CN111749135A - Integral dismantling method for 0# block bracket of continuous rigid frame bridge - Google Patents

Integral dismantling method for 0# block bracket of continuous rigid frame bridge Download PDF

Info

Publication number
CN111749135A
CN111749135A CN202010480924.1A CN202010480924A CN111749135A CN 111749135 A CN111749135 A CN 111749135A CN 202010480924 A CN202010480924 A CN 202010480924A CN 111749135 A CN111749135 A CN 111749135A
Authority
CN
China
Prior art keywords
bracket
lifting rope
bearing beam
block
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010480924.1A
Other languages
Chinese (zh)
Inventor
李志文
陈松洲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
China Communication South Road and Bridge Co Ltd
Original Assignee
Road and Bridge International Co Ltd
China Communication South Road and Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, China Communication South Road and Bridge Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN202010480924.1A priority Critical patent/CN111749135A/en
Publication of CN111749135A publication Critical patent/CN111749135A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to a method for integrally removing a No. 0 bracket of a continuous rigid frame bridge, wherein when the No. 0 bracket is installed, two shoulder pole beams are welded at the bottom of a bearing beam on the upper layer of the bracket, and two ends of each shoulder pole beam are welded with lifting lugs; when 0# concrete is poured, respectively embedding vertical sleeves at positions of 4 lifting lugs right facing the shoulder pole beam as lifting rope through holes; after the 0# block is poured, a guide wheel and a winch are arranged on the top surface of the 0# block close to each lifting rope through hole, and a lifting rope of the winch bypasses the guide wheel and penetrates through the lifting rope through hole to be connected with a lifting lug of the shoulder pole beam; when the support is dismantled, the upper bearing beam is lifted away from the unloading device, and then the unloading device is taken down; the upper layer bearing beam is lowered to the lower layer bearing beam and is temporarily welded; lifting the bracket integrally upwards, removing the bracket and finally dropping the bracket integrally to the ground. Convenient operation, safety, high efficiency have solved the problem of inefficiency, security difference when present 0# piece bracket is demolishd.

