CN110439002A - A kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab - Google Patents

A kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab Download PDF

Info

Publication number
CN110439002A
CN110439002A CN201910648424.1A CN201910648424A CN110439002A CN 110439002 A CN110439002 A CN 110439002A CN 201910648424 A CN201910648424 A CN 201910648424A CN 110439002 A CN110439002 A CN 110439002A
Authority
CN
China
Prior art keywords
fagging
inner support
template
construction
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910648424.1A
Other languages
Chinese (zh)
Inventor
叶海龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN201910648424.1A priority Critical patent/CN110439002A/en
Publication of CN110439002A publication Critical patent/CN110439002A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention provides a kind of method of the interim horizontal structure of inner support as permanent structure beam slab, this method is in excavation of foundation pit staged construction inner support, using inner support as structural slab after the completion of excavation of foundation pit, making the support plate in pattern foundation pit supporting structure stage becomes basement permanent structure plate, is combined into one inner support horizontal structure with basement floor construction.Need to remove to solve the interim horizontal structure of existing inner support in underground structure process of construction or after building up, consume a large amount of human and material resources, and generate a large amount of building waste, not only waste of resource but also not environmentally the problem of.Belong to technical field of building construction.

Description

A kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab
Technical field
The present invention relates to the methods that a kind of interim horizontal structure of inner support is used as permanent structure beam slab, belong to construction skill Art field.
Background technique
Present urban construction has many local peripheries all to build up, and the number of plies that newly-built building basement is built is more, excavates base When hole, foundation pit is very deep but cannot use the support pattern that anchor pole is beaten to outside foundation pit, typically uses the support pattern of inner support, There are the pattern foundation pit supporting structures modes such as stake+inner support, interlocking pile+inner support, diaphram wall+inner support, these inner supports mostly use greatly Concrete beam and board structure, after pit earthwork excavates on earth, when building up in layer with underground structure, these are only The interim horizontal structure of inner support that excavation of foundation pit carries out supporting will be cut, and cutting the interim horizontal structure of these inner supports can consume A large amount of human and material resources, and generate a large amount of building waste, not only waste of resource but also not environmentally.
Summary of the invention
The present invention provides a kind of method of the interim horizontal structure of inner support as permanent structure beam slab, to solve existing interior branch It supports interim horizontal structure to need to remove during Underground Construction or after building up, consumes a large amount of human and material resources, and produce Raw a large amount of building waste, not only waste of resource but also not environmentally the problem of.
To solve the above problems, the interim horizontal structure of such a inner support of proposed adoption is used as the side of permanent structure beam slab Inner support is constructed as beam slab or plank frame, is completed in excavation of foundation pit in excavation of foundation pit staged construction inner support by method, this method Afterwards using inner support as structural slab, the support plate of construction stage is made to become basement permanent structure plate, ties inner support and underground Structure plate is combined into one.
The innovation transformation of fagging: pass through the combination of horizontal inner support construction plan and building basement floor construction plane It with optimization, obtains not only making pattern foundation pit supporting structure horizontal supporting plate, but also can be used for the fagging structural working drawing of basement structure floor, this Fagging meets the stress as the horizontal inner support of foundation pit and the stress as basement structure floor simultaneously, also meets and is used as underground Each profession that the building of room floor, structure, plumbing, electrical, HVAC, fire-fighting, people's air defense, intelligence etc. can relate to is wanted It asks.
Specific step is as follows for the above method:
1) cushion construction
When the elevation location of earth excavation to fagging, cushion construction is carried out, using the lower section soil body as bearing load Main body makes it meet design bearing capacity requirement by reinforcing to ground;
2) interleaving agent is constructed
Before assembling reinforcement, the brushing interleaving agent on bed course in advance;
3) fagging is connect with fender post reinforcing bar
Fagging construction before, fender post surface is handled, on fender post carry out fagging reinforcing steel implant, make fagging with Fender post closely connects, the globality of enhancing structure;
4) structural column is constructed and is connect with support plate reinforcing bar
Construction procedure are as follows: the earthwork is smooth → cushion construction → line setting → pilot hole → insertion reinforcing bar → bolumn cap construction → It is next for positioning stirrup → set column tie-bar → vertical applied force muscle connection → bandage muscle → carry out that well word muscle is welded on stem lattice column Procedure;
5) template is installed
6) fagging concreting.
Above-mentioned steps 4) in:
1. bolumn cap is constructed: inner support is arranged to the form of arch without beam, and bolumn cap is arranged in lattice column and fagging position;
2. stirrup positions: well word muscle is welded on lattice column according to column position, after positioning stirrup and the binding securely of well word muscle Carry out the connection of column main reinforcement;
3. structural column Vertical bar connection: lattice column is when reinforcing bar connects elevationally outward, bar diameter D >=Ф 20 in column, steel Muscle connector squeezes sleeve connection using straight thread, and at bolumn cap position, lattice column surrounding electricity consumption drill hole is put in fagging work progress Enter reinforcing bar, reinforcing bar insertion depth is from bolumn cap bottom end 1m, according to layout design and the straight spiral shell of code requirement after earth excavation Line sleeve is by upper layer and lower layer pressed splice;
4. lattice column and fagging node processing: d=19, L=100 are welded in lattice column and fagging junction on lattice column, Spacing is the peg of 100mm, and steel bracket under beam is arranged at basement driving channel, and steel bracket and lattice column pass through the company of being fully welded It connects;
5. structural column concreting: stayed at the top of bolumn cap and set concrete pouring hole, using vibrate in lattice column+template outside Auxiliary is vibrated to guarantee concrete pouring quality;
It has constructed and fagging and has excavated under fagging after the earthwork, first cleaned lattice column iron rust with steel brush, and using 32.5 Ordinary portland cement prepares plain-water slurry, then successively smears lattice column from top to bottom;
Above-mentioned steps 5) in:
1. fagging lower template: using clay model as the main body of bearing load when fagging structure construction, extremely by earth excavation first Predetermined absolute altitude, leveling, compacting, first pours bed course, in this, as support shuttering under concrete fagging, then in bed course on clay model Upper binding beam reinforced steel bar, casting beams board concrete;
2. side bar template install: side bar using reversed beam design, on the inside of side bar carry out template installation when as follows with Measure carries out installation reinforcing: limit steel bar is arranged in mouth under template, controls mouth absolute altitude under template, keeps it high by one with floor top mark It causes;Limit steel bar is set in supporting steel pipe lower end, it is made not generate displacement and deformation in support shuttering;
3. ring beam template is installed
When circular rings beam forms on the outside of structural slab is installed: template absolute altitude suitable for reading is accurately positioned, makes it in same level On;Shuttering supporting is firm, carries out diagonal brace using steel pipe, together every 1 meter of setting;Template construct is installed to board bottom absolute altitude, suitable for reading Reserved 300mm, is blocked with steel fabric sheet, for reserving structural slab reinforcing bar;When ring beam concreting, special messenger is arranged to be responsible for adjustment As artificially trample and impact force that when concreting generates and caused by template dislocation, deformation;
Above-mentioned steps 6) in:
1. the greasy dirt on sundries and reinforcing bar in template need to be cleaned out, the gap of template and hole are stifled tight;
2. beam, board concrete pour simultaneously, casting method by one end with " catching up with slurry processes " i.e. first casting beams, according to deck-molding Placement layer by layer is at stairstepping, when the concrete for reaching board bottom position Shi Zaiyu plate pours together;
3. after concreting to designed elevation, vibrating head vibration compacting is struck off with long floating rule, concreting 2~ It after 3h, is rolled with iron roller and is compacted several times repeatedly, smeared and flattened with finisher, after waiting concrete to receive water, second again before final set With finisher screeding and compaction repeatedly;
4. being covered in time within 12h after concreting, sprinkling maintenance;
5. reaching requirement of strength design to this layer of fagging, continue earth excavation, carries out lower plywood construction.
Compared with prior art, the present invention transform the interim horizontal structure of existing pattern foundation pit supporting structure as permanent structure, interim water Flat structure carries out certain Deepen Design, allows this interim horizontal structure in excavation of foundation pit, horizontal support effect is played, in underground In the construction of room again can as permanent beam, hardened structure, by the combination of inner support plane and building basement floor level with it is excellent Change, pattern foundation pit supporting structure horizontal supporting plate can not only be made by obtaining this, but also can be used for basement structure floor;There is no interim horizontal structure It cuts, saves the construction time, save the artificial and measure cut, do not generate the building wastes such as concrete quarrel, built without outward transport The expense of building refuse;The interim horizontal structure of pattern foundation pit supporting structure is used as permanent structure, economizes on resources, environment-friendly and green.
Detailed description of the invention
Fig. 1 is inner support of the present invention/underground structure plate structural schematic diagram.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, the present invention is made into one below in conjunction with attached drawing The detailed description of step, it should be understood that described herein specific examples are only used to explain the present invention, is not used to limit this hair It is bright.
Embodiment
Referring to Fig.1, the present embodiment provides the methods that a kind of interim horizontal structure of inner support is used as permanent structure beam slab, will be interior Support is combined into one with underground structure plate, the stress under two kinds of operating conditions is considered, in the excavation of foundation pit stage as inner support, by interior branch Support construction is beam slab or plank frame, is structural slab after the completion of excavation of foundation pit, avoids removing because of temporary support or support replacement is drawn It plays support system Internal Force Redistribution and causes the displacement of foundation pit and deformation or the unexpected off-load of concrete support that will produce to ambient enviroment Raw influence.Making the support plate of construction stage becomes basement permanent structure plate, to realize that inner support and basement structure plate are closed One.It solves the safety problem for carrying out foundation pit operation in city high rise building dense, reduces the cost of construction gib, shorten Construction period.
Concrete construction method is as follows:
1) cushion construction
When the elevation location of earth excavation to fagging, with regard to carrying out cushion construction, before each section of cushion construction, Ying Tiqian is carried out This section of base's measurement and positioning work, location base axis accurately control bed course bottom absolute altitude.Make full use of the lower section soil body as receiving The main body of load makes it meet design bearing capacity requirement: cushion construction thickness 100mm, strong concrete by reinforcing to ground Spend grade C15.It is buried in bed course and pulls U-shaped ring, after blinding concrete final set, reinforce water seasoning.It prevents from artificially trampleing on broken Bad concrete surface should ensure that its surface quality meets related request, and people's walking can be just gone up after intensity reaches 1.2MPa.
2) interleaving agent is constructed
In order to enable structure floor to be detached from bed course, the presentation quality of structure is not influenced, according to the actual situation, in binding steel Before muscle, the brushing interleaving agent on bed course in advance, when pulling the U-shaped ring in bed course, so that bed course and structural slab can preferably take off From.Interleaving agent construction precautions:
1. first removing sundries before interleaving agent brushing, mat surface is cleaned out;
2. coating is strictly watered reconciliation in defined ratio and uses;
3. coating is sprayed on bed course with spray gun or hairbrush after mixing evenly, brushes uniformly, avoid holiday;
4. it must be professional's construction operation, Ying little Xin when brushing, pre- anti-slip;
5. the rainy day is avoided to brush, if encountering the rainy day, brush should be mended in time before reinforcing bar is bound;
3) fagging is connect with fender post reinforcing bar
Before fagging construction, fender post surface need to be handled, fagging reinforcing steel implant is carried out on fender post, makes fagging It is closely connect with fender post, the globality of enhancing structure.
4) structural column is constructed and is connect with support plate reinforcing bar
Construction procedure are as follows: the earthwork is smooth → cushion construction → line setting → pilot hole → insertion reinforcing bar → bolumn cap construction → Well word muscle (up and down each one) is welded on stem lattice column for positioning stirrup → set column tie-bar → vertical applied force muscle connection → bandage Muscle → carry out next process
1. bolumn cap is constructed: this inner support is arranged to the form of arch without beam, and bolumn cap is arranged in lattice column and fagging position, can Solve the problems, such as fagging Punching Shear at column;Reduce the effective span of fagging;Reduce seat shoulder bar.
2. stirrup positions: welding well word muscle on lattice column according to column position.After stirrup and the binding securely of well word muscle will be positioned Carry out the connection of column main reinforcement.Structure column tie-bar can be passed through from the gap between lattice column angle steel, can when stirrup meets lattice column batten plate Punching (aperture is bar diameter+2mm) passes through on batten plate.
3. structural column Vertical bar connection: lattice column is when reinforcing bar connects elevationally outward, to guarantee project progress and quality, column Middle bar diameter D >=Ф 20, splice squeeze sleeve connection using straight thread.In bolumn cap portion in every layer of fagging work progress Position lattice column surrounding electricity consumption drill hole is put into reinforcing bar, and reinforcing bar insertion depth is from bolumn cap bottom end 1m.The basis after earth excavation Layout design and code requirement straight screw sleeve are by upper layer and lower layer pressed splice.
4. lattice column and fagging node processing: d=19, L=100 are welded in lattice column and fagging junction on lattice column, Spacing is the peg of 100mm.Increase the cohesive force with floor by peg.Steel support under beam is set at basement driving channel Frame, steel bracket are connect with lattice column by being fully welded.
5. structural column concreting: since column core has lattice column influence, vibrating spear and lattice are inserted into structural column two sides Gap between column is vibrated difficulty, therefore is stayed at the top of bolumn cap and set concrete pouring hole, using vibrate in lattice column+template outside assist It vibrates to guarantee concrete pouring quality.
After inner support plate of having constructed, lattice column iron rust first is cleaned with steel brush, and using 32.5 ordinary portland cement Plain-water slurry is prepared, then successively smears lattice column from top to bottom, to avoid the corrosion of lattice column.Structural column concreting When in top end, 2 casings are diagonally set, it is ensured that concrete pouring quality.
5) template is installed
1. fagging lower template: inner support contignation applies main body of the utilization of hour clay model as bearing load, first by the earthwork It is excavated to predetermined absolute altitude, leveling, compacting first pour bed course, in this, as support shuttering under concrete fagging on clay model.Then Beam reinforced steel bar, casting beams board concrete are bound on bed course.
2. side bar template is installed: side bar carries out pressing when template installation on the inside of side bar as follows due to designing using reversed beam Method and measure carry out installation reinforcing:
Limit steel bar is arranged in mouth under template, controls mouth absolute altitude under template, keeps it high consistent with floor top mark.
Limit steel bar is set in supporting steel pipe lower end, it is made not generate displacement and deformation in support shuttering.
3. ring beam template is installed
It should be noted that template absolute altitude suitable for reading is accurately positioned when circular rings beam forms on the inside of fagging is installed, make it in same water In plane;Shuttering supporting wants firm, carries out diagonal brace using steel pipe, together every 1 meter of setting;Template construct is installed to board bottom mark Height, reserved 300mm suitable for reading, is blocked with steel fabric sheet, for reserving structural slab reinforcing bar;When ring beam concreting, it should arrange specially People be responsible for adjusting as artificially trample and impact force that when concreting generates and caused by template dislocation, deformation.
6) fagging concreting
1. greasy dirt on sundries and reinforcing bar in template etc. should be cleaned out, the gap of template and hole should be blocked up sternly.
2. beam, board concrete should pour simultaneously, casting method by one end with " catching up with slurry processes " i.e. first casting beams, according to beam High stratification, which pours, builds up stairstepping, when the concrete for reaching board bottom position Shi Zaiyu plate pours together.
3. after concreting to designed elevation, vibrating head vibration compacting is struck off with long floating rule, concreting 2~ It after 3h, is rolled with iron roller and is compacted several times repeatedly, smeared and flattened with finisher, after waiting concrete to receive water, second again before final set With finisher screeding and compaction repeatedly.
4. being covered in time within 12h after concreting, sprinkling maintenance.
5. reaching requirement of strength design to this layer of support plate, continue earth excavation, carries out lower plywood construction.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (5)

1. a kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab, it is characterised in that: this method is opened in foundation pit Staged construction inner support is dug, inner support construct as beam slab or plank frame, using inner support as tying after the completion of excavation of foundation pit Structure plate makes the support plate of construction stage become basement permanent structure plate, inner support and underground structure plate is combined into one.
2. a kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab according to claim 1, feature exists In specific step is as follows for the above method:
1) cushion construction
When the elevation location of earth excavation to fagging, cushion construction is carried out, using the lower section soil body as the main body of bearing load, By reinforcing to ground, it is made to meet design bearing capacity requirement;
2) interleaving agent is constructed
Before assembling reinforcement, the brushing interleaving agent on bed course in advance;
3) fagging is connect with fender post reinforcing bar
Before fagging construction, fender post surface is handled, fagging reinforcing steel implant is carried out on fender post, makes fagging and goes along with sb. to guard him The close connection of stake, the globality of enhancing structure;
4) structural column is constructed and is connect with support plate reinforcing bar
Construction procedure are as follows: the earthwork is smooth → cushion construction → line setting → pilot hole → insertion reinforcing bar → bolumn cap construction → in stem Well word muscle is welded on lattice column carries out down one of work for positioning stirrup → set column tie-bar → vertical applied force muscle connection → bandage muscle → Sequence;
5) template is installed
6) fagging concreting.
3. a kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab according to claim 2, feature exists In above-mentioned steps 4) in:
1. bolumn cap is constructed: inner support is arranged to the form of arch without beam, and bolumn cap is arranged in lattice column and fagging position;
2. stirrup positions: welding well word muscle on lattice column according to column position, will be carried out after positioning stirrup and the binding securely of well word muscle The connection of column main reinforcement;
3. structural column Vertical bar connection: when reinforcing bar connects elevationally outward, bar diameter D >=Ф 20 in column, reinforcing bar connects lattice column Head squeezes sleeve connection using straight thread, and at bolumn cap position, lattice column surrounding electricity consumption drill hole is put in every layer of fagging work progress Enter reinforcing bar, reinforcing bar insertion depth is from bolumn cap bottom end 1m, according to layout design and the straight spiral shell of code requirement after earth excavation Line sleeve is by upper layer and lower layer pressed splice;
4. lattice column and fagging node processing: d=19, L=100, spacing are welded in lattice column and fagging junction on lattice column For the peg of 100mm, steel bracket under beam is set at basement driving channel, steel bracket is connect with lattice column by being fully welded;
5. structural column concreting: stayed at the top of bolumn cap and set concrete pouring hole, using vibrate in lattice column+template outside assist It vibrates to guarantee concrete pouring quality;
Constructed and fagging and excavated under fagging after the earthwork, first cleaned lattice column iron rust with steel brush, and using 32.5 it is common Portland cement prepares plain-water slurry, then successively smears lattice column from top to bottom.
4. a kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab according to claim 2, feature exists In above-mentioned steps 5) in:
1. fagging lower template: using clay model as the main body of bearing load when fagging structure construction, first by earth excavation to predetermined Absolute altitude, leveling, compacting, first pours bed course on clay model, in this, as support shuttering under concrete fagging, then ties up on bed course Prick beam reinforced steel bar, casting beams board concrete;
2. side bar template is installed: side bar is designed using reversed beam, on the inside of side bar when progress template installation as follows and measure Carry out installation reinforcing: limit steel bar is arranged in mouth under template, controls mouth absolute altitude under template, keeps it high consistent with floor top mark;In Limit steel bar is arranged in supporting steel pipe lower end, it is made not generate displacement and deformation in support shuttering;
3. ring beam template is installed
When circular rings beam forms on the outside of structural slab is installed: template absolute altitude suitable for reading is accurately positioned, makes it in same level;Mould Plate support is firm, carries out diagonal brace using steel pipe, together every 1 meter of setting;Template construct is installed to board bottom absolute altitude, suitable for reading reserved 300mm is blocked with steel fabric sheet, for reserving structural slab reinforcing bar;When ring beam concreting, arrange special messenger be responsible for adjustment due to Artificially trample and impact force that when concreting generates and caused by template dislocation, deformation.
5. a kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab according to claim 2, feature exists In above-mentioned steps 6) in:
1. the greasy dirt on sundries and reinforcing bar in template need to be cleaned out, the gap of template and hole are stifled tight;
2. beam, board concrete pour simultaneously, casting method, with " catching up with slurry processes " i.e. first casting beams, is layered by one end according to deck-molding It pours and builds up stairstepping, when the concrete for reaching board bottom position Shi Zaiyu plate pours together;
3. after concreting to designed elevation, vibrating head vibration compacting is struck off with long floating rule, after 2~3h of concreting, It is rolled with iron roller and is compacted several times repeatedly, smeared and flattened with finisher, after waiting concrete to receive water, use troweling before final set for the second time again Machine screeding and compaction repeatedly;
4. being covered in time within 12h after concreting, sprinkling maintenance;
5. reaching requirement of strength design to this layer of support plate, continue earth excavation, carries out lower plywood construction.
CN201910648424.1A 2019-07-18 2019-07-18 A kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab Pending CN110439002A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910648424.1A CN110439002A (en) 2019-07-18 2019-07-18 A kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910648424.1A CN110439002A (en) 2019-07-18 2019-07-18 A kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab

Publications (1)

Publication Number Publication Date
CN110439002A true CN110439002A (en) 2019-11-12

Family

ID=68430828

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910648424.1A Pending CN110439002A (en) 2019-07-18 2019-07-18 A kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab

Country Status (1)

Country Link
CN (1) CN110439002A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627187A (en) * 2020-12-03 2021-04-09 中国建筑股份有限公司 Vertical support assembly and construction method of foundation pit vertical support
CN113565139A (en) * 2021-07-07 2021-10-29 深圳市中地建设工程有限公司 Construction method facilitating demolding of floor beam and floor template

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104652443A (en) * 2013-11-21 2015-05-27 中冶天工上海十三冶建设有限公司 Construction method for temporary horizontal supports serving as permanent structural beams simultaneously of deep foundation pit
CN104895092A (en) * 2015-06-02 2015-09-09 中建四局第六建筑工程有限公司 Method for using inner-support temporary latticed column as permanent structure column
CN104912098A (en) * 2015-06-01 2015-09-16 中建四局第六建筑工程有限公司 Combined construction method for supporting beam plate and structural plate of deep foundation pit
CN107542108A (en) * 2016-12-22 2018-01-05 深圳建业工程集团股份有限公司 A kind of reverse construction method of building basement structure
CN109944250A (en) * 2019-03-07 2019-06-28 上海建工集团股份有限公司 The foundation pit of impermanent vertical support system is along inverse combining construction method
CN210507464U (en) * 2019-07-18 2020-05-12 中国建筑第四工程局有限公司 Annular supporting plate for basement structure floor slab

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104652443A (en) * 2013-11-21 2015-05-27 中冶天工上海十三冶建设有限公司 Construction method for temporary horizontal supports serving as permanent structural beams simultaneously of deep foundation pit
CN104912098A (en) * 2015-06-01 2015-09-16 中建四局第六建筑工程有限公司 Combined construction method for supporting beam plate and structural plate of deep foundation pit
CN104895092A (en) * 2015-06-02 2015-09-09 中建四局第六建筑工程有限公司 Method for using inner-support temporary latticed column as permanent structure column
CN107542108A (en) * 2016-12-22 2018-01-05 深圳建业工程集团股份有限公司 A kind of reverse construction method of building basement structure
CN109944250A (en) * 2019-03-07 2019-06-28 上海建工集团股份有限公司 The foundation pit of impermanent vertical support system is along inverse combining construction method
CN210507464U (en) * 2019-07-18 2020-05-12 中国建筑第四工程局有限公司 Annular supporting plate for basement structure floor slab

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
童天培: "《深基坑支撑板用于地下结构板逆作法施工技术》", 《建筑工程技术与设计》, no. 10, pages 382 - 389 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627187A (en) * 2020-12-03 2021-04-09 中国建筑股份有限公司 Vertical support assembly and construction method of foundation pit vertical support
CN113565139A (en) * 2021-07-07 2021-10-29 深圳市中地建设工程有限公司 Construction method facilitating demolding of floor beam and floor template

Similar Documents

Publication Publication Date Title
CN104895092B (en) The method that a kind of interim lattice column of inner support is used as permanent structure post
CN108951425A (en) Cast-in-situ prestressed concrete continuous box girder primary concreting molding construction method
CN106437142A (en) Construction method and double-layer formwork structure for cast-in-situ slope roof
CN107574762A (en) A kind of construction method for strengthening Cast-in-situ Beam 0# block construction qualities
CN105839850A (en) Basement reverse-construction scape post-casting pre-stressed construction method
CN102505709A (en) Concrete-formwork-precast foundation construction method
CN110761316B (en) Prefabricated foundation ring beam prefabricating method and storage tank construction method applying prefabricated foundation ring beam prefabricating method
CN104831734A (en) Construction method of jet-grouting pile and composite soil-nailed wall support for deep foundation pit construction
CN209703525U (en) A kind of side slope precast assembly lattice girder connected by wet seam
CN104295003A (en) Structural column construction method
CN107989049A (en) A kind of construction method of frame bank protection
CN107100083A (en) A kind of T-shaped high pier Cast-in-place Bent Cap formwork erecting structure and construction method
CN110439002A (en) A kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab
CN209723033U (en) Pipe jacking working well applicable to desert waterless sand layer area
CN114809029A (en) High cutting slope anchor rod frame beam coupling construction method
CN110552371A (en) Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
CN103790168A (en) Application method of soil nailing wall in deep foundation pit supporting
CN114457682A (en) Cast-in-place construction method of cast-in-place concrete bridge
CN109610665A (en) Oil depot assembled fire wall construction method
CN106193120B (en) Basement is encorbelmented, and bottom plate is inverse to make structure and construction method
CN103866982A (en) Petal artistic framework construction method
CN110468879A (en) A kind of electric power work well and the construction method for drawing pipeline
CN210507464U (en) Annular supporting plate for basement structure floor slab
CN116657945A (en) Transformation method for replacing internal structure of steel structure of old historical building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination