CN111236262A - CSM + TRD underground continuous wall comprehensive construction method - Google Patents

CSM + TRD underground continuous wall comprehensive construction method Download PDF

Info

Publication number
CN111236262A
CN111236262A CN202010182260.0A CN202010182260A CN111236262A CN 111236262 A CN111236262 A CN 111236262A CN 202010182260 A CN202010182260 A CN 202010182260A CN 111236262 A CN111236262 A CN 111236262A
Authority
CN
China
Prior art keywords
trd
soil
shaped steel
continuous wall
underground continuous
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010182260.0A
Other languages
Chinese (zh)
Inventor
邓玉萍
黎佺炜
陈明洋
郭云富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Group Co Ltd
Beijing Engineering Co Ltd of China Railway Construction Group Co Ltd
Original Assignee
China Railway Construction Group Co Ltd
Beijing Engineering Co Ltd of China Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Group Co Ltd, Beijing Engineering Co Ltd of China Railway Construction Group Co Ltd filed Critical China Railway Construction Group Co Ltd
Priority to CN202010182260.0A priority Critical patent/CN111236262A/en
Publication of CN111236262A publication Critical patent/CN111236262A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a CSM + TRD underground continuous wall comprehensive construction method which comprises the steps of deepening design, positioning measurement paying off, guide groove excavation, double-wheel milling cutting, cleaning pebbles by a grab bucket trenching machine, backfilling plain soil, TRD forward cutting, TRD return stirring, TRD stirring and grouting wall forming, H-shaped steel insertion, crown beam construction and H-shaped steel recovery. The invention has the beneficial effects that: the safety and reliability are high, the large-section H-shaped steel is used as a main supporting stress member to be matched with the prestressed anchor rods to bear the force together, and the safety and reliability are high compared with the traditional slope protection pile process; the inserted section steel can be recycled, the use of materials such as traditional concrete is reduced, and the requirement of green construction is met; the undisturbed soil is injected into the cement and stirred and then inserted into the H-shaped steel, so that the time for rotary drilling, reinforcement cage processing, concrete pouring and the like in the traditional process is reduced, and the construction period is saved by more than 20 days compared with the traditional process; the main materials are the leased H-shaped steel, the undisturbed soil and part of cement, the use of concrete and steel bars is reduced compared with the traditional process, and the construction cost is low.