Description

Integral dismantling method for 0# block bracket of continuous rigid frame bridge
Technical Field
The invention relates to the technical field of bridge construction, in particular to a method for integrally removing a No. 0 block bracket of a continuous rigid frame bridge.
Background
Continuous rigid frame bridge is because the pier is high, 0# piece often adopts non-console mode support to be under construction, pre-buried shaped steel is used for installing the bracket when pier shaft construction, when the support was set up, set up lower floor's spandrel girder on the bracket, installation sand section of thick bamboo or wedge unload device such as piece that falls on the spandrel girder of lower floor, it sets up upper spandrel girder to unload to fall on the device, set up the distribution roof beam on the spandrel girder of upper strata, the template is pour to installation 0# piece on the distribution roof beam for the load of upper portion cast in situ concrete passes through the support and all transmits the pier shaft. The method is more suitable for high pier bridge construction, the using amount of support materials can be reduced, the cost is reduced, but in the later stage of support removal, because the support is arranged at the bottom of the No. 0 block, the support cannot be vertically lifted for removal, the support members can be pulled out one by one from the lower part of the No. 0 block only by adopting a dragging method, the efficiency is low, and great safety risks exist in high-altitude operation.
Disclosure of Invention
Aiming at the difficulty in dismantling the 0# block bracket of the continuous rigid frame bridge at present, the invention provides the 0# block bracket overall dismantling method which is convenient to operate and high in safety by comprehensively considering the load of the bracket according to the structural characteristics of the 0# block, so that the construction efficiency is improved, and the construction risk is reduced.
The technical scheme of the invention is as follows:
the integral dismantling method for the No. 0 block bracket of the continuous rigid frame bridge is characterized by comprising the following steps of:
(1) when the No. 0 bracket is installed, two shoulder pole beams perpendicular to the upper bearing beam are symmetrically welded at the bottom of the upper bearing beam of the bracket, and two lifting lugs are welded at two ends of each shoulder pole beam;
(2) when 0# block concrete is poured, respectively embedding sleeves which vertically penetrate through the 0# block in positions, which are opposite to 4 lifting lugs of the shoulder pole beam, in the concrete to serve as lifting rope through holes;
(3) after the concrete of the No. 0 block is poured, a guide wheel is fixedly arranged on one side of each lifting rope through hole on the top surface of the No. 0 block, a winch is arranged corresponding to each guide wheel and is temporarily fixed, one end of a lifting rope is connected with the winch, and the other end of the lifting rope bypasses the guide wheels and penetrates through the lifting rope through holes to be connected with lifting lugs of the shoulder pole beams;
(4) when the support is detached, firstly, the unloading device supporting the upper bearing beam is lowered to lower the height of the top of the bracket, then the winch is started to upwards tighten the lifting rope, the upper bearing beam of the bracket is lifted away from the unloading device through the shoulder pole beam, and then the unloading device is taken down;
(5) the hoisting machine loosens the lifting rope downwards, the upper layer bearing beam is lowered to the lower layer bearing beam of the bracket, and the upper layer bearing beam and the lower layer bearing beam are temporarily welded;
(6) the hoisting machine upwards tightens the lifting rope again, the bracket is integrally lifted upwards, the lower-layer bearing beam is lifted away from the bracket, and then the bracket and the bracket installation embedded part on the pier body are removed;
(7) and the hoisting machine releases the lifting rope downwards again, and the bracket is integrally dropped to the ground to finish the dismounting of the bracket of the No. 0 block.
The invention adopts the winch as a power device, connects the shoulder pole beam through the lifting rope, integrally drops the support, has simple structure, convenient operation, high construction efficiency and good safety, and solves the problems of low efficiency and poor safety when the 0# bracket is dismantled at present.
Drawings
FIG. 1 is a schematic structural view of a bracket integral-dismantling device;
fig. 2 is a schematic view showing a state where the sand cylinder is removed after the carrying pole beam is lifted;
FIG. 3 is a schematic view showing a state where the upper bearing beam falls onto the lower bearing beam after the sand cylinder is removed;
FIG. 4 is a schematic view showing a state where the bracket is lifted integrally to remove the support bracket;
fig. 5 is a schematic view showing a state where the carriage is lowered as a whole.
Detailed Description
The specific embodiment of the invention is as follows:
(1) as shown in fig. 1, the structure of the 0# block bracket generally comprises a lower-layer spandrel girder 1, an unloading device 2, an upper-layer spandrel girder 3 and a distribution girder 4, wherein the lower-layer spandrel girder 1 is supported on a bracket 5 fixed on a pier body along the bridge direction, and the bracket 5 is installed and fixed through an embedded part embedded in the pier body 6; the top surface of the lower bearing beam 1 is provided with a discharging device 2, the discharging device is generally a sand cylinder or a wedge-shaped discharging block and is used for adjusting the elevation of the support during support installation and reducing the height of the support during form removal and support removal; the upper bearing beam 3 is supported on the unloading device 2 in the transverse bridge direction, the distribution beam 4 is erected on the upper bearing beam 3, and the 0# block pouring template is installed on the distribution beam 4.
When the No. 0 bracket is installed, two shoulder pole beams 6 vertical to the upper bearing beam are symmetrically welded at the bottom of the upper bearing beam 3 of the bracket along the bridge direction in advance, and two lifting lugs are welded at two ends of each shoulder pole beam 6.
When the 0# block concrete 11 is poured, sleeves which vertically penetrate through the 0# block are respectively embedded in the concrete at positions right opposite to 4 lifting lugs of the carrying pole beam to serve as lifting rope through holes 7.
After the concrete pouring of the No. 0 block is completed, a guide wheel 8 is fixedly installed on one side, close to each lifting rope through hole 7, of the top surface of the No. 0 block, a winch 9 is installed corresponding to each guide wheel 8 and is temporarily fixed, one end of a lifting rope 10 is connected with the winch and wound on the winch, and the other end of the lifting rope 10 is wound around the guide wheel 8 and penetrates through the lifting rope through hole 7 to be connected with a lifting lug of the carrying pole beam 6.
(2) As shown in fig. 2, when the support is removed, the unloading device for supporting the upper layer bearing beam 3 is lowered to lower the height of the top of the bracket, then the winch 9 is started to tighten the lifting rope 10 upwards, the upper layer bearing beam 3 of the bracket is lifted upwards by a certain height through the shoulder pole beam 6, and the unloading device is lifted off and taken down;
(3) as shown in fig. 3, the hoist 9 releases the lifting rope 10 downward, the upper-layer spandrel girder 3 is lowered onto the lower-layer spandrel girder 1, and the upper-layer spandrel girder 3 and the lower-layer spandrel girder 1 are temporarily welded;
(4) as shown in fig. 4, the hoisting machine 9 again tightens the lifting rope 10 upwards, lifts the bracket upwards as a whole, lifts the lower-layer spandrel girder 1 away from the corbel 5, and then removes the corbel 5 and the corbel installation embedded part on the pier body;
(5) as shown in fig. 5, the hoist 9 again releases the hoist rope 10 downward to drop the entire bracket to the ground, thereby completing the removal of the # 0 bracket.

