203A (en) Plugging method of deep-buried large-diameter waste water pipeline
CN105605335A (en) Large-caliber prestressed steel cylinder concrete pipe for jacking construction
CN215718752U (en) Utilize municipal well to carry out super shallow reinforced structure who buries under undercut tunnel and wear existing pipeline
CN115614045A (en) Large underground structure constructed by underground excavation in saturated soft soil and construction method thereof
CN210217743U (en) Steel structure sleeve for trenchless construction
CN114592892A (en) Implementation method for pulling out anchor cable of shield tunnel in steel sleeve in soft soil area
CN110552702B (en) Underground excavation construction method for assembled corrugated steel plate underground comprehensive pipe gallery
CN113863268A (en) Construction and debugging process for fabricated sewage treatment station of epidemic prevention emergency project
CN204098067U (en) Side's culvert formula underground pipe gallery
CN207761645U (en) shield pipe gallery system
CN113006085A (en) Supporting-first-excavating foundation pit supporting system for inclined prefabricated steel piles and construction method of supporting-second-excavating foundation pit supporting system
CN112302669A (en) Subway shield arrival auxiliary construction method and structure under complex environment condition
CN113669084B (en) Lake facies deposition weak stratum subway tunnel-first and station-last segment dismantling method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Wang Liming

Inventor after: Guo Xiaoting

Inventor after: Wang Yufei

Inventor after: Wang Gaoyuan

Inventor after: Jiang Zhihua

Inventor before: Wang Liming

CB03 Change of inventor or designer information
RJ01 Rejection of invention patent application after publication

Application publication date: 20201016

RJ01 Rejection of invention patent application after publication