Description

CSM + TRD underground continuous wall comprehensive construction method
Technical Field
The invention relates to a construction method of an underground diaphragm wall, in particular to a CSM + TRD underground diaphragm wall comprehensive construction method, and belongs to the technical field of foundation pit supporting engineering.
Background
With the acceleration of the urban construction process in China, the density of buildings is getting larger and larger, deep foundation pit projects are increasing day by day, high water level areas have higher and higher requirements on foundation pit supporting engineering, the traditional process adopts forms of slope protection piles, three-shaft stirring piles, interlocking piles and the like, the water stop effect, the verticality and the wall forming quality are difficult to control, and the defect of low construction efficiency exists particularly on hard and complex geology, for the existing construction technology, the double-wheel milling deep layer stirring technology is taken as a cement soil deep layer stirring technology newly developed internationally, and is widely applied in a plurality of fields (such as foundation pit engineering, seepage-proofing engineering, foundation treatment and the like) at present, the chain cutter type continuous wall technology can better realize underground continuous grooving stirring wall forming under various complex geological conditions, can effectively solve the problems of peripheral supporting, pressure bearing, seepage-proofing and water stopping of foundation pits, dams and the like, however, at present, the two technologies cannot be combined for construction, so that the problem of construction of foundation pit support piles of large-particle-size pebble beds and gravel beds cannot be solved well.
Disclosure of Invention
The invention aims to solve the problems and provide a CSM + TRD underground continuous wall comprehensive construction method.
The invention realizes the purpose through the following technical scheme: a CSM + TRD underground continuous wall comprehensive construction method comprises the following steps:
the method comprises the following steps of firstly, deepening design, namely deepening design of a soil layer construction section according to geological conditions reported by a geological survey;
positioning, measuring and setting out, namely drawing a foundation pit supporting and setting out diagram according to coordinates and elevation control points provided by a surveying and mapping company, determining a central line and inner and outer side lines of the underground continuous wall by a professional measurer, and positioning a construction control line at the outer side of the foundation pit to serve as a control line of the whole foundation pit supporting construction;
step three, excavating a guide groove, namely excavating the guide groove by adopting a PC200 back-shovel excavator;
step four, double-wheel milling cutting, aligning a milling wheel of double-wheel milling mechanical equipment with a side line of the underground continuous wall, determining the position, then continuously enabling a milling head of the double-wheel milling equipment to go deep into the underground, injecting water and high-pressure air while stirring the double wheels, cutting a soil body to form cement-soil slurry of a rectangular groove section, ensuring that the specific gravity of the slurry is not more than 1.3, and stopping the double-wheel milling equipment from cutting until a pebble layer stops;
the plane tolerance deviation of the milling wheel is not more than +/-30 mm, the verticality deviation of the mast is controlled to be 1/300, the digging sinking speed is not more than 1.2m/min, the lifting speed is not more than 1.8m/min, during lifting, negative pressure cannot be generated in a hole to cause excessive disturbance of a surrounding soil body, the rotation speed and the lifting speed of the milling wheel are matched with each other, and the soil body and a curing agent can be cut and mixed sufficiently;
cleaning pebbles by using a grab bucket trenching machine, grabbing the pebbles by using a GB46 hydraulic grab bucket trenching machine, cleaning a pebble layer and grabbing the pebble layer to a gravel layer;
backfilling plain soil, namely backfilling the plain soil after the grab bucket grabs the plain soil, filling the wall forming groove with the backfilled plain soil, wherein the compaction coefficient of the backfilled plain soil is determined according to the doping amount of cement;
seventhly, carrying out forward cutting on the TRD, cutting to a designed depth after the TRD equipment is installed in place, and re-cutting the backfilled plain soil;
eighthly, performing TRD return-stroke stirring, namely performing return-stroke stirring after the TRD equipment finishes forward cutting;
step nine, TRD stirring and grouting wall forming, and grouting stirring is carried out after TRD return stroke stirring is finished;
the advancing speed of grouting stirring is determined according to the grouting amount, and when the cement mixing amount is 25%, the volume of a groove section corresponding to the grouting amount in unit time and unit travel time is calculated to determine the advancing speed;
step ten, inserting H-shaped steel, wherein the H-shaped steel is inserted in 30min after the construction of the underground continuous wall is finished, and the H-shaped steel is inserted by adopting a firm positioning clamp;
step eleven, constructing the crown beam, processing the steel bars according to design requirements, confirming the binding sequence of the steel bars according to a drawing, binding the steel bars in place according to the design of the drawing after positioning and paying off are finished, supporting the crown beam template on the outer side of the steel bars, backfilling and tamping the lower part of plain soil, and paving a plastic film;
and step twelve, recovering the H-shaped steel, wherein the H-shaped steel is pulled out and recovered by a special hydraulic pulling machine, and gaps formed after the H-shaped steel is pulled out are timely backfilled by fine sand and cement grout.
As a still further scheme of the invention: in the first step, the soil layer is divided into a soft soil layer, a pebble layer and a gravel layer, the soft soil layer is cut by adopting a double-wheel milling deep-layer stirring technology, the pebble layer is grabbed out by adopting a grab grooving machine, and the gravel layer is constructed by adopting the grab grooving machine.
As a still further scheme of the invention: in the third step, the width of the guide groove excavation is 0.8m, the depth is 1m, and the guide groove excavation is arranged along the wall body.
As a still further scheme of the invention: in the fourth step, the allowable deviation of the milling wheel plane is not more than +/-30 mm, the verticality deviation of the mast is controlled at 1/300, the digging sinking speed is not more than 1.2m/min, and the lifting speed is not more than 1.8 m/min.
As a still further scheme of the invention: in the fourth step, the double-wheel milling machine lifts the drill rod moving milling head back and forth while injecting high-pressure air in the cutting and tunneling construction process.
As a still further scheme of the invention: and step five, strictly controlling the sinking position deviation of the grab bucket in the pebble cleaning process of the grab bucket trenching machine.
As a still further scheme of the invention: in the seventh step, the advancing speed is controlled to be 3 cm/min-5 cm/min.
As a still further scheme of the invention: and step eight, mixing the plain soil and the cement soil slurry again through return stirring, wherein the return traveling speed is controlled within 8 cm/min.
As a still further scheme of the invention: and ten steps, in the inserting process of the H-shaped steel, the lower opening of the H-shaped steel is controlled by a positioning card, and two theodolites are arranged at the upper part in the X direction and the Y direction.
The invention has the beneficial effects that: the CSM + TRD underground continuous wall comprehensive construction method is reasonable in design:
1. the safety and reliability are high, the large-section H-shaped steel is used as a main supporting stress member to be matched with the prestressed anchor rods to bear the force together, and the safety and reliability are high compared with the traditional slope protection pile process;
2. the method is green and environment-friendly, the equipment cutting and tunneling process completely enters the cutting and tunneling ditch, the noise and vibration are greatly reduced, the dust control effect is good, the inserted profile steel can be recycled, the use of the traditional materials such as concrete is reduced, and the requirement of green construction is met;
