CN110500107B - Shield tunneling machine normal-pressure warehouse opening front maintenance tool changing construction method - Google Patents

Shield tunneling machine normal-pressure warehouse opening front maintenance tool changing construction method Download PDF

Info

Publication number
CN110500107B
CN110500107B CN201910756984.9A CN201910756984A CN110500107B CN 110500107 B CN110500107 B CN 110500107B CN 201910756984 A CN201910756984 A CN 201910756984A CN 110500107 B CN110500107 B CN 110500107B
Authority
CN
China
Prior art keywords
cutter head
construction
shield
blasting
operation space
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910756984.9A
Other languages
Chinese (zh)
Other versions
CN110500107A (en
Inventor
雷波
宗朝阳
周小亮
潘传宇
周旋
陈鹏
李福成
周坤
韩毓殷
和堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Railway Investment Construction Group Co Ltd
China Construction Third Bureau Urban Construction Co Ltd
Original Assignee
China State Railway Investment Construction Group Co Ltd
China Construction Third Bureau Urban Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Railway Investment Construction Group Co Ltd, China Construction Third Bureau Urban Construction Co Ltd filed Critical China State Railway Investment Construction Group Co Ltd
Priority to CN201910756984.9A priority Critical patent/CN110500107B/en
Publication of CN110500107A publication Critical patent/CN110500107A/en
Application granted granted Critical
Publication of CN110500107B publication Critical patent/CN110500107B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention relates to a normal-pressure open-warehouse front-side maintenance tool changing construction method of a shield tunneling machine, which comprises the following steps: the method comprises the steps of checking the condition before opening the shield, checking the abrasion of a cutter head → determining the static blasting range → static blasting construction → repairing the cutter head → recovering and tunneling the shield.

Description

Shield tunneling machine normal-pressure warehouse opening front maintenance tool changing construction method
Technical Field
The invention relates to the technical field of civil engineering underground excavation tunnel shield construction, in particular to a shield machine warehouse opening front overhaul tool changing construction method.
Background
With the intensive development of urban construction, the people stream density is continuously increased, and a large amount of urban rail transit transportation systems are urgently needed to be constructed to solve the problem of urban traffic congestion. The shield construction method has the advantages of no influence of ground traffic, high safety, short construction period and the like, so that the shield construction method becomes a main construction method for urban rail traffic construction. The shield tunneling machine cutter head is generally customized according to a geological survey report before the shield tunneling construction, but due to the influences of stratum uncertainty, a geological survey report survey hole site arrangement mode and the like, the detailed condition that a tunnel penetrates through a stratum cannot be accurately grasped, various problems often occur to the shield tunneling machine cutter head in the tunneling process, so that the shield tunneling machine cannot normally tunnel, particularly in a full-face rock stratum, the condition that the cutter head is seriously abraded or blocked in the shield tunneling process is easy to occur, and the shield tunneling machine cutter head needs to be repaired at this time to ensure the normal tunneling of the shield.
Aiming at the problem, the current common solution is ground warehouse opening and removal, namely, a vertical shaft is constructed from the ground to the position of a cutter head, and then a constructor directly goes down to the position of the cutter head to overhaul or replace the shield cutter head. However, the method has large investment and long construction period, the construction of the vertical shaft destroys the stability of an undisturbed soil layer in front of the shield, the earth backfill and the main structure are required to be broken when the shield is pushed again, the construction quality cannot be guaranteed, the construction process is complex on the whole, and the economical efficiency is poor; meanwhile, when the building is positioned at the positions with more people flow, complicated building and construction and the like, projects such as fencing, sign removal, moving and modification and the like need to be carried out, the surrounding environment and traffic are greatly influenced, various approval procedures are complicated, and the total time is difficult to control.
In summary, the method for processing the failure of the cutter head of the shield tunneling machine in the shield tunneling process at present comprises the following steps: on one hand, the construction cost is high, and the construction period is long; on the other hand, when the earth surface environment is complex, the influence on the surrounding environment and traffic is great, the early approval procedure time is long, and the total construction time is difficult to control.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provides a normal-pressure open-cabin front-side maintenance tool-changing construction method of a shield tunneling machine, which comprises the following steps:
the method comprises the following steps: checking and accepting conditions before opening of shield
The method comprises the steps of perfecting field construction conditions, construction machines and safety technical data, checking whether preparation work before shield opening is perfected, and performing shield opening operation after checking;
step two: shield opening and cutter head abrasion inspection
Performing shield opening construction according to a construction scheme, then checking the abrasion and damage conditions of a cutter head of the shield tunneling machine, recording the specific positions of the abrasion and damage of the cutter head, and marking;
step three: determining static blasting scope
According to the abrasion and damage conditions of the cutter head, the position and the size of an operation space required to be provided for cutter head maintenance are researched and determined;
step four: static blasting construction
A static blasting construction scheme is formulated according to the position and the size of the operation space, the operation space is handed over to blasting operators after the operation space is checked and approved, and the operation space blasting operation is carried out strictly according to the blasting parameters and the blasting sequence of the special scheme until the operation space is formed;
step five: cutter head repair
Compiling a cutter head repairing scheme according to the abrasion and damage conditions of the cutter head, and then entering an operation space from the clearance of the cutter head by a professional to carry out cutter head repairing operation;
step six: shield recovery tunneling
After the cutter head is repaired, cleaning construction machines in the soil bin, recovering the shield tunneling construction after the cutter head is prepared and no error is confirmed, slowly tunneling at low rotating speed within the depth range of the operating space during tunneling, and then performing the shield tunneling construction according to normal propelling parameters.
As an improvement, the center of the working space in the third step is coincident with or above the central line of the tunnel, the length and width of the working space are not less than 3m, and the depth of the working space in the direction vertical to the tunnel face of the tunnel is not less than 2 m.
As an improvement, the static blasting in the fourth step is constructed by using an SCA crushing agent, and the single blasting depth is not more than 1 m.
As an improvement, the blasting sequence in the fourth step is carried out from top to bottom and from shallow to deep, before construction, the working space is firstly divided into a plurality of parts, then a pneumatic pick is adopted to chisel the upper left corner part of the working space to form a blasting construction free face, and finally blasting construction is carried out on the rest part of the working space.
As an improvement, in the blasting drilling in the fourth step, a water drill penetrates through a gap of a cutter head of the shield tunneling machine to construct a blast hole in the direction of a tunnel face, after static blasting is completed, a pneumatic pick is used for cleaning broken rock bodies into a soil bin, and produced broken stones are conveyed out of the soil bin in a mode of manually lifting and conveying large broken stones and discharging small broken stone screws.
And as an improvement, when the cutter head in the step five is repaired, an operator repairs the cutter head in the operation space, and in the process of maintenance and cleaning, the cutter head of the shield machine is overhauled and cleaned in all directions by rotating the cutter head of the shield machine.
The invention has the beneficial effects that:
1. compared with the method of opening the cabin from the ground to break and repair the cutterhead, the method has the advantages that the construction process is simple, a large amount of construction investment and construction time can be saved, meanwhile, the method is mainly used for constructing in the earth cabin of the shield tunneling machine, and the method has no influence on surface buildings, traffic organizations and the like.
2. The construction efficiency is high, the investment of personnel, equipment and the like is relatively less, enough space can be provided for cutter maintenance, and the cutter maintenance quality is guaranteed.
3. All construction operations are carried out in the underground tunnel, so that the method has no pollution problem and good environmental protection effect.
Drawings
FIG. 1 is a schematic diagram of the overall construction process of the normal-pressure open-cabin front-side maintenance tool-changing construction method of the shield tunneling machine.
FIG. 2 is a schematic diagram of a cross section of a relative position between an operation space and a shield machine in the normal-pressure open-cabin front-side maintenance tool-changing construction method of the shield machine.
Fig. 3 is a schematic diagram of a vertical face of a relative position between an operation space and a shield machine in the normal-pressure open-cabin front-side maintenance tool-changing construction method of the shield machine.
FIG. 4 is a schematic diagram of the operation space division and the construction sequence of the normal-pressure open-cabin front-side maintenance tool-changing construction method of the shield tunneling machine
As shown in the figure: 1. a shield machine; 2. a working space; 3. a central axis of the tunnel; 4. a tunnel face; 5. blasting sequence; 6. and (5) partitioning lines.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
As shown in fig. 1, a normal-pressure open-cabin front-side maintenance tool-changing construction method for a shield tunneling machine comprises the following steps:
the method comprises the following steps: checking and accepting conditions before opening of shield
The method comprises the steps of perfecting on-site construction conditions, construction machines and safety technical data, and verifying whether the preparation work before shield opening is perfected by units such as supervision, owners or the like together with external experts, wherein the shield opening operation can be performed after the verification;
step two: shield opening and cutter head abrasion inspection
Performing shield opening construction according to a construction scheme, then checking the abrasion and damage conditions of a cutter head of the shield tunneling machine 1, recording the specific positions of the abrasion and damage of the cutter head, and marking;
step three: determining static blasting scope
According to the abrasion and damage conditions of the cutter head, the position and the size of an operation space 2 required to be provided for cutter head maintenance are researched and determined;
step four: static blasting construction
A static blasting construction scheme is formulated according to the position and the size of the operation space 2, the operation space 2 is handed over to blasting operators after the operation space 2 is checked and approved, and blasting operation of the operation space 2 is strictly carried out according to special scheme blasting parameters and sequences until the operation space 2 is formed;
step five: cutter head repair
Compiling a cutter head repairing scheme according to the abrasion and damage conditions of the cutter head, and then entering an operation space 2 from the clearance of the cutter head by a professional to carry out cutter head repairing operation;
step six: shield recovery tunneling
After the cutter head is repaired, cleaning construction machines in the soil bin, recovering shield tunneling construction after preparation and no error is confirmed, slowly tunneling at low rotating speed within the depth range of the operation space 2 during tunneling, and then performing shield tunneling construction according to normal propelling parameters;
as shown in fig. 2 and 3, the center of the working space 2 in the third step coincides with the tunnel center line 3 or is located above the tunnel center line 3, the length and width of the working space 2 are not less than 3m, and the depth of the working space 2 in the direction perpendicular to the tunnel face 4 is not less than 2 m.
As shown in figure 1, the static blasting in the fourth step is carried out by using an SCA crushing agent, and the single blasting depth is not more than 1 m.
As shown in fig. 4, the blasting sequence 5 in the fourth step is performed in the order from top to bottom and from shallow to deep, before construction, the working space 2 is firstly divided into a plurality of parts (wherein the dotted line 6 is a partition line), then a pneumatic pick is used for chiseling a blasting construction free face at the upper left corner of the working space 2, and finally blasting construction is performed on the rest of the working space 2, so that the free face formed at the earlier construction part is fully utilized during blasting construction, and the blasting effect is enhanced.
As shown in fig. 1, in the blasting drilling in the fourth step, a water drill is adopted to pass through a gap of a cutter head of the shield tunneling machine 1 and construct a blast hole in the direction of a tunnel face 4, after static blasting is completed, a pneumatic pick is used for cleaning broken rock masses into a soil bin, and produced broken stones are conveyed out of the soil bin in a mode of manually lifting and conveying large broken stones and discharging small broken stone augers.
As shown in fig. 1, when repairing the cutter head in the fifth step, the operator performs cutter head repair in the working space 2, and in the process of maintenance and cleaning, the cutter head of the shield machine 1 is overhauled and cleaned in all directions by rotating the cutter head of the shield machine 1.
The above examples are given for the purpose of illustrating the invention clearly and not for the purpose of limiting the same, and it will be apparent to those skilled in the art that, in light of the foregoing description, numerous modifications and variations can be made in the form and details of the embodiments of the invention described herein, and it is not intended to be exhaustive or to limit the invention to the precise forms disclosed.

Claims (4)

1. A shield tunneling machine normal-pressure open-cabin front-side maintenance tool changing construction method is characterized by comprising the following steps:
the method comprises the following steps: checking and accepting conditions before opening of shield
The method comprises the steps of perfecting field construction conditions, construction machines and safety technical data, checking whether preparation work before shield opening is perfected, and performing shield opening operation after checking;
step two: shield opening and cutter head abrasion inspection
Performing shield opening construction according to a construction scheme, then checking the abrasion and damage conditions of a cutter head of the shield machine (1), recording the specific positions of the abrasion and damage of the cutter head, and marking;
step three: determining static blasting scope
According to the abrasion and damage conditions of the cutter head, the position and the size of an operation space (2) required to be provided for cutter head maintenance are researched and determined; the center of the working space (2) is superposed with the tunnel center line (3) or is positioned above the tunnel center line (3), the length and the width of the working space (2) are not less than 3m, and the depth of the working space (2) in the direction vertical to the tunnel face (4) is not less than 2 m;
step four: static blasting construction
A static blasting construction scheme is formulated according to the position and the size of the operation space (2), the operation space (2) is handed over to blasting operators after the operation space (2) is checked and approved, and blasting operation is carried out on the operation space (2) strictly according to special scheme blasting parameters and a blasting sequence until the operation space (2) is formed; the blasting sequence (5) is integrally carried out from top to bottom and from shallow to deep, before construction, the operation space (2) is firstly divided into a plurality of parts, then a pneumatic pick is adopted to chisel a blasting construction face in the upper left corner of the operation space (2), and finally blasting construction is carried out on the rest part of the operation space (2);
step five: cutter head repair
A cutter head repairing scheme is compiled according to the abrasion and damage conditions of the cutter head, and then a professional enters an operation space (2) from the clearance of the cutter head to perform cutter head repairing operation;
step six: shield recovery tunneling
After the cutter head is repaired, cleaning construction machines in the soil bin, recovering the shield tunneling construction after the cutter head is prepared and no error is confirmed, slowly tunneling at low rotating speed within the depth range of the operation space (2) during tunneling, and then performing the shield tunneling construction according to normal propelling parameters.
2. The normal-pressure open-cabin front-side overhaul tool-changing construction method of the shield tunneling machine according to claim 1, and is characterized in that: and in the fourth step, the static blasting is carried out by using an SCA crushing agent, and the single blasting depth is not more than 1 m.
3. The normal-pressure open-cabin front-side overhaul tool-changing construction method of the shield tunneling machine according to claim 1, and is characterized in that: and blasting drilling in the fourth step adopts a water drill to penetrate through a construction blast hole in the direction of the tunnel face (4) from the space of a cutter head of the shield machine (1), a pneumatic pick is used for cleaning broken rock bodies into a soil bin after static blasting is finished, and produced broken stones are conveyed out of the soil bin in a mode of manually lifting and conveying large broken stones and discharging small broken stone screw machines.
4. The normal-pressure open-cabin front-side overhaul tool-changing construction method of the shield tunneling machine according to claim 1, and is characterized in that: and when the cutter head in the step five is repaired, an operator repairs the cutter head in the operation space (2), and in the process of maintenance and cleaning, the cutter head of the shield machine (1) is overhauled and cleaned in all directions by rotating the cutter head of the shield machine (1).
CN201910756984.9A 2019-08-16 2019-08-16 Shield tunneling machine normal-pressure warehouse opening front maintenance tool changing construction method Active CN110500107B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910756984.9A CN110500107B (en) 2019-08-16 2019-08-16 Shield tunneling machine normal-pressure warehouse opening front maintenance tool changing construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910756984.9A CN110500107B (en) 2019-08-16 2019-08-16 Shield tunneling machine normal-pressure warehouse opening front maintenance tool changing construction method

Publications (2)

Publication Number Publication Date
CN110500107A CN110500107A (en) 2019-11-26
CN110500107B true CN110500107B (en) 2021-03-02

Family

ID=68588192

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910756984.9A Active CN110500107B (en) 2019-08-16 2019-08-16 Shield tunneling machine normal-pressure warehouse opening front maintenance tool changing construction method

Country Status (1)

Country Link
CN (1) CN110500107B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847921A (en) * 2019-12-05 2020-02-28 华北水利水电大学 Method for getting rid of trouble after shield machine is clamped
CN113216994B (en) * 2021-05-06 2022-07-26 中建铁投轨道交通建设有限公司 Construction method for correcting deviation by overexcavation of inserted hob of shield tunneling machine
CN115218735B (en) * 2022-07-26 2023-06-16 广东***工程有限公司 Method for solving problem of getting stuck due to eccentric wear of cutter

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100564802C (en) * 2006-11-27 2009-12-02 杨仁树 The method of crushing rock formation in the colliery
US9429016B2 (en) * 2009-12-22 2016-08-30 Bouygues Travaux Publics Method for replacing a tunnel boring machine roller cutter, handling device and roller cutter suited to such a method
CN103061776B (en) * 2013-01-06 2015-05-27 中铁隧道集团有限公司 Method for repairing TBM (tunnel boring machine) cutter head in intra-tunnel high-pressure environment
CN103133007B (en) * 2013-03-01 2015-05-13 中铁三局集团有限公司 Shield ground compartment opening method

Also Published As

Publication number Publication date
CN110500107A (en) 2019-11-26

Similar Documents

Publication Publication Date Title
CN110500107B (en) Shield tunneling machine normal-pressure warehouse opening front maintenance tool changing construction method
CN103291308B (en) For boom-type roadheader and the method for tunnel construction of constructing tunnel
EA037864B1 (en) Construction method of strong karst water-rich urban shallow-buried tunnel using cantilever boring machine
CN113431575A (en) Construction method for assisting excavation of stone cutting by plunger type rock hydraulic splitter
CN111577311A (en) Construction process of cantilever type heading machine in soft rock tunnel
Bullock Comparison of underground mining methods
CN110836115A (en) Tunnel drilling method adjacent to existing building
CN102383795B (en) Comprehensive mechanical rock drift excavating process
CN110579143A (en) Hard rock foundation positioning blasting and hydraulic spalling combined excavation construction method
CN114635707B (en) Hydraulic fracturing-based rapid and continuous hard rock roadway or tunnel tunneling method
CN115217483A (en) Intelligent tunneling method of open type large-section tunneling machine
CN216381401U (en) Equipment for preventing tunnel from being dug excessively
CN113107497B (en) Hard rock tunnel tunneling construction method
CN111255473B (en) Excavation construction method of soft rock tunnel cantilever type heading machine
CN116265716A (en) Mechanical tunneling construction method for large-span multi-arch hard rock tunnel
CN113605899A (en) Tunnel excavation method based on hydraulic impact crushing and static crushing
Grasso et al. Construction methods
CN111058862A (en) Starting end reinforcement area boulder treatment method
Thorsager et al. KBS-3H. Summary report of work done during Basic Design
Bäckblom et al. KBS-3H-Excavation of two horizontal drifts at the Aespoe Hard Rock Laboratory during year 2004-2005. Work description, summary of results and experience
Bäckblom et al. Choice of rock excavation methods for the Swedish deep repository for spent nuclear fuel
Snyman et al. E48 cave extension at Northparkes
Xia et al. Application of cantilever roadheader in tunnel construction
CN117072167B (en) Method for protecting reserved ore pillar by opening pre-cracks
Östberg High precision drilling

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20200615

Address after: Room 905, 1st floor, building 3, No. 10, guaxiang Road, Panggezhuang Town, Daxing District, Beijing 100089

Applicant after: China Construction Third Engineering Bureau Urban Construction Co.,Ltd.

Applicant after: CHINA STATE RAILWAY INVESTMENT CONSTRUCTION GROUP Co.,Ltd.

Address before: 102601 room 905, 3 building, 10 Gua Xiang Road, Pang Zhuang Town, Daxing District, Beijing.

Applicant before: CHINA STATE RAILWAY INVESTMENT CONSTRUCTION GROUP Co.,Ltd.

GR01 Patent grant
GR01 Patent grant