CN111622571A - Construction method for pouring reserved plate joint bars on cyclone well pool wall and cantilever plate in stages - Google Patents
Construction method for pouring reserved plate joint bars on cyclone well pool wall and cantilever plate in stages Download PDFInfo
- Publication number
- CN111622571A CN111622571A CN202010318342.3A CN202010318342A CN111622571A CN 111622571 A CN111622571 A CN 111622571A CN 202010318342 A CN202010318342 A CN 202010318342A CN 111622571 A CN111622571 A CN 111622571A
- Authority
- CN
- China
- Prior art keywords
- plate
- bars
- wall
- pool wall
- cantilever
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H7/00—Construction or assembling of bulk storage containers employing civil engineering techniques in situ or off the site
- E04H7/02—Containers for fluids or gases; Supports therefor
- E04H7/18—Containers for fluids or gases; Supports therefor mainly of concrete, e.g. reinforced concrete, or other stone-like material
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F5/00—Sewerage structures
- E03F5/04—Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F5/00—Sewerage structures
- E03F5/10—Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The invention provides a construction method for pouring reserved plate joint bars by stages for a whirlwind well open caisson pool wall and a cantilever plate. Compared with the traditional method, the invention shortens the mounting and dismounting period of the template worker, ensures the construction quality of the reserved plate dowel, improves the labor productivity, reduces the engineering cost and improves the engineering quality.
Description
Technical Field
The invention belongs to the field of construction of a cyclone well open caisson, and particularly relates to a construction method for pouring reserved plate joint bars by stages on a cyclone well pool wall and a cantilever plate.
Background
In the existing traditional construction technology, the construction method for reserving the dowel bars by the platform plate of the pool wall overhanging structure in the construction of the sunk well of the cyclone well is as follows: and reserving the joint bars according to the corresponding holes in the joint bar position template when the template is installed after the installation of the joint bars and the reserved joint bars of the pool wall steel bars and the cantilever beam plate is completed, reserving the joint bars, and planting the joint bars on the steel bars of the pool wall pouring completed back plate. The traditional construction method has the disadvantages that the formwork is provided with holes during the manufacturing of the formwork of the pool wall, the workload of woodworkers is increased, the joint bars reserved in the installation of the formwork correspond to the positions of the holes of the formwork, and the installation and removal operation time of the woodworkers is increased due to the dense space between the joint bars of the formwork; secondly, the plate bar is embedded with bars after the pouring of the pool wall is finished, and the quality factors of the embedded bars are influenced more (construction quality of bar embedding personnel, hole cleaning quality, bar embedding glue quality and the like). Therefore, a construction method for pouring the dowel bars of the reserved plates by stages on the wall of the whirlwind well pool and the cantilever plate, which can reduce the working time of installing and dismantling the templates, improve the labor productivity and ensure the construction quality of the reserved dowel bars, is needed
Disclosure of Invention
The invention aims to solve the technical problem of providing a construction method for pouring the dowel bars of the reserved plates by stages on the wall of the whirlwind well pool and the cantilever plates, which can reduce the working time of installing and dismantling templates, improve the labor productivity and ensure the construction quality of the dowel bars.
The technical scheme adopted by the invention for solving the technical problem is as follows: a construction method for pouring reserved plate joint bars on the wall of a cyclone well and a cantilever plate in stages comprises the following steps:
and 3, removing the side die of the pool wall after the strength of the concrete of the pool wall reaches 30%, chiseling according to the position of the inserted steel bars of the positioning plate and the thickness range of the cantilever plate according to design drawings, chiseling the inserted steel bars of the plate in the chiseling process, correcting the inserted steel bars of the plate and welding or binding and connecting the inserted steel bars of the plate and the cantilever plate steel bars during construction of the cantilever plate.
Further, in the step 3, the chiseling thickness of the chiseling is the thickness of the pool wall steel bar protection layer.
Further, in the step 1, the bending length of the plate joint bar on the reinforcing steel bar at the inner side of the pool wall is greater than that of the reinforcing steel bar at the outer side of the pool wall.
Further, in step 1, the distance between the two bends of the plate joint bar is equal to the thickness of the pool wall.
Further, in the step 2, the formwork installation is carried out after the installation acceptance of the pool wall steel bars and the plate joint bars is qualified, and the pool wall concrete pouring is carried out after the installation acceptance of the formwork is qualified.
Further, in the step 1, the length and the anchoring form of the plate joint bar are set according to drawings and specifications.
According to the construction method, the construction process that the position of the construction joint needs to be roughened when the open caisson pool wall and the inner cantilever beam are poured in stages is utilized, the pool wall is poured after the plate inserted bars are installed and bent in the space with thicker protective layer of the pool wall, and the method that the plate inserted bars are chiseled out and corrected when the construction joint is chiseled out is utilized, so that the installation and dismantling period of a template worker is shortened, the construction quality of the reserved plate inserted bars is guaranteed, the labor productivity is improved, the engineering cost is reduced, and the engineering quality is improved.
Drawings
FIG. 1 is a schematic cross-sectional view of a cell wall according to the present invention;
FIG. 2 is a schematic plan view of the plate grid of the present invention;
fig. 3 is a schematic view of the bent plate bar according to the present invention.
1. Cantilever plate, 2, plate dowel bar, 3, pool wall reinforcing steel bar protective layer, 4, pool wall inner side reinforcing steel bar, 5, pool wall outer side reinforcing steel bar.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 1 to 3, the present embodiment includes a construction method for pouring the dowel bars of the reserved plates in stages on the wall of the cyclone well and the cantilever plate, and includes the following steps:
and 3, removing the side die of the pool wall after the strength of the concrete of the pool wall reaches 30%, chiseling according to the position of the inserted steel bar 2 of the positioning plate and the thickness range of the cantilever plate 1 according to design drawings, chiseling the inserted steel bar according to the thickness of a steel bar protective layer 3 of the pool wall, chiseling the inserted steel bar 2 in the chiseling process, correcting the inserted steel bar 2 of the plate and welding or binding and connecting the inserted steel bar 2 with the plate steel bar of the cantilever beam plate 1 during construction of the cantilever plate 1.
Claims (6)
1. A construction method for pouring reserved plate joint bars on the wall of a cyclone well and a cantilever plate in stages is characterized by comprising the following steps:
step 1, after the tank wall inner side steel bars (4) and the tank wall outer side steel bars (5) of the open caisson of the cyclone well are positioned and installed, the positions of an overhanging plate (1) and a plate inserting bar (2) are positioned according to a design drawing, a plurality of plate inserting bars (2) are arranged along the tank wall inner wall in a same-direction staggered mode, the bending parts at the two ends of the plate inserting bar (2) are respectively arranged at the tank wall inner side steel bars (4) and the tank wall outer side steel bars (5) and fixed, the plate inserting bar (2) is located in the thickness range of the overhanging plate (1), the plate inserting bar (2) is bent and bound into a whole in the same direction on the surface layer in the range of a tank wall steel bar protective layer (3) and is bound and fixed with the main bars of the tank wall inner side steel bars (4) and the tank wall outer side;
step 2, installing the formwork after the installation of the pool wall steel bars (4) and (5) and the plate joint bars (2), and pouring concrete on the pool wall after the installation of the formwork is finished;
and 3, removing the side die of the pool wall after the concrete strength of the pool wall reaches 30%, positioning the positions of the plate insertion ribs (2) and the thickness range of the cantilever plate (1) according to design drawings, chiseling according to the requirements of construction joints, chiseling the plate insertion ribs (2) out in the chiseling process, correcting the plate insertion ribs (2) during construction of the cantilever plate (1), and welding or binding and connecting the plate insertion ribs (2) with the plate ribs of the cantilever plate (1).
2. The construction method for pouring the dowel of the reserved plate by stages for the cyclone well pool wall and the cantilever plate according to claim 1, wherein in the step 3, the chiseling thickness is the thickness of the steel bar protective layer (3) on the pool wall.
3. The construction method for pouring the reserved plate dowel bars between the cyclone well tank wall and the cantilever plate in stages as claimed in claim 1, wherein in the step 1, the plate dowel bars (2) are arranged on the bending length of the steel bars (4) on the inner side of the tank wall and the bending length of the steel bars (5) on the outer side of the tank wall.
4. The construction method for pouring the reserved plate dowel bars between the wall of the cyclone well and the cantilever plate in stages as claimed in claim 1, wherein in the step 1, the distance between two bends of the plate dowel bars (2) is equal to the thickness of the wall of the cyclone well.
5. The construction method for pouring the reserved plate dowel bars by stages for the cyclone well pool wall and the cantilever plate according to claim 1, wherein in the step 2, the pool wall steel bars (4) and (5) and the plate dowel bars (2) are installed and accepted, then the templates are installed, and the pool wall concrete is poured after the templates are installed and accepted.