Claims (1)

1. The integral dismantling method for the No. 0 block bracket of the continuous rigid frame bridge is characterized by comprising the following steps of:
(1) when the No. 0 bracket is installed, two shoulder pole beams perpendicular to the upper bearing beam are symmetrically welded at the bottom of the upper bearing beam of the bracket, and two lifting lugs are welded at two ends of each shoulder pole beam;
(2) when 0# block concrete is poured, respectively embedding sleeves which vertically penetrate through the 0# block in positions, which are opposite to 4 lifting lugs of the shoulder pole beam, in the concrete to serve as lifting rope through holes;
(3) after the concrete of the No. 0 block is poured, a guide wheel is fixedly arranged on one side of each lifting rope through hole on the top surface of the No. 0 block, a winch is arranged corresponding to each guide wheel and is temporarily fixed, one end of a lifting rope is connected with the winch, and the other end of the lifting rope bypasses the guide wheels and penetrates through the lifting rope through holes to be connected with lifting lugs of the shoulder pole beams;
(4) when the support is detached, firstly, the unloading device supporting the upper bearing beam is lowered to lower the height of the top of the bracket, then the winch is started to upwards tighten the lifting rope, the upper bearing beam of the bracket is lifted away from the unloading device through the shoulder pole beam, and then the unloading device is taken down;
(5) the hoisting machine loosens the lifting rope downwards, the upper layer bearing beam is lowered to the lower layer bearing beam of the bracket, and the upper layer bearing beam and the lower layer bearing beam are temporarily welded;
(6) the hoisting machine upwards tightens the lifting rope again, the bracket is integrally lifted upwards, the lower-layer bearing beam is lifted away from the bracket, and then the bracket and the bracket installation embedded part on the pier body are removed;
(7) and the hoisting machine releases the lifting rope downwards again, and the bracket is integrally dropped to the ground to finish the dismounting of the bracket of the No. 0 block.
CN202010480924.1A 2020-05-30 2020-05-30 Integral dismantling method for 0# block bracket of continuous rigid frame bridge Pending CN111749135A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010480924.1A CN111749135A (en) 2020-05-30 2020-05-30 Integral dismantling method for 0# block bracket of continuous rigid frame bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010480924.1A CN111749135A (en) 2020-05-30 2020-05-30 Integral dismantling method for 0# block bracket of continuous rigid frame bridge

Publications (1)

Publication Number Publication Date
CN111749135A true CN111749135A (en) 2020-10-09

Family

ID=72674447

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010480924.1A Pending CN111749135A (en) 2020-05-30 2020-05-30 Integral dismantling method for 0# block bracket of continuous rigid frame bridge

Country Status (1)

Country Link
CN (1) CN111749135A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB946548A (en) * 1959-05-23 1964-01-15 Strabag Bau Ag Methods of constructing concrete bridges and like structures
CN105887694A (en) * 2016-05-20 2016-08-24 中交第航务工程局有限公司 Bridge capping beam bottom formwork demounting device
CN106012852A (en) * 2016-06-15 2016-10-12 江苏燕宁建设工程有限公司 Construction method for overall support removal
CN106368127A (en) * 2016-11-08 2017-02-01 中铁上海工程局集团有限公司 Whole support landing device and method for box girder support
CN205954499U (en) * 2016-08-01 2017-02-15 中国葛洲坝集团第五工程有限公司 Hang and to water bridge 0# piece construction bracket of encorbelmenting
CN110629674A (en) * 2019-06-30 2019-12-31 中国一冶集团有限公司 Method for dismantling integral falling frame of cast-in-place box girder bailey bracket system in highway construction process
CN210066507U (en) * 2019-04-15 2020-02-14 中交路桥建设有限公司 Combined high pier capping beam construction support
CN110820560A (en) * 2018-08-10 2020-02-21 山东中宏路桥建设有限公司 Method for disassembling hoop support of bent cap

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB946548A (en) * 1959-05-23 1964-01-15 Strabag Bau Ag Methods of constructing concrete bridges and like structures
CN105887694A (en) * 2016-05-20 2016-08-24 中交第航务工程局有限公司 Bridge capping beam bottom formwork demounting device
CN106012852A (en) * 2016-06-15 2016-10-12 江苏燕宁建设工程有限公司 Construction method for overall support removal
CN205954499U (en) * 2016-08-01 2017-02-15 中国葛洲坝集团第五工程有限公司 Hang and to water bridge 0# piece construction bracket of encorbelmenting
CN106368127A (en) * 2016-11-08 2017-02-01 中铁上海工程局集团有限公司 Whole support landing device and method for box girder support
CN110820560A (en) * 2018-08-10 2020-02-21 山东中宏路桥建设有限公司 Method for disassembling hoop support of bent cap
CN210066507U (en) * 2019-04-15 2020-02-14 中交路桥建设有限公司 Combined high pier capping beam construction support
CN110629674A (en) * 2019-06-30 2019-12-31 中国一冶集团有限公司 Method for dismantling integral falling frame of cast-in-place box girder bailey bracket system in highway construction process

Similar Documents

Publication Publication Date Title
CN111335187B (en) Construction process for triangular area of open-web rigid frame bridge
CN102912730A (en) Hoisting construction method for single-rib closure rope of large-span reinforced concrete arch bridge
CN112458918A (en) High-pier hydraulic jacking integral steel frame platform formwork turnover construction system and construction method
CN110468743B (en) Movable hanging bracket for transformation of old bridge pier cap and construction method
CN212771960U (en) Whole device of demolising of 0# piece bracket of continuous rigid frame bridge
CN111519545A (en) Pier and capping beam integrated construction platform and construction method thereof
CN103255767B (en) Faceplate sliding formwork with traveling device
CN111749135A (en) Integral dismantling method for 0# block bracket of continuous rigid frame bridge
KR101232704B1 (en) The installation and dismantlement method of main girder for bridge temporary
CN206570700U (en) The continuous lowering system of steel jacket box
CN214329956U (en) Ring rail hoisting device for curtain wall installation
CN209958220U (en) Movable trolley for mounting and dismounting railing
JP4339778B2 (en) How to remove a bridge
CN102102341A (en) Method for constructing viaduct deck
CN111196566A (en) Construction structure and construction method of super high-rise inner climbing tower crane
CN111155433A (en) Method for dismantling movable formwork
CN217629455U (en) Dismantling device and system for box girder template supporting system
CN217148393U (en) Lifting and hoisting device for mounting and dismounting movable formwork
CN216918418U (en) High-altitude non-landing support dismantling system
CN214828576U (en) Self-discharging device for tower crane counterweight
CN113718659B (en) Urban road and bridge construction method
CN210064931U (en) Prefabricated T roof beam template hoist device
CN217710377U (en) Simply supported bridge reinforced structure based on reaction frame traction
CN216474531U (en) Water steel box girder lifting, sliding and installing system with existing bridge penetrating downwards
CN220246713U (en) Beret beam rapid dismantling system for railway protection shed tunnel adding project under limited space

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20201009