CN110565594A - Method for dispatching transformer substation flood control gate - Google Patents

Method for dispatching transformer substation flood control gate Download PDF

Info

Publication number
CN110565594A
CN110565594A CN201910789193.6A CN201910789193A CN110565594A CN 110565594 A CN110565594 A CN 110565594A CN 201910789193 A CN201910789193 A CN 201910789193A CN 110565594 A CN110565594 A CN 110565594A
Authority
CN
China
Prior art keywords
flood
model
area
transformer substation
gate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910789193.6A
Other languages
Chinese (zh)
Inventor
石军
张洋
王晓惠
程春龙
沈旭伟
巫黎明
潘晓春
徐君民
王鹏
刘灿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Energy Engineering Group Jiangsu Power Design Institute Co Ltd
Original Assignee
China Energy Engineering Group Jiangsu Power Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Energy Engineering Group Jiangsu Power Design Institute Co Ltd filed Critical China Energy Engineering Group Jiangsu Power Design Institute Co Ltd
Priority to CN201910789193.6A priority Critical patent/CN110565594A/en
Publication of CN110565594A publication Critical patent/CN110565594A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B1/00Equipment or apparatus for, or methods of, general hydraulic engineering, e.g. protection of constructions against ice-strains
    • E02B1/02Hydraulic models
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/20Movable barrages; Lock or dry-dock gates

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Barrages (AREA)

Abstract

the invention discloses a method for dispatching a transformer substation flood control gate, which belongs to the field of power engineering flood control engineering and comprises the following steps: establishing a rainfall runoff model and a coupling model of a one-dimensional hydrodynamic model and a two-dimensional hydrodynamic model of an area where the transformer substation is located; acquiring rainfall forecast data within a preset time, making a time sequence file, inputting the time sequence file into a rainfall runoff model, operating the coupling model by taking the rainfall runoff model as a boundary condition of the one-dimensional hydrodynamic model, and obtaining a forecast result of the one-dimensional hydrodynamic model on flood gate water level and a forecast result of the two-dimensional hydrodynamic model on the highest flood water level of the transformer substation area; and analyzing the forecast result and judging whether the transformer substation flood gate needs to be closed or not. The method and the system predict the flood possibility of the area where the transformer substation is located in advance, so that the flood gate of the transformer substation can be closed for enough time, and the loss caused by untimely closing of the flood gate is avoided.

Description

Method for dispatching transformer substation flood control gate
Technical Field
the invention relates to a method for dispatching a transformer substation flood control gate, and belongs to the field of power engineering flood control engineering.
Background
Due to environmental restrictions, more and more transformer substation projects are arranged in the flood area near rivers, lakes and even in the flood area, and are directly influenced by flood inundation. When the designed elevation of the transformer substation site in the flood area cannot meet the designed flood level corresponding to the corresponding flood control standard, flood control measures are needed to ensure the flood control safety of the project, and the conventional flood control measures mainly adopt the mode that a flood control wall is arranged below a wall and a flood control gate is arranged at a gate.
The current transformer substation flood gate scheduling mechanism in the flood area is as follows: after the actual flood happens in the engineering area, the transformer substation operation and maintenance personnel immediately close the flood gate to prevent the flood from entering the station area. However, the flood is steep and steep, the confluence speed is high, and when the flood actually occurs, the flood gate is scheduled to be closed, the flood is usually caused to rush into the transformer substation due to short time and no time for operating and closing the flood gate, so that a destructive flood disaster is caused.
Disclosure of Invention
the invention provides a method for dispatching a transformer substation flood gate, which can estimate the flood possibility in the region where the transformer substation is located in advance, thereby ensuring that the transformer substation flood gate has enough time to close and avoiding the loss caused by untimely closing of the flood gate.
In order to achieve the purpose, the technical scheme adopted by the invention is as follows: a method for dispatching a flood gate of a transformer substation comprises the following steps: establishing a rainfall runoff model, a one-dimensional hydrodynamic model and a two-dimensional hydrodynamic model of the area where the transformer substation is located; establishing a coupling model of a one-dimensional hydrodynamic model and a two-dimensional hydrodynamic model; acquiring rainfall forecast data within a preset time; making a time sequence file according to the acquired rainfall forecast data, inputting the time sequence file into a rainfall runoff model, operating the coupling model by taking the rainfall runoff model as a boundary condition of the one-dimensional hydrodynamic model, and obtaining a forecast result of the one-dimensional hydrodynamic model on the flood gate water level and a forecast result of the two-dimensional hydrodynamic model on the highest flood level of the transformer substation area; and analyzing the forecast result of the water level of the flood diversion gate and the forecast result of the highest flood running water level of the transformer substation area, and judging whether the transformer substation flood control gate needs to be closed.
Further, the establishment of the rainfall runoff model comprises the following steps: constructing a rainfall runoff model of a rainfall runoff research area by using an MIKE rainfall runoff module; and collecting typical flood field times in a research area, and calibrating model parameters by using rainfall sequence data of a rainfall station and actual measurement flow series data of a flow station of the corresponding flood field times.
Furthermore, the rainfall runoff research area is a water collection range of hydrological stations at the upstream of the flood diversion gate of the flood area where the transformer substation is located.
Further, the establishing of the one-dimensional hydrodynamic model comprises the following steps: according to a one-dimensional hydrodynamic model, researching a regional water system diagram and river channel section data, and making a river network file and a river channel section file; according to the size of the flood diversion gate and an enabling mechanism, setting a dam break building at the flood diversion gate in the river network file, wherein the enabling condition is that the flood level at the flood diversion gate exceeds the enabling water level of the flood diversion area; and setting a rainfall runoff model as a boundary condition of the one-dimensional hydrodynamic model to obtain the one-dimensional hydrodynamic model.
Further, the one-dimensional hydrodynamic model research area is an area from a hydrological station to a flood area flood diversion gate river channel position.
Further, the establishing of the two-dimensional hydrodynamic model comprises the following steps: manufacturing a terrain file according to terrain data of a two-dimensional hydrodynamic model research area; setting parameters, and constructing a two-dimensional hydrodynamic model in a two-dimensional hydrodynamic model research area
Further, the two-dimensional hydrodynamic model research area is a flood area where the transformer substation is located.
Further, establishing the coupling model means connecting the two-dimensional hydrodynamic model and the one-dimensional hydrodynamic model in a lateral building connection manner through MIKE Flood.
further, the condition of judging whether to close the flood gate of the transformer substation is as follows: if the predicted value of the water level of the flood diversion gate does not exceed the starting water level of the flood diversion gate, the flood area does not run the flood and does not need to close the flood control gate; if the predicted value of the flood diversion gate water level exceeds the flood diversion gate starting water level, checking the forecast result of the highest flood running water level in the transformer substation area, and if the forecast result of the highest flood running water level in the transformer substation area is greater than or equal to the ground elevation of the transformer substation, closing the flood control gate in time; and if the forecast result of the highest flood level of the transformer substation area is smaller than the ground elevation of the transformer substation, closing the flood gate is not needed.
The method adopts future rainfall data, and schedules the transformer substation flood gate based on the flood gate water level forecast result and the transformer substation area flood forecast result, so that the transformer substation flood gate can be ensured to have enough time to close, and the loss caused by untimely closing of the flood gate is avoided.
Drawings
Fig. 1 is a flowchart of a method for scheduling a flood gate of a substation according to an embodiment of the present invention;
FIG. 2 shows a schematic view of a coupling connection of study areas in an embodiment of the present invention;
fig. 3 shows the one-dimensional water level forecast result of the flood diversion gate of the flood area where the transformer substation is located in 96 hours in the future, which is forecast in 2018, 9, month and 20 days in the embodiment of the present invention;
Fig. 4 shows the forecast result of the highest flood level of the transformer substation area in the 96 hours in the future, which is forecasted in 2018, 9, 20 and 8 days in the embodiment of the invention.
Detailed Description
In order to better understand the essence of the invention, the invention is further explained by taking scheduling of the M-substation flood gate in 2018, 9 and 20 as an example.
The M transformer substation is located in a certain flood area in North China, the original ground elevation of a station site is about 1.4M (1985 national elevation standard, the same below), the starting mechanism of the flood area is that the water level of a flood diversion gate reaches 7.0M, the designed flood level of the flood area is 6.0M in 100 years, the ground elevation of the station site is leveled to 2.5M for controlling the manufacturing cost and is far lower than the flood level in the flood area in 100 years, flood walls are adopted for flood control measures, flood gates are arranged on the flood control walls and the gates for ensuring the flood control safety of the station site, the wave climbing height with the cumulative frequency of 1% in 50 years and the safety superelevation are considered, and the top elevation of the flood control walls is set to be 7.5M.
According to a drainage basin water system diagram and a topographic map of a flood area, determining that a water collection range of a hydrological station (node X for short) at the upstream of a flood diversion gate of the flood area where a transformer substation is located is a rainfall runoff module research area A, taking the positions of the river from the node X to the flood diversion gate of the flood area as a one-dimensional hydrodynamic model research area B, and taking the flood area where the transformer substation is located as a two-dimensional hydrodynamic model research area C. The location of the investigation region ABC is shown in fig. 2.
A method for dispatching a flood gate of a transformer substation comprises the following specific steps as shown in figure 1,
Step 1: and establishing a rainfall runoff model of the area where the transformer substation is located. Constructing a rainfall runoff model of the research area A by utilizing an MIKE rainfall runoff module (RR module); collecting rainfall sequence data of a rainfall station and actual measurement flow series data of a flow station in a typical flood field in 7 months 2003, 6 months 2008 and 8 months 2013, and rating model parameters in a research area A, wherein the best parameters after rating are as follows: maximum water content U of surface water storage layermax=19.0mm, maximum water content L of soil layermax=150mm, slope flow coefficient CQOF =0.5, and interflow drainage constant CK1F=99h, CK in flow merging of slope flows12=13 h, slope runoff critical value TOF =0.47, interflow critical value TIF =0.01, root zone groundwater recharge critical value TG =0.45, and basal runoff convergence time CKBF=3000。
Step 2: and establishing a one-dimensional hydrodynamic model. Making a river network file and a river cross section file according to the water system diagram and the river cross section data of the research area B; according to the size of the flood diversion gate and an enabling mechanism, a dam break building is arranged at the flood diversion gate position in the river network file, the size of the dam break building is 100m long, the top elevation is 7.0m, and the enabling condition is that the flood level at the flood diversion gate exceeds 7.0 m; and setting a rainfall runoff model as a boundary condition of the one-dimensional hydrodynamic model, and constructing the one-dimensional hydrodynamic model of the one-dimensional hydrodynamic model research area B.
And step 3: and establishing a two-dimensional hydrodynamic model. And (3) according to the topographic data of the flood area, manufacturing a topographic file, setting parameters such as initial conditions and roughness coefficients, and constructing a two-dimensional hydrodynamic model in the research area C.
And 4, step 4: and establishing a coupling model of the one-dimensional hydrodynamic model and the two-dimensional hydrodynamic model. And connecting the two-dimensional hydrodynamic model and the one-dimensional hydrodynamic model in a lateral building connection mode through the MIKE Flood to form a coupling model.
Step 5: and acquiring rainfall forecast data within a preset time. : and (3) when 9, 20, 8 in 2018, downloading GFS data of 0.25 degrees or 0.25 degrees in the future for 96 hours as an initial field and a boundary field, wherein the time interval of the GFS data is 3 hours, the time interval of outputting a rainfall forecast result is 1 hour, and the grid point resolution is 3 km. The weather forecast mode is set as follows: nesting the two layers, wherein the resolution ratio is respectively 9km and 3km, and the innermost nesting range is the range of the research area A; the WRF mode inner and outer layer main physical process parameters are selected as follows: adopting a KF scheme for the cloud-accumulating convection parameterization scheme, adopting a Lin equivalent scheme for the micro physical process, adopting a YSU scheme for the atmospheric boundary layer and adopting a Noah scheme for the land surface process; the long wave radiation scheme adopts an RRTM scheme, and the short wave radiation scheme adopts a DudhiaScheme scheme.
Step 6: and (5) making a time sequence file from the grid point rainfall forecast data in the step 5 and inputting the time sequence file into the rainfall runoff model. And (4) taking the rainfall runoff model as a boundary condition of the one-dimensional hydrodynamic model and driving and operating the coupling model constructed in the step 4.
And 7: and analyzing the forecast result of the water level of the flood diversion gate and the forecast result of the highest flood running water level of the transformer substation area, and judging whether the transformer substation flood control gate needs to be closed.
and if the predicted value of the water level of the flood diversion gate does not exceed the starting water level of the flood diversion gate, the flood area does not flood and the flood gate does not need to be closed.
If the predicted value of the flood diversion gate water level exceeds the flood diversion gate starting water level, checking the forecast result of the highest flood running water level in the transformer substation area, and if the forecast result of the highest flood running water level in the transformer substation area is greater than or equal to the ground elevation of the transformer substation, closing the flood control gate in time; and if the forecast result of the highest flood level of the transformer substation area is smaller than the ground elevation of the transformer substation, closing the flood gate is not needed.
And the ground elevation of the M transformer substation is 2.5M. After the operation of the coupling model in the step 6 is finished, one-dimensional flood gate water level forecasting results of flood gates from 20 days in 9 months to 23 days in 9 months from 2018, 9 months and 20 days in 2018 are checked, as shown in fig. 3, the water level at the flood gate exceeds 7.0M, the highest flood gate water level forecasting results in 96 hours in the future of the M transformer substation area are checked, as shown in fig. 4, the highest flood gate water level in the M transformer substation area is higher than the ground elevation of the transformer substation from 35 parts at 21 days in 9 months and 23 months in 2018, and the flood gate needs to be closed in time.
it should be noted that while the invention has been described in terms of the above-mentioned embodiments, there are many other embodiments of the invention. It will be apparent to those skilled in the art that various changes and modifications may be made without departing from the spirit and scope of the invention, and it is intended that all such changes and modifications be covered by the appended claims and their equivalents.

Claims (9)

1. A method for dispatching a flood gate of a transformer substation is characterized by comprising the following steps:
Establishing a rainfall runoff model, a one-dimensional hydrodynamic model and a two-dimensional hydrodynamic model of the area where the transformer substation is located;
establishing a coupling model of a one-dimensional hydrodynamic model and a two-dimensional hydrodynamic model;
acquiring rainfall forecast data within a preset time;
Making a time sequence file according to the acquired rainfall forecast data, inputting the time sequence file into a rainfall runoff model, operating the coupling model by taking the rainfall runoff model as a boundary condition of the one-dimensional hydrodynamic model, and obtaining a forecast result of the one-dimensional hydrodynamic model on the flood gate water level and a forecast result of the two-dimensional hydrodynamic model on the highest flood level of the transformer substation area;
And analyzing the forecast result of the water level of the flood diversion gate and the forecast result of the highest flood running water level of the transformer substation area, and judging whether the transformer substation flood control gate needs to be closed.
2. A method of scheduling a substation floodgate according to claim 1, characterized in that: the establishment of the rainfall runoff model comprises the following steps:
Constructing a rainfall runoff model of a rainfall runoff research area by using an MIKE rainfall runoff module; and collecting typical flood field times in a research area, and calibrating model parameters by using rainfall sequence data of a rainfall station and actual measurement flow series data of a flow station of the corresponding flood field times.
3. A method of scheduling a substation floodgate according to claim 2, characterized in that: the rainfall runoff research area is a water collection range of hydrological stations at the upstream of flood diversion gates of the flood area where the transformer substation is located.
4. A method of scheduling a substation floodgate according to claim 1, characterized in that: the establishment of the one-dimensional hydrodynamic model comprises the following steps:
According to a one-dimensional hydrodynamic model, researching a regional water system diagram and river channel section data, and making a river network file and a river channel section file;
According to the size of the flood diversion gate and an enabling mechanism, setting a dam break building at the flood diversion gate in the river network file, wherein the enabling condition is that the flood level at the flood diversion gate exceeds the enabling water level of the flood diversion area;
and setting a rainfall runoff model as a boundary condition of the one-dimensional hydrodynamic model to obtain the one-dimensional hydrodynamic model.
5. The method of dispatching a substation floodgate according to claim 4, wherein: the one-dimensional hydrodynamic model research area is an area from a hydrological station to a flood area flood diversion gate river channel position.
6. A method of scheduling a substation floodgate according to claim 1, characterized in that: the establishment of the two-dimensional hydrodynamic model comprises the following steps: manufacturing a terrain file according to terrain data of a two-dimensional hydrodynamic model research area; and setting parameters, and constructing a two-dimensional hydrodynamic model in a two-dimensional hydrodynamic model research area.
7. The method of dispatching a substation floodgate according to claim 6, wherein: the two-dimensional hydrodynamic model research area is a flood area where the transformer substation is located.
8. a method of scheduling a substation floodgate according to claim 1, characterized in that: the step of establishing the coupling model refers to connecting the two-dimensional hydrodynamic model and the one-dimensional hydrodynamic model in a lateral building connection mode through the MIKE Flood.
9. A method of scheduling a substation floodgate according to claim 1, characterized in that:
Judging whether the condition of closing the flood gate of the transformer substation is as follows:
If the predicted value of the water level of the flood diversion gate does not exceed the starting water level of the flood diversion gate, the flood area does not run the flood and does not need to close the flood control gate;
If the predicted value of the flood diversion gate water level exceeds the flood diversion gate starting water level, checking the forecast result of the highest flood running water level in the transformer substation area, and if the forecast result of the highest flood running water level in the transformer substation area is greater than or equal to the ground elevation of the transformer substation, closing the flood control gate in time; and if the forecast result of the highest flood level of the transformer substation area is smaller than the ground elevation of the transformer substation, closing the flood gate is not needed.
CN201910789193.6A 2019-08-26 2019-08-26 Method for dispatching transformer substation flood control gate Pending CN110565594A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910789193.6A CN110565594A (en) 2019-08-26 2019-08-26 Method for dispatching transformer substation flood control gate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910789193.6A CN110565594A (en) 2019-08-26 2019-08-26 Method for dispatching transformer substation flood control gate

Publications (1)

Publication Number Publication Date
CN110565594A true CN110565594A (en) 2019-12-13

Family

ID=68776253

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910789193.6A Pending CN110565594A (en) 2019-08-26 2019-08-26 Method for dispatching transformer substation flood control gate

Country Status (1)

Country Link
CN (1) CN110565594A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111460742A (en) * 2020-03-31 2020-07-28 长江勘测规划设计研究有限责任公司 Method for constructing urban river and lake water network flood control and rainfall flood resource utilization model
CN113673765A (en) * 2021-08-23 2021-11-19 四创科技有限公司 Small watershed flood forecasting and early warning method and terminal
CN115423346A (en) * 2022-09-20 2022-12-02 中国水利水电科学研究院 Real-time measuring and calculating method for flood season adjustable capacity of open channel water transfer project series gate group

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7039565B1 (en) * 2003-01-03 2006-05-02 Haestad Methods, Inc. Method and system for developing a numerical dynamic sanitary sewer and storm water drainage simulation model
CN107451716A (en) * 2017-06-28 2017-12-08 宁波市水利水电规划设计研究院 A kind of flood control decision support method, electronic equipment, storage medium and system
CN107609787A (en) * 2017-09-27 2018-01-19 福建四创软件有限公司 Automatic scheduling method is combined based on the lock pump group for automatically generating prediction scheme
CN107832931A (en) * 2017-10-31 2018-03-23 上海市政工程设计研究总院(集团)有限公司 A kind of Modularity analysis method of plain river network region waterlogging risk

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7039565B1 (en) * 2003-01-03 2006-05-02 Haestad Methods, Inc. Method and system for developing a numerical dynamic sanitary sewer and storm water drainage simulation model
CN107451716A (en) * 2017-06-28 2017-12-08 宁波市水利水电规划设计研究院 A kind of flood control decision support method, electronic equipment, storage medium and system
CN107609787A (en) * 2017-09-27 2018-01-19 福建四创软件有限公司 Automatic scheduling method is combined based on the lock pump group for automatically generating prediction scheme
CN107832931A (en) * 2017-10-31 2018-03-23 上海市政工程设计研究总院(集团)有限公司 A kind of Modularity analysis method of plain river network region waterlogging risk

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
施露等: "Mike Flood在中小河流洪涝风险分析中的应用", 《河海大学学报(自然科学版)》 *
李传奇等: "一维二维水动力模型耦合的城市洪水模拟", 《水利水电技术》 *
王世旭: "基于MIKE FLOOD的济南的雨洪模拟及其应用研究", 《基础科学辑》 *
章新川等: "基于MIKE水动力模型的渭河下游防洪风险评估决策支持***研究", 《陕西水利》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111460742A (en) * 2020-03-31 2020-07-28 长江勘测规划设计研究有限责任公司 Method for constructing urban river and lake water network flood control and rainfall flood resource utilization model
CN113673765A (en) * 2021-08-23 2021-11-19 四创科技有限公司 Small watershed flood forecasting and early warning method and terminal
CN113673765B (en) * 2021-08-23 2024-06-07 四创科技有限公司 Small drainage basin flood forecasting and early warning method and terminal
CN115423346A (en) * 2022-09-20 2022-12-02 中国水利水电科学研究院 Real-time measuring and calculating method for flood season adjustable capacity of open channel water transfer project series gate group
CN115423346B (en) * 2022-09-20 2023-04-07 中国水利水电科学研究院 Real-time measuring and calculating method for flood season adjustable capacity of open channel water transfer project series gate group

Similar Documents

Publication Publication Date Title
CN110565594A (en) Method for dispatching transformer substation flood control gate
CN108446464B (en) Method for constructing large drainage system by using SWMM model
Amaguchi et al. Development and testing of a distributed urban storm runoff event model with a vector-based catchment delineation
CN110298076A (en) A kind of urban waterlogging intelligent modeling and analysis method based on GIS and SWMM
KR101381192B1 (en) Intelligent management system and method for rainwater based on real time control
CN110276145A (en) Sewerage system simulation modeling and dispatching method
CN112506994B (en) Power equipment flood hidden danger point monitoring and early warning method and related device
CN104851051A (en) Dynamic-modification-combined storm rainfall fine alarming method for power grid zone
CN107169645A (en) A kind of transmission line malfunction probability online evaluation method of meter and Rainfall Disaster influence
CN115391712A (en) Urban flood risk prediction method
CN106529739A (en) Gridding-based flood prediction method
CN115689168A (en) Accumulated water emergency scheduling method based on accumulated water prediction
CN112904458B (en) Hydrological forecasting method and system for super-seepage-full-storage mixed runoff yield mode
CN103729692A (en) Hydropower station drainage basin dividing and face rainfall monitoring method based on GIS
CN111898911A (en) Drainage waterlogging prevention emergency scheme design system
CN115186858A (en) Transformer substation flood inundation risk early warning method and system based on different influence types
Filipova Urban flooding in Gothenburg-A MIKE 21 study
CN113919125A (en) Flood control forecast scheduling method based on regional production convergence coupling model system
CN114528672A (en) Urban hydrological station network layout method and system based on 3S technology
CN110287595A (en) A kind of city different underlying surface mitigation effect analysis method
CN209085710U (en) A kind of online remote supervision system of drainage pipeline networks liquid level
CN110889185A (en) Peak flow analysis method for small watershed and application thereof
Ramadan et al. Flood Protection System to Aswan Under Current and Future Climate Conditions
CN116502739A (en) Rain and flood coupling forecasting method and system for reservoir water inflow and electronic equipment
Suryanti et al. Study of Characteristics and Management of Drainage Problems in Ubud District

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191213