6. The construction method for pouring the reserved plate dowel bars between the wall of the cyclone well and the cantilever plate in stages as claimed in claim 1, wherein in the step 1, the length and the anchoring form of the plate dowel bars (2) are set according to drawings and specifications.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010318342.3A CN111622571B (en) | 2020-04-21 | 2020-04-21 | Construction method for pouring reserved plate joint bars on cyclone well pool wall and cantilever plate in stages |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010318342.3A CN111622571B (en) | 2020-04-21 | 2020-04-21 | Construction method for pouring reserved plate joint bars on cyclone well pool wall and cantilever plate in stages |
Publications (2)
Publication Number | Publication Date |
---|---|
CN111622571A true CN111622571A (en) | 2020-09-04 |
CN111622571B CN111622571B (en) | 2021-11-16 |
Family
ID=72268912
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010318342.3A Active CN111622571B (en) | 2020-04-21 | 2020-04-21 | Construction method for pouring reserved plate joint bars on cyclone well pool wall and cantilever plate in stages |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111622571B (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08120972A (en) * | 1994-10-25 | 1996-05-14 | Ishikawajima Constr Materials Co Ltd | Segment for underground tank |
CN101372872A (en) * | 2008-10-20 | 2009-02-25 | 中冶实久建设有限公司 | Method for implementing hot rolling swirl pool constructional engineering by top-down method |
CN201351279Y (en) * | 2009-01-07 | 2009-11-25 | 中冶天工建设有限公司 | Circular deep foundation pit support |
CN109113068A (en) * | 2018-10-16 | 2019-01-01 | 中冶南方工程技术有限公司 | A kind of inverse construction joint structure for building construction of deep basal pit |
CN109403632A (en) * | 2018-12-08 | 2019-03-01 | 上海宝冶集团有限公司 | A kind of ground-connecting-wall crown beam and superstructure connection construction method |
-
2020
- 2020-04-21 CN CN202010318342.3A patent/CN111622571B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08120972A (en) * | 1994-10-25 | 1996-05-14 | Ishikawajima Constr Materials Co Ltd | Segment for underground tank |
CN101372872A (en) * | 2008-10-20 | 2009-02-25 | 中冶实久建设有限公司 | Method for implementing hot rolling swirl pool constructional engineering by top-down method |
CN201351279Y (en) * | 2009-01-07 | 2009-11-25 | 中冶天工建设有限公司 | Circular deep foundation pit support |
CN109113068A (en) * | 2018-10-16 | 2019-01-01 | 中冶南方工程技术有限公司 | A kind of inverse construction joint structure for building construction of deep basal pit |
CN109403632A (en) * | 2018-12-08 | 2019-03-01 | 上海宝冶集团有限公司 | A kind of ground-connecting-wall crown beam and superstructure connection construction method |
Non-Patent Citations (3)
Title |
---|
张凤勇,王龙: "《冶金大型旋流池内衬结构逆作法施工技术》", 《施工技术》 * |
百度文库: "《旋流井施工方案》", 《HTTPS://WENKU.BAIDU.COM/VIEW/643B33065527A5E9856A561252D380EB629423E1.HTML?FR=SEARCH-1-INCOME6-PSREC1&FIXFR=3NDRJQWCLK%2B%2F74ES%2F0FFRA%3D%3D#》 * |
袁恺枫: "《钢筋剥肋滚轧直螺纹套筒连接技术在马钢新区热轧旋流池逆作施工中的应用》", 《安徽冶金科技职业学院学报》 * |
Also Published As
Publication number | Publication date |
---|---|
CN111622571B (en) | 2021-11-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110509396B (en) | Laminated slab, laminated slab production equipment and laminated slab production method | |
CN102251664A (en) | One-time forming construction method for cast-in-place stair tread template | |
CN110792164B (en) | Transverse assembling device and method for assembled shear wall | |
CN111733873A (en) | Construction method of assembled subway station | |
CN111622571B (en) | Construction method for pouring reserved plate joint bars on cyclone well pool wall and cantilever plate in stages | |
CN105862912A (en) | Construction method of protective walls of concrete antiskid piles | |
CN209907737U (en) | Reserved joint connecting steel bar connecting mechanism for staged construction of concrete structure | |
CN205915488U (en) | Reserve door and window pouring mold | |
CN211200645U (en) | Easy-to-detach template for cast-in-place reinforced concrete gutter inlet | |
CN214739890U (en) | Steel form for concrete constructional column construction | |
CN210459229U (en) | Support assembled in deep basal pit and trade and prop construction frock | |
CN210459631U (en) | Simple interface of prefabricated concrete structure wall | |
CN213859863U (en) | Prefabricated coincide bottom plate side forms that can cyclic utilization | |
CN210002879U (en) | kinds of steel mould for water-stop tongue-and-groove of upstream face external wall | |
CN212836076U (en) | Two-sided coincide wall windowsill | |
CN210798297U (en) | Floor board connection structure is worn to crane span structure | |
CN219158447U (en) | Assembled wall body conversion layer dowel bar positioning steel plate | |
CN113202299B (en) | Constructional column aluminum die assembly and die supporting method thereof | |
CN210798045U (en) | Prefabricated external wall panel of assembly type structure | |
CN214939231U (en) | Bridge expansion joint notch structure | |
CN218541515U (en) | Cast-in-place stair template reinforcing structure of marking time | |
CN219794382U (en) | Windowsill coping prefabricated building block | |
CN218205715U (en) | Regularization template of entrance to a cave is reserved to face | |
CN221168661U (en) | Curved caisson template | |
CN219732277U (en) | Shelve formula prefabrication owner, secondary beam construction connection structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |