CN110777800A - Construction method for dismantling foundation pit concrete purlin - Google Patents

Construction method for dismantling foundation pit concrete purlin Download PDF

Info

Publication number
CN110777800A
CN110777800A CN201911063672.6A CN201911063672A CN110777800A CN 110777800 A CN110777800 A CN 110777800A CN 201911063672 A CN201911063672 A CN 201911063672A CN 110777800 A CN110777800 A CN 110777800A
Authority
CN
China
Prior art keywords
concrete
purlin
concrete purlin
foundation pit
pvc pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911063672.6A
Other languages
Chinese (zh)
Inventor
刘建
乔国强
王栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201911063672.6A priority Critical patent/CN110777800A/en
Publication of CN110777800A publication Critical patent/CN110777800A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention relates to the technical field of foundation pit construction, in particular to a foundation pit concrete purlin dismantling construction method. When the concrete enclosing purlin is constructed, PVC pipes are vertically bound at the position, close to the enclosing structure, of the concrete enclosing purlin to serve as rope penetrating holes of a cutting machine for positioning and segmenting, and then U-shaped ribs are pre-embedded to serve as hanging points. After the construction of the main body structure is finished, a scaffold is erected at the bottom of the concrete purlin to serve as a supporting system, expansion bolts are arranged at proper positions on the concrete purlin to fix a cutting machine, and cutting ropes are connected after penetrating through PVC pipes. And starting a cutting machine to cut off the concrete purlin in sections, and lifting the concrete purlin out in sections through the U-shaped ribs, so that the concrete purlin is finally dismantled. The method has the advantages of short construction period, high construction safety, no environmental pollution and the like, and has good popularization prospect and wide application range. The invention is mainly applied to the aspect of dismantling the concrete purlin.