3. the construction period is fast, the undisturbed soil is injected into the cement and stirred and then is inserted into the H-shaped steel, so that the time for rotary drilling, reinforcement cage processing, concrete pouring and the like in the traditional process is greatly reduced, and the construction period is saved by more than 20 days compared with the traditional process;
4. the construction cost is low, and this technique adopts the main material to lease H shaped steel, undisturbed soil and partial cement, reduces the use of concrete, reinforcing bar than traditional technology, and the construction cost is low.
Drawings
FIG. 1 is a schematic flow chart of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1, a comprehensive construction method of "CSM + TRD" underground diaphragm wall includes the following steps:
the method comprises the following steps of firstly, deepening design, namely deepening design of a soil layer construction section according to geological conditions reported by a geological survey;
positioning, measuring and setting out, namely drawing a foundation pit supporting and setting out diagram according to coordinates and elevation control points provided by a surveying and mapping company, determining a central line and inner and outer side lines of the underground continuous wall by a professional measurer, and positioning a construction control line at the outer side of the foundation pit to serve as a control line of the whole foundation pit supporting construction;
step three, excavating a guide groove, namely excavating the guide groove by adopting a PC200 back-shovel excavator;
step four, double-wheel milling cutting, aligning a milling wheel of double-wheel milling mechanical equipment with a side line of the underground continuous wall, determining the position, then continuously enabling a milling head of the double-wheel milling equipment to go deep into the underground, injecting water and high-pressure air while stirring the double wheels, cutting a soil body to form cement-soil slurry of a rectangular groove section, ensuring that the specific gravity of the slurry is not more than 1.3, and stopping the double-wheel milling equipment from cutting until a pebble layer stops;
the plane tolerance deviation of the milling wheel is not more than +/-30 mm, the verticality deviation of the mast is controlled to be 1/300, the digging sinking speed is not more than 1.2m/min, the lifting speed is not more than 1.8m/min, during lifting, negative pressure cannot be generated in a hole to cause excessive disturbance of a surrounding soil body, the rotation speed and the lifting speed of the milling wheel are matched with each other, and the soil body and a curing agent can be cut and mixed sufficiently;
cleaning pebbles by using a grab bucket trenching machine, grabbing the pebbles by using a GB46 hydraulic grab bucket trenching machine, cleaning a pebble layer and grabbing the pebble layer to a gravel layer;
backfilling plain soil, namely backfilling the plain soil after the grab bucket grabs the plain soil, filling the wall forming groove with the backfilled plain soil, wherein the compaction coefficient of the backfilled plain soil is determined according to the doping amount of cement;
seventhly, carrying out forward cutting on the TRD, cutting to a designed depth after the TRD equipment is installed in place, and re-cutting the backfilled plain soil;
eighthly, performing TRD return-stroke stirring, namely performing return-stroke stirring after the TRD equipment finishes forward cutting;
step nine, TRD stirring and grouting wall forming, and grouting stirring is carried out after TRD return stroke stirring is finished;
the advancing speed of grouting stirring is determined according to the grouting amount, and when the cement mixing amount is 25%, the volume of a groove section corresponding to the grouting amount in unit time and unit travel time is calculated to determine the advancing speed;
when the cement mixing amount is 25%, calculating the volume of a groove section corresponding to the grouting amount in unit time and unit travel time, and determining the advancing speed; the depth of the underground continuous wall is 15m, the width is 0.8m, the volume weight of the undisturbed soil body is 1950kg/m3The cement mixing amount is 25%, and the calculation formula of the cement dosage per unit length is as follows:
15m*0.8m*1950kg/m3*25%=5850kg/m
i.e. 5.85t cement per meter needs to be injected
The working efficiency of the background grouting machine is 300kg/min
Calculating the total grouting time t of 19.5min to 5850/300 min
Therefore, the traveling speed should be 19.5min/m or more.
Step ten, inserting H-shaped steel, wherein the H-shaped steel is inserted in 30min after the construction of the underground continuous wall is finished, and the H-shaped steel is inserted by adopting a firm positioning clamp;
step eleven, constructing the crown beam, processing the steel bars according to design requirements, confirming the binding sequence of the steel bars according to a drawing, binding the steel bars in place according to the design of the drawing after positioning and paying off are finished, supporting the crown beam template on the outer side of the steel bars, backfilling and tamping the lower part of plain soil, and paving a plastic film;
and step twelve, recovering the H-shaped steel, wherein the H-shaped steel is pulled out and recovered by a special hydraulic pulling machine, and gaps formed after the H-shaped steel is pulled out are timely backfilled by fine sand and cement grout.
Further, in the embodiment of the present invention, in the first step, the soil layer is divided into three parts, namely a soft soil layer, a pebble layer and a gravel layer, the soft soil layer is cut by using a deep stirring technology of a double-wheel milling machine, the pebble layer is grabbed out by using a grab trenching machine, and the gravel layer is constructed by using the grab trenching machine.
Further, in the third step of the present invention, the width of the trench is 0.8m, the depth is 1m, and the trench is arranged along the wall and can be used as a CSM trench for mixing slurry and replacing water.
Furthermore, in the fourth step of the present invention, the allowable deviation of the plane of the milling wheel is not more than ± 30mm, the deviation of the verticality of the mast is controlled at 1/300, the digging sinking speed is not more than 1.2m/min, the lifting speed is not more than 1.8m/min, excessive disturbance of the surrounding soil body caused by negative pressure generated in the hole during raising is avoided, the rotation speed of the milling wheel is matched with the lifting speed, and the soil body and the curing agent are cut and mixed sufficiently.
Further, in the fourth step of the invention, in the cutting and tunneling construction process of the double-wheel milling machine, the milling head is lifted back and forth to move by lifting the drill rod while injecting high-pressure air, so that the adhesion of clay on the milling head can be avoided.
Further, in the embodiment of the invention, in the fifth step, in the process of cleaning pebbles by the grab bucket trenching machine, the sinking position deviation of the grab bucket is strictly controlled, so that the damage of the grab bucket trenching machine to peripheral soil bodies is avoided, and the bulging phenomenon of subsequent continuous wall trenching is reduced.
Furthermore, in the embodiment of the invention, in the seventh step, the advancing speed is controlled to be 3cm/min to 5cm/min, so that the sufficient cutting of the plain soil is ensured.
Further, in the embodiment of the present invention, in the step eight, the raw soil and the cement-soil slurry are re-mixed by the return stirring, and the return traveling speed is controlled within 8cm/min, so that the raw soil is ensured to be fully contacted with the cement-soil slurry, and the raw soil is ensured to be fully fused with the cement-soil slurry.
Furthermore, in the embodiment of the invention, in the ten steps, in the inserting process of the H-shaped steel, the lower opening of the H-shaped steel is controlled by adopting a positioning card, two theodolites are arranged at the upper part in the X direction and the Y direction, the integral verticality is respectively controlled in the X direction and the Y direction, and the inserting verticality of the H-shaped steel is ensured.
The working principle is as follows: when the CSM + TRD underground continuous wall comprehensive construction method is used, a double-wheel milling deep layer stirring technology (CSM construction technology) is firstly adopted to cut a soil layer, after a large-particle-size pebble layer is cut, a grab bucket grooving machine is adopted to grab out the large-particle-size pebble layer and grab to a designed height, then a TRD technology is adopted to carry out grouting and stirring work on the cement-soil continuous wall, and finally H-shaped steel is inserted to form the underground continuous wall.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (9)

1. A CSM + TRD underground continuous wall comprehensive construction method is characterized in that: the method comprises the following steps:
the method comprises the following steps of firstly, deepening design, namely deepening design of a soil layer construction section according to geological conditions reported by a geological survey;
positioning, measuring and setting out, namely drawing a foundation pit supporting and setting out diagram according to coordinates and elevation control points provided by a surveying and mapping company, determining a central line and inner and outer side lines of the underground continuous wall by a professional measurer, and positioning a construction control line at the outer side of the foundation pit to serve as a control line of the whole foundation pit supporting construction;
step three, excavating a guide groove, namely excavating the guide groove by adopting a PC200 back-shovel excavator;
step four, double-wheel milling cutting, aligning a milling wheel of double-wheel milling mechanical equipment with a side line of the underground continuous wall, determining the position, then continuously enabling a milling head of the double-wheel milling equipment to go deep into the underground, injecting water and high-pressure air while stirring the double wheels, cutting a soil body to form cement-soil slurry of a rectangular groove section, ensuring that the specific gravity of the slurry is not more than 1.3, and stopping the double-wheel milling equipment from cutting until a pebble layer stops;
the plane tolerance deviation of the milling wheel is not more than +/-30 mm, the verticality deviation of the mast is controlled to be 1/300, the digging sinking speed is not more than 1.2m/min, the lifting speed is not more than 1.8m/min, during lifting, negative pressure cannot be generated in a hole to cause excessive disturbance of a surrounding soil body, the rotation speed and the lifting speed of the milling wheel are matched with each other, and the soil body and a curing agent can be cut and mixed sufficiently;
cleaning pebbles by using a grab bucket trenching machine, grabbing the pebbles by using a GB46 hydraulic grab bucket trenching machine, cleaning a pebble layer and grabbing the pebble layer to a gravel layer;
backfilling plain soil, namely backfilling the plain soil after the grab bucket grabs the plain soil, filling the wall forming groove with the backfilled plain soil, wherein the compaction coefficient of the backfilled plain soil is determined according to the doping amount of cement;
seventhly, carrying out forward cutting on the TRD, cutting to a designed depth after the TRD equipment is installed in place, and re-cutting the backfilled plain soil;
eighthly, performing TRD return-stroke stirring, namely performing return-stroke stirring after the TRD equipment finishes forward cutting;
step nine, TRD stirring and grouting wall forming, and grouting stirring is carried out after TRD return stroke stirring is finished;
the advancing speed of grouting stirring is determined according to the grouting amount, and when the cement mixing amount is 25%, the volume of a groove section corresponding to the grouting amount in unit time and unit travel time is calculated to determine the advancing speed;
step ten, inserting H-shaped steel, wherein the H-shaped steel is inserted in 30min after the construction of the underground continuous wall is finished, and the H-shaped steel is inserted by adopting a firm positioning clamp;
step eleven, constructing the crown beam, processing the steel bars according to design requirements, confirming the binding sequence of the steel bars according to a drawing, binding the steel bars in place according to the design of the drawing after positioning and paying off are finished, supporting the crown beam template on the outer side of the steel bars, backfilling and tamping the lower part of plain soil, and paving a plastic film;
and step twelve, recovering the H-shaped steel, wherein the H-shaped steel is pulled out and recovered by a special hydraulic pulling machine, and gaps formed after the H-shaped steel is pulled out are timely backfilled by fine sand and cement grout.
2. The CSM + TRD underground continuous wall comprehensive construction method according to claim 1, characterized in that: in the first step, the soil layer is divided into a soft soil layer, a pebble layer and a gravel layer, the soft soil layer is cut by adopting a double-wheel milling deep-layer stirring technology, the pebble layer is grabbed out by adopting a grab grooving machine, and the gravel layer is constructed by adopting the grab grooving machine.
3. The CSM + TRD underground continuous wall comprehensive construction method according to claim 1, characterized in that: in the third step, the width of the guide groove excavation is 0.8m, the depth is 1m, and the guide groove excavation is arranged along the wall body.
4. The CSM + TRD underground continuous wall comprehensive construction method according to claim 1, characterized in that: in the fourth step, the allowable deviation of the milling wheel plane is not more than +/-30 mm, the verticality deviation of the mast is controlled at 1/300, the digging sinking speed is not more than 1.2m/min, and the lifting speed is not more than 1.8 m/min.
5. The CSM + TRD underground continuous wall comprehensive construction method according to claim 1, characterized in that: in the fourth step, the double-wheel milling machine lifts the drill rod moving milling head back and forth while injecting high-pressure air in the cutting and tunneling construction process.
6. The CSM + TRD underground continuous wall comprehensive construction method according to claim 1, characterized in that: and step five, strictly controlling the sinking position deviation of the grab bucket in the pebble cleaning process of the grab bucket trenching machine.
7. The CSM + TRD underground continuous wall comprehensive construction method according to claim 1, characterized in that: in the seventh step, the advancing speed is controlled to be 3 cm/min-5 cm/min.
8. The CSM + TRD underground continuous wall comprehensive construction method according to claim 1, characterized in that: and step eight, mixing the plain soil and the cement soil slurry again through return stirring, wherein the return traveling speed is controlled within 8 cm/min.
9. The CSM + TRD underground continuous wall comprehensive construction method according to claim 1, characterized in that: and ten steps, in the inserting process of the H-shaped steel, the lower opening of the H-shaped steel is controlled by a positioning card, and two theodolites are arranged at the upper part in the X direction and the Y direction.
CN202010182260.0A 2020-03-16 2020-03-16 CSM + TRD underground continuous wall comprehensive construction method Pending CN111236262A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010182260.0A CN111236262A (en) 2020-03-16 2020-03-16 CSM + TRD underground continuous wall comprehensive construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010182260.0A CN111236262A (en) 2020-03-16 2020-03-16 CSM + TRD underground continuous wall comprehensive construction method

Publications (1)

Publication Number Publication Date
CN111236262A true CN111236262A (en) 2020-06-05

Family

ID=70873486

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010182260.0A Pending CN111236262A (en) 2020-03-16 2020-03-16 CSM + TRD underground continuous wall comprehensive construction method

Country Status (1)

Country Link
CN (1) CN111236262A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114718083A (en) * 2022-04-08 2022-07-08 中交天津港湾工程研究院有限公司 Construction method of foundation pit support anti-seepage composite structure of highly permeable layer foundation
CN115059106A (en) * 2022-06-30 2022-09-16 中煤科工集团西安研究院有限公司 Construction device and construction method for in-situ stratum deformable water interception curtain

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103938617A (en) * 2014-05-21 2014-07-23 中鼎国际工程有限责任公司 Super-deep underground continuous wall and construction method thereof
CN105178288A (en) * 2015-07-31 2015-12-23 中铁隧道集团有限公司 Construction method of underground continuous wall below viaduct
CN108589699A (en) * 2018-04-20 2018-09-28 浙江大学城市学院 A kind of interpolation H profile steel TRD walls and its construction method
WO2019017498A1 (en) * 2017-07-20 2019-01-24 Giken Ltd. Method for constructing continuous underground wall and steel pipe pile

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103938617A (en) * 2014-05-21 2014-07-23 中鼎国际工程有限责任公司 Super-deep underground continuous wall and construction method thereof
CN105178288A (en) * 2015-07-31 2015-12-23 中铁隧道集团有限公司 Construction method of underground continuous wall below viaduct
WO2019017498A1 (en) * 2017-07-20 2019-01-24 Giken Ltd. Method for constructing continuous underground wall and steel pipe pile
CN108589699A (en) * 2018-04-20 2018-09-28 浙江大学城市学院 A kind of interpolation H profile steel TRD walls and its construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
姜树震: ""CSM+TRD"技术在全鑫园工程基坑支护中的应用", 《铁道建筑技术》 *
张凤龙: "《软弱地层超大深基坑地下车站施工综合技术》", 30 June 2015 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114718083A (en) * 2022-04-08 2022-07-08 中交天津港湾工程研究院有限公司 Construction method of foundation pit support anti-seepage composite structure of highly permeable layer foundation
CN115059106A (en) * 2022-06-30 2022-09-16 中煤科工集团西安研究院有限公司 Construction device and construction method for in-situ stratum deformable water interception curtain
CN115059106B (en) * 2022-06-30 2023-11-17 中煤科工集团西安研究院有限公司 Construction device and construction method of in-situ stratum deformable water interception curtain

Similar Documents

Publication Publication Date Title
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
WO2022096024A1 (en) Construction method for super-long small-diameter hole bored pile
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN110952528A (en) Construction method of cement-soil underground continuous wall under complex geological conditions
CN113669073B (en) Construction method for controlling adjacent building deformation of water-rich sandy stratum by tunneling before station
CN113266392B (en) Pipe jacking construction method for penetrating through existing anchor cable group
CN101343868A (en) Underground continuous wall construction method of city-across pipeline
CN111705786A (en) Method for vertical combination construction of composite stratum underground continuous wall and cast-in-situ bored pile
CN112064751A (en) Deep groove construction method for drainage pipeline
CN111236262A (en) CSM + TRD underground continuous wall comprehensive construction method
CN112281810A (en) Construction method of underground diaphragm wall with water-rich fine sand layer
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN110747848A (en) Construction method of gravel layer foundation deep cement mixing pile diaphragm wall
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN218060412U (en) Utility tunnel enclosure wall construction structures
CN208293588U (en) A kind of Cut Slopes of Expansive Soil reinforcement formula, which is changed, fills out compages
CN115627788A (en) TRD (blast furnace pressure recovery device) reinforcement construction method for metro section connection channel
CN113266362B (en) Top pipe cover excavation construction method for penetrating through existing dense anchor cable area
CN114232602A (en) Underground continuous pile construction process
CN211171922U (en) Construction structure for improving stability of groove wall
CN114016495A (en) Construction method for underground continuous wall system under weak geological conditions in sea reclamation area
CN111749229A (en) Construction method of ultra-deep equal-thickness cement soil wall capable of falling into rock
CN113404043A (en) Construction method of full-rotation full-casing drilling machine suitable for karst cave geology
CN113089645B (en) Slotted hole structure system for reinforcing concrete impervious wall by penetrating silt layer and construction method
CN212688964U (en) Deep and large foundation pit sinking construction system for complex urban environment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200605

RJ01 Rejection of invention patent application after publication