Description

Construction method for dismantling foundation pit concrete purlin
Technical Field
The invention relates to the technical field of foundation pit construction, in particular to a foundation pit concrete purlin dismantling construction method.
Background
In a foundation pit supporting system, the rigidity of the enclosing purlin has a great influence on the rigidity of the whole supporting structure, and in order to ensure the overall stability of the enclosure structure, more and more concrete enclosing purlins are used for replacing steel enclosing purlins to appear in the design and construction of the foundation pit supporting system. At present, the traditional method for breaking the concrete purlin is mechanical breaking and manual breaking, vibration, noise and dust generated by the mechanical breaking not only affect a main body structure and have large influence on the surrounding environment, but also can affect surrounding building enclosures to affect a foundation pit supporting system, and meanwhile, the machine walks on a plate to be not beneficial to protecting finished products and embedded pipes. When the concrete purlin is broken manually, the labor intensity is high, the labor amount is large, the generated dust is not easy to control, and the construction period is long due to the cleaning of later-stage residues and waste steel bars.
Disclosure of Invention
In order to overcome the defects in the prior art, the invention provides the construction method for dismantling the concrete purlin, which protects the stability of the existing structure when the concrete purlin is dismantled, and has the advantages of low labor intensity, short construction period and little pollution.
In order to solve the technical problems, the technical scheme adopted by the invention is as follows:
a foundation pit concrete purlin dismantling construction method is characterized by comprising the following steps:
a. before the concrete is poured into the concrete purlin, the PVC pipes are firmly and vertically tied, the PVC pipes are tightly attached to the inner side of the enclosure structure, the bottom of each PVC pipe is flush with the bottom of the concrete purlin, the top of each PVC pipe is higher than the top of the concrete purlin, one PVC pipe is tied to each section of the concrete purlin, and the two ends of each PVC pipe are bound by adhesive tapes so as to prevent the PVC pipes from being blocked by reverse pouring when the concrete is poured;
b. when the concrete purlin is bound with reinforcing steel bars, U-shaped ribs are welded on the two sides of the vertical main ribs, so that the concrete purlin can be conveniently lifted in a segmented mode and inserted in a shackle, and the U-shaped ribs are arranged at intervals in the middle of the concrete purlin;
c. during the construction of a foundation pit main body, after the construction of a main body structure is finished, a support bracket is erected at the bottom of the concrete purlin by adopting a steel pipe fastener scaffold, and the top surface of the bracket is erected in a manner of clinging to the concrete purlin;
d. after the scaffold is built, installing expansion screws at proper positions, fixing a cutting machine and a guide wheel, erecting the cutting machine, penetrating the disconnected cutting rope into two adjacent preformed holes for connection, and starting a rope saw cutting machine to cut off the concrete purlin in sections;
e. when the cutting is carried out, a truck crane is arranged to enter the site, the hoisting buckles are clamped into the U-shaped ribs, and the concrete purlin is lifted out in sections and loaded for outward transportation.
The PVC pipe in the step a is a PVC pipe of DN25 model.
And c, arranging one PVC pipe in the step a every 2 meters.
And c, arranging the U-shaped ribs in the step b at the middle part of the concrete purlin every 1.5 meters.
Compared with the prior art, the invention has the beneficial effects that:
the construction operation speed is fast, the noise is low, no vibration exists, the dust and waste gas pollution is small during the site construction, the cut is straight and smooth, the post-processing treatment is not needed, the convenience is provided for the treatment after the cut surface, the protection of the embedded pipe fitting of the existing structure of the bottom plate is facilitated, and the method has the advantages of low construction cost, good effect and better popularization prospect.
Drawings
FIG. 1 is a plan view of the present invention in construction;
FIG. 2 is a cross-sectional view of the construction of the present invention;
in the figure: the concrete enclosing structure comprises an enclosing structure 1, a concrete enclosing purlin 2, a PVC pipe 3, a U-shaped rib 4, a cutting machine guide wheel 5, a cutting rope 6, a scaffold 7 and a main structure 8.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 1 and 2, a construction method for dismantling a foundation pit concrete purlin includes the following steps:
a. reserving a stringing hole, and positioning and segmenting. Before the concrete surrounding purlin 2 is poured with concrete, a binding wire is adopted to vertically bind the PVC pipe 3 tightly and tightly to the inner side of the enclosure structure 1, the bottom of the PVC pipe 3 is flush with the bottom of the concrete surrounding purlin 2, the top of the PVC pipe is 20mm higher than the top mark of the concrete surrounding purlin 2, and two ends of the PVC pipe are bound by transparent adhesive tapes to prevent the PVC pipe 3 from being blocked by reverse pouring when the concrete is poured;
b. and pre-burying U-shaped ribs 4. When the concrete purlin 2 steel bars are bound, U-shaped phi 28 round steel is welded on the two sides of the vertical main steel bars of the concrete purlin 2, the elevation of the vertical main steel bars is 100mm higher than the top surface of the concrete purlin 2, and the concrete purlin 2 can be conveniently lifted in a segmented mode and can be conveniently broken off and penetrated.
c. And (4) building a concrete surrounding purlin 2 supporting system. During the construction of the foundation pit main body, after the construction of the main body structure 8 is finished, a support bracket is erected at the bottom of the concrete purlin 2 by adopting a phi 48 multiplied by 3.0 steel pipe fastener scaffold 7, and the top surface of the bracket is erected close to the concrete purlin 2 so as to ensure the safety of the bracket in the cutting process.
d. And cutting off the concrete purlin 2. After the scaffold 7 is built, the cutting machine is erected, firstly, people are arranged to clean the cutting rope through holes to enable the cutting rope to be smooth, and expansion screws are installed at proper positions to be used for fixing the cutting machine and the cutting machine guide wheels 5. And erecting a cutting machine, penetrating the disconnected cutting rope 6 into two adjacent preformed holes, connecting, and starting the rope saw cutting machine to cut off the concrete purlin 2 in sections.
e. And hoisting the concrete enclosing purlin 2. When the cutting reaches a certain stage, a 50T truck crane is arranged to enter the field. The hoisting buckle is clamped into the U-shaped rib 4, and the concrete purlin 2 is hoisted out in sections and loaded for outward transportation.
Preferably, the PVC pipe 3 in the step a is a PVC pipe 3 of DN25 model.
Preferably, the PVC pipes 3 are arranged at intervals of 2 meters in the step a.
Preferably, the U-shaped ribs 4 in the step b are arranged at the middle part of the concrete purlin at intervals of 1.5 meters.
Although only the preferred embodiments of the present invention have been described in detail, the present invention is not limited to the above embodiments, and various changes can be made without departing from the spirit of the present invention within the knowledge of those skilled in the art, and all changes are encompassed in the scope of the present invention.

Claims (4)

1. A foundation pit concrete purlin dismantling construction method is characterized by comprising the following steps:
before the concrete is poured into the concrete purlin, the PVC pipes are firmly and vertically tied, the PVC pipes are tightly attached to the inner side of the enclosure structure, the bottom of each PVC pipe is flush with the bottom of the concrete purlin, the top of each PVC pipe is higher than the top of the concrete purlin, one PVC pipe is tied to each section of the concrete purlin, and the two ends of each PVC pipe are bound by adhesive tapes so as to prevent the PVC pipes from being blocked by reverse pouring when the concrete is poured;
when the concrete purlin is bound with reinforcing steel bars, U-shaped ribs are welded on the two sides of the vertical main ribs, so that the concrete purlin can be conveniently lifted in a segmented mode and inserted in a shackle, and the U-shaped ribs are arranged at intervals in the middle of the concrete purlin;
during the construction of a foundation pit main body, after the construction of a main body structure is finished, a support bracket is erected at the bottom of the concrete purlin by adopting a steel pipe fastener scaffold, and the top surface of the bracket is erected in a manner of clinging to the concrete purlin;
after the scaffold is built, installing expansion screws at proper positions, fixing a cutting machine and a guide wheel, erecting the cutting machine, penetrating the disconnected cutting rope into two adjacent preformed holes for connection, and starting a rope saw cutting machine to cut off the concrete purlin in sections;
when the cutting is carried out, a truck crane is arranged to enter the site, the hoisting buckles are clamped into the U-shaped ribs, and the concrete purlin is lifted out in sections and loaded for outward transportation.
2. The foundation pit concrete purlin dismantling construction method according to claim 1, characterized in that: the PVC pipe in the step a is a PVC pipe of DN25 model.
3. The foundation pit concrete purlin dismantling construction method according to claim 1, characterized in that: and c, arranging one PVC pipe in the step a every 2 meters.
4. The foundation pit concrete purlin dismantling construction method according to claim 1, characterized in that: and c, arranging the U-shaped ribs in the step b at the middle part of the concrete purlin every 1.5 meters.
CN201911063672.6A 2019-11-04 2019-11-04 Construction method for dismantling foundation pit concrete purlin Pending CN110777800A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911063672.6A CN110777800A (en) 2019-11-04 2019-11-04 Construction method for dismantling foundation pit concrete purlin

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911063672.6A CN110777800A (en) 2019-11-04 2019-11-04 Construction method for dismantling foundation pit concrete purlin

Publications (1)

Publication Number Publication Date
CN110777800A true CN110777800A (en) 2020-02-11

Family

ID=69388652

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911063672.6A Pending CN110777800A (en) 2019-11-04 2019-11-04 Construction method for dismantling foundation pit concrete purlin

Country Status (1)

Country Link
CN (1) CN110777800A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997063A (en) * 2020-08-21 2020-11-27 上海市机械施工集团有限公司 Static cutting method for pre-buried pipe-penetrating type concrete structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104963344A (en) * 2015-07-17 2015-10-07 江苏江都建设集团有限公司 Deep foundation pit underground construction method allowing concrete support removal and structure construction to be conducted simultaneously
CN108560560A (en) * 2018-05-02 2018-09-21 中铁北京工程局集团城市轨道交通工程有限公司 A kind of method for dismounting of foundation pit enclosure structure
CN109267764A (en) * 2018-11-05 2019-01-25 中建设集团有限公司 Engineering method is cut and disassembled in reinforced concrete support mechanization
CN109356167A (en) * 2018-11-22 2019-02-19 深圳市福田建安建设集团有限公司 Brace in Deep Footing Groove removes system and construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104963344A (en) * 2015-07-17 2015-10-07 江苏江都建设集团有限公司 Deep foundation pit underground construction method allowing concrete support removal and structure construction to be conducted simultaneously
CN108560560A (en) * 2018-05-02 2018-09-21 中铁北京工程局集团城市轨道交通工程有限公司 A kind of method for dismounting of foundation pit enclosure structure
CN109267764A (en) * 2018-11-05 2019-01-25 中建设集团有限公司 Engineering method is cut and disassembled in reinforced concrete support mechanization
CN109356167A (en) * 2018-11-22 2019-02-19 深圳市福田建安建设集团有限公司 Brace in Deep Footing Groove removes system and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997063A (en) * 2020-08-21 2020-11-27 上海市机械施工集团有限公司 Static cutting method for pre-buried pipe-penetrating type concrete structure

Similar Documents

Publication Publication Date Title
CN106088148B (en) Pipe gallery template and its application
CN111155451A (en) Method for dismantling highway-span iron bridge
CN109184189A (en) A kind of diameter Silo conical shell silo roof construction method
CN110359671B (en) Construction method of assembled rail top air duct
CN113279582A (en) Hanging construction method for overhanging and hanging type cast-in-place plate
CN110777800A (en) Construction method for dismantling foundation pit concrete purlin
CN213173317U (en) Be used for T roof beam wet seam construction equipment of encorbelmenting
JP6027389B2 (en) Foundation structure built using the frame of an existing structure
JPH08134848A (en) Execution method of steel pipe-concrete composite structure pier
CN218508158U (en) Can have enough to meet need concatenation formula construction pavement
CN216549362U (en) Assembling and hoisting device for components above foundation pit
CN106522566B (en) A kind of roof system steel truss sliding rail and assembly and disassembly methods
CN206279441U (en) A kind of high speed railway box beam bridge floor pre-fabricated electric cables groove
CN105421780B (en) A kind of construction method of prefabricated concrete structure
CN106284372A (en) The method for supporting of roof plate template during a kind of electric power ditch is integrated poured
CN211143121U (en) Prefabricated rail top air duct structural unit
CN210685282U (en) Prefabricated rail top air duct assembly structure
CN106592438A (en) Two-column pier and middle tie beam construction method employing integral movement of trusses
CN207846906U (en) A kind of prefabricated Reinforced Concrete Plate Stairs
CN112627543A (en) Shaft inner lifting frame for mounting steel beams of core tube elevator shaft and steel beam construction method
JP2004003186A (en) Building structure with track guide disposed therein
CN206319622U (en) A kind of roof system steel truss sliding rail
KR20040076245A (en) Wall structure with method of R.C steel reinforcing ground assembly(assembly plant) the method of estalishment with pulling up
KR20210068283A (en) Structural Systems and Methods for Floor Structural Work in Elevator Machine Room of Apartment Housing
CN209737905U (en) Prefabricated mould of hot water backward flow well decorative wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200211

RJ01 Rejection of invention patent application after publication